CONSULTANT: DC QC Form No.

QI-04 CONTRACTOR:
(Version-2, 20/10/10)

DAILY REPORTS

CLIENT: Abu Dhabi Sewerage Services Company Date: 22 January 2012


PROJECT & CONTRACT NO: CONSTRUCTION WORKS ASSOCIATED LOCATION :
WITH REHABILITATION AND REPLACEMENT OF EXISTING SEWER LINES IN Sectors W2, W4, W6 & W7
ABUDHABI ISLAND AREA Contract No. O - 1792

WORK DONE , WORK TESTED & TESTING DETAILS, WORK ACCEPTED,


DESCRIPTION OF MATERIALS USED and QUANTITY
* Sector W2 – Pipe Laying and Backfilling bet H25 to H25/1 , Backfilling bet H25/2 to H25/1 , H25/1 to H25/6 .
* Sector W4,– Dewatering for lines 4, 6 & 9 . at line 9 : Laying and fixing of Pipe Connection at D53/26 from CH 38 to 46
bet D53/26/1 to D53/26 . at Line 10 : Compaction Test 7 th and 8th Layer Bet D53/23/2 to D53/23/1 , Removal of safety
fence and Trench Sheet and I-Beam . at Line 4 : Lowering Excavation for BD replacement from 150mm to 200 mm at
D53/12 , Compaction test for 2 nd and 3rd Layer bet D53/12/1 to D53/12 . at Line 6 : Compaction test for 6 th and 7th
Layer . lamination work for ring and Cover slab .
* Sector W6– at line 2 : Removal of Beam at H13/8 BD , demolishing of ext Port at H13/8A . at line 4 : Hydro test Completed
bet H13/12A/3 to H13/12A/4 , Connection at H13/12A/3 and /2 Completed , Backfilling and Compaction . at Line 10 :
Reinstatement of Tiles .
* Sector W7 – at Line 11 : Removal of Tiles . Excavation at H9 BD Location . Preparation for handing Over bet H9/2 to H9/4 to
H9/2 to H9/2/1 .
Manpower:
Staf No. Total Staf No. Total Staf No. Total
Construction Director 01 Secretary 01 Charge Hand* 07
Project Manager 01 Time keeper 01 Asst. Surveyor* 01
Dy. Project Manager 01 CAD Technician 04 Mason* 03
Construction Manager 01 HSE Engineer 01 Operator* 11
Site Agent 01 Office boy 02 Pipe Fitter* 03
QS 01 Site Engineer* 03 Welder* 03
PRO 01 Foreman* 01 Carpenter* 04
Accountant 01 Safety Officer* 04 Steel Fixer* 00
QA/QC 01 Surveyor* 04 Laminator* 02
Planning Engineer 01 Chainman* 04 Watchman 05
Supervisor 01 Driver* 05 Others: (SOP) 00
Material Engineer 01 Labors* 78 Asst. Welder 01
Remarks: * Direct Staff particularly involved in mentioned sectors.

PLANT / MACHINERY: [ WG = Working; IL = Idle; BD = Break Down ]


Type Model No. WG IL BD Type Mod No. WG IL BD
Pick Up (3T) 03 03 Bob Cat 02 02
DC Pick Up 00 00 Dewatering Pumps:
Mini Bus (14 Seat)* Electrical Pumps 01 01
01 01 (Submersible)
Mini Bus (65 Seat)* 01 01 Diesel Pumps (6" & 08 08
Car (Salon) 03 03 Jetting Pumps 04 04
JCB 03 03 Overpumping Pumps:
Asphalt Cutter Elec’l Pumps 11 11
01 01 (Submersible)
Compressor Jack Hammer 02 02 Diesel Pumps (6" & 04 04
Excavator 06 06 Welding Machine 02 02
Plate Compactor 03 03 Shovel 00 00
Crane * 00 00 Jack Hammer Exc. 00 00
Tipper 03 03 Generator 00 00
Drill Excavator 00 00 Vibrator 00 00
Remarks: Common equipment with mark of “*” being utilized for the whole project.
For Contractor: Checked by (DC):

Date: Date: