Time ( weeks )

Activity
1 2 3 4 5 6 7
Move-in
Stake-out
Excavate, Column Footings
Excavate, Wall Footings
Excavate, Drain Pipes and Catch Basins
Install Forms and Rebars, Column Footings and Rebars and Columns

Install Forms and Rebars, Wall Footings


Install Drain Pipes and Catch Basins
Backfill and Compact Drainage Excavation
Pour Concrete, Column Footings
Pour Concrete, Wall Footings
Fabricate Timber Trusses
Pour Concrete, Columns
Install Forms, Columns
Erect First Few Layers of CHB
Erect Next Layers of CHB
Erect Trusses and Cross Frames
Install Girts and Tie Girts
Install Purlins
Backfill, Grade and Compact Ground
Install Forms and Rebars, Slab
Pour Concrete, Slab
Concrete Works, Sidewalk
Install G.I. Roof Sheets and Gutters
Install Ceilings
Install Doors and Windows
Plaster Walls
Erect Double-Wall Partition
Paint Roof
Install PVC Downspouts
Paint Exterior/Interior
Clean-up