PHASE 2B SCHEDULE AS OF 2017‐04‐06

COMPONENT 1: Substructure
DATE (2017) STATUS DRAWINGS BY
PHASE 2B SUBSTRUCTURE SCHEDULE
Mar 20 DONE PRSP Advance Copy 1: Architectural Baseplans for PBD/Team (Sy^2, MEP, KuKu, ID) ‐  Sub (together w/ PH, The Offices) PRSP
April 24‐28 (4 wks fr Mar 20) Progressive MEPF CADD Drawings (all trades) MEP
‐ include PH items that have impact to Sub
‐ include The Offices items that have impact to Sub
April 24‐28 (4 wks fr Mar 20) Progressive Sy^2 CADD Drawings Framing and Schedules (Sub) Sy^2
May 05 (2.5wks before May 24)
( k b f ) Ph2B Substructure ‐ final baseplans 
h b f lb l PRSP
May 15‐19 MEP and Sy^2 Final E‐File Copy before Plotting: PRSP to review (consistency, completion) MEP, Sy^2
May 24 Ph2B Substructure 100%CD Complete Package (PBD) ‐ A0, A3, and e‐files Sy^2‐PRSP‐MEP

COMPONENT 2: Performing Arts Theatre & Museum (PAT&M)
DATE (2017) STATUS DRAWINGS BY
Feb 14‐15 ID‐KUKUs WORKSHOP 1: Acoustics & Stage Rigging Team with KuKus
Feb 20 March 21  (INITIAL ); Rest in DD Ceiling and Bridge Drawings/Details (for ID reference) KuKu
Feb 24 DONE Initial Plans (reduced footprint, orchestra pit) to 9Works PRSP
Feb 24 Feb 28: Seat Study for Kukus (add'l row) Initial Plans (reduced footprint, orchestra pit) to KuKu & ID for STAGE  & HOUSE only PRSP
Mar 06: Dwgs for ID (from PMG Mar 02)
Feb 27‐Mar 03 DONE Review of Initial Plans  9 Works
Mar 06‐10  DONE; for refinement BOH Workshop PRSP, 9 Works
Mar 06
M 06 PENDING Feedback on Freight Elevator
F db k F i ht El t Kone
K
Mar 06 DONE, PH sent Feb 27 Initial Plans for Sy^2‐MEP: PH Superstructure PRSP
Mar 06 on‐going Start of Review for Structural & MEPF Systems Sy^2‐MEP
Mar 06 MARCH 20 (SD); Wall Tags/Types will be in DD Specifications/Details and Drawings on Acoustics Kuemmel
Mar 10 (new) Initial Plans for Sy^2‐MEP: Ph2B SUB & Sixth Tower Super  PRSP
Mar 13‐17 DONE Fine‐tuning of Plans based on Workshop with 9 Works PRSP
Mar 20 DONE PRSP Advance Copy 1: Architectural Baseplans for PBD/Team (Sy^2, MEP, KuKu, ID): PH (together with Sub) PRSP
Mar 20 APRIL  03 (PH only); pending SUB Structural Framing (CADD); confirmation of shearwall sizes Sy^2
Mar 27‐31 March 24 (INITIAL); Others to FOLLOW Load Plans for structural reference KuKu
Mar 27‐31 DONE (March 27 & 28) ID‐KUKUs WORKSHOP 2: ID Concepts, Acoustics, & Stage Rigging Team with KuKus‐BV
Mar 29 DONE Latest Architectural Drawings for ID Reference  PRSP
Apr 03‐14 Load Plans for structural reference ‐ additional info requested by Sy^2 KuKu
Apr 05‐12 Fine‐tuning of BOH areas (from PMG March 24 comments) PRSP, 9 Works
Apr 05‐12 (3 wks fr mar 20) MEP Advance Copy 1: Progressive MEPF Drawings (all trades) MEP
Apr 07‐12 Progressive Architectural Sections for ID Reference (email to all consultants) PRSP
Apr 10‐May 12 (4 wks) ID Start: House and FOH ‐ from March workshop & incorporate Kuku Dwgs expected on April 24‐28 BV & E&A
April 24‐28 KuKus will try before April 24 (April 10‐21?) Drawings from KuKu (DD Advance Copy) KuKu
April 24‐28 (4 wks fr Mar 20) Sy^2 Advance Copy 1: Sy^2 CADD Drawings Framing and Schedules (PH and The Offices) Sy^2
April 24‐28 Fine‐tuning of BOH areas (from PMG March 24 comments): for Approval PRSP‐9 Works‐RLC
May 12 (for E&A/BV confirmation if okay) ID Advance Copy 1: House, FOH, and BOH ‐ Initial Drawings for review and coordination BV & E&A
May 17 PRSP Advance Copy 2: for Team (ID reference, MEP baseplan) PRSP
‐ BOH: updated from April 24‐28
‐ House: updated from ID's May 12 Advance Copy 1
‐ FOH: updated from ID's May 12 Advance Copy 1
May 17‐26 (1.5 wks) Workshop based on ID Advance Copy 1, PRSP Advance Copy 1, and Sy^2 Advance Copy 1 PRSP, E&A, MEP, Sy^2
May 22 Drawings from KuKu (Complete/Additional Details) Kuku
May 22‐ June 02 (2 wks) Team review of DD Kuku Package PRSP, E&A, MEP, Sy^2, RLC
June 05‐09  (tentative, for RLC confirmation) ID‐KUKUs WORKSHOP 3: Design and Details ‐ approval Team with KuKus‐BV
June 12‐23 (2 wks) ID ‐ House, FOH, & BOH: Revision of Drawings (from June workshop, coordination & approval) BV & E&A
June 23 ID Advance Copy 2: House, FOH & BOH ‐ updated drawings for team, for team review BV & E&A
June 26‐30 (1 wk) Comments to ID Advance Copy 2 PRSP‐RLC
DATE (2017) STATUS DRAWINGS BY
June 30 PRSP Advance Copy 3: for Team (ID reference, MEP baseplan) PRSP
‐ incorporate ID Advance Copy 2
‐ incorporate agreements from coordination/workshop
June 30 Sy^2 Advance Copy 2: Structural Framing (CADD) for PAT&M and The Offices ‐ PBD Sy^2
Jul 3‐14 (2 wks) PRSP‐RLC review of Sy^2 Advance Copy 2 PRSP‐RLC‐Sy^2
Jul 3‐14 (2 wks) Comments to PRSP Advance Copy 3 RLC
July 17 (2 wks from June 30 comments) ID Drawings Package  BV & E&A
July 17 (2 wks from June 30) MEP Advance Copy 2: based on PRSP Advance Copy 3  and coordination/workshops MEP
Jul 17‐21 Comments to ID Advance Copy 2 PRSP‐RLC
Jul 17‐21 Comments to MEP Advance Copy 2 PRSP‐RLC
July 24‐Aug 04 Workshop based on ID Advance Copy 2, PRSP Advance Copy 3, Sy^2 Advance Copy 2, and MEP Advance Copy 2 PRSP, E&A, MEP, Sy^2
Aug 07 Final Architectural Baseplans, RCP to team (MEP) for 100%CD
August 25 MEP and Sy^2 Final E‐File Copy before Plotting: PRSP to review (consistency, completion) MEP, Sy^2
Aug 31 (3 wks fr comments) Team Issuance of 100%CD PRSP‐Sy^2‐MEP

COMPONENT 3: The Offices at the Proscenium
DATE (2017) STATUS DRAWINGS BY
Mar 20 DONE PRSP Advance Copy 1: Architectural Baseplans to Team (Sy^2, MEP, KuKu, ID): The Offices (together w/ Sub and PH) PRSP
April 24‐28 (4 wks fr Mar 20) MEP Advance Copy 1: Progressive MEPF CADD Drawings (The Offices) MEP
April 24‐28 (4 wks fr Mar 20) Sy^2 Advance Copy 1: Progressive Sy^2 CADD Drawings Framing and Schedules (The Offices) Sy^2
May 02‐12 (2 wks) Workshops & Coordination  PRSP‐Sy^2‐MEP
May 17 PRSP Advance Copy 2: for team coordination, progressive drawings PRSP
‐ drawings for ID reference
May 22‐ June 23 (5 wks) Workshops & Coordination  PRSP‐Sy^2‐MEP‐ E&A
June 16 (4 wks from baseplans)
J 16 (4 k f b l ) ID Advance Copy 1
ID Ad C 1 E&A
June 19‐30 Workshops & Coordination  PRSP‐Sy^2‐MEP‐ E&A
June 30 PRSP Advance Copy 3: for Team (ID reference, MEP baseplan)
‐ incorporate ID Advance Copy 1
‐ incorporate agreements from coordination/workshop
June 30 Sy^2 Advance Copy 2: Structural Framing (CADD) for PAT&M and The Offices ‐ PBD Sy^2
Jul 3‐14 (2 wks) PRSP‐RLC review of Sy^2 Advance Copy 2 PRSP‐RLC‐Sy^2
Jul 3‐14 (2 wks) Comments to PRSP Advance Copy 3 RLC
July 17 (2 wks from baseplans) ID Drawings Package E&A
July 17 (2 wks from June 30) MEP Advance Copy 2: based on PRSP Advance Copy 3  and coordination/workshops MEP
Jul 17‐21 Comments to MEP Advance Copy 2 PRSP‐RLC
July 17‐28 (2 wks) Workshops & Coordination  PRSP‐Sy^2‐MEP‐ E&A
Aug 02 Final Architectural Baseplans, RCP to team (MEP) for 100%CD
August 25 MEP and Sy^2 Final E‐File Copy before Plotting: PRSP to review (consistency, completion) MEP, Sy^2
Aug 31 (3 wks fr comments) Team Issuance of 100%CD PRSP‐Sy^2‐MEP