Вы находитесь на странице: 1из 11

See

discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/237190668

Factors influencing formwork productivity

Article in Canadian Journal of Civil Engineering · February 2011


DOI: 10.1139/l93-015

CITATIONS READS

21 1,599

2 authors:

Gary R. Smith Awad S Hanna


North Dakota State University University of Wisconsin–Madison
25 PUBLICATIONS 384 CITATIONS 97 PUBLICATIONS 1,325 CITATIONS

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Gary R. Smith on 27 April 2015.

The user has requested enhancement of the downloaded file.


Factors influencing formwork productivity
GARYR. SMITH
Department of Civil and Environmental Engineering, The Pennsylvania State University, University Park,
PA 16802, U.S.A.
AND
AWADS. HANNA
Faculty of Engineering and Applied Science, Metnorial University of Newfoundland, St. John's, Nfld., Canada
A 1B 3x5
Received September 3, 1991
Revised manuscript accepted June 1, 1992
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

Estimates indicate that 30 to 70 percent of cast-in-place concrete cost is attributable to the assembly and stripping
of formwork. This wide percentage range is partially due to factors that are not well understood with regard to their
influence on productivity. The purpose of this paper is to identify the factors that influence formwork productivity
and identify a methodology to evaluate productivity data. Two groups of factors were found to have a great effect
on formwork productivity: non-measurable factors such as contract document and measurable factors such as engineering
design. This paper discusses the effect of both groups of factors on the productivity of vertical formwork. T o quantify
the effect of the measurable factors on formwork productivity, a case study of the productivity of a crew of carpenters
erecting wall formwork for a three-story underground parking structure is presented and analyzed. Data were collected
by physically measuring the daily output of vertical formwork erected and the total daily work hours.
Key words: formwork, productivity, construction methods.

Des estimations revdent qu'entre 30 et 70 pour cent des cofits du beton coule sur place sont attribuables a l'assemblage
des coffrages et au demoulage. Ce grand ecart est en partie attribuable a des facteurs qui influent sur la productivite
et qui sont ma1 compris. Le but de cet article est d'identifier ces facteurs et d'etablir une mithodologie afin d'evaluer
les donnees de productivite. On a constate que deux groupes de facteurs avaient une grande influence, soit des facteurs
For personal use only.

non mesurables de nature contractuelle et des facteurs mesurables comme la conception technique. Cet article discute
de l'effet de ces deux groupes de facteurs sur la productivite dans le domaine de la mise en place de coffrages verticaux.
Afin de quantifier cet effet, une etude de cas de la productivite d'une Cquipe de charpentiers travaillant a l'erection
des coffrages d'un garage de stationnement souterrain de trois Ctages est presentee et analysee. La collecte de donnies
s'est faite en mesurant la quantite quotidienne de coffrages verticaux erigis et le nombre total d'heures de travail par jour.
Mots clis : coffrage, productivite, methodes de construction.
[Traduit par la redaction]

Can. J. Civ. Eng. 20, 144-153 (1993)

Introduction The final factor is the formwork system selection. This


Formwork productivity may be affected by design, site is the most important factor with regard to labor produc-
conditions, and formwork system factors. tivity. The influences of formwork systems can be many.
Design factors relate to all aspects of the design that will Examples would be the number of ties required, the
increase or decrease the time required to fabricate, erect, modularity of the system, wale design, hardware, and the
and dismantle the forms. A typical example of a design fac- number of loose parts. Their significance is highlighted when
tor that impacts productivity is the formed surface finish the field personnel use a system other than the one chosen
specification often formed by architectural requirements. when the bid was prepared or when more than one system
Other factors may be peculiar wall intersection angles or is used at the site.
changes in wall thickness. Design influences are fixed factors
and cannot be reconciled in the field. The contractor must Responsibilities of parties involved in formwork selection
budget sufficient time for these conditions at the bidding The proper selection of the formwork systems to be used
stage. in a cast-in-place concrete building is of concern to all
Site factors relate to those planning and organizational involved parties. Some of the major responsibilities of these
aspects of the formwork operations that increase or decrease parties which need to be considered to achieve the proper
the efficiency at a construction site. Examples of site factors and optimum selection of the formwork systems are dis-
include the area available for material storage, access to cussed below (Hanna 1989).
formwork area, and the planning and sequential arrange- Owner's role
ment of formwork operations. Management controls the The owner's chief objectives are to minimize overall proj-
allocation of space and therefore the contractors should ect cost and construction time and assure specified quality
account for the site impact in the estimate. and safety of the finished product. Recognizing the fact that
formwork is a high-cost item which controls the pace of con-
NOTE: Written discussion of this paper is welcomed and will be struction, a knowledgeable owner should be involved or
received by the Editor until June 30, 1993 (address inside informed early in the project about the advantages and
front cover). disadvantages of the selected system. Special mock-ups
Printed in Canada / Imprlmc au Canada
SMlTH AND HANNA 145

should be shown to the owner when special materials such Contract document
as architectural concrete are required. Contract documents are not a measurable factor with
respect to concrete formwork productivity. However, the
Designer's role influence of the contract on performance can be a major
Economical design for concrete is not necessarily achieved
factor on the project. The flexibility of the contract docu-
by minimizing the dimensions of the structural elements.
ment in allowing the constructor to use personal experience
Some other factors have larger influences on building costs.
in designing and constructing the forms affects the degree
For example, labor for formwork is an item representing
to which labor can be effectively used on site in formwork
38% of cast-in-place concrete costs; thus a few changes in production. When possible, the exact location of construc-
column size or wall height to achieve uniformity and repeti-
tion joints should be determined by the design engineer and
tion can result in a substantial cost reduction in overall form-
the contractor to maximize form reuse and, consequently,
work cost. When designing a building, the designer should
increase productivity. If the contract document does not
consider each of the following methods of reducing the cost
specify a particular method of construction, the constructor
of formwork (Hanna 1989):
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

is able to use familiar methods of ~roduction.The construc-


1. Repetition. Repeating the same layout from floor to tor should design for adequate, but not excessive, strengths
floor assures that the workers learn quickly, thus increasing and rigidity, fabricate the forms into modular sizes suitable
the productivity (learning curve) and decreasing the labor for the project, select form material considering reuses, and
cost. Also, the same forms can be effectively reused from evaluate other factors that will enhance the efficiency at the
floor to floor. site. In addition, contract documents that specify unreason-
able values for tolerances and cumbersome inspection pro-
2. Standardization. Basing the design on readily available cedures should be avoided.
standard form sizes is less expensive than specifying custom-
built forms for the project. For example, in designing a joist
or waffle slab, the designer should consider the standard System selection
size pans available and base the design on these sizes. System selection should be a combined effort between
design engineer and contractor during the planning phase.
3. Consistency and simplicity. The designer can save sub- Research into the selection criteria for formwork covers the
stantial construction costs by keeping the design simple and topics of building shape and support systems, speed of con-
For personal use only.

the elements consistent. Uniformity is achieved by maintain- struction needed, and other factors. These factors have been
ing a constant dimension for the different structural catalogued elsewhere for application in knowledge-based
elements. Specific examples of consistency include (a) expert systems. Table 1 is a summary for vertical formwork
maintaining constant breadth and depth for all beams, (b) extracted from a broader research effort (Hanna and
maintaining constant column dimensions and spacing Sanvido 1990). While this table has a great deal of infor-
between columns, and (c) maintaining constant spacing mation related to the selection of formwork systems for a
between beams and joists. project, it represents one facet of the system selection
equation. f able 2 is a partial list of criteria that should be
Contractor's role
considered by a contractor when selecting or comparing
Most contractors carefully study the influence of form-
work on project cost and progress. In selecting formwork, various concrete form suppliers.
a contractor's primary list of concerns (Hanna 1989) is the Selecting the proper formwork system requires adequate
following: information about available forming systems. Any infor-
1. To design formwork to achieve high quality with a mation collected that describes the formwork systems should
minimum of possible cost and time. Safety is another major include the criteria used by contractors to select the system.
concern for the contractor; inadequate shoring and reshoring These criteria (Hanna 1989) are the following:
can result in failure or excessive deflection which requires 1. The formwork system should be available and its use
chipping and grinding or demolition. economically feasible for the contractor.
2. To use forming systems instead of job-built forms; this 2. All major parties - owner, designer, and contractor
reduces labor costs (which represent 38% of the cost of cast- - should be familiar with the selected forming systems,
in-place concrete. Formwork systems can reduce the labor since certain systems, such as slip forms, require special
cost by 50%. economic evaluation, design configurations, and safety
3. To plan the formwork as an integrated part of the precautions.
overall planning procedure so that the process of erecting 3. The selected formwork system must be consistent with
and dismantling the forms can be accelerated. the architectural and structural requirements of the building.
For example, if architectural concrete is required for the
external columns, then slip form systems do not provide the
Factors affecting formwork productivity appropriate forming solution.
Two groups of factors were found to have an effect on 4. The selected system must be compatible with the
formwork productivity: non-measurable factors such as con- mechanical and electrical requirements of the building. For
tract document and measurable factors such as engineering example, self-rising forms are not an economical solution
design. This paper discusses the effect of some of these when there are extensive penetrations through the slab (e.g.,
measurable factors on the productivity of vertical formwork. electrical and mechanical).
These measurable factors include factors related to engineer- Systems requiring special assembly tools can create unex-
ing design such as interior versus exterior walls and straight pected problems. When critical assembly tools for pro-
versus interrupted walls and factors related to construc- prietary formwork systems are misplaced or otherwise
tibility such as modular versus gang forms. unavailable, productivity rapidly decreases. Good
TABLE1. Factors affecting selection of vertical formwork systems (Hanna 1989)

Formwork systems
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

Conventional
Influence factor column/wall form Ganged forms Jump form Slip form Self-raising form
(a) Building design
Lateral support
Lateral support system Most suited for frames Shear walls Shear walls Shear walls Shear walls
and retaining walls Bearing walls Frames and framed Tube systems
Retaining walls shear wall Tube-in-tube

Building height Avg. 400 ft (122 m) At least 300 ft (91 m)


Min = 60 ft (18 m) No max
Max = 600 ft (180 m)

Building shape
Column/wall size System can handle Same as for System can handle Walls should be of System can handle
and location variation of column/ conventional column/ moderate variation of the same location reasonably modular
For personal use only.

wall size and location wall form system columns/walls size Walls size variation design
and location can be accommodated

System can handle Variation in opening's Openings/inserts Should be minimum System can handle
openings/inserts of size/location can be should be regularly Too many openings/ moderate variation in
different size and accommodated at occurring from floor inserts make this openings size and
location additional cost to floor system impractical location

(b) Job specification


Speed of construction
Concrete finish "AS cast" concrete Produces smooth exposed concrete finish System produces Smooth concrete
finish Tie pattern and number should be designed rough concrete finish finish
Form liners can be used to produce architectural NO ties Form liners can be
concrete used

Construction sequence Slabs and walls are Slabs and walls are System is used when Typically walls are Walls are ahead of
placed concurrently placed concurrently no floor slab is placed entirely or at the floor
Walls can be placed available least several stories Other method is used
ahead of the floor slab ahead of the floor for the first 2-3 stories
Cycle time 1 floor every 3-4 days 1 floor every 2-3 days 1 floor every day 1 floor every 2-3 days
Rate of placing
= 8-20 in./h

(c) Supporting organization


Cost
Stripping Hand strip Crane is used to strip Forms are equipped Forms are stripped at Forms are equipped
High stripping cost the system with mechanism for the end of the project with mechanism for
High stripping cost stripping Minimum stripping cost stripping
Minimum stripping cost Minimum stripping cost
TABLE1 (concluded)
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

Formwork systems

Conventional
Influence factor column/wall form Ganged forms Jump form Slip form Self-raising form

Reuse Less than 10 Between 40 and 50 Between 15 and 30 Between 50 and 100 At least 30 reuses
Reuses could be (i.e., between 200 and should be available
horizontally or 400 ft high) vertically
vertically

Hoisting equipment
Location of adjacent Generally not a factor A major factor, system Same as for ganged Minimum free space Not a major factor,
building and must have a free space forms should be available for system can be used in
obstruction to be moved from crane movement downtown restricted
For personal use only.

floor to floor areas

Crane time Not a factor, system Crane dependent System substantially Crane is used only for Crane independent
can be hand set system, sufficient crane reduce crane time materials delivery and system
time is a must Average crane time pick concrete placing
= 20 min

Operating system Hand-set system, Crane-set system Crane is used only to Motion is provided by System is lifted by
crane increases system Crane serves two lift the forms electric, or hydraulic hydraulic, electric, or
efficiency and reduces functions: lifting and Crane is not used for jacks climbing on steel pneumatic lifters
cost supporting the forms forms dismantling rods

Safety management
Safety No special safety Special care for Safe guarded platform For hydraulic systems, Same as for slip form
features is required handling the large No one needs to be on special safety precautions
ganged units by crane the form during crane must be taken to prevent
handling fire several hundred feet
above the ground

Yard facility
Supporting yard System is more System must have an System is rented Continuous materials System is preassembled
facility, supplier efficient, if a local adequate make-up area or purchased delivery; uninterrupted Make-up area is not
or make-up area yard facility is available or close by supplier concrete placement must a factor
be assured
CAN. 1. CIV. ENG. VOL. 20, 1993

TABLE2. Criteria for supplier systems (Smith and Hanna 1991)

Cost per square foot per use Flexibility of the system


Number of connections Connection hardware
Number (and type) of ties required Interchangeable system hardware
Weight for handling Panel attachments
Ease of stripping Ease of attaching accessories
Ease of ganging panels Availability of accessories
Cost of replacement parts Safety accessories
Technical design support available

TABLE3 . Estimates of factors impacting formwork labor productivity (Thomas et a/. 1991)
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

No. of projects
Value factor Source included Impact Remarks

General factors Thomas et a/. Numerous Varies from 5% Information, staff, crew,
Management PTI Report (1990) to over 100% supervision, tools,
direct or indirect congestion, overtime,
changes

Placement method Estimating manuals Unknown


Modular Means (1986) Baseline
Gang Richardson (1990) 10-20% less Sources agree
Job-built Adrian (1975, 1989) 200 ( + ) 233% more Adrian

Design details Data inconclusive


Member height Qabbani (1987) 1 5-10% Depends on type and number
For personal use only.

Corners Qabbani; Richardson 2.5-4 times Multiplied by unit rate


Bulkheads Qabbani; Richardson 3-5 times Multiplied by unit rate
Boxouts Richardson (1990) 12% more
Pilasters Richardson; Means 4-5 times Multiplied by unit rate
Corbels Richardson (1990) 6 times Multiplied by unit rate
Overhangs Richardson (1990) 3 times Multiplied by unit rate

Material type Weight/assembly


Steel Adrian (1989) 200 ( + ) Baseline
Plywood 7% Less than steel
Aluminum 27 To Less than steel

Shape
Straight Means (1986) Baseline
Curved Richardson (1990) 1.5-2% Greater than straight

Support/shoring EFCO rate sheets 3 8-10% Of total time


scaffolding (1975) Varies Depends on type
Richardson; Means

Connections Needs more study


Form Hardware EFCO rate sheets 3 30-40% Of install/strip times
Ties (no. and type) Means (1986) Unknown Approx. 10%

Locations Unclear
Interior/exterior Bennett (1990); Qabbani 2 30-75% Confused factors
2nd level up Means; Peurifoy (1979) Add 10% Of installation

Learning curve Qabbani (1987) 1 76-84% rate From regression

Disruptions Bennett (1990) 1 0.27-0.53 Indices listed in PTI report

housekeeping and inventory management skills for the hard- sulted, a tabulation similar t o Table 3 can be generated to
ware associated with some modular systems are important show the current estimates and impact of various factors
to maintaining peak productivity rates. It is easy to imagine influencing concrete formwork productivity. Many of the
that the system which uses the fewest pieces to complete a factors have been based on single project studies or by the
wall section would have the edge in productivity. When same researcher. Without comparative studies, no definitive
various literature and manufacturers' resources are con- conclusion should be drawn from the information.
SMITH A N D H A N N A

TABLE
4. Design factors influencing formwork productivity (Smith and Hanna 1991)

Dimensions of walls Height of wall or column


Length of walls Number of vertical intersections
Joint pattern Surface finish
Irregular spacings Inconsistent column sizes
Irregular floor heights Shape irregularities
Column or wall orientation Pilasters
Irregular footing elevation Brick edge
Column capitals Sloped or stepped surface
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13
For personal use only.

FIG. 1. Wall configuration plan.

Design factors Formwork materials normally consist of either lumber,


Formwork productivity can be constrained by the struc- steel, or aluminum. Steel and lumber have standard
tural design via architectural design. Table 4 identifies design manufactured dimensions. Where concrete shapes are
factors that influence the time required to erect the form- designed in modules of the standard dimensions, the time
work. A typical example of design detail that impacts the for cutting and assembling forms is reduced to the minimum.
erection and cost of concrete formwork is the surface finish For example, in waffle-floor construction, forms are easily
specification. Rustication strips, ornate patterns, and surface erected and dismantled when the waffle pattern is designed
treatments all influence the system erection and stripping to the standards and modules of commercial forms such as
time. The specified surface finish also impacts formwork metal pans and corrugated sheets.
facing material and tie spacing. Another important design factor is the shape and dimen-
The adequacy of the design is very important. A project sion of the concrete structure. Table 1 suggests that varia-
should be designed with the minimum number of modifica- tions in building shape are most easily accommodated with
tions to dimensions and shapes to permit efficient use of the conventional hand-set and gang-set forms. However,
formwork. Site superintendents are able to plan form pro- there are other influences, like changes in the direction due
duction in a way that offers repetitive use of the compo- to wall intersections, that impact productivity when conven-
nent parts. The sizes of the components are pre-standardized tional hand-set and gang form systems are used even though
according t o the shapes to be formed. An inappropriate the system may have been selected appropriately for the
design causes numerous change orders involving dimensions structure. Forms for drains and channels, domes, amphi-
and shapes. Therefore, previously selected components have theaters, and other curvilinear structures generally require
to be remeasured and reassembled which ultimately reduces much greater care in measuring dimensions, joining pieces
productivity. together, forming recesses, overall fabrication to the right
A design that accounts for the repetition of dimensions size, erection, and dismantling. Productivity in such struc-
lends itself to the achievement of efficiency in formwork tures can be low as compared to simple straight wall
production. In large building works where bays or groups structures.
of bays are of equal dimensions, less time is spent in inter- Management factors
preting plans and measuring and cutting materials. The gain Productivity in formwork is not only influenced by design
in productivity should be more noticeable when the bays are factors and the specification in the contract document but
also repetitive from floor to floor. by site planning, construction processes, and supervision.
150 CAN. J . CIV. ENG. VOL. 20, 1993

TABLE 5. Project summary data Bracing: Once wall panels were set, the panels were
braced with wales and strongbacks. Bracing need to be
Project cost $10 million removed and reset for individual parlels and the constructed
Underground structure 3 levels, reinforced concrete walls remain attached to the gang form system. Measure-
Aboveground structure 7 levels, reinforced masonry ment of bracing was estimated on the basis of the square
Floor plan area 2028 m2
feet of the form which had wales and strongbacks attached.
Site area 2545 m 2
Formwork contact area 4837 ft' Alignment: Alignment included installation of the tie
Number of work days required 148 rods, plumbing vertically, and levelling the form system.
Time frame January-August 1987 Time spent on additional adjustments to prepare the form-
Average crew size 14 work for concrete placement was also included. Measure-
Labor force Nonunion ment of alignment was based on the square feet of the wall
section prepared for concreting.
Stripping: Stripping is the removal of the formwork sys-
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

tem from the curing concrete. Cleaning and oiling the forms
The ability of the site supervisory personnel to interpret the for the next use were considered incidental work. Measure-
drawings as accurately as possible and to effectively com- ment of stripping was based on the square feet of form
municate what shape is to be formed, how it should be removed from the wall.
formed, and what tolerances are needed will reduce rework
and increase speed and efficiency in form construction. Rules of credit
An engineer at the site can influence productivity through All of the tasks described above are not usually performed
adequate planning. Adequate planning involves examining in a single day on the same wall section. Rules of credit were
the drawings in detail and extracting the component parts developed (Thomas and Kramer 1987) as a method to
that have the same dimensions to allow for repetitive use. account for the effort contributed by each task to a com-
Adequate planning also involves fabricating the forms into pleted section of formwork. The rules provide a simple
modular and largest sizes possible according to the available procedure for counting the contribution of partially com-
handling equipment that will permit reuses without pleted work to the overall work package (Thomas and
re-fabrication. Kramer 1987).
For personal use only.

Productivity includes the work hours required for a com-


Case study
plete unit of work meaured as a square foot of contact area.
Project description Concrete formwork productivity is measured in terms of the
The case study project records tracked the construction work hours per square metre of form (wh/m2) or work
of footings, columns, slabs, and walls for a three-story hours per square foot (wh/ft2). The work hours were
underground parking structure (Smith and Thomas 1991). collected by reviewing the foreman's daily time sheets. As
Table 5 lists the important attributes of the project. Figure 1 noted before, the reported values only included the time
is a sketch of the lowest level of floor plan showing the wall associated with formwork and not with placing reinforce-
outlines. The walls were subdivided into categories for the ment or concrete.
purpose of data collection. Long straight walls with few The same concept of rules of credit was applied with gang
intersections were found at the northeast (NE) and southwest forms and modular forms. The initial rules of credit included
(SW) sides of the building. The side walls are also long and subtask for bracing. After the first 30 days, the most of the
straight but have numerous blockouts, integral columns, and formwork used consisted of gang forms, and the bracing
corbels. Side walls were identified at the northwest (NW) subtasks were not separately recorded. When modular forms
and southeast (SE) walls. All the interior walls were were recorded, the time required for bracing was included
incubated in a single data classification. The case study with the alignment time. The final rules of credit for gang
discussion and analysis will focus on the wall forms. wall formwork are shown in Table 6.
Construction methods
The contractor used metal frame modular formwork Data collection
panels (gang form) to construct the wall forms. The indi- Data collection was a daily task on the case project site.
vidual wall panels were 0.61 m (2 ft) wide and 2.44 m (8 ft) The number of panels erected for the first and second sides
high. Gang forms were assembled on site and lifted into of walls was counted each day and converted to square feet.
place with a tower crane. Work tasks were established as Alignment quantities were found to be very difficult to mea-
follows: wall panel erection, bracing, alignment, and strip- sure. When forms were erected and aligned and the concrete
ping. Concrete placement and reinforcing steel placement poured in a single day, the alignment quantity was the same
were not included as part of the forming work data as the contact area poured. However, when concrete was
collection. not placed the same day, the alignment area was defined
Wall erection: The erection sequence for the panel was to be the area where the tie rods had been securely fastened
performed in two steps. The first side of the wall is nor- to the second panel. Accurate sketches were needed to avoid
mally the most difficult to erect. The layout time was double counting tie rods on following days. The area
included in the time for setting the first side. Boxout and stripped was determined by counting the number of panels
wall sleeves were installed before reinforcing steel was removed and converting the panel count to square feet. Daily
erected. The second side of the wall form was erected after quantities in each category were appropriately weighted and
the reinforcing steel was placed. Form ties were commonly summed as the equivalent total quantity installed. Collecting
installed in the first set to aid in setting and aligning the the data required a single site visit for approximately
second side. 45-60 min at the end of each day.
SMITH AND HANNA

TABLE6 . Rules of credit for gang formwork

Subtask Description Unit Weight

Erect first side Place and secure panels ft hr m' 0.90


Erect second side Place and attach panels ft' or m' 0.70
Alignment Install tie rod, plumb, and level form ft' or m' 0.10
Stripping Remove, clean, and oil ft' or m' 0.10

-
Interior Wall, Level 2

-
SE Walls, Level 2
---.----
lnterior Wall, Level 3

SE Walls. Level 3
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

SWLalls, Level 2 NE Walls, Level 3 SW Walls, Level 3

I 0 Weather
A Material - related
Sequencing
1 0 Accident
0 Ironworkers did not work
Gangforms

mw2
-
rn Modular forms
Mixed forms
For personal use only.

w
,q
Workdays
FIG. 2. Daily productivity plot.

In addition to recording the daily quantities of formwork, plished on time, and therefore disrupted the work of the
other notations were made in the records about major prob- formwork crew. Shore removal and incomplete footing
lems that occurred on the site. Weather was noted as an preparation were also noted as sequencing problems.
influential factor when extremely cold temperatures were
recorded. On 7 days it snowed either the night before or
during the day. One workday had heavy rain that suspended Analysis
work for the entire day. Various categories of disruptions had a noticeable impact
Productivity is measured in terms of work hours per unit to daily productivity. The overall mean productivity for days
area (wh/m2). As a result, higher productivity is repre- without disruptions was estimated as 4.95 wh/m2 and daily
sented by smaller numbers. Figure 2 illustrates a sample plot productivity on disrupted days averaged 14.42 wh/m2.
of the equivalent daily productivity rates for 80-120 When statistically tested, this relation has an F-ratio of 47.17
workdays. Review of Fig. 2 reveals high productivity and a level of significance, P, of 0.000. Disruptions were
between workdays 80 and 90 and low productivity between further classified into weather, material management,
workdays 100 and 120. The low productivity was caused by sequencing, and accident disruptions for analysis. Table 7
interference, safety, and materials problems. Material summarizes the mean productivity for each disruption cat-
storage was a problem because of the inadequate storage egory. However, the finer categorization of data reduces the
area on the project. All materials were stored inside the researchers' ability to confidently analyze the data, and no
building footprint. Material storage areas were often moved significance can be clearly identified from the analysis.
as the building progressed. The frequency of movement Since no classification scheme has been developed that
resulted in some materials being misplaced, lost, or could differentiate design difficulty factors, the walls were
damaged. Sequencing was noted as a disruption in several separated into three ad hoc groups. Straight easy walls were
occasions. The movement of material was not being accom- those that had no intersecting walls such as the northeast
152 CAN. J. CIV. ENG. VOL. 20, 1993

TABLE
7. Mean productivity: disruptions by category TABLE
8. Wall formwork productivity

Productiyity 95% confidence Average unit rate


Data type Count (wh/mU) interval Wall type (wh/m2) Sample size, n

Nondisrupted 115 4.93 0.341-0.575 Exterior wall


Weather 8 9.32 0.433-1.299
Material 5 18.3 1.15-2.240 NE and SW walls
Sequencing 15 16.6 1.23-1.860 (straight, easiest)
Accidents 3 10.15 0.236-1.650 Gang form
- - - - Modular
NOTE:wh/m2 = work hours per square metre of contact area.
NW and SE walls
(straight, hardest)
and southwest walls which were long and straight and had Gang form
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13

few intersections or changes in direction. Straight hard walls Modular


were the remaining sidewalls. These were classified as Interior core walls
"hard" due to the presence of corbels, integrals columns, Gang forms
and numerous blockouts. All the interior walls were grouped Modular
together and represented one unit rate, since they were all NOTE:wh/m2 = work hours per square metre.
short, straight walls with some boxouts or other inserts.
Table 8 shows the effect of engineering design and con-
structibility on formwork productivity. Engineering design
effect is shown by the difference in productivity rate between the contractor and should be considered during the initial
straight and intersecting walls. Straight walls had a mean project planning.
productivity of 4.65 wh/m2 (n = 74), while the interior Improvements in data collection and a much larger data
core walls had an average unit rate of 8.96 wh/m2 base are necessary before definite conclusions can be made.
( n = 71). The significance level for these values was deter- Toward this end, a formwork data collection procedures
mined to be 0.024. On the other hand, constructibility effect manual is under development to enable researchers to collect
For personal use only.

is shown by the difference between the productivity of data in a consistent manner for inclusion in a larger data
modular versus ganged forms. The mean gang form pro- set and for further analysis. The focus of continued research
ductivity was 5.5 wh/m2 (n = 86) and the mean modular will be to update or identify the impact factors affecting
form productivity was 6.88 wh/m2 (n = 47); no statistical formwork productivity. Better definition will enable con-
significance could be measured between these two values. tractors to better predict resource requirements and costs.

Discussion Adrian, J. J. 1975. Column, gang, and hand-set forming produc-


Several factors discussed in this paper have been shown tivity study. Report for Symons ~ a n u f a c t u r i ncompany.
~ con-
to cause severe impact in formwork productivity, namely struction System CO., Peoria, '''.
constructibilit~,material management, safety, and engineer- Adrian, J.J. 1989. Cost study: a comparison of concrete block vs.
cast-in-place. In residential foundation walls. Symons
ing design. A quantitative procedure to measure these factors Des Plains,
has been presented. Constructibility has proven be an Bennett, P.D. 1990. A case study of the validity of the daily crew-
important factor in formwork productivity. Ganged forms based productivity measurements. M.Sc. thesis, department of
are more efficient than modular forms. The productivity of Civil Engineering, The Pennsylvania State University, University
exterior wall form with no intersection was higher than that Park, Pa.
of interior wall form with intersections. A lower produc- EFCO. 1976. Rate of progress worksheets. Economy Forms Corp.,
tivity rate was observed due to unsafe work conditions, Des Moines, Iowa.
inadequate materials management, and bad weather EFCO. 1990-1991. Form marks. Economy Forms carp., ~ e s
conditions. Moines, Iowa.
Hanna, A.S. 1989. An interactive knowledge based formwork selec-
Conclusion tion system for buildings. Ph.D. dissertation, Department of Civil
Engineering, Pennsylvania State University, University Park, Pa.
The procedure presented above for measuring and Hanna, A.S., and Sanvido, V.E. 1990. Interactive vertical form-
evaluating ~roductivityis a flexible tool for evaluating a work selection system. Concrete International: Design and
variety of productivity influences. The daily site visits col- Construction, American Concrete Institute, Detroit, MI.
lected sufficient data in a short time period for a prelimi- Means. 1986. Concrete and masonry cost data. R.S. Means Inc.,
nary evaluation of the overall factors influencing the project. Kingston, Mass.
The rules of credit functioned to provide a common basis Peurifoy, R.L. 1979. Construction planning, equipment and
for evaluating the output. The conclusions drawn from the methods. 3rd ed. hIcGraw-Hill Book Company, New York, N.Y.
analysis are that disruptions clearly reduce productivity and P e ~ r i f o yR.L.,
, and Oberlender, G.D. 1989. Estimating construc-
the complexity of the forms is an important factor. The comb tion costs. McGraw-Hill Book Company, New York, N.Y.
Qabbani, Z.S. 1987. Forrnwork economy and productivity analysis.
parison of modular and gang forms did not yield a signifi- Master of Science in Engineering Report, University of Colorado-
cance difference, although additional data may support an Boulder, Boulder, Cola.
opposite conclusion. Additional consideration of the data ~ i ~ ~ h ~ ~ services.
~ d 1990.
~~ ~~~~~~~l~i construction
~ ~
in Table 7 indicates that the two largest disruptions, mate- estimating standard, designs, practices, and procedures.
rial and sequencing, are factors that can be controlled by McGraw-Hill Book Company, New York, N.Y.
S M I T H AND HANNA 153

Smith, G.R., and Hanna, A.S. 1991. Factors affecting formwork Report to the Construction Industry Institute (CII), Austin, Tex.,
productivity. The Annual Conference of the Canadian Society Source Document 35.
for Civil Engineering, Vancouver, B.C. Thomas, H.R., Smith, G.R., and Horner, R.M.W. 1991. Proce-
Smith, G.R., and Thomas, H.R. 1991. Formwork productivity dures manual for collecting productivity and related data of
measurement and analysis. Proceedings, International Con- labor-intensive activities on commercial construction projects:
ference on Construction Project Modeling and Productivity, concrete formwork. The Pennsylvania State University, Univer-
Dubrovnik, Yogoslavia, pp. 235-240. sity Park, Pa.
Thomas, H.R., and Kramer, D.F. 1987. The manual of construc-
tion productivity measurement and performance evaluation.
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Hubei university on 06/04/13
For personal use only.

View publication stats

Вам также может понравиться