Following Loadings have been considered:

AREA LOADING
Stair Case Roof 
1 a. Live  (Inaccessible Roof) 1.5 kPa
b. SDL (Finishes) 1.125 kPa
Roof 
a. Live  (Accessible Roof) 2.5 kPa
2
b. SDL Includes Finishes MEP (HVAC) and HVAC Equipment  7.125 kPa

Toilet, Pantry and Gas Cylinder Roof Top
3 a. Live  (Inaccessible Roof) 1.5 kPa
b. SDL (Finishes and HVAC) 1.125 kPa
First Floor
i. Control Room/Telecom Room 5 kPa
ii. Toilet and Pentry 2 kPa
4 iii. Gas Cylinder 5 kPa
a. Live 
iv. Office and Store 5 kPa
v. Stair Steps  5 kPa
vi. Corridor 5 kPa
i. Toilet and Pentry area (Soil fill and Finishes) 9.5 kPa
ii. Terrace  2.125 kPa
iii. Office and Store Area 2.125 kPa
iv. Gas Cylinder Room 2.125 kPa
b. SDL
v. Corridor 2.125 kPa
vi. Raised Floor  3.625 kPa
v. Panel Load 9 kPa
vi. Stair Steps 3.125 kPa
POINT LOADING
ROOF TOP
OVERHEAD WATER TANK
1
a. Live  (Water Load) 51.5 kN
b. SDL (Dead Load of OHWT) 75 kN
TELECOM TOWER 
2
a. SDL ‐ (Dead Load + Wind Load) 50 kN
LINE LOADING
1 SDL Partition Load (includes all external and internal block masonry wall)