ID Task Task Name Duration Start Finish Predecessors

Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018


Mode Aug Sep Oct Nov Dec Jan Feb Mar
1 FORMATION OF 2 days Mon Tue 9/19/17
GROUP 9/18/17
2 4 STOREY SHOP LOT 40 days Wed 9/20/17Tue 11/14/171
3 FINDING DESIGN 7 days Wed Thu 9/28/17 1
OF BUILDING 9/20/17
STRUCTURE
4 PREPARATION OF 7 days Fri 9/29/17 Mon 3
PROPOSAL 10/9/17
5 GROUND FLOOR PLAN2 days Tue 10/10/17Wed 10/11/174
6 FIRST FLOOR PLAN 2 days Thu 10/12/17Fri 10/13/17 5
7 SECOND FLOOR PLAN2 days Mon 10/16/17Tue 10/17/176
8 THIRD FLOOR PLAN2 days Mon 10/16/17Tue 10/17/176
9 ROOF PLAN 2 days Wed 10/18/17Thu 10/19/178
10 FRONT ELEVATION 2 days Fri 10/20/17 Mon 9
PLAN 10/23/17
11 RIGHT ELEVATION 2 days Fri 10/20/17 Mon 9
PLAN 10/23/17
12 LEFT ELEVATION PLAN
2 days Fri 10/20/17 Mon 10/23/179
13 A-A SECTION VIEW 2 days Fri 10/20/17 Mon 9
PLAN 10/23/17
14 DESIGN 16 days Tue 10/24/17Tue 11/14/1713
15 BEAM 5 days Fri 10/27/17 Thu 11/2/17 16
16 SLAB 3 days Tue 10/24/17Thu 10/26/1713
17 COLUMN 3 days Fri 11/3/17 Tue 11/7/17 15
18 RC WALL 4 days Fri 11/3/17 Wed 11/8/1715

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: capestone
Summary Manual Summary Rollup Progress
Date: Wed 1/17/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Mode Aug Sep Oct Nov Dec Jan Feb Mar
19 STAIRCASE 2 days Tue 10/24/17Wed 10/25/1713
20 FOUNDATION 4 days Thu 11/9/17 Tue 11/14/1718
21 2 STOREY OFFICE 39 days Wed 11/15/17 Mon 1/8/18 20
22 GROUND FLOOR 7 days Wed Thu 13
PLAN 11/15/17 11/23/17
23 1ST FLOOR PLAN 5 days Fri 11/24/17 Thu 11/30/1722
24 FRONT ELEVATION 3 days Fri 12/1/17 Tue 12/5/17 23
PLAN
25 REAR ELEVATION 3 days Wed Wed 24
PLAN 12/6/17 12/13/17
26 DESIGN 18 days Thu 12/14/17Mon 1/8/18 25
27 BEAM 7 days Thu 12/21/17Fri 12/29/17 28
28 SLAB 5 days Thu 12/14/17Wed 12/20/1725
29 COLUMN 3 days Mon 1/1/18 Wed 1/3/18 27
30 STAIRCASE 3 days Thu 12/14/17Mon 12/18/1725
31 FOUNDATION 3 days Thu 1/4/18 Mon 1/8/18 29

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: capestone
Summary Manual Summary Rollup Progress
Date: Wed 1/17/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2

Вам также может понравиться