Вы находитесь на странице: 1из 22

ABSTRACT

Prestea central shaft, one of the main active surface shafts of New Century Mine was
surveyed to ascertain it vertical alignment, lateral and horizontal motion that has occurred
since its existence. The survey was from shaft collar to 30 level even though previous
survey conducted for similar purpose in 1984 focused on 9 to 16 levels which was the
area that had undergone considering earth movement. The method used for the survey
was the plumb bob method by taking perpendicular offset measurements from a freely
suspending weighted wire at the corners of each compartment of the shaft to the shaft
walls and its lining.

The whole project from surface to 30 level was undertaken in two phases due to plumb
wires touching either the cage or the setts between 9 and 16 level. The first phase
spanning a period of three weeks from January to February 2007 saw to completion of
that for the shaft collar to 9 level. The second phase, which continued from 9 to 30 level,
was subdivided into batches of three (9 to 17, 17 to 24, and 24 to 30 levels) due to short
piano wire lengths. In general, the shaft was straight with some of the steel setts displaced
towards southwest and the others corroded.
TABLE OF CONTENTS

TABLE OF FIGURES.........................................................................................................1
INTRODUCTION...............................................................................................................2
Background......................................................................................................................2
Objectives........................................................................................................................3
Scope of Work.................................................................................................................3
METHODOLOGY..............................................................................................................4
Resources Used ..............................................................................................................4
Possible Sources of Errors...............................................................................................5
Precaution........................................................................................................................5
Set-Up..............................................................................................................................7
Measurements ................................................................................................................8
OBSERVATIONS...............................................................................................................9
DISCUSSION AND CONCLUSION...............................................................................10
RECOMMENDATION.....................................................................................................11
.......................................................................................................................................17
APPENDICES…......13-20
TABLE OF FIGURES
Figure 2-1 Set-up of the Pulley for the Piano Wires...........................................................7
Figure 2 Central Shaft Compartments from Surface to 30 Level (Plan View) ...............12
12
Figure 3 Plumb Wires Installed from Surface Collar to nine Level and Code for their
Corresponding North and South Offsets (Plan View).......................................................13
Figure 4 Positions of Plumb Wires Installed From Surface Collar to nine Level And Code
for their Corresponding East and West Offsets (Plan View).............................................14
Figure 5 Positions of Plumb Wires Installed from 9 Level to 30 Level (Plan View)........15
Table 1 Plumb Wires and their Corresponding Codes for Measurement..........................16
DETAIL SURVEY

INTRODUCTION

The object of survey is to produce, in general a graphical or numerical form, a


representation of natural and fabricated features in order that engineering works
can be located in their correct position on the ground. To carry a survey into a
mine through a shaft by means of heavily weighted fine wires hung vertically in
the shaft, the line of sight passing through the wires at the surface is thus
transferred to the mine workings. An important piece of work: in mineshafts, and
in transferring courses or bearings from one level to another.

While executing maintenance works on a shaft of an underground mine, it is


essential to maintain the vertical alignment of the shaft for the smooth working of
cages. The position of the center of the shaft should be known throughout the
shaft and needs to be transferred at various levels in the mine. Shaft detailing
and survey was as thus undertaken to graphically represent the shaft in three-
dimension (3D) and determine the position of the shaft sets, the verticality of the
shaft, and earthwork volumes.

The whole project from surface to 30 level was undertaken in two phases due to
a number of reasons with the first phase spanning a period of three weeks from
January to February 2007. The first phase covered surface to 9 level and the
second phase, which continued from nine to 30 level, was subdivided in batches
of three.

Background

New Century Mine is a shaft mine situated at Prestea. The Central Shaft is one
of the two active shafts of the Underground Mine. It serves as the main entrance
to the 35 level underground mine at Prestea with an interval of 150 meters
between levels and as emergency exit to Bondaye Main Shaft because they are
inter-connected. It is a 4-compartment shaft with a portion of the fist and second
compartments serving as ladder way and opening to service pumps, cables, etc,

Survey Department 2 8/3/2007


DETAIL SURVEY

the other portion for the skip cage. The third and fourth compartments are used
for man-riding and carrying equipments and machines up to surface and down to
underground.

It became imperative for shaft maintenance to be carried out on the shaft since
most of the sets were worn-out and rusty making it unsafe for hoisting. A shaft
survey was therefore undertaken to plot the shaft and its members in three-
dimension.

Objectives

The main objectives for the shaft plumbing is


• to measure with precision the positions of shaft steels
• to provide reference points for future bunton installation
• to determine the vertical alignment of the shaft and the shaft lining.
• to determine volume of earthwork between shaft sets and the walls
Scope of Work
• Setting out of plumb wires at the corners ends of the compartments
• Checking alignment of hung plumb wires
• Measuring perpendicular offsets from plumb wires to the steel sets, walls
and guides
• Establishing controls at level stations to take coordinates of plumb wires

Survey Department 3 8/3/2007


DETAIL SURVEY

METHODOLOGY

The conventional shaft survey techniques make use of plumb wires suspended
from the top of the shaft in order to transfer the position of a point and that of the
direction of a plumb plane from the surface to the pit bottom underground.

Plumbing a shaft mechanically means lowering a thin wire into the shaft using a
winch and a guide weight. This method is known as the Plumb Bob Method.

Empirical methods show a divergence of 0.00ft (0.00mm) to 0.10ft (30.00mm) for


every 4000 feet (1220.00m) of plumb line suspended. The longest plumb wire
suspended was about 900 feet (275.00m) which would have a divergence range
of zero feet (0.00mm) to 0.0223097 (6.80mm) if the wires are assumed to have a
steady divergence with depth increase.

For a measurement carried out with a tape measure which gives measurement
accuracy of decimals of a centimeter (1mm), the fractional error per meter depth
would be 40441.00mm; an error of 1.00mm divergence for every 40.00 meter
depth reached which is not significant as thus the plumb bob method used being
adequately accurate and acceptable.

Coordinates difference for plumb line suspended from 24 level was taken for 24
and 30 levels and the corresponding divergence for each plumb line and as such
the mean divergence for. The coordinate difference measured at 17 level, their
corresponding divergence and the mean divergence calculation is attached as
equation 1.

Resources Used
• Piano wires running round a pulley
• Plumb bobs (25-10kg - which do not exceed the tensile strength of wire)
• Pair of pliers
• Nails (2-5’’) and Hammer
Survey Department 4 8/3/2007
DETAIL SURVEY

• Wooden Boards (4”x6”x8’), (1”x2”x2’)


• Eye bolts of 4mm diameter.
• Engine oil and Grease
• Polythene bags
• Total station
• Steel tape
Possible Sources of Errors

The determination of the position of the freely hanging plumb bobs and as such,
the vertical position of the plumb wires is subject to a variety of influences, such
as:
• rotational oscillation of plumb bob
• longitudinal oscillations of plumb wire
• mechanical load the weight imposes on the wire
• thickness of wire
• mechanical stretch and stiffness of wire
• precision of position detection - the error obtained in coordinates of the
plumb wire which is consecutively transmitted to the calculated positions
of the other points since the offsets were taken from the plumb wire

The rotational oscillation of the plumb bob is overlapped by longitudinal


oscillations of the wire. If these are asymmetric to the pendulum oscillation, then
additional movements are induced, this can then cause a significant shift of the
apparent rest position if measures are not put in place to eliminate them.

Precaution

The following precautions were taken to reduce if not eliminate the above-
mentioned errors as much as possible. Other precautions were taken for safety
reasons and workload reduction involved.

Survey Department 5 8/3/2007


DETAIL SURVEY

• A thorough inspection was done to make sure the plumb wires and as the
plumb bobs touched nothing. This was done to ensure the plumb wires
from which the plumb bobs were suspended pointed directly to the earth's
center of gravity; used to determine the true vertical from a given point.
• The rotational oscillation of the plumb bob and longitudinal oscillations of
the wire were taken care of by damping the heavy weighted bobs in highly
viscous oil.
• Heavy plumb bobs were hung on thin wires to make the wires taut. This
eliminates errors introduced by mechanical stretch and stiffness of wire
and that of the thickness of wire. This also ensures verticality of plumb
wires.
• The plumb wires were guarded from any disturbances since any
displacement in the wire will cause an error in the readings taken.
• The position of the plumb wires were measured with utmost accuracy
since a significant error in the coordinates would introduce errors in the
positions of points obtained since the offsets were taken from the plumb
wire.

The following precautionary measures were taken to make work easier and for
safety reasons.
• Polythene bags were used to cover the piano wire to prevent wires from
rusting.
• Smaller plumb bobs were used to lower the wires before replacing with
bigger and heavy plumb bobs.
• Eye bolts were fixed to each plumb line at sets 2 and 10 of a vertical
distance of 14.095m to serve as guide in case any displacements.
• A wooden platform built to form a base for drums containing the oil to be
used for damping and falling objects from finding the underlying bottom of
the shaft.

Survey Department 6 8/3/2007


DETAIL SURVEY

Set-Up

A reconnaissance survey was undertaken to determine appropriate points where


all plumb lines could be seen to establish controls.

Piano wires coiled around a winch as shown in figure 2.1 and fixed to a wooden
board - to ensure stability and firm grip to the ground - were stationed close to
the corners of the compartment to be measured. The plumb wires were lowered
with the help of light weighted bobs from the starting base station (surface collar,
9, 17, and 24 level gangways) to their corresponding destination base stations (9,
17, 24 and 30 level gangways) respectively.

A wooden platform was built four (4) sets below the corresponding destination
level within the specified compartment to form a worktable for drums containing
the oil to be used for damping and also prevent falling objects from getting to the
shaft bottom.

The light plumb bobs were replaced with the heavy ones to make the wires
adequately taut. The plumb bobs were dampened by putting them in the drum of
oil.

Figures 5-1, 5-4 and 5-5 show a diagram of the shaft compartments and the
general set-up for the plumb lines.

Figure 2-1 Set-up of the Pulley for the Piano Wires

Survey Department 7 8/3/2007


DETAIL SURVEY

Measurements

After the plumb wires had been set-up, an inspection was again conducted to
make sure the wires were hanging freely. Some few minutes was allowed to
elapse to make sure the wire and bob are in a state of equilibrium.

Perpendicular offsets were then taken from the plumb wires on the northern and
southern side of the shaft to their respective north and south wall plates, north
and south walls, end plates, dividers and guides.

The observational procedure was repeated for each set down the shaft. The
vertical interval between one shaft set to the next was measured as the cage
moved down. The label mapping code used for the measurement is attached as
table 5-1. Figures 5-2, 5-3, 5-4, and 5-5 show diagrams of the set-ups for the
various modes of measurement. The same measurement procedure and code
format were used for all the phases.

The coordinates of the plumb wires were then measured with a total station to be
used to compute the coordinates of the various components of the shaft lining.

The positional set-up of the plumb lines was altered and thus giving the different
sets of offset readings. The calculations involved are outlined as equations 2, 3,
4, 5, and 6.

Survey Department 8 8/3/2007


DETAIL SURVEY

OBSERVATIONS

• The shaft lining from surface to three (3) level were intact due to its
concrete walls.
• From three (3) level to nine (9) level had good sets with a couple of
corroded ones with some portions replaced with buntons.
• A vertical plane put through the middle of the shaft’s DTM from surface to
9 level was within limit.
• The vertical alignment of the shaft sets from surface to 17 level was
skewed towards the west up to thirty centimeters (30cm) in an average
gradient of 0.0414% ( 1 in 0.0004141) as its depth increased down the
shaft.
• Most of the sets between 12 and 16 level were worn-out.
• The plumb wires hanged from 9 to 17 level at the transferred position of
the plumb wires from surface to 9 level touched most of the shaft sets
between 12 and 15 levels.
• There was so much water in the shaft.

Survey Department 9 8/3/2007


DETAIL SURVEY

DISCUSSION AND CONCLUSION

Survey Department 10 8/3/2007


DETAIL SURVEY

RECOMMENDATION

Survey Department 11 8/3/2007


Not drawn to scale
No 1 Compartment No 2 Compartment No 3 Compartment No 4 Compartment

E C
N
A

Plumb line F D
Ladder way Pipes and Cables Vent
3 2 1
B

Shaft Walls South Wall Plate Dividers Cage Guide North Wall Plate Plumb Wires

Figure 2 Central Shaft Compartments from Surface to 30 Level (Plan View)

Not drawn to scale

12
Plumb Wires

AN2 AN1 CN2 CN1


A
N
C EN1 EN2 E
GN2 GN1 IN1 IN2
G I
AG CG
E
EG2
EG1 C GG
A IG

B DPlumb lineDS2 F HB
BS2 BS1 DS1 F
FS1 FS2 D HS1 HS2 JS1 JS2
J
3 2 1

Figure 3 Plumb Wires Installed from Surface Collar to nine Level and Code for their Corresponding North and South Offsets (Plan View)

Not drawn to scale


13
AW1 GW 1E2
AW2 CE EE IE1

A C E G I

E C A

F H J

B D
Plumb line F D
3 2 1
B

FE HW
BW1 JE1 JE2
BW2 DE

Figure 4 Positions of Plumb Wires Installed From Surface Collar to nine Level And Code for their Corresponding East and West Offsets
(Plan View)

Not drawn to scale

14
A C
N
E G

E C A

H
D F
B
Plumb line F D
3 2 1
B

Figure 5 Positions of Plumb Wires Installed from 9 Level to 30 Level (Plan View)

15
FROM PLUMB TO POSITION CODE FROM PLUMB TO POSITION CODE
WIRE WIRE

A North Wall plate AN1 F South Wall FS2

A North Wall AN2 F East Divider Set FE

A West End plate AW1 G North Wall plate GN1

A West Wall AW2 G North Wall GN2

A Guide AG G West Divider Set GW

B South Wall Plate BS1 G Guide GG

B South Wall BS2 H South Wall Plate HS1

B Western end plate BW1 H South Wall HS2

B Western wall BW2 H West Divider Set HW

C North Wall plate CN1 I North Wall plate IN1

C North Wall CN2 I North Wall IN2

C East Divider Set CE I East End plate IE1

C Guide CG I East Wall IE2

D South Wall Plate DS1 I Guide IG

D South Wall DS2 J South Wall Plate JS1

D East Divider Set DE J South Wall JS2

E North Wall plate EN1 J East End Plate JE1

E North Wall EN2 J East Wall JE2

E East End plate EE

E Guide EG

F South Wall Plate FS1

Table 1 Plumb Wires and their Corresponding Codes for Measurement

16
Equation 1
divergence = 0.00 ft − 0.10 ft (30 .00 mm ) for every 4000 ft (1220m)

30 mm
If 1220 ≈ 30 , then x= × 275 m
1220 m

∴x = 6.80mm

KEY WORDS

Shaft or Cage guides

Conductor made of wood, iron or steel, or wire rope; used to guide the cages in the shaft and
to prevent them from swinging and colliding with each other while in motion.

Shaft inset

The point where a horizontal tunnel intersects a shaft.

Shaft lining

17
The timber, steel, brick, or concrete structure fixed around a shaft to support the walls. In
modern shafts, a concrete lining is generally favored as a permanent shaft support.

Shaft mine

A mine in which the vein is reached by a vertical shaft which may vary in depth from less than
100 ft (30 m) to several thousand feet.

Or a mine in which the main entry or access is by means of a shaft.


Shaft pillar

A solid block of ore left around the shaft where it crosses the lode, for protection against earth
movement.

Shaft plumbing

The operation of transferring one or more points at the surface of a vertical shaft to plumb line
positions at the bottom of the shaft; a method to ensure that a shaft is sunk in the true vertical
line.

Survey operation in which the orientation of two plumb bobs is measured both at the surface
and at depth in order to transfer the bearing underground.

Shaft section

A drawing or log giving details of the structure and the nature of strata intersected by a shaft.

Shaft set

A Supporting frame of timber, masonry, or steel that supports the sides


of a shaft and the gear; Composed of two wall plates, two end plates, and
dividers that form shaft compartments.

A system of mine timbering similar to square sets. The shaft sets are placed from the surface
downward, each new set supported from the set above until it is blocked in place. New wall
plates are suspended from those of the set above by hanging bolts. Blocking, wedging, and

18
lagging complete the work of timbering. At stations, the shaft posts are made much longer
than usual to give ample headroom for unloading timber and other supplies.

Shaft signal

Code of electric ringing, or for shallow depths, knocking, among the onsetter or hitcher at the
shaft bottom, the banksman at the top, and the engineman who operates the winder. Signals
inform the latter as to type of load, etc. A telephone is also installed.

Tensile Strain

Deformation along a line segment that increases in length when a load is applied along that
line.

Tensile stress

The stress state leading to expansion; that is, the may be increased until the reach of tensile
strength, namely the limit state of stress.

The formula for computing the tensile stress in a wire is:

Where σ is the tensile stress, F is the tensile force over the rod and A is the cross-sectional
area of the rod.
Units for tensile stress are newtons per square meter (N/m², also called Pascals, Pa)

19

Вам также может понравиться