Академический Документы
Профессиональный Документы
Культура Документы
PRESUPUESTO DE OBRA
OBRA SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
Departamento Cusco Provincia Paruro Distrito Pillpinto
3.0 DESARENADOR
3.1 TRAZO Y REPLANTEO EN OBRAS DE ARTE M2 2.50 1.45 3.63 1.35 3.38
3.2 EXCAVACION EN TERRENO CONGLOMERADO M3 4.14 8.17 33.83 1.50 6.23
3.3 ENCOFRADO Y DESENCOFRADO NORMAL M2 6.32 13.02 82.30 11.77 74.40
3.4 CONCRETO F'c=175 kg/cm2+30% P.M. M3 0.10 250.34 25.03 220.34 22.03
3.5 CONCRETO F'c=175 kg/cm2 M3 1.49 297.84 443.78 267.84 399.08
3.6 ACERO CORRUGADO F'y=4200 kg/cm2 KG 15.00 4.80 71.98 4.70 70.48
3.7 SUMINISTRO E INSTALACION ACCESORIOS DESARENADOR GLB 1.00 424.94 424.94 419.94 419.94
Fecha 11/15/2011
M.O. NO CALIFIC
C.Unit Parcial
6.29 6.29
0.10 0.81
6.67 47.40
1.25 19.23
30.00 169.80
2.50 2.50
0.10 0.25
6.67 27.60
1.25 7.90
30.00 3.00
30.00 44.70
0.10 1.50
5.00 5.00
0.10 0.10
6.67 6.67
1.25 4.55
30.00 12.60
5.00 5.00
1.67 5.43
0.10 2.35
5.00 5.00
0.10 0.40
6.67 26.67
1.25 18.20
30.00 50.40
5.00 20.00
1.67 21.73
0.10 9.40
5.00 20.00
0.05 331.00
1.55 10,261.00
0.20 1,324.00
0.20 1,324.00
1.25 8,275.00
0.10 176.50
0.10 48.00
0.10 104.00
0.08 146.80
0.08 120.00
5.00 5.00
0.07 441.33
0.10 1.25
6.67 50.00
1.25 12.50
30.00 54.00
Fecha 11/15/2011
M.O. NO CALIFIC
C.Unit Parcial
5.00 250.00
5.00 205.00
10.00 90.00
0.10 2.23
6.67 89.00
1.25 40.05
30.00 96.12
5.00 445.00
5.00 445.00
544.59 6,535.02
0.00 0.00
31,416.28
31,416.28
ANALISIS DE PRECIOS UNITARIOS
Obra SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO Fecha
Departamento Cusco Provincia Paruro Distrito Pillpinto
Partida 4.5 TAPA METALICA 0.60x0.60 CON LLAVE DE TUERCAS 1/8" C.TOTAL AGRORURAL
Rendimien 4.00 UND/DIA Costo unitario directo por : UND 104.94 99.94
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 2.00 4.75 9.50
PEON HH 1.00 2.00 2.50 5.00
Materiales
TAPA METALICA DE 0.60x0.60 m LLAVE TUERCAS E= UND 1.00 90.00 90.00
Equipos
HERRAMIENTAS MANUALES %MO 0.03 14.50 0.44
ANALISIS DE PRECIOS UNITARIOS
Obra SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO Fecha
Departamento Cusco Provincia Paruro Distrito Pillpinto
Partida 5.5 RELLENO APISONADO ZANJAS CON MATERIAL PROPIO C.TOTAL AGRORURAL
Rendimien 16.00 M/DIA Costo unitario directo por : M 1.53 0.28
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 0.10 0.050 4.75 0.24
PEON HH 1.00 0.50 2.50 1.25
Equipos
HERRAMIENTAS MANUALES %MO 0.03 1.49 0.04
Partida 5.6 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 6" C-5 C.TOTAL AGRORURAL
Rendimien 200.00 M/DIA Costo unitario directo por : M 30.28 30.18
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.04 4.75 0.19
OFICIAL HH 1.00 0.04 4.25 0.17
PEON HH 1.00 0.04 2.50 0.10
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 6" x 5m M 1.00 29.60 29.60
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.46 0.01
Partida 5.7 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 4" C-5 C.TOTAL AGRORURAL
Rendimien 200.00 M/DIA Costo unitario directo por : M 14.68 14.58
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.04 4.75 0.19
OFICIAL HH 1.00 0.04 4.25 0.17
PEON HH 1.00 0.04 2.50 0.10
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 4" x 5m M 1.00 14.00 14.00
Equipos
ANALISIS DE PRECIOS UNITARIOS
Obra SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO Fecha
Departamento Cusco Provincia Paruro Distrito Pillpinto
HERRAMIENTAS MANUALES %MO 0.03 0.46 0.01
Partida 5.9 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 3" C-5 C.TOTAL AGRORURAL
Rendimien 200.00 M/DIA Costo unitario directo por : M 9.18 9.08
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.04 4.75 0.19
OFICIAL HH 1.00 0.04 4.25 0.17
PEON HH 1.00 0.04 2.50 0.10
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 3" x 5m M 1.00 8.50 8.50
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.46 0.01
Partida 5.11 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 2" C-5 C.TOTAL AGRORURAL
Rendimien 250.00 M/DIA Costo unitario directo por : M 5.29 5.21
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.032 4.75 0.15
OFICIAL HH 1.00 0.032 4.25 0.14
PEON HH 1.00 0.032 2.50 0.08
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 2" x 5m M 1.00 4.70 4.70
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.37 0.01
Partida 5.12 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 1 1/2" C-7.5 C.TOTAL AGRORURAL
Rendimien 250.00 M/DIA Costo unitario directo por : M 4.09 4.01
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.032 4.75 0.15
OFICIAL HH 1.00 0.032 4.25 0.14
PEON HH 1.00 0.032 2.50 0.08
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-7.5 1 1/2" x 5m M 1.00 3.50 3.50
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.37 0.01
MONC
6.29
Total
17.55
145.73
0.53
MONC
0.10
Total
0.35
0.73
0.37
MONC
6.67
Total
7.93
0.24
MONC
1.25
Total
5.75
7.10
0.17
MONC
30.00
Total
48.00
200.90
1.44
11/15/2011
MONC
2.50
Total
7.25
200.00
0.22
MONC
30.00
Total
48.00
248.40
1.44
MONC
0.10
Total
0.46
4.33
0.01
MONC
5.00
Total
14.50
410.00
0.44
MONC
5.00
Total
14.50
90.00
0.44
11/15/2011
MONC
1.67
Total
4.83
6.22
0.15
MONC
5.00
Total
14.50
324.53
0.44
MONC
5.00
Total
14.50
513.53
0.44
MONC
0.05
Total
0.18
0.02
11/15/2011
0.19
MONC
1.55
Total
1.90
0.07
MONC
0.20
Total
0.24
0.01
MONC
0.20
Total
0.24
0.02
MONC
1.25
Total
1.49
0.04
MONC
0.10
Total
0.46
29.81
0.01
MONC
0.10
Total
0.46
14.21
11/15/2011
0.01
MONC
0.10
Total
0.46
8.71
0.01
MONC
0.08
Total
0.37
4.91
0.01
MONC
0.08
Total
0.37
3.71
0.01
MONC
5.00
Total
14.50
11/15/2011
3,557.05
0.44
11/15/2011
MONC
0.07
Total
0.19
0.06
MONC
5.00
Total
14.50
62.11
0.44
MONC
10.00
Total
29.00
748.61
0.87
MONC
5.00
Total
14.50
35.00
0.44
MONC
5.00
Total
14.50
35.28
0.44
11/15/2011
MONC
10.00
Total
19.50
524.50
0.59
MONC
0.00
Total
1,000.00
ANALISIS DE PRECIOS UNITARIOS
Obra SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO Fecha
Departamento Cusco Provincia Paruro Distrito Pillpinto
Partida 4.5 TAPA METALICA 0.60x0.60 CON LLAVE DE TUERCAS 1/8" C.TOTAL AGRORURAL
Rendimien 4.00 UND/DIA Costo unitario directo por : UND 104.94 99.94
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 2.00 4.75 9.50
PEON HH 1.00 2.00 2.50 5.00
Materiales
TAPA METALICA DE 0.60x0.60 m LLAVE TUERCAS E= UND 1.00 90.00 90.00
Equipos
HERRAMIENTAS MANUALES %MO 0.03 14.50 0.44
Partida 6.5 RELLENO APISONADO ZANJAS CON MATERIAL PROPIO C.TOTAL AGRORURAL
Rendimien 16.00 M/DIA Costo unitario directo por : M 1.53 0.28
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 0.10 0.050 4.75 0.24
PEON HH 1.00 0.50 2.50 1.25
Equipos
HERRAMIENTAS MANUALES %MO 0.03 1.49 0.04
Partida 6.6 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 6" C-5 C.TOTAL AGRORURAL
Rendimien 200.00 M/DIA Costo unitario directo por : M 30.28 30.18
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.04 4.75 0.19
OFICIAL HH 1.00 0.04 4.25 0.17
PEON HH 1.00 0.04 2.50 0.10
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 6" x 5m M 1.00 29.60 29.60
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.46 0.01
Partida 6.7 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 4" C-5 C.TOTAL AGRORURAL
Rendimien 200.00 M/DIA Costo unitario directo por : M 14.68 14.58
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.04 4.75 0.19
OFICIAL HH 1.00 0.04 4.25 0.17
PEON HH 1.00 0.04 2.50 0.10
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 4" x 5m M 1.00 14.00 14.00
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.46 0.01
ANALISIS DE PRECIOS UNITARIOS
Obra SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO Fecha
Departamento Cusco Provincia Paruro Distrito Pillpinto
Partida 6.8 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 3" C-5 C.TOTAL AGRORURAL
Rendimien 200.00 M/DIA Costo unitario directo por : M 9.18 9.08
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.04 4.75 0.19
OFICIAL HH 1.00 0.04 4.25 0.17
PEON HH 1.00 0.04 2.50 0.10
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 3" x 5m M 1.00 8.50 8.50
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.46 0.01
Partida 6.9 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 2" C-5 C.TOTAL AGRORURAL
Rendimien 250.00 M/DIA Costo unitario directo por : M 5.29 5.21
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.032 4.75 0.15
OFICIAL HH 1.00 0.032 4.25 0.14
PEON HH 1.00 0.032 2.50 0.08
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-5 2" x 5m M 1.00 4.70 4.70
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.37 0.01
Partida 6.10 SUMINISTRO E INSTALACION TUBERIA PVC-SAP 1 1/2" C-7.5 C.TOTAL AGRORURAL
Rendimien 250.00 M/DIA Costo unitario directo por : M 4.09 4.01
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
OPERARIO HH 1.00 0.032 4.75 0.15
OFICIAL HH 1.00 0.032 4.25 0.14
PEON HH 1.00 0.032 2.50 0.08
Materiales
PEGAMENTO PARA PVC OATEY GLN 0.002 105.00 0.21
TUB. PVC SAP PRESION C-7.5 1 1/2" x 5m M 1.00 3.50 3.50
Equipos
HERRAMIENTAS MANUALES %MO 0.03 0.37 0.01
MONC
6.29
Total
17.55
145.73
0.53
MONC
0.10
Total
0.35
0.73
0.37
MONC
6.67
Total
7.93
0.24
MONC
1.25
Total
5.75
7.10
0.17
MONC
30.00
Total
48.00
200.90
1.44
11/15/2011
MONC
2.50
Total
7.25
200.00
0.22
MONC
0.10
Total
0.35
0.73
0.37
MONC
6.67
Total
7.93
0.24
MONC
1.25
Total
5.75
7.10
0.17
MONC
30.00
Total
48.00
200.90
1.44
11/15/2011
MONC
30.00
Total
48.00
248.40
1.44
MONC
0.10
Total
0.46
4.33
0.01
MONC
5.00
Total
14.50
410.00
0.44
MONC
0.10
Total
0.35
0.73
0.37
MONC
6.67
Total
7.93
0.24
11/15/2011
MONC
1.25
Total
5.75
7.10
0.17
MONC
30.00
Total
48.00
248.40
1.44
MONC
5.00
Total
14.50
90.00
0.44
MONC
1.67
Total
4.83
6.22
0.15
MONC
0.10
Total
0.46
4.33
0.01
11/15/2011
MONC
5.00
Total
14.50
324.53
0.44
MONC
0.10
Total
0.35
0.73
0.37
MONC
6.67
Total
7.93
0.24
MONC
1.25
Total
5.75
7.10
0.17
MONC
30.00
Total
48.00
248.40
1.44
11/15/2011
MONC
5.00
Total
14.50
90.00
0.44
MONC
1.67
Total
4.83
6.22
0.15
MONC
0.10
Total
0.46
4.33
0.01
MONC
5.00
Total
14.50
513.53
0.44
MONC
0.05
Total
0.18
0.03
11/15/2011
0.19
11/15/2011
MONC
1.55
Total
1.90
0.07
MONC
0.20
Total
0.24
0.01
MONC
0.20
Total
0.24
0.02
MONC
1.25
Total
1.49
0.04
MONC
0.10
Total
0.46
29.81
0.01
MONC
0.10
Total
0.46
14.21
0.01
11/15/2011
MONC
0.10
Total
0.46
8.71
0.01
MONC
0.08
Total
0.37
4.91
0.01
MONC
0.08
Total
0.37
3.71
0.01
MONC
5.00
Total
14.50
3,557.05
0.44
11/15/2011
MONC
0.07
Total
0.19
0.06
MONC
0.10
Total
0.35
0.73
0.37
MONC
6.67
Total
7.93
0.24
MONC
1.25
Total
5.75
7.10
0.17
MONC
30.00
Total
48.00
248.40
1.44
11/15/2011
MONC
5.00
Total
14.50
35.00
0.44
MONC
5.00
Total
14.50
62.11
0.44
MONC
10.00
Total
29.00
748.61
0.87
MONC
0.10
Total
0.35
0.73
0.37
MONC
6.67
Total
7.93
0.24
11/15/2011
MONC
1.25
Total
5.75
7.10
0.17
MONC
30.00
Total
48.00
248.40
1.44
MONC
5.00
Total
14.50
35.00
0.44
MONC
5.00
Total
14.50
35.28
0.44
11/15/2011
MONC
10.00
Total
19.50
524.50
0.59
MONC
0.00
Total
1,200.00
SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
Cant.
Nº Descripción insumo Unidad Precio Parcial
Requerida
MANO DE OBRA
1.00 TOPOGRAFO HH 6.25 134.41 840.09
2.00 OPERARIO HH 4.75 2,049.81 9,736.59
3.00 OFICIAL HH 4.25 337.42 1,434.03
4.00 PEON (APORTE COMUNAL) HH 2.50 9,952.50 24,881.26
MATERIALES
1.00 ALAMBRE NEGRO RECOCIDO # 8 KG 6.50 8.19 53.26
2.00 ALAMBRE NEGRO RECOCIDO # 16 KG 6.50 6.63 43.06
3.00 CLAVOS PARA MADERA C/C 2" KG 6.50 5.04 32.73
4.00 CLAVOS PARA MADERA C/C 3" KG 6.50 16.39 106.52
5.00 CLAVOS PARA MADERA C/C 4" KG 6.50 8.19 53.26
6.00 ACERO CORRUGADO PROMEDIO KG 4.00 132.50 530.00
7.00 CEMENTO PORTLAND TIPO IP (42.5KG) BOL 23.00 105.25 2,420.66
8.00 YESO BOL 8.00 7.12 56.99
9.00 CINTA TEFLON RLL 1.50 71.50 107.25
10.00 CINTA TEFLON (APORTE COMUNAL) RLL 1.50 18.00 27.00
11.00 CANASTILLA SP PVC SAP DE 6" UND 110.00 2.00 220.00
12.00 CANASTILLA SP PVC SAP DE 4" a 3" UND 38.00 4.00 152.00
13.00 CORDEL M 5.00 6.62 33.10
14.00 TRANSICION PVC SAP DE 3" UND 42.00 18.00 756.00
15.00 TRANSICION PVC SAP DE 1 1/2" UND 2.50 82.00 205.00
16.00 ADITIVO IMPERMEABILIZANTE GLN 25.00 1.63 40.75
17.00 PEGAMENTO PARA PVC OATEY GLN 105.00 13.44 1,411.10
18.00 ASPERSOR VYR-60 DE UNA BOQUILLA DE 4.36MM (APORTE COM UND 82.00 36.00 2,952.00
19.00 WINCHA DE 50 METROS UND 50.00 1.99 99.30
20.00 HORMIGON M3 60.00 14.49 869.19
21.00 ARENA FINA M3 60.00 0.33 19.56
22.00 PIEDRA MEDIANA M3 20.00 2.30 46.08
23.00 CARTEL DE OBRA SEGÚN MODELO UND 119.73 1.00 119.73
24.00 REGILLA METALICA DE 4.0*0.4*1.0 DE 1/2" UND 200.00 1.00 200.00
25.00 COMPUERTA METALICA TIPO IZAJE SEGÚN MODELO UND 300.00 1.00 300.00
26.00 TAPA METALICA DE 0.60x0.60 m LLAVE DE TUERCAS E=1/8" UND 90.00 5.00 450.00
27.00 TAPA METALICA DE 0.20x0.25 GALVANIZADA UND 35.00 139.00 4,865.00
28.00 MADERA NACIONAL P/ENCOFRADO-CARP P2 2.50 147.49 368.73
29.00 MADERA EUCALIPTO ROLLIZO P2 1.00 26.00 26.00
30.00 TRIPODE METALICO PARA ASPERSOR (APORTE COMUNAL) UND 18.00 36.00 648.00
31.00 ELEVADOR DE ALUMINIO 3/4"x1.00M (APORTE COMUNAL) UND 13.00 36.00 468.00
32.00 TUB. PVC SAP PRESION C-10 EC DE 3/4" x5m M 2.00 89.00 178.00
33.00 TUB. PVC SAP PRESION C-7.5 EC DE 1 1/2" x 5m M 3.50 1,500.00 5,250.00
34.00 TUB. PVC SAP PRESION C-5 EC 2" x 5m M 4.70 1,835.00 8,624.50
35.00 TUB. PVC SAP PRESION C-5 EC 3" x 5m M 8.50 1,040.00 8,840.00
36.00 TUB. PVC SAP PRESION C-5 EC 4" x 5m M 14.00 500.00 7,000.00
37.00 TUB. PVC SAP PRESION C-5 EC 6" x 5m M 29.60 1,770.00 52,392.00
38.00 REDUCCION SP PVC SAP DE 2" A 3/4" UND 6.00 50.00 300.00
39.00 REDUCCION SP PVC SAP DE 1 1/2" A 3/4" UND 4.70 39.00 183.30
40.00 REDUCCION SP PVC SAP DE 6" A 4" UND 42.00 2.00 84.00
41.00 REDUCCION SP PVC SAP DE 6" A 3" UND 38.00 3.00 114.00
42.00 REDUCCION SP PVC SAP DE 4" A 3" UND 18.00 2.00 36.00
43.00 REDUCCION SP PVC SAP DE 3" A 2" UND 9.00 18.00 162.00
44.00 REDUCCION SP PVC SAP DE 2" A 1 1/2" UND 3.50 20.00 70.00
45.00 CRUZ PVC SAP DE 4" UND 65.00 1.00 65.00
46.00 CRUZ PVC SAP DE 3" UND 45.00 8.00 360.00
47.00 CRUZ PVC SAP DE 2" UND 18.00 2.00 36.00
48.00 UNION PE 25 MM (APORTE COMUNAL) UND 8.00 24.00 192.00
49.00 BAYONETA DE ACOPLE RAPIDO DE 3/4" (APORTE COMUNAL) UND 12.00 12.00 144.00
50.00 TEE PE DE 25 MM (APORTE COMUNAL) UND 11.00 24.00 264.00
51.00 TEE PVC SAP 6" X 6" X 6" UND 75.00 3.00 225.00
52.00 TEE PVC SAP 4" X 4" X 4" UND 52.00 3.00 156.00
53.00 TEE PVC SAP 3" X 3" X 3" UND 34.00 9.00 306.00
54.00 TEE PVC SAP 2" X 2" X 2" UND 10.00 2.00 20.00
55.00 TEE PVC SAP 1 1/2" X 1 1/2" X 1 1/2" UND 6.50 2.00 13.00
56.00 CODO PE 25 MM 3/4" UNION MACHO (APORTE COMUNAL) UND 7.00 24.00 168.00
57.00 CODO SP PVC SAP DE 90º 6" UND 66.00 1.00 66.00
PRECIOS Y CANTIDADES DE INSUMOS REQUERIDOS
OBRA SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
Departamento Cusco Provincia Paruro Distrito Pillpinto
Cant.
Nº Descripción insumo Unidad Precio Parcial
Requerida
58.00 CODO SP PVC SAP DE 45º 6" UND 66.00 22.00 1,452.00
59.00 CODO SP PVC SAP DE 90º 4" UND 45.00 8.00 360.00
PRECIOS Y CANTIDADES DE INSUMOS REQUERIDOS
OBRA SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
Departamento Cusco Provincia Paruro Distrito Pillpinto
Cant.
Nº Descripción insumo Unidad Precio Parcial
Requerida
60.00 CODO SP PVC SAP DE 90º 3" UND 28.00 8.00 224.00
61.00 CODO SP PVC SAP DE 90º 2" UND 8.00 5.00 40.00
62.00 CODO SP PVC SAP DE 90º 1 1/2" UND 6.50 2.00 13.00
63.00 VALVULA DE ACOPLE RAPIDO 3/4" UND 27.00 89.00 2,403.00
64.00 MANGUERA PE 25 MM ALTA PRESION M 2.00 720.00 1,440.00
65.00 VALVULA DE AIRE INCLUYE ACCESORIOS GLB 240.00 9.00 2,160.00
66.00 VALVULA DE COMPUERTA DE BRONCE DE 3" UND 420.00 9.00 3,780.00
67.00 VALVULA DE BOYA DE 3" UND 360.00 4.00 1,440.00
68.00 VALVULA DE COMPUERTA DE BRONCE DE 1 1/2" UND 57.00 41.00 2,337.00
EQUIPOS
1.00 BALDE PRUEBA-TAPON-ABRAZ. Y ACCESORIOS HE 1.00 331.00 331.00
2.00 TAMIZ DE 3/4" HE 0.10 860.60 86.06
3.00 TEODOLITO HE 5.00 134.41 672.07
4.00 NIVEL HE 4.00 134.41 537.64
HERRAMIENTAS
1.00 TRANSPORTE DE MATERIALES GLB 1,000.00 1.00 1000.00
2.00 HERRAMIENTAS MANUALES %MO 36,891.96 0.03 1,165.02
TOTAL INCLUIDO MANO NO CALIFICADA
Aporte comunal (mano no calificada+ modulo de riego)
COSTO DIRECTO A FINANCIAR
NOTA: EL APORTE COMUNAL este expresado en los PEONES
Subtotal
36,891.96
Subtotal
Subtotal
118,578.07
1,626.77
2,165.02
159,261.82
(31,416.28)
127,845.54
SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
PRESUPUESTO ANALITICO
OBRA: SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
Departamento Cusco Provincia Paruro Distrito Pillpinto
APORTE
PARTIDA DESCRIPCION AGRORURAL
COMUNAL
COSTO DIRECTO 127,845.54 31,416.28
02.00 BIENES 113,208.07 6,535.02
30 Materiales de consumo (Materiales de Construcción) 112,043.05 6,535.02
51 Herramientas 1,165.02
SON : CIENTO CUARENTA Y OCHO MIL SEISCIENTOS DIESINUEVE CON 00/100 NUEVOS SOLES
11/15/2011
o Pillpinto
TOTAL
159,261.82
119,743.09
118,578.07
1,165.02
39,518.73
1,626.77
12,010.70
1,000.00
24,881.26
10,548.35
300.00
300.00
10,248.35
9,000.00
200.00
150.00
898.35
3,125.11
50.11
50.11
3,075.00
3,000.00
75.00
2,100.00
700.00
800.00
600.00
5,000.00
5,000.00
180,035.28
DISTRIBUCION DE COSTOS INDIRECTOS
GASTOS GENERALES
PROYECTO SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
Departamento Cusco Provincia Paruro Distrito Pillpinto
PRECIO
DESCRIPCION UNIDAD CANTIDAD
UNITARIO
Pago de honorarios de Residencia Mes 3.00 3,000.00
Utiles de Escritorio Mes 3.00 100.00
Pasajes , viaticos y asignaciones Glb 1.00 200.00
Gastos bancarios Glb 1.00 150.00
Liquidacion de obra Glb 1.00 898.35
TOTAL
GASTOS DE SUPERVISION
PRECIO
DESCRIPCION UNIDAD CANTIDAD
UNITARIO
Movilidad y viaticos supervisor planta Glb 1.00 75.00
Honorarios supervisor obra Mes 3.00 1,000.00
Materiales de Escritorio Glb 1.00 50.11
TOTAL
GASTOS DE CAPACITACION
PRECIO
DESCRIPCION UNIDAD CANTIDAD
UNITARIO
Alimentacion de participantes Glb 1.00 700.00
Honorarios capacitador de obra Glb 1.00 800.00
Materiales de Escritorio Glb 1.00 600.00
TOTAL
GASTOS DE PRE INVERSION
PRECIO
DESCRIPCION UNIDAD CANTIDAD
UNITARIO
Elaboracion del expediente tecnico Glb 1.00 5,000.00
TOTAL
DESCRIPCION
COSTO DIRECTO
COSTO DIRECTO SIN MANO DE OBRA NO CALIFICADA
MANO DE OBRA NO CALIFICADA
GASTOS GENERALES
GASTOS DE PRE INVERSION (EXPEDIENTE TECNICO)
GASTOS DE CAPACITACION
GASTOS DE SUPERVISION
COSTO TOTAL DEL PROYECTO
SON : CIENTO OCHENTA Y UN MIL OCHOCIENTOS CINCUENTA Y CINCO CON 78/100 NUEVOS SOLES
TOS
TOTAL
9,000.00
300.00
200.00
150.00
898.35
10,548.35
ON
TOTAL
75.00
3,000.00
50.11
3,125.11
ON
TOTAL
700.00
800.00
600.00
2,100.00
ION
TOTAL
5,000.00
5,000.00
ROYECTO
MONTO
159,261.82
127,845.54
(31,416.28)
10,548.35
5,000.00
2,100.00
3,125.11
180,035.28
SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
METRADOS
SISTEMA DE RIEGO PRESURIZADO HUARANCCA TARCUYO
Departamento Cusco Provincia Paruro Distrito Pillpinto
Nº Sub
Concepto Und Cantidad Altura Ancho Largo Total
Veces Total
INSTALACIONES PROVISIONALES
Cartel de obra según diseño Und 1.00 1.00 1.00
Nº Sub
Concepto Und Cantidad Altura Ancho Largo Total
Veces Total
TRANSPORTE DE MATERIALES
Traslado de materiales a pie de obra Glb 1.00 1.00 1.00 1.00 1.00 1.00 1.00
ESPECIFICACIONES
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Conduc y Distribucion
Interior cajas
muro
ESPECIFICACIONES