Академический Документы
Профессиональный Документы
Культура Документы
١) If a stakeholder has any questions about project deliverables, as the PM, you should direct
him to the:
a) WBS
b) Project plan
٢) Your construction project was damaged by an earthquake. Your contractor says that he
cannot fulfil the terms of the contract due to a specific clause you both had signed in the
contract. He is referring to the:
a) Force majeure clause
b) Fixed price clause
c) Contract obligation terms
d) None of the above
٣) Your vendor has confirmed in writing that he will not be able to provide the products
contracted to him, in the time mentioned in the contract. You can terminate the contract and
sue for damages. This is a type of:
a) Minor breach
b) Anticipatory breach
c) Material breach
d) Fundamental breach
٤) As a PM, you manage multiple projects. One of your projects is over budget while the other
is under budget. You decide to transfer money from the latter to the former and report both
projects as within budget. This is against the PMI code of ethics and is called:
a) Unethical management
b) Budget tampering
c) Fraudulent reporting
d) Cost leveling
٥) Your brother can influence bids in the vendor company that has been contracted for your
project. You should:
a) Disclose the bid price that is most likely to make him win
b) Reject other vendors and award him the contract
c) Refrain from the decision-making process and make a full disclosure to stakeholders and wait
for their decision before you proceed
d) Pretend during meetings that you don't know your brother
٦) A project you are managing is about to be completed. But there is a minor defect in the
work produced by the contractor. You should:
a) Neglect the defect if it is trivial
b) Ask the contractor to fix according to SOW
c) Submit a change request
d) None of the above
٧) As a PM, you have identified some low priority risks. You should:
٨) One of your team members' A's father was sick when you were in the planning stage of your
project. A had informed you that he might have to leave to visit his father if the situation
arose. You had planned for this and spoke to the functional manager of your group to provide a
back-up resource, B to be used if necessary.
Now, A has left to see his father and B is filling in for him. But B is taking more than expected
time to get up to speed and this impacts project cost and schedule.
This is an example of a:
a) Residual risk
b) Secondary risk
c) Contingency plan
٩) To motivate your team, you decided to reward a team member who performed well.
This hurt cohesion in the team. You should:
١٠) Your project uses a vendor who has completed ٥٠٪ of the contracted work. You are unsure
of how much to pay the vendor. You should refer to the:
b) Contract
c) Response to bid
d) Statement of work
a) Use random guessing and estimate for all activities as there will be changes anyways
c) Estimate for what the cost will allow and not include buffers
١٢) When there are people from different countries and cultures in a team, the PM should:
١٣) If your business sponsor has an important but minor change to the scope, and he requests
that you make the change without having to process a change request:
d) Request the client that the change management process has to be followed
١٤) If a stakeholder directly asks a team member to make changes and the team member
accomodates it:
a) Admonish the team member during the team meeting so that other team members are also
aware
b) Inform the stakeholder that he should not talk to your team member
c) Talk to the stakeholder and team member in private, and emphasise gently that the
Integrated Change Control process should be followed
١٥) When your client is ready to accept the product your project has produced, you should:
d) Let go off the project resources and assign them to other projects
١٦) Appreciating a team member's good work in front of the team results in:
b) Encouragement for the team member and motivation for other team members
١٧) As the project manager of an important project, you learnt many helpful tools and tips.
What should you do?
b) Archive your learning in the project folder and share with other PMs
١٨) You just found out that the company that you were planning to use in your project is known
for being late in delivering their products that can lead to losses to the project. You decide to
go with a different company to ______ the risk.
a) Mitigate
b) Reject
c) Transfer
d) Avoid
١٩) You are the project manager of a project that involves sensitive information. You are
inviting bids from vendors for some tasks on this project. Since the winning vendor will have
access to the sensitive information, you should:
a) Decide to drop the vendor and instead do the tasks using an internal team
٢٠) A project is behind schedule. Two senior resources are added to help speeden work. The
result is:
c) Project may not be completed on time due to increased number of communication channels
١ Questions ٢١-٤٠
٢٢) Requested changes to scope and recommended corrective action belong to which
process:
a) Scope verification
b) Scope definition
c) Scope control
d) All of the above
٢٣) Scope planning takes place:
a) After requirements are gathered
b) Early in the project
c) After scope is finalized
d) None of the above
٢٦) Qualitative risk analysis is a process that belongs to which process group in Risk
Management:
a) Planning
b) Executing
c) Monitoring
d) Controlling
٢٧) Quantitative risk analysis is a process that belongs to which process group in Risk
Management:
a) Planning
b) Executing
c) Monitoring
d) Controlling
٣٢) A risk is a bad event that will adversely impact the project. This statement is:
a) Always true
b) Always false
c) Sometimes true
d) None of the above
a) i, ii
b) i, ii, iii
c) i, ii, iv
d) None of the above
٣٩) Software Project A took ٥ months to complete. Project B, very similar to Project A will
probably take about ٥ months to complete. This expert judgement technique is:
a) Analogous estimating
b) Critical path
c) Expert estimation
d) Compression
٤٠) Crashing:
a) Is a schedule compression technique
b) Increases cost
c) Is achieved by adding resources
d) All of the above
١٫١٫١
Questions ٤١-٦٠
٤١) Fast tracking:
a) Is a schedule compression technique
b) Does sequential activities in parallel
c) Increases risk of rework
d) All of the above
٤٢) Quality audit:
i) Is a tool in Perform quality assurance
ii) Checks the efficiency of the quality process
iii) Tries to improve product acceptance
iv) Reduce overall cost of quality
a) i, iii, iv
b) None of the above
c) All of the above
d) ii, iii
٤٤) Some managers believe that people do not work willingly and must be watched and
managed continuosly. They are of type:
a) Theory X
b) Theory Y
c) Theory XY
d) Theory V
٤٥) When an individual's lower level needs are met, the next level's needs are his
motivation. This forms the basis of:
a) Theory Y
b) Maslow's hierarchy
c) Theory X
d) None of the above
٤٨) A project manager manages a team of ٥. The number of communication channels is:
a) ١٥
b) ١٠
c) ٥
d) None of the above
٥١) A bar graph that shows resource assignments over time is:
a) Resource leveling
b) Resource histogram
c) Resource chart
d) Gantt chart
a) i, ii, iii
b) i, iv
c) ii, iii, iv
d) iii, iv
٥٦) Earned value=١٠٠, Planned value=١١٠, the schedule performance index is:
a) ١٫١
b) ٠٫٩١
c) -١٠
d) ١٠
٥٧) Earned value=١٠٠, Actual cost=١٢٠, the cost performance index is:
a) ٠٫٠١
b) ٢٠
c) ٠٫٨٣٣
d) -٢٠
b) Risk ranking
d) Risk response
a) Risk register
a) Expert judgement
c) Modeling
d) Only A
٦٧) Examine the statement-"A detailed risk response plan should be prepared no matter
how huge or trivial the risk is, irrespective of whether the effort is cost-effective or not, as
this is the process." This statement is:
a) Always true
b) Always false
c) Sometimes true
d) Sometimes false
a) Good risks
b) Opportunities
c) Advantages
d) Project plusses
٦٩) The four strategies used to deal with negative threats are:
d) Can't say
d) Can't say
a) Avoiding
b) Transferring
c) Mitigating
d) Working around
a) Risk analysis
b) Risk register
c) Risk monitor
٧٦) How to define, monitor and control risks in a project is documented in:
b) Risk register
d) Workshops
b) Expert judgement
c) Contract types
٧٨) Unclear scope definition in a project using Fixed price contract can lead to losses for:
a) the buyer
b) the vendor
٧٩) Request for proposal, Request for Information, Invitation for bid are broadly called:
a) Procurement documents
b) Vendor documents
c) Bidding documents
d) Contract documents
١٫١٫٣
Questions ٨١-١٠٠
٨١) Closing a Project involves:
a) Updating organization process assets
b) Closing contract
c) Creating documentation, archives, and lessons learned
d) All of the above
d) Price-free contracts
٨٦) A tool/rechnique used in the Develop Human Resource plan process is:
a) Political factors
b) Organization chart
c) Personnel policies
d) Interpersonal factors
c) Both a and b
d) Neither a nor b
a) Cost-benefit analysis
b) Control charts
c) Benchmarking
a) Prevention
b) Correction
c) Conformance
٩٢) Juran's fitness for use theory of cost of quality can be summarized as:
a) Continuous improvement
a) Actual cost
c) Earned value
a) Infinite duration
b) Zero duration
c) No importance
٩٩) A room used for project planning, and where team members work on issue
resolution is called:
a) Conference room
b) Resolution room
c) War room
a) EAC-AC
b) BAC-EAC
c) Both a and b
d) Neither a nor b
a) Meetings
b) Issue resolution
c) Managing stakeholders
d) Risk analysis
١٠٢) The cost of a contractor is $٢٥ per hour. Two contractors working for ١٠ hours will
cost $٥٠٠. This is an example of:
a) Analogous estimating
b) Parametric estimating
c) Three-point estimating
d) Bottom-up estimating
١٠٣) Using PERT, calculate the time it takes for a task with the following information:
Pessimistic time=٥ hours, Optimistic time=٢ hours, Most likely time=٥ hours. The answer
is:
a) ٤٫٥ hours
b) ٣ hours
c) ٥ hours
d) ١٫٥ hours
a) Control thresholds
١٠٥) The revenue earned from doing a project is $١٠٠٠. The costs involved sum to $٥٠٠.
The benefit cost ratio is:
a) ٢
b) ٠٫٥
c) ٥٠٠٠٠٠
c) Cannot be determined
a) ٠٫٥
b) ٢
c) ١٠٠٠
١٠٨) Earned value=$٢٠٠٠. Planned value=$٢٥٠٠. The schedule performance index is:
a) ٠٫٨
b) ١٫٢٥
c) ٥٠٠
a) ٠٫٥
b) ٢
c) ١٠٠٠
a) -١٠٠٠
b) ٢
c) ١٠٠٠
a) $١٠٠٠
b) $١٤٠٠
c) $٨٠٠
a) $١٠٠٠
b) $١٢٠٠
c) $٨٠٠
a) Phase exits
b) Stage gates
c) Kill points
a) It is higher inthe beginning as uncertainty is high and gets lesser as the project
continues
b) It remains the same thoughout the project
c) It is lesser inthe beginning as uncertainty is high and gets better as the project
continues
a) Little or none
b) Limited
c) Low
d) Moderate
b) Limited
c) Low to moderate
d) Moderate to high
a) High
b) Limited
d) Moderate to high
a) Functional manager
b) Project manager
c) Mixed
١١٩) Deming's cycle is used for continuous improvement of processes. The four-step
management method is:
a) Plan-Do-Check-Act
b) Plan-Act-Check-Do
c) Plan-Act-Do-Check
١٫١٫٥
Questions ١٢١-١٤٠
١٢١) Administer procurements belongs to:
a) Problem
b) Market
c) Opportunity
a) Authorizes a project
a) Business needs
b) Risks
c) Quality plan
a) WBS
b) WBS dictionary
a) Cost-benefit analysis
b) Payback period
١٢٩) WBS:
c) Provides the team with an understanding of where their pieces fit in the project plan
b) Poor planning
c) Poor control
b) A value-adding change
c) An external event
a) Brainstorming
b) Risk identification
d) Powerpoint presentations
١٣٣) WBS includes all project work. Which of the following is also true about WBS?
c) Total of work at lowest levels need not always roll up to higher levels as some extra
work may be completed
١٣٤) Critical chain method and critical path method are tools and techniques used in
which process of the Project TIme management area?
b) Control schedule
c) Develop schedule
b) Control schedule
c) Both a and b
d) Neither a nor b
١٣٧) The outputs of 'Activity Definition' and 'Create WBS' respectively are:
a) Float
c) Lag
d) Activities
a) Preferential logic
b) Soft logic
c) Preferred logic
a) Acceleration
b) Deceleration
c) Tracking
d) Regression
١٫١٫٦
Questions ١٤١-١٦٠
١٤١) Lag results in _____ of successor activity:
a) Acceleration
b) Delay
c) Tracking
d) Regression
a) Known unknowns
c) Both a and b
d) Neither a nor b
a) Unknown unknowns
c) Both a and b
d) Neither a nor b
١٤٤) Outputs of Monitor and control project work are:
a) Recommended corrective actions
b) Recommended preventive actions
c) Requested changes
d) All of the above
a) Project management
b) Cost reduction
c) Schedule compression
d) Schedule estimation
b) A time-phased budget
١٤٧) The difference between maximum funding and the end of cost baseline is:
a) Management reserve
b) Cost baseline
c) Cost overrun
١٤٨) Identifying quality standards relevant to the porject and determing how to satisfy
them is:
a) Quality planning
b) Quality assurance
c) Quality control
d) Quality management
١٤٩) Applying planned, systematic quality activities to ensure that proejct employs all
processes needed to meet requirement is:
a) Quality planning
b) Quality assurance
c) Quality control
d) Quality management
١٥٠) Monitoring specific project results to determine whether they comply with relevant
quality standards and identifying ways to eliminate causes of unsatisfactory performance
is:
a) Quality planning
b) Quality assurance
c) Quality control
d) Quality management
a) Scatter diagram
b) Statistical sampling
c) Inspection
d) Defect repair
a) Product reviews
b) Audits
c) Walkthroughs
a) Staff acquisition
b) Release criteria
c) Training needs
b) Model-telling
a) Leadership styles
c) Planning style
a) Schedule
b) Project priorities
c) Resources
d) All of the above
١٥٧) Power that a PM has on the basis of the special skills he possesses is:
a) Referent
b) Expert
c) Reward
d) Penalty
a) Smoothing
b) Collaborating
c) Recognizing
d) Withdrawal
a) Confrontation
b) Accomodation
c) Compromise
d) Smoothing
١٦٠) The motivational theory that focuses onteam, lifetime employment and collective
decision making is:
a) Theory X
b) Theory Y
c) Theory Z
١٦٢) In a communication model, the method used to convey the message is:
a) Email
b) Medium
c) Language
d) Decoding
a) Formal written
b) Informal written
c) Formal verbal
d) Informal verbal
b) Physical distance
c) Environmental factors
a) Facilitating
b) Promotional
c) Conciliatory
d) Authoritarian
١٦٦) A management skill that establishes direction, aligns people, motivates and inspires
team is:
a) Communicating
b) Leading
d) Problem solving
a) Delphi technique
b) Brainstorming
c) Interviewing
b) Risk categories
b) Communication
c) Risk management
d) Tracking
١٧٢) At what stage of your current project should you use the techniques you learnt on
your previous projects as PM?
a) Executing phase
b) Planning phase
١٧٤) If you are implementing the risk response plan, you are in:
a) Planning phase
b) Initiating phase
c) Implementation phase
d) Closing phase
b) Report performance
c) Distribute information
d) Plan communications
١٧٦) The tool that assigns a numeric weight, rates sellers based on total weight is:
a) Weighting system
b) Independent estimates
c) Screening system
d) Expert judgement
b) Screen contractors
١٧٨) You send a formal request to each vendor for a service. This is used as the basis
upon which the vendor prepares a bid for the requested service. The formal request you
sent is called:
a) Contract
b) Purchase Order
١٫١٫٨
Questions ١٨١-٢٠٠
١٨١) Project charter
i) Includes preliminary project budget at summary level
ii) Is created during the Develop Project Charter process
iii) Includes a milestone-level schedule
iv) Includes high level project requirements
d) Neither a nor b
١٨٩) Variance analysis compares actual results to planned results. This can be done for:
a) Cost
b) Schedule
c) Quality
c) Both a and b
d) Neither a nor b
١٩١) The longest path through the network that shows the shortest duration in which the
project can be completed is:
a) Critical path
b) Project schedule
a) Project manager
b) Team members
c) Project sponsor
d) Functional manager
١٩٩) Using which of the below can you predict future performance of team:
a) Trend analysis
b) EMV
c) Control limits
d) Risk analysis
٢٠٠) Salary of full-time employees and cost of hardware bought specially for your project
count as:
a) Direct costs
b) Indirect costs
c) Project costs
d) None of the above
١٫١٫٩
Questions ٢٠١-٢٠٦
٢٠١) A Request for Proposal:
a) May invite suppliers to submit a proposal for a product
b) Indicates what product/service is required
c) Both a and b
d) Neither a nor b
a) Analogous estimating
b) Parametric estimating
c) Three-point estimating
d) PERT estimating
٢٠٣) Payback period is the time it takes to get back money invested in a project. Hence:
a) The longer the payback period, the better it is for the project
b) The shorter the payback period, the better it is for the project
c) Not enough information to decide
d) Depends on the present value of money invested
a) Board of directors
b) Risk response
c) Risk analysis