Daily Information of 63/100 kVA Distribution Transform

No. of Dist. Trans. failed & No. of Dist. Trans.


Replaced from 01.04.2014 to on stock as on
13.11.2014. 1.11.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.

Balance to
Failed Replaced New Repair
be replace

63 KVA 32 32 0 0 0
1 PALGHAR
100 KVA 91 91 0 3 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New DTC issued to Palghar(W) from Palghar division stores, 100 KVA 01 Nos
22) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 30.09.2014.
23) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 02.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 01.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 07.10.2014.
25) 100KVA 01 Nos New dtc issued to Jawhar subdivision as on 10.10.2014.
26) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 09.10.2014.
27) 100KVA 01 Nos dtc issued to Vikramgad subdivision as on 15.10.2014 received from Parol S
28) 100KVA 01 Nos New dtc issued to Choradi, 63KVA 3Nos issued to Jawhar section,100KVA 1
29) same as above
30) 100KVA 01 Nos , 63KVA 01 Nos NWGP repair dtc issued to Vikramgad subdivision as on 28.1
31) same as above
32) 100 KVA 02 Nos New DTC issued to Dhanu,Aashagad section , 100KVA 01 Nos New DTC issu
33) 100 KVA 02 Nos New DTC issued to Dhanu as on 31.10.2014
34) 100 KVA 01 Nos, 63 KVA 01 Nos Repair DTC issued to Mokhada as on 03.11.2014
35) same as above
36) 100 KVA 01 Nos New DTC issued to Chinchani Boisor [R], as on 07.11.2014
37) 100 KVA 01 Nos NWGP Repair DTC issued to Vikramgad ,as on 10.11.2014
37) 100 KVA 01 Nos NWGP Repair DTC issued to Dhanu Section as on 13.11.2014
Transformer as on DTD. 14.11.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 13.11.2014. on 01.04.2014 to
13.11.2014. 13.11.2014. 13.11.2014.

17 0 173 7
24 0 214 31

Capacity Jobs on Subdivision level.


t Sawarkhand Sec. of Palghar S/dn.
4 at Dahanu S/dn.
ikramgad S/dn.

ikramgad S/dn.
4 at Dahanu S/dn.
014 at Dahanu S/dn.
er guarantee period as on 13.09.2014 at Dahanu S/dn.
eplacement of failed DTC and 01 balance at Filter Unit.

er guarantee period as on 23.09.2014 at Boisar-R S/dn.

akhare kothrapada DTC no 4159664 on 25.09.2014.


0 KVA 01 Nos New DTC issued to Dahanu (Kosbad) as on 27.09.2014.

d from Parol Store.


tion,100KVA 1Nos issued to vikramgad, 63KVA 1Nos issued to Mokhada as on 18.10.2014 received from
ion as on 28.10.2014.

New DTC issued to Boisor [R],Saravali subdivision as on 30.10.2014.


ed to Mokhada as on 18.10.2014 received from Parol Store.
Daily Information of 63/100 kVA Distribution Transform

No. of Dist. Trans. failed & No. of Dist. Trans.


Replaced from 01.04.2014 to on stock as on
7.11.2014. 7.11.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.

Balance to
Failed Replaced New Repair
be replace

63 KVA 32 32 0 0 0
1 PALGHAR
100 KVA 90 90 0 4 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New DTC issued to Palghar(W) from Palghar division stores, 100 KVA 01 Nos
22) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 30.09.2014.
23) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 02.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 01.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 07.10.2014.
25) 100KVA 01 Nos New dtc issued to Jawhar subdivision as on 10.10.2014.
26) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 09.10.2014.
27) 100KVA 01 Nos dtc issued to Vikramgad subdivision as on 15.10.2014 received from Parol S
28) 100KVA 01 Nos New dtc issued to Choradi, 63KVA 3Nos issued to Jawhar section,100KVA 1
29) same as above
30) 100KVA 01 Nos , 63KVA 01 Nos NWGP repair dtc issued to Vikramgad subdivision as on 28.1
31) same as above
32) 100 KVA 02 Nos New DTC issued to Dhanu,Aashagad section , 100KVA 01 Nos New DTC issu
33) 100 KVA 02 Nos New DTC issued to Dhanu as on 31.10.2014
34) 100 KVA 01 Nos, 63 KVA 01 Nos Repair DTC issued to Mokhada as on 03.11.2014
35) same as above
36) 100 KVA 01 Nos New DTC issued to Chinchani Boisor [R], as on 07.11.2014
37) 100 KVA 01 Nos NWGP Repair DTC issued to Vikramgad ,as on 10.11.2014
Transformer as on DTD. 10.11.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 7.11.2014. on 7.11.2014. 01.04.2014 to
7.11.2014. 7.11.2014.

17 0 173 7
24 0 213 31

Capacity Jobs on Subdivision level.


t Sawarkhand Sec. of Palghar S/dn.
4 at Dahanu S/dn.
ikramgad S/dn.

ikramgad S/dn.
4 at Dahanu S/dn.
014 at Dahanu S/dn.
er guarantee period as on 13.09.2014 at Dahanu S/dn.
eplacement of failed DTC and 01 balance at Filter Unit.

er guarantee period as on 23.09.2014 at Boisar-R S/dn.

akhare kothrapada DTC no 4159664 on 25.09.2014.


0 KVA 01 Nos New DTC issued to Dahanu (Kosbad) as on 27.09.2014.

d from Parol Store.


tion,100KVA 1Nos issued to vikramgad, 63KVA 1Nos issued to Mokhada as on 18.10.2014 received from
ion as on 28.10.2014.

New DTC issued to Boisor [R],Saravali subdivision as on 30.10.2014.


ed to Mokhada as on 18.10.2014 received from Parol Store.
Daily Information of 63/100 kVA Distribution Transform

No. of Dist. Trans. failed & No. of Dist. Trans.


Replaced from 01.04.2014 to on stock as on
13.10.2014. 13.10.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.

Balance to
Failed Replaced New Repair
be replace

63 KVA 26 26 0 0 0
1 PALGHAR
100 KVA 78 78 0 1 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New DTC issued to Palghar(W) from Palghar division stores, 100 KVA 01 Nos
22) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 30.09.2014.
23) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 02.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 01.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 07.10.2014.
25) 100KVA 01 Nos New dtc issued to Jawhar subdivision as on 10.10.2014.
26) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 09.10.2014.
ution Transformer as on DTD. 13.10.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 13.10.2014. on 01.04.2014 to
13.10.2014. 13.10.2014. 13.10.2014.

18 0 167 7
26 0 202 31

Higher Capacity Jobs on Subdivision level.


.2014 at Sawarkhand Sec. of Palghar S/dn.
08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.

ate under guarantee period as on 23.09.2014 at Boisar-R S/dn.

S/D at Sakhare kothrapada DTC no 4159664 on 25.09.2014.


ores, 100 KVA 01 Nos New DTC issued to Dahanu (Kosbad) as on 27.09.2014.
Daily Information of 63/100 kVA Distribution Transform

No. of Dist. Trans. failed & No. of Dist. Trans.


Replaced from 01.04.2014 to on stock as on
08.10.2014. 08.10.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.

Balance to
Failed Replaced New Repair
be replace

63 KVA 26 26 0 0 0
1 PALGHAR
100 KVA 76 76 0 3 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New DTC issued to Palghar(W) from Palghar division stores, 100 KVA 01 Nos
22) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 30.09.2014.
23) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 02.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 01.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 07.10.2014.
ution Transformer as on DTD. 08.10.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 08.10.2014. on 01.04.2014 to
08.10.2014. 08.10.2014. 08.10.2014.

18 0 167 7
26 0 200 31

Higher Capacity Jobs on Subdivision level.


.2014 at Sawarkhand Sec. of Palghar S/dn.
08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.

ate under guarantee period as on 23.09.2014 at Boisar-R S/dn.

S/D at Sakhare kothrapada DTC no 4159664 on 25.09.2014.


ores, 100 KVA 01 Nos New DTC issued to Dahanu (Kosbad) as on 27.09.2014.
Daily Information of 63/100 kVA Distribution Transform

No. of Dist. Trans. failed & No. of Dist. Trans.


Replaced from 01.04.2014 to on stock as on
06.10.2014. 06.10..2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.

Balance to
Failed Replaced New Repair
be replace

63 KVA 26 26 0 0 0
1 PALGHAR
100 KVA 75 75 0 4 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New DTC issued to Palghar(W) from Palghar division stores, 100 KVA 01 Nos
22) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 30.09.2014.
23) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 02.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 01.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 07.10.2014.
ution Transformer as on DTD. 07.10.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 06.10.2014. on 01.04.2014 to
06.10.2014. 06.10.2014. 06.10.2014.

18 0 167 7
26 0 199 31

Higher Capacity Jobs on Subdivision level.


.2014 at Sawarkhand Sec. of Palghar S/dn.
08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.

ate under guarantee period as on 23.09.2014 at Boisar-R S/dn.

S/D at Sakhare kothrapada DTC no 4159664 on 25.09.2014.


ores, 100 KVA 01 Nos New DTC issued to Dahanu (Kosbad) as on 27.09.2014.
Daily Information of 63/100 kVA Distribution Transform

No. of Dist. Trans. failed & No. of Dist. Trans.


Replaced from 01.04.2014 to on stock as on
06.10.2014. 06.10..2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.

Balance to
Failed Replaced New Repair
be replace

63 KVA 26 26 0 0 0
1 PALGHAR
100 KVA 74 74 0 5 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New DTC issued to Palghar(W) from Palghar division stores, 100 KVA 01 Nos
22) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 30.09.2014.
23) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 02.10.2014.
24) 100KVA 01 Nos New dtc issued to Dahanu subdivision as on 01.10.2014.
ution Transformer as on DTD. 06.10.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 06.10.2014. on 01.04.2014 to
06.10.2014. 06.10.2014. 06.10.2014.

18 0 167 7
26 0 198 31

Higher Capacity Jobs on Subdivision level.


.2014 at Sawarkhand Sec. of Palghar S/dn.
08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.

ate under guarantee period as on 23.09.2014 at Boisar-R S/dn.

S/D at Sakhare kothrapada DTC no 4159664 on 25.09.2014.


ores, 100 KVA 01 Nos New DTC issued to Dahanu (Kosbad) as on 27.09.2014.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
30.09.2014. 30.09.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 26 26 0 0 0
1 PALGHAR
100 KVA 72 72 0 7 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New DTC issued to Palghar(W) from Palghar division stores, 100 KVA 01 Nos
22) 100KVA 01 Nos New dtc issued to Boisar-R subdivision as on 30.09.2014.
ution Transformer as on DTD. 30.09.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 30.09.2014. on 01.04.2014 to
30.09.2014. 30.09.2014. 30.09.2014.

18 0 167 7
26 0 196 31

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.

ate under guarantee period as on 23.09.2014 at Boisar-R S/dn.

S/D at Sakhare kothrapada DTC no 4159664 on 25.09.2014.


ores, 100 KVA 01 Nos New DTC issued to Dahanu (Kosbad) as on 27.09.2014.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
29.09.2014. 29.09.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 26 26 0 0 0
1 PALGHAR
100 KVA 72 72 0 7 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
20) 100KVA 01 Nos failed replaced against New WGP 63KVA For Talasari S/D at Sakhare kothra
21) 100KVA 01 Nos New WGP issued to Palghar(w) from Palghar division stores, 100KVA 01 Nos
ution Transformer as on DTD. 29.09.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 29.09.2014. on 01.04.2014 to
29.09.2014. 29.09.2014. 29.09.2014.

18 0 167 7
26 0 196 31

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.

ate under guarantee period as on 23.09.2014 at Boisar-R S/dn.

S/D at Sakhare kothrapada DTC no 4159664 on 25.09.2014.


ores, 100KVA 01 Nos New WGP issued to dhanu (Kosbad) as on 28.09.2014.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
23.09.2014. 23.09.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 26 26 0 0 0
1 PALGHAR
100 KVA 68 68 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
17) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
18) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
19) 63 KVA 01 Nos. New WGP DTC Replaced on 23.09.2014.
ution Transformer as on DTD. 23.09.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 23.09.2014. on 01.04.2014 to
23.09.2014. 23.09.2014. 23.09.2014.

18 0 168 7
26 0 192 31

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.

ate under guarantee period as on 23.09.2014 at Boisar-R S/dn.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
17.09.2014. 17.09.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 25 25 0 0 0
1 PALGHAR
100 KVA 67 67 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
16) 63 KVA 01 Nos. & 04 Nos. 100 KVA New WGP DTC Replaced.
ution Transformer as on DTD. 17.09.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 17.09.2014. on 01.04.2014 to
17.09.2014. 17.09.2014. 17.09.2014.

18 0 167 7
26 0 192 31

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
13.09.2014. 13.09.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 24 24 0 0 0
1 PALGHAR
100 KVA 63 63 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC Accurate under guarantee
16) 63 KVA 02 Nos. DTC received from Agency as on 15.09.2014. 01 DTC used for replacement o
ution Transformer as on DTD. 13.09.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 13.09.2014. on 01.04.2014 to
13.09.2014. 13.09.2014. 13.09.2014.

18 0 166 7
26 0 188 31

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
ate under guarantee period as on 13.09.2014 at Dahanu S/dn.
ed for replacement of failed DTC and 01 balance at Filter Unit.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
03.08.2014. 03.09.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 24 24 0 0 0
1 PALGHAR
100 KVA 63 63 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 63 KVA 1 Nos. of DTC replaced by 63 KVA New WGP Repaire DTC as on 30.08.2014 at Palgh
ution Transformer as on DTD. 03.09.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 03.09.2014. on 01.04.2014 to
03.09.2014. 03.09.2014. 03.09.2014.

18 0 166 7
25 0 188 31

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
n 30.08.2014 at Palghar S/dn
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
03.08.2014. 03.09.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 23 23 0 0 0
1 PALGHAR
100 KVA 61 61 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 63 KVA 1 Nos. of DTC replaced by 63 KVA New WGP Repaire DTC as on 30.08.2014 at Palgh
ution Transformer as on DTD. 03.09.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 03.09.2014. on 01.04.2014 to
03.09.2014. 03.09.2014. 03.09.2014.

18 0 165 6
25 0 187 30

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
n 30.08.2014 at Palghar S/dn
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
30.08.2014. 30.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 23 23 0 0 0
1 PALGHAR
100 KVA 59 59 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
15) 63 KVA 1 Nos. of DTC replaced by 63 KVA New WGP Repaire DTC as on 30.08.2014 at Palgh
ution Transformer as on DTD. 30.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 30.08.2014. on 01.04.2014 to
30.08.2014. 30.08.2014. 30.08.2014.

18 0 165 6
26 0 185 29

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
n 30.08.2014 at Palghar S/dn
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
28.08.2014. 28.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 22 22 0 0 0
1 PALGHAR
100 KVA 59 59 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
ution Transformer as on DTD. 28.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 28.08.2014. on 01.04.2014 to
28.08.2014. 28.08.2014. 28.08.2014.

18 0 164 6
26 0 185 29

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
27.08.2014. 27.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 22 22 0 0 0
1 PALGHAR
100 KVA 59 59 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
14) 100 KVA 1 Nos. of DTC replaced by 100 KVA Repaire agency DTC as on 26.08.2014 at Dahan
ution Transformer as on DTD. 27.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 27.08.2014. on 01.04.2014 to
27.08.2014. 27.08.2014. 27.08.2014.

18 0 164 6
26 0 185 29

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
26.08.2014 at Dahanu S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
21.08.2014. 21.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 22 22 0 0 0
1 PALGHAR
100 KVA 58 57 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
13) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 23.08.2014 at Dahanu S
ution Transformer as on DTD. 23.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 21.08.2014. on 01.04.2014 to
21.08.2014. 21.08.2014. 21.08.2014.

18 0 164 6
27 0 184 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


08.2014 at Dahanu S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
21.08.2014. 21.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 22 22 0 0 0
1 PALGHAR
100 KVA 57 56 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
12) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on22.08.2014 at Vikramgad S/dn
ution Transformer as on DTD. 21.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 21.08.2014. on 01.04.2014 to
21.08.2014. 21.08.2014. 21.08.2014.

18 0 164 6
27 0 185 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.

014 at Vikramgad S/dn.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
20.08.2014. 20.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 22 22 0 0 0
1 PALGHAR
100 KVA 56 56 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
11) 1 NO. of DTC's 63 KVA Replaced against failure New WGP 63 KVA.
ution Transformer as on DTD. 20.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 20.08.2014. on 01.04.2014 to
20.08.2014. 20.08.2014. 20.08.2014.

18 0 164 6
27 0 184 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
19.08.2014. 19.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 56 56 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
10) 100 KVA 1 Nos. of DTC replaced by 200 KVA Repaire DTC as on19.08.2014 at Vikramgad S/dn
ution Transformer as on DTD. 19.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 19.08.2014. on 01.04.2014 to
19.08.2014. 19.08.2014. 19.08.2014.

18 0 164 6
27 0 184 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
014 at Vikramgad S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
18.08.2014. 18.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 55 55 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
ution Transformer as on DTD. 18.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 18.08.2014. on 01.04.2014 to
18.08.2014. 18.08.2014. 18.08.2014.

18 0 164 6
27 0 183 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
17.08.2014. 17.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 55 55 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
ution Transformer as on DTD. 17.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 17.08.2014. on 01.04.2014 to
17.08.2014. 17.08.2014. 17.08.2014.

18 0 164 6
27 0 183 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
16.08.2014. 16.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 55 55 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
9) 100 KVA 1 Nos. of DTC replaced by 100 KVA F.U. Repaire DTC as on 16.08.2014 at Dahanu S
ution Transformer as on DTD. 16.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 16.08.2014. on 01.04.2014 to
16.08.2014. 16.08.2014. 16.08.2014.

18 0 164 6
27 0 183 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


08.2014 at Dahanu S/dn.
Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
15.08.2014. 15.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 54 54 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
ution Transformer as on DTD. 15.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 15.08.2014. on 01.04.2014 to
15.08.2014. 15.08.2014. 15.08.2014.

18 0 164 6
27 0 183 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
14.08.2014. 14.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 54 54 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Job
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
9) 25 KVA 1 Nos. of DTC replaced by 63 KVA F.U. Repaire DTC as on 14.08.2014 at Sawarkhand
ution Transformer as on DTD. 14.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 14.08.2014. on 01.04.2014 to
14.08.2014. 14.08.2014. 14.08.2014.

18 0 164 6
27 0 183 28

Higher Capacity Jobs on Subdivision level.

.2014 at Sawarkhand Sec. of Palghar S/dn.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
13.08.2014. 13.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 54 54 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Jobs on Subdivision
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
ution Transformer as on DTD. 13.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 13.08.2014. on 01.04.2014 to
13.08.2014. 13.08.2014. 13.08.2014.

18 0 165 6
27 0 183 28

city Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
12.08.2014. 12.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 21 21 0 0 0
1 PALGHAR
100 KVA 54 54 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Jobs on Subdivision
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
8) 63 KVA 3 Nos. of DTC replaced by New WGP.
ution Transformer as on DTD. 12.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 12.08.2014. on 01.04.2014 to
12.08.2014. 12.08.2014. 12.08.2014.

18 0 165 6
27 0 183 28

city Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
08.08.2014. 08.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 18 18 0 0 0
1 PALGHAR
100 KVA 54 54 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Jobs on Subdivision
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
ution Transformer as on DTD. 08.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 08.08.2014. on 01.04.2014 to
08.08.2014. 08.08.2014. 08.08.2014.

18 0 162 6
27 0 183 28

city Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
07.08.2014. 07.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 15 15 0 0 3
1 PALGHAR
100 KVA 54 54 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Jobs on Subdivision
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
ution Transformer as on DTD. 07.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 07.08.2014. on 01.04.2014 to
07.08.2014. 07.08.2014. 07.08.2014.

18 0 159 6
27 0 183 28

city Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
06.08.2014. 06.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 14 14 0 0 4
1 PALGHAR
100 KVA 53 53 0 0 1

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Jobs on Subdivision
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
7) 100KVA failed T/F replaced by new wgp 100KVA.
ution Transformer as on DTD. 06.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 06.08.2014. on 01.04.2014 to
06.08.2014. 06.08.2014. 06.08.2014.

18 0 158 6
27 0 182 28

city Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
05.08.2014. 05.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 14 14 0 0 1
1 PALGHAR
100 KVA 52 52 0 0 1

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher Capacity Jobs on Subdivision
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Manor s/s.
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
6) 100 KVA DTC issued against 200 KVA DTC failure to Dahanu Subdivision.
ution Transformer as on DTD. 05.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 05.08.2014. on 01.04.2014 to
05.08.2014. 05.08.2014. 05.08.2014.

18 0 158 6
27 0 181 28

city Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
04.08.2014. 04.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 14 14 0 0 1
1 PALGHAR
100 KVA 52 52 0 0 2

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher C
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Mano
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
ution Transformer as on DTD. 04.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 04.08.2014. on 01.04.2014 to
04.08.2014. 04.08.2014. 04.08.2014.

18 0 158 6
27 0 181 28

ntation of Higher Capacity Jobs on Subdivision level.

33/22/11 KV Manor s/s.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
03.08.2014. 03.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 13 13 0 0 0
1 PALGHAR
100 KVA 51 51 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher C
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Mano
4)' 03 nos 63kva failed t/f replaced by 100 kva nwgp repaired tf.
5) 03 100 kva FAILE t/f REPLACE BY 100 kva new WGP T/F repaired t/f
ution Transformer as on DTD. 03.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 03.08.2014. on 01.04.2014 to
03.08.2014. 03.08.2014. 03.08.2014.

18 0 157 4
27 0 180 24

ntation of Higher Capacity Jobs on Subdivision level.

33/22/11 KV Manor s/s.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
02.08.2014. 02.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 10 10 0 0 0
1 PALGHAR
100 KVA 48 48 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher C
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Mano
ution Transformer as on DTD. 02.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 02.08.2014. on 01.04.2014 to
02.08.2014. 02.08.2014. 02.08.2014.

18 0 154 4
27 0 177 24

ntation of Higher Capacity Jobs on Subdivision level.

33/22/11 KV Manor s/s.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
01.08.2014. 01.08.2014.
Sr. Name of Circle / Capacity of
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace

63 KVA 10 10 0 0 0
1 PALGHAR
100 KVA 48 48 0 0 0

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher C
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Mano
ution Transformer as on DTD. 01.08.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 01.08.2014. on 01.04.2014 to
01.08.2014. 01.08.2014. 01.08.2014.

18 0 154 4
27 0 177 24

ntation of Higher Capacity Jobs on Subdivision level.

33/22/11 KV Manor s/s.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 31.7.2014. 31.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 10 10 0 0 0
1 PALGHAR
100 KVA 47 47 0 0 1

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher C
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
3) 1 NO. of DTC's 63 KVA Replaced against failure by 100 KVA at 33/22/11 KV Mano
ution Transformer as on DTD. 31.07.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 31.7.2014. on 31.7.2014. 01.04.2014 to
31.7.2014. 31.7.2014.

18 0 154 4
27 0 176 24

ntation of Higher Capacity Jobs on Subdivision level.

33/22/11 KV Manor s/s.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 30.7.2014. 30.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 9 9 0 0 0
1 PALGHAR
100 KVA 46 46 0 0 3

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher C
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
ution Transformer as on DTD. 30.07.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 30.7.2014. on 30.7.2014. 01.04.2014 to
30.7.2014. 30.7.2014.

18 0 153 4
27 0 175 24

ntation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 28.7.2014. 28.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 9 9 0 0 0
1 PALGHAR
100 KVA 45 45 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 27 27 0 8 7
CIRCLE 100 KVA 66 66 0 1 3

Note :-
1) 3 Nos. of DTC's replaced by spare jobs by section after augmentation of Higher C
2) 1 NO. of DTC's 100 KVA Replaced against failure New WGP 100 KVA.
ution Transformer as on DTD. 28.07.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as 28.7.2014. on 28.7.2014. 01.04.2014 to
on28.7.2014. 28.7.2014.

18 0 153 4
27 0 174 24
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 205 26
33 0 220 37

ntation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transform
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 26.7.2014. 26.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 9 9 0 0 0
1 PALGHAR
100 KVA 44 44 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 27 27 0 8 7
CIRCLE 100 KVA 65 65 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


ution Transformer as on DTD. 26.07.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 26.7.2014. on 26.7.2014. 01.04.2014 to
26.7.2014. 26.7.2014.

18 0 153 4
27 0 173 24
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 205 26
33 0 219 37

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 25.7.2014. 25.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 9 9 0 0 0
1 PALGHAR
100 KVA 44 44 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 27 27 0 8 7
CIRCLE 100 KVA 65 65 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 25.07.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 25.7.2014. on 25.7.2014. 01.04.2014 to
25.7.2014. 25.7.2014.

18 0 153 4
27 0 173 24
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 205 26
33 0 219 37

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 24.7.2014. 24.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 9 9 0 0 0
1 PALGHAR
100 KVA 44 44 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 27 27 0 8 7
CIRCLE 100 KVA 65 65 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 24.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 24.7.2014. on 24.7.2014. 01.04.2014 to
24.7.2014. 24.7.2014.

18 0 153 4
27 0 173 24
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 205 26
33 0 219 37

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 23.7.2014. 23.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 9 9 0 0 0
1 PALGHAR
100 KVA 44 44 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 27 27 0 8 7
CIRCLE 100 KVA 65 65 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 23.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 23.7.2014. on 23.7.2014. 01.04.2014 to
23.7.2014. 23.7.2014.

18 0 153 4
27 0 173 24
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 205 26
33 0 219 37

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 22.7.2014. 22.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 9 9 0 0 0
1 PALGHAR
100 KVA 44 44 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 27 27 0 8 7
CIRCLE 100 KVA 65 65 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 22.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 22.7.2014. on 22.7.2014. 01.04.2014 to
22.7.2014. 22.7.2014.

18 0 153 4
27 0 173 24
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 205 26
33 0 219 37

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 20.7.2014. 20.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 8 0 0 0
1 PALGHAR
100 KVA 42 42 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 26 0 8 7
CIRCLE 100 KVA 63 63 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 20.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 20.7.2014. on 20.7.2014. 01.04.2014 to
20.7.2014. 20.7.2014.

18 0 152 4
28 0 171 23
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 204 26
34 0 217 36

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 19.7.2014. 19.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 8 0 0 0
1 PALGHAR
100 KVA 42 42 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 26 0 8 7
CIRCLE 100 KVA 63 63 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 19.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 19.7.2014. on 19.7.2014. 01.04.2014 to
19.7.2014. 19.7.2014.

18 0 152 4
28 0 171 23
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 204 26
34 0 217 36

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 18.7.2014. 18.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 8 0 0 0
1 PALGHAR
100 KVA 42 42 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 26 0 8 7
CIRCLE 100 KVA 63 63 0 1 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 18.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 18.7.2014. on 18.7.2014. 01.04.2014 to
18.7.2014. 18.7.2014.

18 0 152 4
28 0 171 23
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
21 0 204 26
34 0 217 36

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 17.7.2014. 17.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 8 0 0 0
1 PALGHAR
100 KVA 39 39 0 3 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 26 0 8 7
CIRCLE 100 KVA 60 60 0 4 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 17.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 17.7.2014. on 17.7.2014. 01.04.2014 to
17.7.2014. 17.7.2014.

11 0 159 4
25 0 171 23
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
14 0 211 26
31 0 217 36

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 16.7.2014. 16.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 8 0 0 0
1 PALGHAR
100 KVA 38 38 0 3 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 26 0 8 7
CIRCLE 100 KVA 59 59 0 4 3

Note :- 3 Nos. of DTC's replaced by spare jobs by section after augmentation of H


mer as on DTD. 16.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 16.7.2014. on 16.7.2014. 01.04.2014 to
16.7.2014. 16.7.2014.

11 0 159 4
26 0 170 22
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
14 0 211 26
32 0 216 35

augmentation of Higher Capacity Jobs on Subdivision level.


Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 15.7.2014. 15.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 8 0 0 0
1 PALGHAR
100 KVA 35 35 0 0 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 26 0 8 7
CIRCLE 100 KVA 56 56 0 1 3
mer as on DTD. 15.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 15.7.2014. on 15.7.2014. 01.04.2014 to
15.7.2014. 15.7.2014.

11 0 159 4
26 0 168 21
3 0 16 0
5 0 19 0
0 0 36 22
1 0 27 13
14 0 211 26
32 0 214 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 14.7.2014. 14.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 34 34 0 6 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 23 3 8 7
CIRCLE 100 KVA 55 55 0 7 3
mer as on DTD. 14.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 14.7.2014. on 14.7.2014. 01.04.2014 to
14.7.2014. 14.7.2014.

11 0 159 4
26 0 167 21
3 0 16 0
3 0 22 0
0 0 36 22
1 0 27 13
14 0 211 26
30 0 216 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 10.7.2014. 10.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 32 32 0 8 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 23 3 8 7
CIRCLE 100 KVA 53 53 0 9 3
mer as on DTD. 10.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 10.7.2014. on 10.7.2014. 01.04.2014 to
10.7.2014. 10.7.2014.

11 0 159 4
26 0 166 21
3 0 16 0
3 0 22 0
0 0 36 22
1 0 27 13
14 0 211 26
30 0 215 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 9.7.2014. 9.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 31 31 0 9 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 23 3 8 7
CIRCLE 100 KVA 52 52 0 10 3
mer as on DTD. 9.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 97.2014. on 9.7.2014. 01.04.2014 to
9.7.2014. 9.7.2014.

11 0 158 4
26 0 164 21
3 0 16 0
3 0 22 0
0 0 36 22
1 0 27 13
14 0 210 26
30 0 213 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 8.7.2014. 8.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 30 30 0 10 8
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 23 3 8 7
CIRCLE 100 KVA 51 51 0 11 11
mer as on DTD. 8.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 8.7.2014. on 8.7.2014. 01.04.2014 to
8.7.2014. 8.7.2014.

11 0 158 4
26 0 162 21
3 0 16 0
3 0 22 0
0 0 36 22
1 0 27 13
14 0 210 26
30 0 211 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 7.7.2014. 7.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 30 30 0 10 8
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 14 14 0 0 6
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 26 23 3 8 7
CIRCLE 100 KVA 51 51 0 11 11
mer as on DTD. 7.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 7.7.2014. on 7.7.2014. 01.04.2014 to
7.7.2014. 7.7.2014.

11 0 158 4
26 0 162 21
3 0 16 0
3 0 22 0
0 0 36 22
1 0 27 13
14 0 210 26
30 0 211 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 6.7.2014. 6.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 30 30 0 10 8
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 13 13 0 0 7
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 25 22 3 8 8
CIRCLE 100 KVA 51 51 0 11 11
mer as on DTD. 6.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 6.7.2014. on 6.7.2014. 01.04.2014 to
6.7.2014. 6.7.2014.

11 0 158 4
26 0 162 21
3 0 16 0
3 0 22 0
0 0 35 22
1 0 27 13
14 0 209 26
30 0 211 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 4.7.2014. 4.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 26 26 0 10 8
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 8
3 VASAI
100 KVA 16 16 0 0 3
63 KVA 24 21 3 8 9
CIRCLE 100 KVA 47 47 0 11 11
mer as on DTD. 4.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 4.7.2014. on 4.7.2014. 01.04.2014 to
4.7.2014. 4.7.2014.

11 0 158 4
26 0 160 21
3 0 16 0
3 0 22 0
0 0 34 22
1 0 27 13
14 0 208 26
30 0 209 34
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 3.7.2014. 3.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 26 26 0 10 8
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 15 15 0 0 1
63 KVA 24 21 3 8 6
CIRCLE 100 KVA 46 46 0 11 9
mer as on DTD. 3.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 3.7.2014. on 3.7.2014. 01.04.2014 to
3.7.2014. 3.7.2014.

11 0 158 4
26 0 160 21
3 0 16 0
3 0 23 0
3 0 34 19
5 0 26 9
17 0 208 23
34 0 209 30
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 2.7.2014. 2.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 26 26 0 10 8
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 15 15 0 0 1
63 KVA 24 21 3 8 6
CIRCLE 100 KVA 46 46 0 11 9
mer as on DTD. 2.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 2.7.2014. on 2.7.2014. 01.04.2014 to
2.7.2014. 2.7.2014.

11 0 158 4
26 0 160 21
3 0 16 0
3 0 23 0
3 0 34 19
5 0 26 9
17 0 208 23
34 0 209 30
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 1.7.2014. 1.7.2014.
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 25 25 0 10 9
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 15 15 0 0 1
63 KVA 24 21 3 8 6
CIRCLE 100 KVA 45 45 0 11 10
mer as on DTD. 1.7.2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 1.7.2014. on 1.7.2014. 01.04.2014 to
1.7.2014. 1.7.2014.

11 0 158 4
26 0 159 21
3 0 16 0
3 0 23 0
3 0 34 19
5 0 26 9
17 0 208 23
34 0 208 30
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 30/06/2014 30/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 24 24 0 10 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 15 15 0 0 1
63 KVA 24 21 3 8 6
CIRCLE 100 KVA 44 44 0 11 1
mer as on DTD. 30/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 30.06.2014 on 30.06.2014 01.04.2014 to
30.06.2014 30.06.2014

11 0 158 4
36 0 158 11
3 0 16 0
3 0 23 0
3 0 34 19
5 0 26 9
17 0 208 23
44 0 207 20
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 29/06/2014 29/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 24 24 0 10 0
63 KVA 4 4 0 8 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 15 15 0 0 1
63 KVA 24 21 3 8 6
CIRCLE 100 KVA 44 44 0 11 1
mer as on DTD. 29/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 29.06.2014 on 29.06.2014 01.04.2014 to
29.06.2014 29.06.2014

11 0 158 4
36 0 158 11
3 0 16 0
3 0 23 0
3 0 34 19
5 0 26 9
17 0 208 23
44 0 207 20
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 27/06/2014 27/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 22 22 0 12 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 14 14 0 0 2
63 KVA 23 20 3 9 6
CIRCLE 100 KVA 41 41 0 13 2
mer as on DTD. 27/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 27.06.2014 on 27.06.2014 01.04.2014 to
27.06.2014 27.06.2014

11 0 158 4
36 0 156 11
3 0 15 0
3 0 23 0
3 0 34 19
5 0 25 9
17 0 207 23
44 0 204 20
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 26/06/2014 26/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 22 22 0 12 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 14 14 0 0 2
63 KVA 23 20 3 9 6
CIRCLE 100 KVA 41 41 0 13 2
mer as on DTD. 26/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 26.06.2014 on 26.06.2014 01.04.2014 to
26.06.2014 26.06.2014

11 0 158 4
36 0 156 11
3 0 15 0
3 0 23 0
3 0 34 19
5 0 25 9
17 0 207 23
44 0 204 20
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 25/06/2014 25/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 5 3 0 0
1 PALGHAR
100 KVA 20 20 0 13 1
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 5 5 0 1 0
63 KVA 12 12 0 0 5
3 VASAI
100 KVA 14 14 0 0 2
63 KVA 23 20 3 9 6
CIRCLE 100 KVA 39 39 0 14 3
mer as on DTD. 25/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 25.06.2014 on 25.06.2014 01.04.2014 to
25.06.2014 25.06.2014

11 0 157 4
36 0 154 11
3 0 15 0
3 0 23 0
3 0 34 19
5 0 25 9
17 0 206 23
44 0 202 20
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 24/06/2014 24/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 8 4 4 0 0
1 PALGHAR
100 KVA 18 18 0 13 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 11 11 0 0 6
3 VASAI
100 KVA 13 13 0 0 3
63 KVA 22 18 4 9 7
CIRCLE 100 KVA 35 35 0 15 3
mer as on DTD. 24/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 24.06.2014 on 24.06.2014 01.04.2014 to
24.06.2014 24.06.2014

11 0 157 4
36 0 153 11
3 0 15 0
3 0 22 0
3 0 33 19
5 0 24 9
17 0 205 23
44 0 199 20
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 23/06/2014 23/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 17 17 0 16 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 11 11 0 0 6
3 VASAI
100 KVA 13 13 0 0 3
63 KVA 21 18 3 9 7
CIRCLE 100 KVA 34 34 0 18 3
mer as on DTD. 23/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 23.06.2014 on 23.06.2014 01.04.2014 to
23.06.2014 23.06.2014

12 0 157 3
37 0 153 10
3 0 15 0
3 0 22 0
3 0 33 19
5 0 24 9
18 0 205 22
45 0 199 19
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 22/06/2014 22/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 17 17 0 16 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 11 11 0 0 6
3 VASAI
100 KVA 13 13 0 0 3
63 KVA 21 18 3 9 7
CIRCLE 100 KVA 34 34 0 18 3
mer as on DTD. 22/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 22.06.2014 on 22.06.2014 01.04.2014 to
22.06.2014 22.06.2014

12 0 157 3
37 0 153 10
3 0 15 0
3 0 22 0
3 0 33 19
5 0 24 9
18 0 205 22
45 0 199 19
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 21/06/2014 21/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 17 17 0 16 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 11 11 0 0 6
3 VASAI
100 KVA 13 13 0 0 3
63 KVA 21 18 3 9 7
CIRCLE 100 KVA 34 34 0 18 3
mer as on DTD. 21/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 21.06.2014 on 21.06.2014 01.04.2014 to
21.06.2014 21.06.2014

12 0 157 3
37 0 153 10
3 0 15 0
3 0 22 0
3 0 33 19
5 0 24 9
18 0 205 22
45 0 199 19
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 20/06/2014 20/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 16 16 0 17 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 10 10 0 0 7
3 VASAI
100 KVA 13 13 0 0 3
63 KVA 20 17 3 9 8
CIRCLE 100 KVA 33 33 0 19 3
mer as on DTD. 20/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 20.06.2014 on 20.06.2014 01.04.2014 to
20.06.2014 20.06.2014

12 0 157 3
37 0 153 10
3 0 15 0
3 0 22 0
3 0 31 19
5 0 21 9
18 0 203 22
45 0 196 19
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 19/06/2014 19/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 13 13 0 0 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 9 9 0 0 8
3 VASAI
100 KVA 12 12 0 0 4
63 KVA 19 16 3 9 9
CIRCLE 100 KVA 29 29 0 2 4
mer as on DTD. 19/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 19.06.2014 on 19.06.2014 01.04.2014 to
19.06.2014 19.06.2014

12 0 155 3
37 0 152 10
3 0 15 0
3 0 22 0
3 0 31 19
5 0 21 9
18 0 201 22
45 0 195 19
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 18/06/2014 18/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 13 13 0 0 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 9 9 0 0 8
3 VASAI
100 KVA 11 11 0 0 5
63 KVA 19 16 3 9 9
CIRCLE 100 KVA 28 28 0 2 5
mer as on DTD. 18/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 18.06.2014 on 18.06.2014 01.04.2014 to
18.06.2014 18.06.2014

12 0 155 3
37 0 152 10
3 0 15 0
3 0 22 0
3 0 31 19
5 0 21 9
18 0 201 22
45 0 195 19
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 17/06/2014 17/06/2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 13 13 0 0 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 4 4 0 2 0
63 KVA 9 9 0 0 8
3 VASAI
100 KVA 11 11 0 0 5
63 KVA 19 16 3 9 9
CIRCLE 100 KVA 28 28 0 2 5
mer as on DTD. 17/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 17.06.2014 on 17.06.2014 01.04.2014 to
17.06.2014 17.06.2014

12 0 155 3
37 0 152 10
3 0 15 0
3 0 22 0
3 0 31 19
5 0 21 9
18 0 201 22
45 0 195 19
Daily Information of 63/100 kVA Distribution Transformer as on DTD.
No. of Dist. Trans. failed & No. of Dist. Trans.
Replaced from 01.04.2014 to on stock as on
Sr. Name of Circle / Capacity of 16.06.2014 16.06.2014
No. Zone Dist. Trans.
Balance to
Failed Replaced New Repair
be replace
63 KVA 7 4 3 0 0
1 PALGHAR
100 KVA 13 12 1 1 0
63 KVA 3 3 0 9 1
2 VIRAR
100 KVA 3 3 0 2 0
63 KVA 9 9 0 0 8
3 VASAI
100 KVA 10 10 0 0 6
63 KVA 19 16 3 9 9
CIRCLE 100 KVA 26 25 1 3 6
mer as on DTD. 16/06/2014.
No. of Dist. Trans. No. of Dist. No. of Dist. No. of Dist. Trans.
lying for repair Trans. lying at Trans. lying at received from repairer
with repairer site as on filter unit as agency from
agency as on 16.06.2014 on 16.06.2014 01.04.2014 to
16.06.2014 16.06.2014

12 0 155 3
37 0 152 10
3 0 15 0
3 0 22 0
9 0 31 13
7 0 21 7
24 0 201 16
47 0 195 17