Академический Документы
Профессиональный Документы
Культура Документы
Deerwood North
Building 300
Jacksonville, Florida
An architectural precast concrete, loadbearing wall panel
system not only saved costs but also provided the desired
aesthetics for a four-story, Class A office building in
Jacksonville, Florida.
T
panels did not meet the required aes els. These panels would not only be
from the owner-developer was thetic standards. self-supporting but would also carry
to design a four-story, 117,000 Working closely with the precaster, part of the steel frame and floor load.
sq ft (10,900 m
) Class A office build
2 Gate Precast Company, the precast Importantly, the new design would
ing to meet high aesthetic standards specialty engineer, LEAP Associates eliminate all the perimeter steel
and a tight budget in a fiercely com International, Inc., and the structural columns. Another decision taken was
petitive office market. The owner, Fla engineer from The Haskell Company, to make the elevator shaft into a pre
gler Development Company, knew together they devised a more efficient cast concrete lateral load resisting
that to remain competitive in the of design using structural loadbearing frame.
fice market, a more innovative build precast concrete. There was some The result of this new precast sys
ing system had to be developed. precedent for this collaboration be tem was that it significantly improved
The architect, Rolland Delvalle & cause two earlier office buildings in the aesthetics of the building but it
Bradley, accepted the challenge and the same development program had also saved more than $250,000 over a
started to study various design alterna been clad with architectural non-struc conventional precast and structural
tives. Initially, the building was to tural precast concrete with the same steel building of similar size.
have been a steel-framed structure precaster. Two-story loadbearing window
with a gypsum board elevator shaft The basic concept was to replace the punch wall units were engineered to
and clad with tilt-up wall panels. tilt-up wall panels with loadbearing ar become an integral part of the struc
However, the inclusion of tilt-up wall chitectural precast concrete wall pan- ture taking the vertical and horizontal
136
PCI JOURNAL
Ij —--1
IOIW
1 - i-fl U4•
i-fl. 7-2)1)2 0
4) WI 2-V V-fl’ 24’
1 2’
sir rr r-r 2-V 2-V ‘-i’ 1-V 2-20 sir ii p.p ir
II 1 I IT
sir r-r 1-2 ‘-2 2-2 2-V i-V ‘-V 2)50
() C;)
4 II1 I.. I
4 llI-\ II Iii
-
—_ Ii 1 II
4 II
0”
a
n —
>
(1) I
r1
z
-I 0
-‘ (J
‘4
& m
2°
m
z 2°
0 ‘4 z
(JD
n I
z m
C’)
I:
-4
.2.
&
iIFI [J 1
Of
4
-o , r-wfl
I L51uI
C)
C i-is/yin fl)1oIll’ir-r
0
I ,JJr-ssir
2asirV (4)iP.ii-V4’V ‘-4’ ftO3O2.WW
C
2-5)14’ Y-V eM1FC2’
z
>
I-
the lateral loads imparted to the build
ing. Coordination between LEAP and
The Haskell Company resulted in a
system where the frames would carry
50 percent of the lateral load, and the
precast elevator shaft would carry the
remaining 50 percent. This resulted in
a smaller foundation under the shaft,
smaller foundation connections, and
lighter chord forces in the building di
aphragm. To achieve this even distri
bution of lateral loads, LEAP designed
a foundation connection in the eleva
tor shaft that achieved the desired
strength, yet allowed for enough elon
gation to create comparable drift with
the exterior frames.
LEAP, the precast specialty engi Photographer: Brian Griffis, Gate Precast Company
neer, was responsible for preparing the
shop drawings for the building. Even
during the early stages of the project,
LEAP provided expertise in areas such
as drafts, drips, panel sizes, reveals,
and mold building issues. There was
also close collaboration between the
general contractor and design team
with regard to the foundation design
of the building.
Preliminary design work on the pro
ject began in November 2002. This
continued through the next year until
the final design was approved in
February 2003.
The precast concrete components
were fabricated by Gate Precast Com
pany at their plant in Kissimmee, start
ing in March 2003. Production took
about two months. The components
were then shipped by tractor-trailer to
the project site, a distance of about The entire design-construction tern) in the same development pro
150 miles (240 km). While the precast team, and especially the owner-devel gram has been approved for construc
components were being fabricated, the oper, are very pleased with the manner tion and is now underway.
concrete foundation of the building in which this project evolved and the
was being completed. final completed structure.
Erection of the precast panels The aesthetics of the building are. CREDiTS
started in May 2003, first with the in particularly appealing, and it is ex
pected the building will have a long Owner: Flagler Development Com
terior panels of the lower level work
durable life with minimal mainte pany, Jacksonville, Florida
ing all the way to the upper levels. The
nance. This confidence is best ex Architect: Rolland Delvalle &
erection process took only nine weeks.
pressed by the statement of the devel Bradley, Jacksonville, Florida
Gate Precast Company was responsi
oper’s construction manager. “The Structural Engineer and General Con
ble for both the transportation and
loadbearing architectural precast sys tractor: The Haskell Company,
erection of the precast components.
tem allowed us to capture most of the Jacksonville, Florida
The project was completed in mid-
cost savings usually attributed to tilt- Precaster: Gate Precast Company,
December 2003 and was occupied by
up construction and gave us the assur Kissim.mee, Florida
several offices in early 2004. The
ance that we would have the aesthetics Precast Specialty Engineer: LEAP As
early sentiment is that their personnel
we wanted.” sociates International, Inc., Tampa,
are already enjoying the new facility.
Already, a fourth office building Florida
The total cost of the project was
about $6,800,000. (using the same precast concrete sys [GDNJ
139
September-October 2004