`LUS-CP7B-QDSBG-DRP-PM-00015

Revision: October 2012 Contractor Consultant


PM/CM

LREDC-INFRASTRUCTURE DEPARTMENT

Daily Site Diary Date 1-05-2016

ACTIVITIES (NIGHT SHIFT ) REMARKS


HYDROSERV
 Monitoring &Maintenance In Progress ( Night Shift )
 House Keeping In progress (Night shift)

BAUER INTERNATIONAL / QD-SBG


 Primary (P95) – Concreting on Going @ Zone-3 On Going (Night Shift ) (D-WALL )
 Primary ( 62 )- Excavation on Going & Steel cage Ready for Installation (Zone-3 In Progress ( Night Shift ) @ Zone-3
 Secant Piles (900 dia.)-S64a,S74a,S77a,S83a –( Casting Done ) @ Zone 6 Casted ( Night Shift ) @ Zone- 6
 90a,103a, 116a, 95 & 101- concreting Done and 124a- Ready for Casting Casted ( Night Shift ) @ Zone-7

 136, 133 and 130 - Ready to Install the steel Cage Casted (Night Shift) @ Zone-7

UNITED GROUP
 Shifting of 2 HDPE on Zone-2 In Progress ( Night Shift )

 Repairing a broken valve on Zone-2 In Progress ( Night Shift )


 Welding of HDPE pipe on Zone-1 In Progress ( Night Shift )
 Monitoring & Maintenance In Progress ( Night Shift )
 Housekeeping In Progress ( Night Shift )
ZONE-1
 Steel fixing & Shuttering for Raft foundation
 Housekeeping

ZONE-3
 Blinding Concrete – on Going @ Central Area On Going Casting ( Night Shift )


ZONE-4
 Steel Fixing & Shuttering for Raft foundation In Progress (Night Shift )
 Removing of materials from Trench In Progress ( Night Shift )
 Housekeeping

ZONE-5
 Ready for Casting Capping Beam –Pile No. 262 to Pile No. 266 In Progress ( Night Shift )
 Backfilling ( Concrete ) work- Pile no. 222 to Pile no. 232 ,Pile no. 252 to 262 In Progress ( Night Shift )

ZONE No. 1 In Progress ( Night shift )

 QD-SBG – Excavation and Hauling In progress ( Night Shift )

Zone No. 02 (Emdaad and Al-Bahaari )


 AL BAHARRI- Excavation and Hauling In Progress ( Night Shift )

Zone No. 03 (Emdaad and Cons. Tech.)


 EMDAD-Excavation and hauling In Progress ( Night Shift )
 CONS.TECH- Excavation and Hauling In Progress ( Night Shift )
Zone No. 04 ( Black Pearl )
 Black pearl- Excavation and Hauling In Progress ( Night Shift )
Zone No. 05 (Emdaad and Al Bahaari)
 Emdaad- Excavation and Hauling In Progress (Night Shift )
 Al Bahari- Excavation and Hauling In Progress ( Night Shift )
Zone No.06 (Cons.Tech.)
 Cons. Tech- Excavation and Hauling In Progress ( Night Shift )

Zone No. 07 (Emdaad )


 Excavation and hauling work In Progress ( Night Shift )

Contractor: QD- SBG Consultant:

Submitted: May 1,2016 Signature: RUSSEL J. ARABANI Received On: Signature