Ministry of Provincial Councils and Local Government

Contract: Wellawatta Wastewater Treatment Plant


Contract No : GCWWMIIP-TR3/ADB/ICB-02/2017
Bid Clarification No.01 (3 question sets)

(1) Responses to questions received from bidders on 01 August 2017

No Questions Answers
1.1 Pursuant to the ITB 21.1(Page 2-3) -Section 2-Volume 1
There are two employers in the bidding document: Ministry of Provincial Councils and
Local Government, as well as Colombo Municipal Council. The questions about Bid
security:
For the purpose of the Bid Security, the Employer/Beneficiary is:
a. Who is the beneficiary? Ministry of Provincial Councils and Local Government
b. Where is the address of beneficiary? No. 330, Union Place
Colombo 2.
c. What is the contact information of beneficiary? The above address & +94 11 2305326,27 / +94 11 2303280
d. When is the exact issuing date of Bid security? The question is not clear. Bidder can get the Bid Security issued
on any date prior to bid submission deadline. What is important
is for the Bid Security to be valid for 210 days beyond the
deadline (or any extended deadline) for submission of bids.
1.2 Pursuant to (Page 6a-2) - Para 12 - Clause 1.2 of Section 6a of Volume 2 - Initial Can be collected from the following Google Drive link.
Investigations and Studies https://goo.gl/U5PwmT
Please provide existing Base Geotechnical Report.

1.3 Pursuant to (Page 6a-33) - Para 172 - Clause 3.1.4 of Section 6a of Volume 2 – Can be collected from the following Google Drive link.
Geology and Soil Condition https://goo.gl/U5PwmT

Please provide Geotechnical Survey of project site (Auto CAD).

1.4 Pursuant to (Page 6a-33) - Para 176 - Clause 3.1.5 of Section 6a of Volume 2 All available drawings are accessible under the following link.
https://goo.gl/U5PwmT
Please provide data of existing building of project site as below: A list of available drawings is available in the same link and As
Attachment 1 for these replies.
a. Wellawatta new pump station (as-built drawings).

b. Wellawatta old pump station building (as-built drawings).

1 / 10
No Questions Answers
c. Office building used by the National Water Supply and Drainage Board as Colombo
South Sewerage Operations Office (as-built drawings)

d. Sea outfall land based junction chamber (as built drawings).

e. Old single story housing units of CMC officers (quarters) and pump station stores
(as-built drawings).

f. Fire brigade training centre and associated facilities (as-built drawings).

g. CMC community building located within the present playground area (as-built
drawings).

h. Some abandoned structures which were part of the old treatment plant which was
abandoned some time ago.

1.5 Pursuant to (Page 6a-34) - Para 181 - Clause 3.1.6 of Section 6a of Volume 2 All available drawings are accessible under the following link.
Please provide data of buried sewerage pipes of project site as below: https://goo.gl/U5PwmT
a. Outfall pipe 1.5 meter diameter RCC outfall pipe - pipe trace and A list of available drawings is available in the same link and As
as-built drawings. Attachment 1 for these replies.

b. 1100 mm DI force main from the S8 pump station to outfall junction


chamber -pipe trace and as-built drawings.

c. 400 mm force main from the Dehiwala - Mount Lavinia to outfall


junction chamber - - pipe trace and as-built drawings.

d. Force main from Sri Jayawardhenapura to Wellawatta new pump station- as built
drawings.

e. Force main from the Colombo South Hospital to Wellawatta new pump
station-as-built drawings.

f. W1Gravity Sewer carrying wastewater to the Wellawatta new pumping station -as
built drawings.

g. Shortforce main transferring the wastewater from Wellawatta new pumping station
to Wellawatta outfall junction chamber-- as built drawings.

2 / 10
No Questions Answers
1.6 Pursuant to (Page 6a-45) - Para 245 - Clause 3.8 of Section 6a of Volume 2 Specified discharge standards are available at CEA and in the
Please provide Discharge Standards. following web site of CEA.
http://www.cea.lk/web/images/pdf/envprotection/G_1534_18.pdf

1.7 Pursuant to Section 6d of Volume 2 – Supplementary information All available drawings are accessible under the following link.
https://goo.gl/U5PwmT
Please provide Details and as-built drawings of A list of available drawings is available in the same link and As
Colombo Sewerage Network. Attachment 1 for these replies.
2. Responses to questions received from bidders on 03 August 2017
2.1 Page P1 -19, Clause ITB 39.2, Please provide ITB 39.2. The ITB (page 2-6) stops at Section 2 is to give details if so stated in Section 1. In Section 1
38.1
after 38.1, no clause indicates making reference to Section 2.
So it is correct that Section 2 stops with 38.1
2.2 Page P2 -2, Clause ITB 13.1, Please specify which alternative is not permitted. Having Bidder is expected to submit an offer for whatever methodology
not received any design, we do not understand on which base we could propose an to conform to the Employer’s Requirements as detailed in
alternative. Section 6. Only one such methodology is expected from the
bidder, and the bidder does not have the opportunity to give
another alternative methodology.
2.3 Page P1 -3, Clause ITB 2.2, Please provide a copy of the "Financing agreement" Refer to the ADB website with Project Reference 45148-008 &
Loan references 3348 & 3349. ‘Greater Colombo Water and
Wastewater Management Improvement Investment Program
(Tranche 3)’
2.4 Page P6a -37, Para 199, Please provide a copy of the letter of environment clearance Copy of environmental clearance certificate is available in the
and environment compliance requirements imposed by the CEA Google Drive link subject to extension (Application for the
extension to this certificate has already been submitted to CEA)
Copy of no objection letter from Coast Conservation and Costal
Resource Management Department (CCCRMD) letter is
available in the Google Drive link. This no objection is subjected
to submission of successful DBO contractor his design for the
approval of CCCRMD.
Copy of environmental clearance certificate from Marine
Environment Protection Authority is available in the following
Google Drive link
https://goo.gl/U5PwmT under folder ‘Environmental Clearance’
2.5 Page P6a -37, Para 199, Please provide a copy of the EMP & Environmental Copy of EMP which includes Environmental compliance in the
Compliance Requirements will be issued as an addendum.

3 / 10
No Questions Answers
2.6 Page P2-2, Clause ITB 13.4, Please provide TECH 1.3 and TECH 1.4 These should be read as TECH 3 and TECH 4. These are
provided at the end of Section 4.
2.7 Page P4-15, schedule 5b, Please specify if we have to consider the annual volume as The table 5b provides the overall quantity of wastewater
a daily average or daily max values once divided by 365. anticipated for a year to the treatment plant. This should not be
mixed with the design requirements related to hydraulic load as
given in the Employer Requirement. The design should be able
to accommodate with minimum, average and peak daily flows.
For this purpose. Employer Requirement gives Peak WWF,
Peak DWF and ADWF. The contractor can assume the
minimum flows to the plant based in the above details.
2.8 Page P4-22, 4(a), Please confirm the Design Report needed for 60% payment is the Confirmed. On acceptance of Design Report
one defined in item 40 page 6a-6
2.9 Page P6a -43, Section 6a-Clause 3.7.1, What is the wastewater influent temperature Take the temperature as 280C; with minimum and maximum as
(min, max, average) ? 260C and 290C.
2.10 Page P6a -38-43, Section 6a-Clause 3.4.6, The flows coming to the WWTP are not Answer not finalized. Will be answered later.
fully clear and identified in the description for our calculations.
Would it be possible to make a comprehensive list/table of all incoming flows with
forecasted flows and characteristics at the different time horizons 2020 and 2040 (PS8
pump station, Dehiwala Pump Station, Sri Jayawardherapura Pump Station, Gravity
flow to Wellawata WTP, Colombo South Hospital Pump Station, …) ?
2.11 Page P6a -38-44, Section 6a-Clause 3.4.6, Could you also precise concerning those Answer not finalized. Will be answered later.
flows :

o what is understood with MAX. flow rate, i.e. instantaneous, hourly peak -- i.e. what
can the duration be of these maximum flow rates?
o How often can the MAX. flow rate occur ?
2.12 Page P6a -38-45, Section 6a-Clause 3.4.6,Could you please confirm that the following Answer not finalized. Will be answered later.
understanding of the design flow for the WWTP is correct :

2.13 Page P6a -38-46, Section 6a-Clause 3.4.6, Can we assume the MAXIMUM Wet Yes, MAXIMUM and PEAK Wet Weather flows are same
Weather flow to be equal to the PEAK Wet Weather flow (both terms are mentioned,
see 235&236)?

4 / 10
No Questions Answers
2.14 Page P6c -2, Section 6c, Could you please confirm that the norms for the effluents to Discharge standards mentioned in the Schedule of Guarantees
be respected are the ones in section 6c - schedule of is a must meet requirement irrespective of discharge through
guarantees whatever the discharging methods (near shore, short outfall and long near shore, short or long outfall. This standard shall be met
outfall) ? before releasing the treated effluent to the outfall.

2.15 Page P6a -36-7, Section 6a-Clause 3.2, Who is in charge of permits (all permits to be Operating License to operate for 18 years would be given by the
listed) for the project during the D&B and during the Operation period? Colombo Municipal Council, who would be the employer for the
Operation Service Period.
All other permits required to be obtained by the Contractor
during the Design-Build period if so specified by law, need to be
obtained by the Contractor at their cost, for which assistance
would be provided by the Employer.
Any permits need to be obtained by the Employer by law, would
be obtained by the Employer.
2.16 Page P4 -21, Section 4-para 3, 'Could you please confirm that the second payment for The schedule No 2 payment would be 40%. Hence the total
the Schedule n°1 – plant and equipment supplied from abroad - & Schedule n°2 – Plant payment made at that stage would be 40% + 20% (advance),
and equipment supplied from within the Employer’s Country - is 40 % of the total totally to 60%.
amount which means that the payment at that time for those schedules reaches 60% of
the total payment (including 20% advance payment) ? Or do we have to understand
that this payment is 20% of the total amount which means that the payment at that time
for those schedules reaches 40% of the total payment (including 20% of advance
payment) ?
2.17 General - Would it be possible to receive an electronic version of the tender Section 4 – Bidding Forms are available in the following link as
documents? (Not PDF but "Word" & "Excel" files) WORD files.
https://goo.gl/U5PwmT under folder’ Bidding Forms’
2.18 Genera - Can we please receive the “As-built” drawing of the sea outfall? As built drawing of the Sea Outfall is available in the following
link
https://goo.gl/U5PwmT under folder ‘Drawings & Details of
Structures’ In Sub-Folder ‘Sea Outfall’.
2.19 Page P6d -2-4, Section 6d, can we please receive officially: - As stated in Section 6d, Page 6d -2, Climate data is a
collectible from the Meteorological Department.
- Climate Data - Geological, Geotechnical information and Land Survey Plan
- Geological Information can be collected from https://goo.gl/U5PwmT link.
- Geotechnical Information - Available details of existing utilities is available in the following
- Land survey plan link
- Details of Existing Utilities https://goo.gl/U5PwmT A list of available drawings is provided in
- Details and as-built drawings of Colombo Sewerage Network the same link and As Attachment 1 for these replies.
- Coastal Zone Development Work

5 / 10
No Questions Answers
-Available as-built is available in the following link
https://goo.gl/U5PwmT A list of available drawings is provided in
the same link and As Attachment 1 for these replies.
- Coastal zone development work is not a collectible from project
office.
2.20 Page P6a -46 to 52, Section 6a, Please provide clear plans, drawings & pictures for Please collect the required drawings from the Soft Copy of the
Figures 1 - 7 document available in the following link.
https://goo.gl/U5PwmT
2.21 Page P6a -33, Section 6a, Could you please provide us all as-built documents Available as-built drawings is in the following link
concerning the existing pumping stations and existing buildings & Structures at Site https://goo.gl/U5PwmT A list of available drawings is provided in
the same link and As Attachment 1 for these replies..
2.22 Page P6a -33, Section 6a, Could you please describe exactly what is meant by “trade” We could not trace this word in the quoted location. However,
waste water? the trade wastewater means wastewater from
business/industries involved with commerce and buying and
selling businesses
2.23 General - Could you please describe exactly the sources (flow/characteristics) of There are no major industries in Colombo. Separate wastewater
industrial waste water or any flow other than domestic waste water into the overall data for small industries are not available.
flows ?
2.24 Page P6a -42, para 232, Is the flow in 2020 limited to 35 MLD (average dry weather) No; Design need to consider peak factors and wet weather
because it is forecasted that the transboundary water flows will be eliminated? contribution
2.25 Page P6a -43, para 240, Will the Employer continue the sampling & analysis of the No: not planned during the bidding period
waste water to have a more representative composition of the current waste water?
2.26 Page P6a -45, para 245, Could you please forward the legal minimum discharge Specified discharge standards are available at CEA and in the
standards officially as we could not find it directly on the mentioned internet site? following web site of CEA.
http://www.cea.lk/web/images/pdf/envprotection/G_1534_18.pdf
2.27 Page P6a -45, para 247, Although it is not intended to use those new norms could you We are not authorized to release this. You may contact the CEA
please send us the “not yet legalized” but planned new standards for near shore, short if you need to have an idea about those proposed standards
outfall and long outfall effluent discharge?
2.28 Page P6a -9, para 55g, Could you please indicate a clear definition of what is meant by Answer not finalized. Will be answered later.
“stabilization” of sludge (definition/limits/units)?
2.29 Page P4-14, Section 4 bidding forms 4.14 Schedule 5a, Could you please indicate the 20 United States Dollars (USD) per ton
exact unit for the discharge costs of sludge 20 USD/x ?

6 / 10
No Questions Answers
3. Responses to questions received from bidders on 09 August 2017
3.1 Page P3-8, Section 3, Clause 2.4.1- Bidder’s Experience, we have successfully Evaluation would be done as per the criteria given in Section 3 of
the Bidding Document. It is left for the Technical Evaluation
executed one project meeting both capacity and estimated value. Team and the Procurement Committee to decide whether any
Also we have for ref similar projects meeting the capacity requirement of tender but of particular bidder is qualified or not depending on the documents
lesser value. submitted by the bidder.
Pl confirm if our request can be considered for qualification to bid

3.2 Page P3-8, Section 3 , Clause 2.4.1- Bidder’s Experience, All our ref projects are Evaluation would be done as per the criteria given in Section 3 of
the Bidding Document. It is left for the Technical Evaluation
located in home country – India. Team and the Cabinet Appointed Procurement Committee
Kindly confirm if our credentials of home country for both projects can be considered (CAPC) to decide whether any particular bidder is qualified or
for participation not depending on the documents submitted by the bidder.
3.3 Page P3-8, Section 3 , Clause 2.4.1- Bidder’s Experience , Contract operating period Evaluation would be done as per the criteria given in Section 3 of
the Bidding Document. It is left for the Technical Evaluation
of 12 years or more Team and the Cabinet Appointed Procurement Committee
Pl confirm if lesser operating period for reference project can be considered for bid (CAPC) to decide whether any particular bidder is qualified or
participation not depending on the documents submitted by the bidder.
3.4 Page P6a-7, Section 6a, Para 44- Disposal of unwanted material, As per clause the Para 44 applies to material due to demolition. Contractor shall
dispose such material on his own. However the disposal site
unwanted building material shall be disposed by contactor at disposal site. Please shall be acceptable to the Employer’s Representative due to
clarify the distance of disposal site from the WWTP site. environmental reasons.

3.5 Page P6a-7, Section 6a, Clause 1.9, We presume that only construction of outfall Construction work related to the outfall chamber and pipes will
depend on the change that the Contractor propose to the
chamber at WWTP site is in the scope of contactor. The disposal pipe (if any) from the treatment plant and the disposal arrangement
outfall chamber to sea outfall is not in the scope of contractor. Please Confirm.
3.6 Page P6a-8, Section 6a, Para 54, We presume that the bypass arrangement for Yes; However providing the overflow ahead of process units but
untreated wastewater shall be provided from the inlet chamber only. Kindly confirm after the inlet chamber is also acceptable
3.7 Page P6a-8, Section 6a, Para 54, As per Clause an electromagnetic flow meter shall As we are aware, magnetic flow meters are available for partially
be provided in the channel for the flow measurement of wastewater. filled pipes and open channel flow now. The Bidder/Contractor
For the flow measurement in open channel ultrasonic type of flow meter is used. Please shall determine installation location of the flow meter as per the
allow the contractor to use the ultrasonic flow meter for flow measurement. specifications given in the bid.

7 / 10
No Questions Answers
However, if a better, more reliable and accurate measuring
device compared to electromagnetic flow meter, which meets
the purpose of flow measurement and better suited for the
treatment plant design of yours you may propose in the bid.
3.8 Page P6c-3, Section 6C, There is some mismatch between peak flows. As per Answer not finalized. Will be answered later.
Guarantee Schedule, it is 1.3 of average flow, whereas in clause 233-page no. 6a -42,
Peak flow is 2.5 – 3 times of average flow.
Kindly clarify.
3.9 Page P6a-8, Section 6a, Para 54, We presume that for the flow measurement, a weir Refer 3.7 above.
with ultrasonic flow meter can be used.
Kindly confirm.
3.10 Page P6a-9, Section 6a, Para 54, We presume that the odor control system shall be Odour control shall cover all the process units where odour can
be a problem. Contractor is responsible for accurate
provided only in the WWTP Pumping Station, pretreatment area i.e. inlet chamber, determination of such processes.
screen and grit chamber.
Kindly confirm.

3.11 Page P6a-33, Section 6a, Para 54, As the Geo technical investigation has already Geo Technical report is available in the following link.
https://goo.gl/U5PwmT
carried out. Please Provide the report to bidder for estimation purpose. It may not representative of the entire site. Thus should be
considered as only indicative and the Client is not responsible
for the accuracy of the data.

3.12 Page P6a-34-35 Section 6a, Clause 3.1.16, As per clause, the contractor will No those will not be paid extra
investigate the buried utilities with the help of drawing available with CWM for
condition assessment.
The damage utilities shall be replaced and also relocate the utilities as per site
requirement.
We assume the cost of replacement, relocation shall be paid as extra. Please confirm.

8 / 10
No Questions Answers
3.13 Page P6a-42, Section 6a, Clause 3.6.2 para 235, We assume that the flow by 2020 Answer not Finalized. Will be answered later.
shall be 60% i.e. 35 MLD and 100% i.e. 50 MLD by 2040.
Kindly confirm.
3.14 Page P6a-43, Section 6a, Para 241, The Raw wastewater characteristics given in the Medium Strength is Confirmed
Table 3 given as Weak, Medium and Strong. We understand, parameters and values
listed under ‘medium concentration’ to be used for designing the WWTP. Please
confirm.
3.15 Page P6a-69, Section 6a, Clause 5.2.10, We assume that the permanent site boundary Yes the boundary wall shall cover the entire site
shall be done for complete site shown in the figure - 3, page no. 6a – 48 in green
outline.

3.16 Page P6a-97, Section 6a, Clause 8.1, Please clarify, In case of new Pumping station Both options are acceptable
the SCADA for pumping station need to be provided and integrated with WWTP
SCADA, or a common SCADA system can be provided.

3.17 Page P6c-2, Section 6c, we understand that plant shall be design to achieve the As per the Section 6c Discharge testing standards include
several heavy metals. The raw water quality tests that were
parameter given in table at page no. 6c – 2. As per the clause no. 244 page no. 6a – 45, done by us include small amounts of heavy metals (see raw
there is no significance concentration of heavy metals in wastewater. water quality data). Therefore, decision regarding heavy metal
Since the WWTP is being design for removal of organic pollutant only. We removal or not is entirely with the bidder. Treated effluent needs
to meet the prescribed quality standards in Section 6c.
understand, treatment unit for precipitation of heavy metal need not be proposed.
Please confirm.
3.18 Page P6b-1, Section 6b, we understand that during O&M, the electricity and fuel Entire cost of operation during the Operation Period including
electricity, fuel etc., shall be in the scope of the Contractor, and
charges for DG for O&M of WWTP shall be in scope of employer or in contractor’s. to be borne by the contractor.
Kindly clarify.
3.19 Page P6a-93, Section 6a, Clause 7.6, As per clause 545, there shall be 12 hours per
Answer is not Finalized. Will be answered later.
day power interruption and DG set to be used to operate the plant during this period.
We understand that if the interruptions will more than 12 hours, then the fuel charges
of DG set shall be reimbursed.

9 / 10
No Questions Answers
3.20 Page P6a-111, Section 6a, Clause 10, We understand that the energy generation/ Yes, it is optional.
recovery is optional.
Kindly confirm.
3.21 Kindly provide the duration allocated for the construction testing and commissioning It is given as 910 days in Section 8 under Sub-Clause 1.1.78
of WWTP.

10 / 10
Ministry of Provincial Councils and Local Government
Contract: Wellawatta Wastewater Treatment Plant
Contract No: GCWWMIIP-TR3/ADB/ICB-02/2017
BID CLARIFICATION NO. 2 (2 Question Sets)

No. Questions Answers


1. Responses to questions received from bidders on 11 August 2017
1.1 Volume 2, Page 6a-2, Para 8, we request client to provide clear drawings Locations of all the buildings and structures are indicated in the Survey Plan
which is available under “SI 06 - WELLAWATTA SITE” drawing in following link.
details indicating for all units to be demolished i.e. buildings & structures'
https://goo.gl/U5PwmT .
dimensions and locations marked on plot plan for WWTP & Pump Houses. With regard to details of structures, we will furnish the details available in the
same link and a list of the drawings is available in the link.

1.2 Volume 2, Page 6a-49, Fig. 4, We request client to provide available area With regard to details of drawings requested (AutoCad file) please refer the
details under Item 1 above.
details and plot plan (preferably AutoCAD file) for the area identified for
With regards to LWL and HWL at Pump houses, Refer drawings available at
WWTP & Pump Houses as the image indicated in Vol.2 do not have any following link https://goo.gl/U5PwmT in the folder ‘Drawings & Details of
dimension or coordinate. Structures’ in below sub-folders..
- 1. ‘10 Old PS’
We also request client to provide Finished Ground Level of the WWTP site - 2. ‘Wellawatta New PS’
and (Low Water Level) LWL & (High Water Level) HWL at Pump houses
(Both Old & New)
1.3 Volume 2, Page 6a-2, Para 10, and Page 6a-7, Para 45, Kindly specify Existing Junction Box not experienced any inundation/ overflowing in peak
monsoon weather conditions.
existing outfall inundates during peak monsoon or not? If yes, kindly specify
Available Flood information with us, from the Dept. of Irrigation and SLLRDC, is
the new HFL details to be considered for sizing WWTP. given in the link https://goo.gl/U5PwmT in following folder.
Also, mention existing Outfall HFL details and please provide As-built “Flood Level Information”
Please collect any further details as required from Dept of Irrigation and
drawings of outfall as mentioned under Para 215, page 6a-38 of Volume 2. SLLRDC.
As specified in Bid document Volume 2, page 6a – 35 there was no major
flooding according to historical data.
1.4 Volume 2, Page 6a-7, Para 46, Ultimate size required for designing of outfall Outfall capacity is 2400 l/s (207 MLD) : Page 6a-7 Para 46
This is a larger capacity than the design peak flow of 3 × ADWF2040. (3×50 MLD =
is in WWTP contractor's scope? Kindly clarify.
150 MLD) : Page 6a-42 Table 1 & Para 233.
Also, clarify the sizing criteria as we are unable to comprehend the clause Hence, unless otherwise the contractor plans to store and release (batch
specified under section 1.9 for sizing of Outfall design capacity. treatment) treated WW in a higher flow rate, there is no need to design the outfall.
While the outfall does not require any modifications as per above description,
Junction Box may require modifications/ shifting according to contractor’s design
and site layout of WWTP.

  1 / 28 
 
No. Questions Answers
1.5 Volume 2, Page 6a-52, Fig. 7, In case, New Outfall design is in Contractor's Please refer details under item 1.4 above with regard to Outfall design.
Kindly note that all the flows currently being directly pumped to Junction Box,
scope, kindly provide Mass Balance for Figure 7.0
should flow through the WWTP and only treated effluent should flow through the
Junction Box to the sea, once the WWTP is operational.
1.6 Volume 2, Page 6a-8, Para 55 and Page 6a-24, Para 119, The Scope for I. The scope for the project starts from the required reroutings for FMs, & if
necessary Gravity Sewers, to contractors desired locations.
this project starts from Inlet chamber of WWTP i.e. inlet chamber of Main
II. Wellawatta PS receives WW from Forcemains and Gravity sewers.
Pumping Station (MPS). Please Confirm. III. Junction Box receives WW from Directly connected FMs including short FMs
Also clarify whether Contractor need to include collection of sewerage from Wellawatta PSs.
IV. All the WW coming into Wellawatta should follow the processes described
(pipeline work) prior to inlet chamber of MPS. under Page 6a-8 Para 55 a. (i.e oil & Grease removal, Screening, Grit
If yes, please specify the complete details along with L-Section drawings for Chamber & secondary treatment).
the Sewerage network, if any. V. Since the FMs are in a relatively higher elevation than the Gravity sewers,
contractor has the option to perform the initial processes of Oil Grease
removal, screen and de-gritting separately for FM collected WW and
separately for Gravity Sewers.
VI. Available drawings of the FMs are provided in following link.
https://goo.gl/U5PwmT under following folder
“Forcemain Drawings”
VII. Also refer the sewer inflow sketches available in the same link under
following folder.
“Sewer Arrangement in Wellawatta PS SKETCH”
1.7 Volume 2, Page 6a-41, Para 224, Please provide the invert level and ground There are two pump houses at the proposed treatment plant site (i.e. Old
Wellawatta pump station and the new Wellawatta pump station). You will receive
at inlet arrangement to be considered for WWTP pump house. Also, meniton
the drawings of the two pump stations with these clarifications. The invert levels
in case if Contractor chooses New Pump house (10 Yrs old) to revamp and can be obtained from those drawings. Refer answer 1.2 above.
use the invert level inside that pump house will remain same or not? In case
Once the site is handed over to the WWTP Contractor any modifications to old or
of opting New Pump house (10 yrs Old) do contractor needs to include new pump stations will be as per the design requirements of the Contractor, thus
catchment of other sewerage areas whcih are not covered by this New Pump whether the invert levels will remain or not is your decision.
House? If yes please provide complete details of those catchments.
It is not clear what you meant by “need to include catchment of other sewerage
area”. The following important factors should be taken into consideration by the
DBO Contractor.
(a) All wastewater streams coming to the WWTP site shall be treated
(b) At present CFM9 force main and the force main Dehiwala-Mt Lavinia
scheme are directly discharged to the outfall land-based junction
chamber.
(c) Wellawatta old and new pump stations are hydraulically connected at the
inlet chambers to the two pump stations (Refer Sketch mentioned below)

  2 / 28 
 
No. Questions Answers
(d) Wellawatta new pump station is not operating now and pumping is
carriedout through the wellawatta old pump station. The pumped
wastewater is also discharged at the outfall land-based junction
chamber.
(e) Following wastewater streams are discharging to pump houses,
wastewater coming under gravity in W1 sewer line; wastewater coming
under gravity through CS16 sewer line; wastewater coming under gravity
through X1sewer line;
(f) In addition wastewater force main coming from Sri Jayawardhenapura
(g) In the near future new 1400mm trunk sewer will be laid along the Marine
Drive which will be connected to the inlet of the old pumping station of
Wellawatta

Present inflow and discharge scenario and discharge scenario after the Marine
Drive trunk sewer are shown schematically in the attached illustrations in
following link https://goo.gl/U5PwmT under folder “Sewer Arrangement in
Wellawatta PS SKETCH”
However, there will be no increase of design flow due to Marine Drive trunk
sewer. This new trunk sewer will intercept the wastewater discharged from Slave
Island, Polwatta and Bambalapitiya pump stations and bring it to Wellawatta.
Presently this wastewater is flowing through the CFM 9 force main. Thus after the
construction of the trunk sewer there will be reduction in the flow coming through
CFM 9 force main and the same quantity will flow through the trunk sewer.

1.8 Volume 2, Page 6a-43, Table 2, Since, the values of Organic content in As mentioned in Page 6a -111 Para 664, energy recovery is encouraged, but not
a compulsory requirement. Bidder may or may not choose energy recovery
Wastewater is fairly dilute (Lean values of BOD, COD etc.), we do not find
based on Bidder’s process and viability of this option.
Energy Recovery via Biogas (Methane) Generation and Power Production
feasible. Therefore, we request client to kindly exclude the requirement of
Energy Recovery from Contractor's scope.
1.9 Volume 2, Page 6a-45, Para 247, Kindly provide these mentioned discharge Draft standards are not relevant to this contract.
standard / draft of these standard (if not finalized.)
1.10 Volume 2, Page 6b-2, Section 1.2, Tipping fees for Sludge disposal to This cannot be changed.
nearest landfill is normally under scope of Client due to better liasoning of
Owner with MSW (Municipal Solid Waste). Therefore, we request client to
exclude the same from Contractor's scope. However, we confirm that the

  3 / 28 
 
No. Questions Answers
sludge disposal from WWTP site to Landfill shall remain in our scope abiding
all MSW guidelines.

1.11 Volume 2, Kindly confirm the Environmental Clearances and permissions Copy of environmental clearance certificate is available in the Google Drive link
subject to extension (Application for the extension has already been submitted to
(such as Coastal Zone clearances, utilities departments & departments &
CEA)
another environmental department) required for this project are already Copy of no objection letter from Coast Conservation and Costal Resource
taken by Client. Management Department (CCCRMD)letter is available in the Google Drive link.
This no objection is subjected to submission of successful DBO contractor his
design for approval of CCCRMD.
Copy of environmental clearance certificate from Marine Environment Protection
Authority is available in the following Google Drive link
https://goo.gl/U5PwmT under folder “Environmental Clearance”
1.12 Volume 2, Page 6a-6, Para 39, Our Software for Process Design shall be xls files are not acceptable. As mentioned in Page 6a-6, Para 39; a reputed
software (BioWin or equivalent) should be used.
encrypted xls files based upon sizing & design calculations as per Latest
Metcalf & Eddy for Wastewater Engineering. Kindly accept
General / Finance
1.13 Volume 1, Page 1-6, Clause 7.1, Bid submission date is of 6th Oct 2017, Yes
can we submit our queries before 21 days from 6 Oct 2017, as there are
many clarifications bound to arise after site visit? Kindly confirm.
1.14 Volume 1, Page 4-21, We request client to kindly consider the retention as Answer not finalized. Will be answered later
5% in place of 10% of CIF.
1.15 Volume 1, Page 4-21, From this clause we understand that Defect Liability Confirmed.
Period is of 1 year after successful commissioning of plant (i.e. getting
commissioning certificate). Request you to confirm it.
1.16 Volume 2, Request Client to furnish the Single Line Diagram of the facilities The Single Line Diagram of only the New PS is available in the following link
https://goo.gl/U5PwmT under Folder ‘Drawings & Details of Structures” in the sub
for better understanding of the Power Distribution philosophy.
folder ‘Wellawatta NEW PS’.
Please note that this does not include the modifications or alterations (If any) by
the CMC maintenance department.
1.17 Volume 2, Request Client to furnish the Soil Resistivity report. A soil resistivity report is not available.
1.18 Volume 2, Request Client to provide Soil Bearing Capacity, Soil Investigation Available under following link under “SI 05 - Wellawatta Report with all annexes”.
https://goo.gl/U5PwmT
report, Borehole Data at Project location.

  4 / 28 
 
No. Questions Answers
1.19 Volume 2, Page 6d-4, Para 8, Specifications indicate that the referred data Available drawings are accessible from following link.
https://goo.gl/U5PwmT A list of drawings is available in the same link.
is available with client. Kindly provide the same.
1.20 Volume 2, Page 6d-3, Para 7, Specifications indicate that the referred detail Available drawings are accessible from following link.
https://goo.gl/U5PwmT A list of drawings is available in the same link.
of existing utilities available with client. Kindly provide the same.
1.21 Volume 2, Page 6d-3, Para 6, Land Survey Plan including GIS Data This is available under following link. Please refer details/ answer given under
Answer 1.1 above.
required, as it is mentioned that same data is available with client. Therefore
https://goo.gl/U5PwmT A list of drawings is available in the same link.
We, request client to provide the same.
Instrumentation
1.22 Volume 2, Page 6a-2, Para 8, CCTV Specification in tender is not detailed. The number of cameras will be as per the WWTP layout. The commercially
available systems have minimum storage of one year within the system.
Kindly specify the number of CCTV cameras, their details, storage capacity,
Additional storage is possible with extra hard disks. These equipment are
location etc. standard items.
1.23 Volume 2, We understand that, there shall be a modem for wireless We have no comment on this statement. Details of the SCADA system will have
to be finalized at detail design stage. We do not see any reason for making the
connectivity to be provided at local control room of STP Plant which will be
WWTP data available in India.
connected to SCADA system and same SCADA will be published for remote
web client. However, complete SCADA system with its historical data and
trends can be monitored using simple Web browser with any internet
connection anywhere in India.
1.24 Volume 2, Tender doesn't specify the measurement of Mechanical vibration We do not consider vibration monitoring as mandatory for all rotating machinery
although it may be beneficial for high capacity submersible pumps. However
in rotating machinery. Thus, we have assumed measurement of Mechanical
these issues may be sorted out at the detail design stage when the equipment
vibration in rotating machinery is not required as no heavy duty or HT motors data are available.
envisaged. In case if it required, our scope shall be limited to only HT Motors
mechanical vibration measurement only.
1.25 Volume 2, Page 6a-96, Para 579, We could not find the details of Fire Alarm Fire alarm system needs to be finalized after finalizing the WWTP design.
system. Kindly provide complete details of the system required.
1.26 Volume 2, Page 6a-96, Para 580, We could not find the details of Telecommunication system needs to be finalized after finalizing the WWTP
design.
Telecommunication system. We request client to provide complete details for
the following.

  5 / 28 
 
No. Questions Answers
1.27 Volume 2, We could not find the details for Public Addressing System Public Addressing System needs to be finalized after finalizing the WWTP
design.
(loudspeaker talk-back communication system). Hence, we presume that the
same is not envisaged. Please confirm.
Electrical Queries
1.28 Volume 2, Page 6a-93, Para 545 and 546, Please clarify the number of We have indicated 12 Hours as the maximum expected duration of power
interruption. It does not mean that there are regular power interruptions.
hours mentioned as 12 is per day power outage or per week.
No diesel charges will be borne by the Employer.
Also, confirm Diesel charges during power outage / grid failure shall be borne
Client.
1.29 Volume 2, Page 6a-91, Para 536, Kindly note that the valid Type test reports This is not acceptable. All the testing should be done as specified in the Bidding
Document Volume 2 Chapters 4 and 5.
(with in last five years), conducted on equipment of similar or higher rating,
will be submitted during execution stage for information.
Conducting Type tests is not envisaged. Please confirm.
1.30 Volume 2, Page 6a-108, Para 647, As the efficiency class of motors is not The efficiency class of the motors are to be decided by the bidder based on
return on investment and his commitment to environment
mentioned in the tender specifications, we request client to specify the same.
1.31 Volume 2, Page 6a-92, Para 542, Kindly specify the distance from CEB till The location of the MDB for the STP will depend on the distribution of loads.
MDB. Which shall provide HT / LT Supply to STP / MPS.
Supply is available at 400/230V for capacities up to 1000kVA. Supply is also
Also, specify the details of Supply i.e. kV line details to size step down available at 11kV for higher capacities.
transformer if required.
2. Responses to questions received from bidders on 14 August 2017
2.1 Volume 1, Page 2-3, Price schedule, as per our understanding VAT Understanding is correct.
applicable on Schedule No.2, 3, 4,5 and 6 not to be included the Price
Schedule which will be paid extras as applicable during the contract Period by
the Employer.
Please confirm our understanding.
2.2 Volume 1, Page 4-7, Price schedule, please clarify whether the Tenderer Understanding is correct that the customs duty will be reimbursed on actuals.
shall be permitted to submit revised list of Schedule -1 during Contract However it does not mean that the items and CIF prices can be revised. Please
Execution to custom Duty payment and reimbursement. Since it may be not refer to sub clause 14.1 of Section-08, Page 8-15.
possible to estimate actual quantity requirement during proposal stage.

  6 / 28 
 
No. Questions Answers
2.3 Volume 1, Page 8-150, Sub-Clause 14.1, Whether the Contractor to All taxes applicable to the contractor, other than VAT have to be included in the
consider NBT (National building Tax) in the Bid price. rates/prices quoted.
2.4 Volume 1, Page 3-3, Clause 1.3.1, We understand the domestic preference Yes the understanding is correct. In this regard please refer Sub-Clause 5.2 in
will be given for only those products which are manufactured in Sri Lanka. Page 1–5 of Section 1 - Instructions to Bidders
2.5 It is expected the Bidder to have identified a sub-contractor for any specific items
Volume 1, Page 3-10, Sun-contractor, please clarify whether the qualification or work listed at the bidding stage and the price quoted by the bidder based on
of subcontractors has to be submitted with the bid or it can be submitted at a such sub-contractor. If for any valid reason the Sub-Contractor need to be
later stage. changed, it may be possible with the concurrence of the Employer’s
Representative. Please refer Sub-Clause 4.4 in FIDIC Condition of Contract.
2.6 Volume 1, Page 4-32, Bid Security Format, we have gone through the letter Answer not finalized. Will be answered later.
and feel that in 4th para, 3rd line, the word “AND” to be replaced with “OR”
because the expiry date of the BG is referring to two different activities and it
cannot be “AND”. Please confirm our understanding.
2.7 Volume 1, Page 4-32, Bid Security Format, we have gone through the letter This is already provided for as a footnote in page 4-32
and understand that ICC publication no to be modified as “758” i/o “458”,
since “458 version” is no more exist in the current banking practice and it
being obsolete. Please confirm our understanding.
2.8 Volume 1, Page 4-32, Bid Security Format, We feel that the Bid Security is Confirmed. The Bid Security can indicate the end date of the validity period.
open ended and can be modified further by
a. At the end of the 4th para, include a separate sub-division for clear expiry
date followed by the word “WHICHEVER IS EARLIER”.
B.At the end of the 5th para, we have once again provided the provision to
add the expiry date for the fact that the statement is ending with “ON OR
BEFORE THAT DATE” which is not clearly defined.
Request your confirmation for the above points.
2.9 Volume 1, Page 3-4, Please clarify how the contract value will be assessed Answer not finalized. Will be answered later.
in case it is in different currency and executed in last 10 years.

  7 / 28 
 
No. Questions Answers
2.10 Volume 1, Page 8-7, Sub-Clause 20.3, If there is no condense in appointing DAB has been provided to be 3 members. Please refer Sub-Clause 20.3 in FIDIC
a sole person then three members should be appointed as DAB i.e. one Conditions of Contract in Section 7 of the Bidding Document
member by each party and the third member by both the selected members.
Please confirm.
2.11 Volume 1, Page 8-7, Sub-Clause 20.3, We request you to consider our It is not possible to change these provisions.
request of changing the arbitration from ICC to SINGAPORE
INTERNATIONAL ARBITRATION CENTRE, AT SINGAPORE BY SOLE
ARBITRATOR.
2.12 Volume 1, Page 8-11, Sub-Clause 4.14 , Please note that since we do not Answer not finalized. Will be answered later.
have any details of underground cables and other buried utilities, the
consequential damages cannot be accepted. Request you to consider this
request.
2.13 Volume 1, Page 8-14, Sub-Clause 10.2, We understand that instruction The Employers Representative is expected to issue instruction within 28 days.
shall be issued within 28 days of the commissioning certificate and in case it However if it is unable to be done so, then the Variation procedure as provided for
is not done, it shall be considered as deemed approval for operation in GCC 13.1 and 13.3 will apply
commencement and contractor is liable to raise the bills.
2.14 Volume 1, Page 8-6, Sub-Clause 17.8, The total liability of 110% of the Answer not finalized. Will be answered later.
amount given in the LOA for the design built period is very high and it should
be capped at 100%. Please confirm.
2.15 Volume 1, Page 3-9, and your letter ref. Wastewater from demolition sites will not be allowed to sewerage system except
GCWWMIIP/TR3/ADB/ICB-02/2017, We understood that any influent for any domestic type wastewater such as from labour quarters, site offices, etc.
coming from building and demolition sites can also be classified as Trade
Wastewater. Any waste coming from building will be domestic wastewater as
per the definitions laid in various literatures on wastewater, and there is no
specific definition of demolished site wastewater in any literatures. Hence, we
request you to clarify it further.

  8 / 28 
 
No. Questions Answers
2.16 Volume-2; Pg:6a-101, Clause 8.5, Para 608, From the Tender Document Detail specifications for any of the equipment are not available and are to be done
we understand that there are no Detailed Technical specification by DBO contractor. Section 6a- Design & Build Requirement – 8.
requirements provided for Instrumentation and Control system and the bidder Instrumentation and SCADA describe the requirements for the Instrumentation
is free to propose the required specification for Instrumentation and control as and SCADA. All IEC standards applicable for instrumentation and control
per good engineering practice. system are to be followed.
2.17 Vol-II; Pg:6a-97, Clause 8.0, We understand that transmitters and analyzers Confirmed
shall have 4-20mA DC output for process value measurement. Kindly confirm
2.18 Vol-II; Pg:6a-100, Clause 8.5, Para 598, We understand that bidder can No. The control of equipment in each area shall be by local PLC’s independent of
propose Remote I/O Panels for different areas in the plant. These Remote I/O any centralized PLC.
panel can be connected to a central PLC. Kindly confirm
2.19 Vol-II; Pg:6a-100, Clause 8.5, Para 598, The Plant shall have a PLC based There is no redundancy requirement for the processor, power supply,
control system with redundant processor/controller, redundant power supply communication or IO.
modules, redundant communication module and Non-Redundant
Inputs/Outputs (I/O). Kindly confirm our understanding
2.20 Vol-II; Pg:6a-100, Clause 8.5, Para 598, With wide experience in Water We have no objections
Treatment sector, we are proposing the following channel density for IO cards
(AI, AO, DI, and DO). The following channel density will ensure efficient use
of control room space and also spare management without compromising on
the monitoring, controlling and safe operation of the sewage treatment plant.
DI – 32 Channel DO – 32 ChannelAI – 16 Channel AO – 8 Channel Kindly
confirm if this is acceptable.
2.21 General - We understand that instrument and valve signal cables shall be It is preferable to lay yard cables in flexible HDPE conduits from building to
directly buried underground in outside areas and shall be laid in cable trays building to avoid seepage of water and salt. However this is an issue to be
within buildings. Kindly confirm addressed at design stage.
2.22 Vol-II; Pg:6a-6, Clause 1.8, Para 43, In case of demolishing the existing We have no objection after quality check. Please note that joints are not allowed in
2Nos pumping stations, the Power & control cables from the existing building these installations.
shall be utilized by the bidder for the proposed new plant. Kindly confirm
2.23 Vol-II; Pg:6a-6, Clause 1.8, Para 43, Kindly furnish the Quantity & sizes of This information not available.
cables available at the existing pumping stations.

  9 / 28 
 
No. Questions Answers
2.24 CEB transformers are the property of CEB. Power supply is billed at 400/230V
level. However the supply is also available at 11kV (under different tariff) and in
Vol-II; Pg:6a-32, Clause 3.1.7, Para 187a, Kindly share the technical details
this case the transformer need to be supplied and maintained by the consumer.
of the existing CEB transformer (rating, voltage, make) existing fault level and
Bidder is free to decide on the optimum tariff system. Latest tariff details are
the drawings of existing panel (available spare breaker ratings & qty) at old
available in the CEB Website. Transformers are normally manufactured by Lanka
pump station which is feeding our new pumping station panels.
Transformers Ltd. Fault level at transformer out is generally considered to be
35kA fault level.
2.25 Vol-II; Pg:6a-32, Clause 3.1.7, Para 187a, Kindly confirm whether only one At present only one power supply is available for the new and old power stations.
power supply is made available for the new pumping station. Also furnish the Whatever information available on the existing facilities indicated in the as-built
scope of cables from the old pumping station to new pumping station and drawings available under following link.
location of old & new pumping stations. https://goo.gl/U5PwmT under folder ‘Drawings & Details of Structures’.
2.26 The local pump stations (Existing within the premises) are presently powered with
Vol-II; Pg:6a-32, Clause 3.1.7, Para 187b, For local pumping stations if any the CEB main power available. As indicated in the bidding document requirement,
the power supply for the local pumping station panels shall be taken from the decision as to whether to retain these pump station or abolish them is with the
nearby CEB mains power available. Kindly confirm. contractor. As such there is no requirement for using the available power supply.
Contractor is free to decide on the power distribution for optimizing.
2.27 Vol-II; Pg:6a-71, Clause 5.2.14, Para 376, Cable laying outside the plant Please refer to Vol-II; Pg:6a 94 Para 562, Clause 7.13 for cable laying
area for interconnection if any shall be through buried underground cable. requirements
Kindly confirm.
2.28 Vol-II; Pg:6a-90, Clause 7.1, Para 531, This clause is applicable only if Confirmed. However, contractor has to ensure basic requirement for
bidder utilizes the existing building. Otherwise no electrical work will be environmental, safety and other general requirement of the structures.
carried out in any of the existing buildings. Kindly confirm.
2.29 Vol-II; Pg:6a-92, Clause 7.4, Para 538, Purchaser to furnish the details of As indicated in 2.24 above, the existing transformer is the property of CEB and it is
existing transformer datasheet, year of installation, years of service to maintained by CEB. Therefore, the healthiness of the transformer is not important
determine the healthiness of the existing transformer. Kindly provide the to the contractor at present.
required details.
2.30 Vol-II; Pg:6a-92, Clause 7.4, Para 538, In case the existing transformer is The question is not clear. However, we like to clarify once again, there is an
not used, kindly clarify whether the new transformer will receive the power existing transformer installed by CEB which provide power supply to the entire
directly from CEB or from any of the existing panels. premises at 400/230V. The decision as to whether this supply

  10 / 28 
 
No. Questions Answers
 to be used as it is or
 upgrade the capacity or
 obtain a new transformer additionally or
 completely discard the existing power supply and obtain new power
connection at 11kV or any other voltage/ any other tariff system
is a decision at contractor’s discretion. Please refer 2.33 & 2.34.
2.31 Vol-II; Pg:6a-92, Clause 7.4, Para 538, Kindly furnish the terminal details of Proposed plant is contractor’s design which is not available presently.
CEB power and furnish the distance of the CEB power from the Proposed
plant.
2.32 Vol-II; Pg:6a-92, Clause 7.4, Para 542, This clause does not match with Answer not finalized. Will be answered later.
S.no538. Kindly confirm whether the proposed plant shall be supplied from
the existing transformer or CEB power will be terminated till new transformer
primary.
2.33 CEB has installed 11/.4 kV transformer and CMC has signed an agreement with
CEB to obtain sufficient power for the pump stations. The capacity is
Vol-II; Pg:6a-92, Clause 7.4, Para 542, Kindly furnish the details of the approximately 250kVA (400A Incoming breaker) For the power requirement
available CEB power. including the WWTP, the contractor will have to make his own arrangement with
CEB to enhance the capacity or add another supply point according to his power
requirement and distribution plan
2.34 Vol-II; Pg:6a-92, Clause 7.4, Para 542, Power cable & required control Please refer to Item No. 2.30 & 2.33 above. Supply of a new transformer is
cables termination up to new transformer primary terminal shall be in applicable only if the bidder proposes to receive power supply at 11kV under 11kV
Purchaser's scope. Kindly confirm. Bidder's scope starts from the supply of tariff. In that case the bidder will have to bear the cost of the transformer power &
new transformer only. control cables and switchgear and maintenance cost.
2.35 Vol-II; Pg:6a-93, Clause 7.7.2, Para 550, MDB shall be provided with 2 Two interlocked incomers will be required to implement load transfer between
incomers one from CEB power & other from the DG set. Kindly confirm. CEB and DG. Confirmed.
2.36 Vol-II; Pg:6a-93, Clause 7.8, Para 5553, For measuring the power for Tariff meters will be supplied by the CEB. The contractor needs to provide energy
electricity bills for pump house (if retained) & treatment plants suitable monitoring as a performance indicator. (Clause 556)
measuring instruments shall be provided at the incomer feeder. Kindly
confirm.

  11 / 28 
 
No. Questions Answers
2.37 Vol-II; Pg:6a-94, Clause 7.11, Para 547, in case the old & new pump house Confirmed.
retained for operation, then all these houses are already having existing
power supplies. Hence there is no need of providing supply from the
proposed plant MDB. Kindly confirm.
2.38 Vol-II; Pg:6a-95, Clause 7.16, Para 567, Only routine test for electrical Final product shall be witness tested as per ERQ. For the major components type
equipment’s shall be carried out for the offered equipment. However, for type tests/ routine test are acceptable.
test, typical test certificates of similar rated equipment shall be submitted.
Kindly confirm.
2.39 As per the Geotechnical Report the ground water table is at 2 – 3m from the
Vol-II; Pg:6a-33, Clause 3.1.4, Design Water Table:
existing ground level. But as mentioned in the Vol-II; Pg:6a-33, Clause 3.1.4,
Design ground water levels for checking uplift of civil units shall be as per
Design Water Table, despite this, contractor shall study the water table
recommendations in the geotechnical investigation repertoire, 2 m from
conditions as part of his geo-technical investigations to verify the data already
existing ground level. Please confirm.
furnished.
2.40 Vol-II; Pg:6a-33, Clause 3.1.5, Existing buildings, Structures at site: Please refer reply / details under Bid Clarification 02, Item 1.1 of the “Responses
Please provide as built drawings of New pumping station, old pumping to questions received from bidders on 11 August 2017”.
station, office building and Sea outfall land based junction chamber.
2.41 Vol-II; Pg:6a-35, Clause 3.1.8, Drainage and Flooding: Not available. Please collect the required details from Meteorological Department
Kindly furnish the design rainfall intensity for Storm Water Drainage Design as specified under Page 6d-2 of Volume 2.
and also furnish the disposal point of Storm Water Drainage from the site
boundary.
2.42 Vol-II; Pg:6a-35, Clause 3.1.8, Soil Condition: Each bidder may decide on this based on the proposed treatment process and his
We presume Finished Ground Level(FGL) will be same as that of existing design layout.
ground level. We will be doing micro grading near the structures, wherever
required. Kindly confirm.
2.43 Bidders may follow relevant RDA standards / acceptable International standards
Vol-II; Pg:6a-71, Clause 5.2.15, Specifications of Roads and Parking
regarding the cross section of the Internal roads including Stormwater drainage
Areas: Please furnish the Cross-sectional details of Plant Roads.
design.

  12 / 28 
 
No. Questions Answers
2.44 Vol-II; Pg:6a-76, Clause 5.2.25, Design of Concrete Structures: Please follow the Standards and Codes of Practice given under Vol-II; Section 5
We presume minimum grade of concrete for liquid retaining structures shall Civil Works.
be C35(Cube Strength) and C30(Cube Strength) for other structures.
2.45 Please follow the instruction as specified in the Vol-II; Pg:6a-36, Clause 3.1.9.
The length is to be determined after assessing the existing boundary walls and
Vol-II; Pg:6a-36, Clause 3.1.9, Length of Boundary Wall: bidder’s architectural / landscaping designs/ security/ structural/ Social/
Please provide the total length of new boundary wall to be constructed. Environmental designs. The wall should cover the perimeter of the land allocated
for the WWTP. Please refer Drawing provided under “SI-6A” in the following link
https://goo.gl/U5PwmT in the folder “Key Map & Survey”
2.46 Vol-II; Pg:6a-6, Clause 1.16, Structural Design Software: Answer not finalized. Will be answered later.
We request you to include STAAD Pro V8i also in the list.
2.47 As specified under Vol-II; Pg:6a-78 Para 445. Cement to be used should be
conforming to national or international standards acceptable to Employer’s
Vol-II; Pg:6a-78, Clause 5.2.27, Type of cement:
representative. Cement type shall suit the purpose of the structure and
Kindly furnish the type of cement to be used for the concreting works
environmental setting. Contractor shall choose the cement type and obtain the
employer representative’s approval.
2.48 Generally follow the Vol 2: Section 5 Civil Works.
Architectural work should be performed by a qualified architect experienced in
Architectural specifications:
similar work, and all the architectural & landscape designs should be aesthetically
General - Kindly provide architectural requirements such as brick/ block
pleasing and matching with the environment and the surrounding of the Site.
works, plastering, painting, joinery’s, roof treatment, flooring etc.
Contractor may follow relevant ICTAD (CIDA) specifications of Sri Lanka, and
internationally accepted architectural practices for similar works.
2.49 Volume I – Page. 4 – 16, Schedule 5c, it is mentioned as " COD removal Answer not finalized. Will be answered later.
shall cover the contractor's energy cost and chemical cost associated with
removal of COD".
Query: We wish to inform that fixed power like plant internal lighting,
continuous operation of clarifiers and thickener mechanism is not dependent
on the COD removal. We request the client to provide separate line item for
capturing fixed power cost. Please confirm

  13 / 28 
 
No. Questions Answers
2.50 Volume I – Page: 4 – 16 & Page: 6c – 2, It is mentioned as "Failure to meet Answer not finalized. Will be answered later.
one or more of the effluent discharge standards specified in the schedule of
guarantee - Penalty is 10,000 USD/day"Query:We would like to inform that,
as per the discharge and testing standards; testing frequency of pH and
temperature is per hour basis and measuring of TSS and fecal coliforms is
per day. All other parameters are mentioned as weekly, monthly, quarterly
and every 6 months once. We understand that the bidder shall meet pH,
temperature, TSS and fecal coliforms on daily basis and all day will be
imposed to bidder. Please confirm other parameters as per the schedule. If
the bidder fails to meet the above parameter like pH, Temperature, TSS and
fecal coliforms on daily basis than the penalty of 10,000 USD /
2.51 Volume I – Page: 8 – 4, Defects, Period for notification of errors, faults and Volume 1 Page 8-4, Sub clause 5.1 is referring to FIDIC GCC 5.1 in Section 7.
other defects - 56 days Please refer FIDIC Clause 5.1.
Query:
We understand that this contract does not have any defect notification period
and contract period is 910 days of construction period and 18 years O&M
period. Please confirm.
2.52 Vol. II – Page: 6b – 2, Clause 1.2, It states "the Contractor shall arrange for In such instances, the Variation procedure as provided for in GCC 13.1 and 13.3
the disposal of all waste derived from the Works to a site to be nominated by will apply.
CMC not more than 20 km from the Colombo city limits.
Query:
We understand that approved disposal land for sludge disposal will be
provided by client and during the O&M period of 18 years if the sludge
disposal site exceeds beyond 20 kms than the sludge transportation cost for
excess distance will be reimbursed by client. Please confirm.

  14 / 28 
 
No. Questions Answers
2.53 Vol-I; Insurance, It is mentioned as follows. Answer not finalized. Will be answered later.
1) Insurance of Contractor’s Equipment
2) Amount of professional liability insurance
3) Period for which professional liability insurance required
4) Injury to persons and damage to property
5) Injury to employees
Query: We understand the above insurance clause is applicable during
Design built stage. We request the employer to confirm the insurances that
will be applicable for 18 years O&M period. Please clarify.
2.54 Vol. I – Page: 4 – 16, Appendix-1 Schedule of Performance damages, Answer not finalized. Will be answered later.
Sludge, Smell and Noise Standards
It is mentioned as Minimum volume of on—site storage to be provided - unit is
m3 and allowable limit is 5 days
Query:
We understand that the bidder can store the generated waste / grits and
sludge collected in the WWTP for 5 days. Please confirm
2.55 Vol. I – Page: 4 – 16, Appendix-1 Schedule of Performance damages, Answer not finalized. Will be answered later.
Hydraulic capacity standards
Query:
We request the client to kindly specify the timing and duration of peak flow
under Hydraulic capacity standards
2.56 Vol. I – Page: 4 – 16, Maximum LD, No change can be done.
10% of the Accepted Contract Amount.
Query:
The maximum LD specified during O&M period is very high & unreasonable
as it is on total contract value. We request the client to kindly consider
maximum LD during operation period as 10% of the annual contract fee.
Please confirm

  15 / 28 
 
No. Questions Answers
2.57 Vol. II – Page 6a- 17, Para 81, The Contractor shall provide transport Confirmed.
facilities to the Employer’s Representative on the following basis
Query:
We understand that the bidder shall provide transport facilities to the
employer’s representative only during design-built stage and not in operation
period. Please confirm.
2.58 Volume I – Page: 4 – 28, Price schedule 5a, with effect from the bid base Colombo Consumer Price Index is one figure and there are no further categories.
date rate of USD 20 equivalent in LKR charge fee for sludge disposal shall be
adjusted Colombo Consumer Price Index published by the Government of Sri
Lanka Department of Census and Statistics.Query: We request the client to
kindly provide the category under consumer price Index that will be used for
adjustment of sludge disposal tipping fee annually.
2.59 During design and construction phases, any activity of the contractor connected
with these Force mains should not disrupt the on-going flow. ER’s approval should
Volume II – Page: 6a – 34, Clause 3.1.6, It is mentioned as follows be taken prior to such activities.
b) 1100 mm DI force main from the S8 pumping station to outfall junction
champer. It is NOT Contractor’s responsibility to maintain/ operate the Feeding Pumping
c) 400 mm force main from the Dehiwala - mount lavinia stations and Force mains to Wellawatta WWTP. However, the Force main
d) Force main from Srijayawardhenpura to Wellawatta new pumping station segments within WWTP premises will remain the responsibility of the contractor
e) Force main from colombo south hospital to Wellawatta new pumping during whole Design Build and Operation period of 18 years.
station
Query: During operation period, if contractor requires doing any modifications/
We understand that bidder should maintain the existing collection system maintenance work, there should be no disruption to the flow from the incoming
pumping station like S8 pumping station, Dehiwala pumping station, Sri Force mains and Gravity Sewers. ER’s approval should be taken prior to such
Jayawardhenpura PS, Colombo south hospital PS during 18 years O&M activities, in case a need arises.
period. Please confirm.
Also, contractor should make sure to treat the WW coming from all the Force
mains and gravity sewers during Operation period of 18 years.

  16 / 28 
 
No. Questions Answers
2.60 Volume II – Page: 6a – 44, table 3, Typical Composition of Untreated Available records of wastewater analysis results were provided to the bidders.
Domestic Wastewater Client has no intention of carrying bout further analysis. If any bidder wants to
Query carry out his own analysis, Employer can allow the bidder to collect samples.
We request Client to provide us the latest raw sewage analysis reports for
arriving at the design basis
2.61 Volume II – Page: 6b – 2, clause 1.2, It is mentioned as "Contractor shall Please prepare the Technical and Price proposal assuming the disposal site will
pay a tipping fee of US$20 equivalent in LKR per ton of waste sludge be as specified in Vol 2 Page 6b-2 Clause 1.2.
delivered to the CMC solid waste disposal facility nominated by the CMC, GOSL is currently in the process of identifying and establishing such disposal
which is to be increased as provided for in the price schedules" sites, Most probably such sites will be operational by 2020.
Query
We request Client to kindly specify the approved disposal site for disposal of
screenings/grit generated during operation of existing pumping stations
2.62 Volume II – Page: 6b – 2, clause 1.2, It is mentioned as "Contractor shall Please refer above answer.
pay a tipping fee of US$20 equivalent in LKR per ton of waste sludge
delivered to the CMC solid waste disposal facility nominated by the CMC,
which is to be increased as provided for in the price schedules
"QueryWe request Client to kindly specify the approved disposal site for
disposal of screenings/grit generated during operation & maintenance period.
Also specify the tipping charges if applicable
2.63 Volume II – Page no: 6a – 94, Contractor shall determine the changes Answer not finalized. Will be answered later.
required to the existing power supply arrangement and the power supply for
the pump station
Query
As paying electricity charges by the contractor which make huge impact on
cash flow during O&M. So, we request client to consider the electricity
charges shall be paid by employer directly to the electricity authority. Kindly
accept this request.

  17 / 28 
 
No. Questions Answers
2.64 Volume I – Page:4 – 13 - B2, Price schedule 04, Existing Wellawatta No price escalation is provided for Price Schedule 4
pumping station - Operations and maintenance during entire Design-built
Period
Query Please explain how the payments will be done in case the electricity
prices increase in Design and Built period.
2.65 Volume I – Page no:4 – 13 - B2, Price schedule 04, Existing Wellawatta Operation and maintenance during the Design-Built Period is the entire
pumping station - Operations and maintenance during entire Design-built responsibility of the Contractor.
Period
Query
Please confirm which authority will be responsible for payments of operation
and maintenance during Design and Built period.
2.66 Volume I – Page no:4 – 13 - B2, Price schedule 04, Existing Wellawatta Payments for Operation and Maintenance during Design-Built Period could be
pumping station - Operations and maintenance during entire Design-built made on a monthly basis
Period
Query
We understand O&M payment of existing pumping stations during
Design-built Period will be on monthly basis. Please confirm.
2.67 General - From the site visit we understood there are installed equipment’s at Refer the details available in the following link
the site and some of them are functional and some are not. Hence in order to https://goo.gl/U5PwmT in the folder “Wellawatta PS Pumps & Screens Details”
properly estimate the operation and maintenance cost during design built
period we request you to provide following details:
Pumps: a. Year of installation
b. Flow and Head
c. Pump Efficiency curved.
Pump kWe.
Pump manufacturer details along with local service provider details
Screens and its related accessories:a. Manufacturer details along with
local service provider details.
b. Complete design details of screens.

  18 / 28 
 
No. Questions Answers
2.68 Volume II – Page :6a – 1, clause 1.1 para 6 & Page :6a – 33, clause 3.1.5 , Available details and drawings are provided in the following link
Para 176a,b, We request the client to provide the following details of the https://goo.gl/U5PwmT under folders “Drawings & Details of Structures” & “Force
Pumping Stations (Old and New) as minimum: main Drawings”.
1.As built drawings
2.Mechanical datasheet of Pumps (To know the capacity, head and other
details of Existing pumps).
3.P&ID drawings of the Pump Station
4.L- section drawings of Incoming Gravity lines to Pump Stations
5.Detailed Drawings of Sewerage Network.
2.69 Volume II – Page :6a – 2, clause 1.1 para 7 & Page :6a – 33, clause 3.1.5, Please refer drawings provided under following link for Junction Box Drawing
Para 176d, & Page :6a – 34, clause 3.1.5, Para 181a, we request the Client https://goo.gl/U5PwmT under folder “Drawings & Details of Structures”.
to provide us As- Built Drawings/Pipe Trace and L-Section drawings of
1. Sea Outfall Pipeline and Junction Chamber.
2. Outfall Pipe 1.5 m diameter RCC outfall pipe

2.70 Volume II – Page :6a – 2, clause 1.2 a. Contractor has to perform a hydraulic analysis with respect to existing
1. We request the Client to provide details of the following for design of the outfall pipe, diffuser arrangement and size and determine the Maximum
WWTP. water level to be considered. The Outfall drawings are available under
a. Max. Water level to be Considered in the Outfall Structure in the Proposed following link. https://goo.gl/U5PwmT under folder “Drawings & Details of
WWTP. Structures” In Sub folder ‘Sea Outfall’
b. The Proposed Bottom of Pipe (BOP) of the Outfall Pipeline discharging into b. Please refer the drawings in the above link under “Drawings & Details of
the Sea. Structures” Folder, in Sub-Folder “Sea Outfall”
c. Whether the Client intends to maintain the Elevation of the Outfall pipeline c. Yes. Outfall Structure Drawing is available in the above link under
as per the Existing design and elevation. If Yes, Client to provide the required “Drawings & Details of Structures” folder.
as built drawings of the Outfall Structure. d. Top Water Level in the Inlet chamber proposed by Bidder, will be as per
d The Top Water Level (TWL) in the Inlet Chamber to be considered or if Bidder’s Design.
whether the TWL in the Inlet Chamber shall be as per Bidder design.

  19 / 28 
 
No. Questions Answers
2.71 Volume II – Page :6a – 9, clause 1.10, para 55a & Volume II – Page :6c – Answer not finalized. Will be answered later.
3,
As per Clause No.1.10- Wastewater Treatment plant- "Temporary sludge
storage facility adequate to store the dewatered sludge volume of 2 days shall
be provided." / 6c-3 specifies 5 days.
2.72 No, coarse screens are not provided for FM from Sri Jayawardenapura. Flow from
Volume II – Page :6a – 40, clause 3.4.3c,
the Force main from Sri Jayawardenapura Should be screened and de-gritted by
We understand that the facility of Coarse screen provided for the Force main
the DBO contractor.
incoming flow at Wellawatta Pumping Station from Sri Jayawardhenapura is
Refer the Sketch available at the below link to identify the sewers which are
in good working condition.
already screened & de-gritted before coming to the Wellawatta PS.
Also, kindly provide the Coarse Screen specifications like Type, Capacity and
https://goo.gl/U5PwmT Folder ‘Sewer Arrangement in Wellawatta PS SKETCH’
Dimensions.

Volume II – Page :6a – 42, clause 3.6.2, Colombo South Hospital is not directly coming through a Force main to
We understand that the facility of Coarse screen provided for the force main Wellawatta PS. Hence these data are not relevant.
incoming flow at Wellawatta Pumping Station from Colombo South Hospital is
in good working condition.
Also, Kindly provide the Coarse Screen specifications like Type, Capacity and
Dimensions.

  20 / 28 
 
No. Questions Answers
2.73 Volume II – Page :6a – 42, & Page:6c – 3, Answer not finalized. Will be answered later.
As per the Clause 3.6.2 it is indicated that "the maximum wet weather
contribution in 2020 as 60% of the average dry weather flow and in 2040 as
40 % of the Average Dry Weather flow"
Therefore, Wet weather contribution in 2040 is calculated as:
Average Dry Weather Flow of 50 MLD * 0.4= 20 MLD.
Hence, the total Peak Flow in 2040 inclusive of Wet weather is calculated as
50 + 20=70 MLD.
As per the Hydraulic Capacity Standards, the Design Peak flow is indicated
as 65 MLD.
Therefore, We request the Client to clarify the above discrepancies and
confirm the Peak Wet Weather Flow to be considered for the Hydraulic
design of WWTP.
Further, As per Clause no 3.6, point no 233-" Diurnal variation is expected of
the dry weather flow with peak dry weather flow to be between 2.5-3 times
the average daily dry weather flow, and therefore the Peak Dry Weather flow
is worked out as
Average Dry Weather Flow of 50 MLD x 3 times = 150 MLD.
We understand that the above flow of 150 MLD will not pass through the
WWTP and any flow in excess of Design peak flow (as per Hydraulic capacity
standards - Section 6C) will overflow into the Bypass.

2.74 Volume II – Page :6a – 43, clause 3.7, WWTP should be able to treat the incoming WW having ‘Metcalf and Eddy
As per Clause 3.7- TABLE 2, Summary Wastewater Characteristics at Medium Strength of wastewater’ and meet the discharge standards in Section
Wellawetta Outfall, a wide range of parameters are provided which will be 6(c).
difficult to consider for design purpose.Further, As per Clause no- 3.7
TABLE 3, the parameters have been provided based on "Metcalf and Eddy" However as reported in the wastewater characteristics (Table 2 in Section 6a)
for Medium Strength Wastewater.We understand that for the design of presently the wastewater is, below this strength. Nevertheless, the treatment shall
WWTP, the parameters mentioned in Table 3 (As per Metcalf and Eddy- meet the discharge standards given in Section 6(c) for lower strengths as well.
Medium Strength) shall be considered. Please confirm.
  21 / 28 
 
No. Questions Answers
This means the WWTP shall be capable of treating the wastewater to be in
compliance with the discharge standards given in Section 6(c) for all
wastewaters having different strengths up to the strength given in ‘Metcalf and
Eddy Medium Strength of wastewater’
2.75 Volume II – Page :6a – 42, clause 3.6, para 233 Answer not finalized. Will be answered later.
As per Clause no 3.6, point no 233-" Diurnal variation is expected of the dry
weather flow with peak dry weather flow to be between 2.5-3 times the
average daily dry weather flow."
We understand that the Diurnal variation is only Hourly variation and not to be
applied for Daily Peak Dry Weather Flow calculation. Please confirm.
2.76 Volume II – Page :6a – 45, clause 3.8, para 249 & Page:6c – 2, para 32 Answer not finalized. Will be answered later.
Schedule of Guarantees Wastewater Effluent Discharge and Testing
Standards, Sl. No 32, the Fecal Coliform Maximum concentration or limit is
indicated as 10^7 MPN/100 ml.
Whereas, As per the applicable discharge standards governed by the
Environmental Protection Regulations "TOLERANCE LIMITS FOR
INDUSTRIAL AND DOMESTIC WASTE DISCHARGED INTO MARINE
COASTAL AREAS", the Faecal coliform Tolerance Limit Value is indicated as
60 MPN/100 ml (Sl. No 27).
Kindly clarify the Discrepancy and confirm the correct value to be considered
for design and guarantee.
2.77 Volume II – Page :6a – 44, clause 3.7, para 243, Refer Answer 2.74 above.
We understand that as per Clause no 3.7 Influent Characteristic, Point No -
243- "Reports of the already conducted wastewater characteristics....." are for
Reference only and the design and sizing of the WWTP shall only be based
on Table 3: Typical Composition of Untreated Domestic Wastewater (Metcalf
and Eddy for Medium Strength of wastewater). Please confirm.

  22 / 28 
 
No. Questions Answers
2.78 Volume II – Page :6a – 44, clause 3.7, para 242, WWTP should be able to treat the incoming WW having ‘Metcalf and Eddy
As per the Clause it is mentioned that "The Contractor is required to study all Medium Strength of wastewater’ and meet the discharge standards in Section
the already carried out wastewater analysis reports of the Colombo sewerage 6(c).
system and also carry out own studies of the same system and other However as reported in the wastewater characteristics (Table 2 in Section 6a)
wastewater system in SriLanka which could be considered as representative presently the wastewater is, below this strength. Nevertheless, the treatment shall
of the Colombo system and determine the wastewater characteristics meet the discharge standards given in Section 6(c) for lower strengths as well.
including the parameter variability for the design of the WWTP." This means the WWTP shall be capable of treating the wastewater to be in
We understand that the Contractor is required to carry out wastewater compliance with the discharge standards given in Section 6(c) for all
analysis of another wastewater sample in SriLanka and the parameters of wastewaters having different strengths up to the strength given in ‘Metcalf and
such reports will only be for Reference only and will not be used for design. Eddy Medium Strength of wastewater’
The design and Sizing of teh WWTP shall only be based on Table 3: Typical The contractor needs to have good understanding of low strength of the
Composition of Untreated Domestic Wastewater (Metcalf and Eddy for wastewater and its variations. This understanding is important for his design and
Medium Strength of wastewater). Kindly confirm. operation to meet the performance standards specified in Section 6(c).
2.79 Volume II – Page :6a – 44, clause 3.7, para 243, We request the Client to Wastewater analysis reports are available under following link.
provide the mentioned Wastewater analysis reports of the Colombo https://goo.gl/U5PwmT in the folder “Wastewater Reports”
sewerage system for Reference Purpose.
2.80 Volume I – Page: 4 – 8, Clause 11, Schedule 1& Clause 15, Schedule 2, Answer not finalized. Will be answered later.
The Mentioned Clauses indicate “Plant and mandatory spare parts supplied
from abroad for the Design built Period".
Kindly provide the Mandatory Spare Part List.
2.81 Volume II – Page:6a – 1, Clause 1.1 Please Refer answer for 2.73 above of Bid Clarification set 2.
As per Clause 1.1, which states "The WWTP should be built to cater to
Average Dry Weather Flow (ADWF) of 50,000 m³/ day"
Volume II – Page :6a – 42, Clause 3.6.1 para 232,
As per Clause 3.6.1, Point No 232, which states "The design dry weather flow
is proposed as 35 MLD +/- 10% in 2020 and 50 MLD +/- 10% in 2040." which
is calculated as 55 MLD or 55,000 m3/day.We understand that the design dry
weather flow of WWTP for design and sizing of units shall be for 55 MLD only
and not 50 MLD. Kindly confirm.

  23 / 28 
 
No. Questions Answers
2.82 Volume I – Page 3.10 -7, Clause 2.5, we Understand that the document Bidders are expected to identify the subcontractors at the bidding stage and
FORM EXP-3 is to be submitted only after the award of Contract and not submit bids based on such subcontractors. Hence completed EXP-3 is expected
during the BID submission, and only Manufacturers Authorization for the to be submitted along with the bid
major items of the Plant is to be submitted along with the BID. Kindly confirm.
2.83 Volume I – Page: 2-2, Clause IBT 13.4, As per the Mentioned ITB which These should be read as TECH 3 and TECH 4. These are provided at the end of
states " Alternative Technical solutions in Respect of Reference Standards Section 4.
and Reference Specifications would be considered only as detailed in TECH
1.3 and 1.4 in Section 4 - Bidding Forms"
Please provide the TECH 1.3 and TECH 1.4 Bidding forms as they are not
available in the Tender document.
2.84 Volume lI – Page No 6a-7, clause 1.10, para 47, As per the Mentioned Use of acceptable standards as mentioned is acceptable.
clause which states " The Process Design of Various units of the WWTP shall However as mentioned in Volume lI – Page No 6a-7, clause 1.10, para 47,
be carried out as the design Criteria and norms prescribed in standard contractor should provide justification and calculations on the design criteria and
literature, texts such as Metcalf and Eddy (Wastewater Engineering)." design procedure (unit operations) & finally meet the specified discharge
standards in “TOLERANCE LIMITS FOR INDUSTRIAL AND DOMESTIC WASTE
We understand that as per the above clause Internationally acceptable DISCHARGED INTO MARINE COASTAL AREAS" of Volume lI – Page No 6c-2.
design standards and references such as "GERMAN ATV-DVWK Rules and
Standards" may also be used. kindly confirm.
2.85 Volume lI – Page 6a-7, clause 1.10, para 49, As per the Mentioned clause Answer not finalized. Will be answered later. 
which states " Plant shall be designed to provide flexibility for operation and
meeting the treatment performance standards as stipulated by CEA at 28
days prior to the closing of the bid"

The above statement is not understood properly. kindly clarify the above
statement.

  24 / 28 
 
No. Questions Answers
2.86 Volume 2 – Page 6a-8, clause 1.10, para 55b, As per the Mentioned clause As we are aware, magnetic flow meters are available for partially filled pipes and
which states " Flow Measurement: Treatment plant shall include an open channel flow now. The Bidder/Contractor shall determine installation
Electromagnetic flow measuring device fixed to a channel delivering the location of the flow meter as per the specifications given in the bid.
wastewater to treatment system. The flow measuring channel shall be so
designed to deliver the flow to treatment trains properly." However, if a better, more reliable, cost effective and accurate measuring device
The above statement is contradictory, as Electromagnetic flow measuring compared to electromagnetic flow meter, which meets the purpose of flow
device are suitable only for measuring flows in pipes and not channels. kindly measurement and better suited for the treatment plant design of yours you may
confirm the exact requirement on the type of flow meter to be used and its propose in the bid.  
installation location as Flow measurement in channels requires construction
of Parshall flumes with Ultrasonic Type Flow Meter. Kindly clarify.
2.87 Volume 2 – Page 6a-8, clause 1.10, para 55b, As per the Mentioned clause Refer 2.86 above.
which states " In addition an Electromagnetic flow measuring meter shall be
installed at measure the total treated effluent to the sea outfall"
kindly confirm the type of flow measuring device can also be channel
mounted type or shall be left to bidders choice based on the site layout
arrangement.
2.88 Volume 2 – Page 6a-34 Clause 3.1.6 Para 181b,c & Page 6a-52, figure 5,  All the flows coming to Wellawatta should be treated in WWTP.
As per the mentioned clauses, the following two pipelines are connected to  Please see the attached diagram of inflow arrangement to the WWTP site
outfall junction chamber. available under following link.
1. 1100 DI force main from S8 Pump station. https://goo.gl/U5PwmT in the folder “Sewer Arrangement in Wellawatta
2. 400 mm Force main Dehiwala - Mount Lavinia. PS SKETCH”
3. Line from Bambalapitya.
Kindly provide the flowrates and other necessary details from each of the
pump station and clarify if these flows needs to be connected and treated in
the proposed WWTP.
2.89 Volume 2 – Page 6a-50, Figure 5, Please collect the Figure from the soft copy of the bid document available at
The Figure in not available in the Tender document. Kindly provide the following link
Drawing. https://goo.gl/U5PwmT

  25 / 28 
 
No. Questions Answers
2.90 Please collect the Figure from the soft copy of the bid document available at
Volume 2 – Page :6a-46, Figure 1, The Figure in not available in the Tender
following link
document. Kindly provide the Drawing.
https://goo.gl/U5PwmT
2.91 Volume 1, Page:4-59, The bidder shall state the manufacturer and the type No such wording had been given in the quoted text. Please read instructions given
of material listed below.( Table: Pipes, Gates, Valves and equipment etc...) on Page 4-58 for filling of Schedules.
The bidder shall select 3 Vendors per items and the same shall be submitted
along with the technical Bid. As per the given format in tender.Please
Confirm,
2.92 There are 3 gravity sewer lines presently flowing to Wellawatta & One proposed
Gravity sewer. Details are as follows.
Volume 2, 6a-1, Clause 6, There are two wastwater pumping stations at the Name of Sewer Status Dia Material
site. These are defined in here as OLD (built over 50 years ago) and new
X1 Present 12” VC
(built just about 10 years ago).
CS-16 Present 450mm VC
Please provide Pipe line size and Material of Construction of existing gravity
W1 Present 36”×24” Brick
sewer Inlet line to old pumping stations.
Marine Drive Trunk Proposed 1400mm RCP with HDPE
liner

2.93 Volume 2, 6a-10, Clause 57(L), This something you have to propose it should be your choice. However, the
All sluice gates, valves, piping, screens, de-gritting equipment, aerators and proposed material is acceptable. The responsibility of obtaining material approval
air piping, sludge handling equipment, etc which will be submerged in or in from the Employer at the DB stage remain stand.
conduct with wastewater or sludge or ladders and hand railing for access and
platforms and walkways shall be designed with corrosive resistant material.
i.e Stainless Steel 316.
We presume that Valve body shall be Ductile Iron and wedge/disc, stem shall
be SS 316.
Please confirm.

  26 / 28 
 
No. Questions Answers
2.94 Volume 2, 6a-10, Clause 57(L), No. All piping need not be SS 316.
All sluice gates, valves, piping, screens, de-gritting equipment, aerators and
air piping, sludge handling equipment, etc which will be submerged in or in
conduct with wastewater or sludge or ladders and hand railing for access and
platforms and walkways shall be designed with corrosive resistant material.
i.e Stainless Steel 316.
We presume that all Piping inside pumping station shall be SS 316.
Please confirm.
2.95 Volume 2, 6a-10, Clause 57(L), All air piping shall be SS 316.
All sluice gates, valves, piping, screens, de-gritting equipment, aerators and
air piping, sludge handling equipment, etc which will be submerged in or in
conduct with wastewater or sludge or ladders and hand railing for access and
platforms and walkways shall be designed with corrosive resistant material.
i.e Stainless Steel 316.We presume that all Air piping shall be SS 316.Please
confirm.
2.96 Volume 2, 6a-10, Clause 57(L), This is something you have to propose it should be your choice. However, the
All sluice gates, valves, piping, screens, de-gritting equipment, aerators and proposed material is acceptable. The responsibility of obtaining material approval
air piping, sludge handling equipment, etc which will be submerged in or in from the Employer at the DB stage remains stand.
conduct with wastewater or sludge or ladders and hand railing for access and
platforms and walkways shall be designed with corrosive resistant material.
i.e Stainless Steel 316.
We presume that all interconnecting Piping between equipment / Structures
shall be Ductile Iron.
Please confirm.

  27 / 28 
 
No. Questions Answers
2.97 Volume 2, 6a-10, Clause 57(L), Welding of Stainless Steel 316 pipes shall be in accordance with relevant BS, BS
All sluice gates, valves, piping’s screens, de-gritting equipment, aerators and EN or any other standards acceptable to the Employer/Engineer as per the
air piping, sludge handling equipments, etc which will be submerged in or in specifications of this Bid/Contract including Non-Destructive Testing of Welding.
conduct with wastewater or sludge or ladders and hand railing for access and
platforms and walkways shall be designed with corrosive resistant material.
i.e Stainless Steel 316.
We presume that all Stainless Steel 316 pipe thickness shall be welded 10 S
as per ASME B36.19M.
Please confirm.
2.98 Volume 2, 6a-34, Clause 181(B), All the available drawings are accessible from following link.
a) Outfall pipe 1.5 meter diameter RCC outfall pipe - pipe trace and as-built https://goo.gl/U5PwmT A List of drawings/ details is available in the same link for
drawings are available with the employer's Representative.b) 1100 mm DI easy reference.
force main from the S8 pump station to outfall junction chamber- pipe trace
and as-built drawing are available with the employer's Representative.c) 400
mm force main from the Dehiwala-Mount lavinia to outfall junction chamber
-pipe trace and as-built drawing are available with the employer's
Representative.d) W1 Gravity sewer carrying wastewater to the Wellawatta
new pumping station - as-built drawing are available with the employer's
Representative.e) short force main transferring the waste water from
Wellawatta new pumping station to Wallawatta outfall junction chamber
-as-built drawing are available with the employer's Representative.f) Junction
Chamber as built drawings.Kindly Share all the drawings (AutoCAD format).
2.99 General – Bidders are free to decide the pipe sizing of the proposed plant. However, they
We presume that the Bidders are free to choose the Velocities for Pipe Sizing need to be compatible with engineering norms and relevant standards.
shall be selected as per Good Engineering Practice and the same shall be
submitted with the technical offer.
Please Confirm.

  28 / 28 
 
Ministry of Provincial Councils and Local Government
Contract: Wellawatta Wastewater Treatment Plant
Contract No: GCWWMIIP-TR3/ADB/ICB-02/2017
Bid Clarification No. 03 (2 Question Sets)
(1) Responses to questions received from bidders on 10 August 2017

No Questions Answers
1.1 Volume 2, Page 6a-32, Para 167, Which area must be allowed to the new playground, and Given under the “Drawing No. SI 6A” in the following
Google Drive link. https://goo.gl/U5PwmT in the folder
where?
‘Key map & Survey’
1.2 Volume 2, Page 6a-33, Para 174, Can you please send us the measurement report? Available under “SI 05 - Wellawatta Report with all
annexes” in the following Google Drive Link.
https://goo.gl/U5PwmT
1.3 Volume 2, Page 6a-34, Para 181, It seems that information about two of the sewer mains See the attached sketch on inflow arrangement to the
Wellawatta WWTP site available under the following link.
are missing? Please advise.
https://goo.gl/U5PwmT in the folder ‘Sewer Arrangement
in Wellawatta PS SKETCH’
1.4 Volume 2, Page 6a-38 to 41, Para 212 to 230, Details on the sewer networks (existing & Refer above answer 1.3
future arrangements) are not clear. Could you
please send us the concerned as built and / or projected drawings?
1.5 Volume 2, Page 6a-39 to 40, Para 217 to 220, Could you precise the projected works and Refer above answer 1.3
flows concerned?

1.6 Volume 2, Page 6a-40 & 41, Para 221 & 224, Do we have to include these points in our Your bid rates and prices should cover to comply with all
Employer’s Requirements
scope /offer (price and delay)?
1.7 Volume 2, Page 6a-41, Para 226, Could we receive the details of the outfall flow capacity The outfall as built drawing together with the outfall
estimation / calculation (with lay-out, levels…)? Could you precise the maximal high tides land-based junction chamber at the Wellawatta WWTP site
levels to be considered? Which pluviometry do we have to consider (intensity & rain is available in the following link https://goo.gl/U5PwmT
occurrences period)? under Folder “Drawings & Details of Structures”, in the
Where are the sewer overflows of the different mains? sub-folder ‘Sea Outfall’.
The outfall capacity is reported as 2400l/s. Bidder shall
carry out his own hydraulic analysis to verify this.

  1 / 6 
 
No Questions Answers
1.8 Volume 2, Page 6a-42, Para 234, Could you please detail us this point? There are numerous defects in the sewer collection
network. As a result, there are cross connections with
storm water system at some places. Infiltration and inflow
is also high. As a result, the estimate of wastewater,
inflow, and infiltration quantities may not reflect the true
position accurately. The wastewater characteristics
reported through sampling studies show weak wastewater
strength. This is assumed as mainly due to dilution of
wastewater through the ingress of infiltration and
sometimes inflow of drainage in stromwater system into
the sewer system. Due to system defects the ratio
between wet weather low to dry weather flow can be
higher than what is traditionally expected.
1.9 Volume 2, Page 6a-44, Para 242, Could you please send us all these reports? Wastewater Reports are provided in the following link.
https://goo.gl/U5PwmT under folder ‘Wastewater
Are the design scopes to be included in the delay of execution?
Reports’.
Second question is not clear
1.10 General, Can you please confirm that the transformer will be placed by CEB and paid by Contractor has to determine the capacity of transformer
based on his WWTP design. If new transformer is
the Employer
necessary the cost to be paid to CEB shall be included in
(Contractor will determine the capacity)? the contract cost. No payment will be made by employer.
Please refer Section 6a- Clause 7.4
General, Will this transformer be integrated into the existing transformer building or into a This is to be decided by the contractor depending on the
1.11 estimated power requirement and distribution
new building?
arrangement.

1.12 General, Are electrical cabinets enclosures types 3 or 4? Degree of segregation of Form-3 is applicable for
enclosures for equipment up to 125 kW. Form-4 is
applicable for enclosures for equipment rated higher and
equipment with operating voltages higher than 400V.
1.13 General, Can you please confirm that the wastewater effluent discharge characteristics Answer not finalized. Will be answered later.
limits (see section 6c – Schedule of Guarantees page 6c – 2) will not change during the
D&B period and O&M period? (equivalent of 20.5 years as from the coming into force of the
contract)

  2 / 6 
 
No Questions Answers
1.14 Volume 2, Page 6a-44, table 3, Contractor has to guarantee the effluent quality by Question will arise only if the wastewater characteristics
deviate from medium strength sewage characteristics of
designing a plant capable of treating Weak and Medium
Metcalf and Eddy and the wastewater deviates from
composition of untreated Domestic Wastewater (Table 3-page 6a-44). Can you please domestic wastewater category, which means that it does
specify and confirm who is responsible for the quality of the incoming wastewater (e.g. if it not contain toxic material to levels that inhibit biological
treatment. Bidder/Contractor shall carry out his
can't be treated in a biological way - inhibition, ...) and detail the process and guidelines on designs/operations based on this stated inflow character.
the impact of the O&M operations. If there is change to these conditions the impacts of such
changes will be handled as per the provisions in this
Contract
1.15 General, Can you please define and detail what the Employer means by stabilized sludge Answer not finalized. Will be answered later.
(parameters that can be monitored and measured)?

1.16 Volume 1, Page 4-11, Schedule No.2, Can you please confirm that Customs Duties have Schedule No. 2 is for Plant items supplied from with Sri
Lanka. So if such items had been already imported much
to be paid by the Contractor for goods imported from abroad? This is unusual, importing
earlier, the Duties already paid also should be included in
goods is always under the responsibility of the Public Authority in Sri Lanka and Customs the bid prices as indicated. Then the Contractor would get
Duties paid by the Sri Lankan authority and not by the Contractor. paid for those prices when installed. However, if items are
to be imported during the contract and for the Contract,
then such items should be included in Schedule 1, where
the Employer will reimburse the actual customs duty paid
as indicated in Page 4-8

(2) Responses to questions received from bidders on 15 August 2017


2.1 Volume 1-Section 3-Evaluation and Qualification Criteria-2. Qualification, mentioned Criteria as clearly mentioned in Section 3 will be applied
for determination of qualification for selection.
that It is the legal entity or entities comprising the Bidder, and not the Bidder’s parent
companies, subsidiaries, or affiliates, that must satisfy the qualification criteria described
below.
Please clarify whether the subsidiary company’s experience can be recognized and
adopted as qualified experience for the parent company that will attend this tender? Usually
for Design Build Operate (DBO) contracts with long tenures such as this project, most
companies establish local subsidiaries under a Special Purpose Vehicle (SPV) to execute

  3 / 6 
 
No Questions Answers
the contract due to legal requirements from their parent companies / governments to
adhere to local taxation laws, local employment / labour laws etc. Therefore, the experience
of most DBO or other PPP type contracts such as BOT, BOOT, BOO are usually contained
in a subsidiary or affiliate companies that are established for executing such contracts.
2.2 Volume 1-Section 3-Evaluation and Qualification Criteria- 2.4.1 Contracts of Similar Criteria as clearly mentioned in Section 3 will be applied
for determination of qualification for selection.
Size and Nature, mentioned that participation as lead (managing) contractor in at least two
DBO contracts where the Design-Build component has been successfully completed within
the last 10 years and that are similar to the proposed contract, where the value of the
Bidder’s participation in each contract for the design-build component exceeds $32 million.

Please clarify whether the DBO/BOT/BOOT/BOO projects with treatment capacity less
than 50MLd can be recognized as similar projects in capacity?
2.3 As per Volume 1 - ITB 21.1 of Section 2 Bid Data Sheet, we understand that the bid Indicating a expiry date within the stipulated period for the
bid guarantee is acceptable.
bond shall be validated till 210 days from the bid submission deadline date (or any
extended deadline). In the bid security format provided in Section 4 – Bidding Forms, it
appears that the required bank guarantee does not explicitly mention any expiry date. As
standard requirement by all issuing banks and correspondent banks in Sri Lanka, the bank
guarantee will need to indicate an actual expiry date. As such, the corresponding bank in
Sri lanka has proposed to include an expiry date, as described below (in bold):

“This guarantee will expire: (a) if the Bidder is the successful Bidder, upon our receipt of
copies of the Contract Agreement signed by the Bidder and the performance security
issued to you upon the instruction of the Bidder; and (b) if the Bidder is not the successful
Bidder, upon the earlier of (i) our receipt of a copy your notification to the Bidder of the
name of the successful Bidder; or (ii) 28 days after the expiration of the Bidder’s bid or
(c) …………………(expiry date).”

Please kindly confirm if the proposed amendments by the corresponding bank in Sri Lanka
is acceptable

  4 / 6 
 
No Questions Answers
2.4 Volume 2,
1. Please provide designed raw water temperature, minimum and maximum.
1. Consider temperature be 26 degree C to 30 C

2. Please provide required dryness of dewatered sludge 2. Sludge solids content to be around 70%. An
addendum will be issued clarifying this.

3. Please provide as built drawings for sea outfall,existing pump station and force main 3. Available under the following Google Drive link.
pipelines within the site. https://goo.gl/U5PwmT A list of available drawings is
available in the same link and as Attachment 1 for these
replies.
4. Please provide Raw water parameters analysis corresponding to TOLERANCE
LIMITS FOR INDUSTRIAL AND DOMESTIC WASTE DISCHARGED INTO MARINE 4. Please obtain the required information from Central
Environmental Authority or its website http://www.cea.lk/
COASTAL AREAS (28 items) as the document on the nominated website is less than
28 items.

5. Design alkalinity and oil grease contents are given in


5. Please supply alkalinity figures, sand content and oil & grease content in raw water. Volume II Table 3 of Section 6a. Sand content is not
available.
6. Please clarify test method, sampling method and sample preparation.
6. Please contact CEA for details

7. Please provide air emission standards for odor control, test and sampling method of 7. Please contact CEA for details
air emission.
8. Full treatment plant to be completed within the
8. Is it permitted to choose modeling design for different capacity in 2020 and 2040, and stipulated construction period
constructed in 2 stages. 9. Answer not finalized. Will be answered later.

9. Please clarify Relation between Clause 236 and Clause 72 in Volume 2, Section 6 – 10. Odor control approach is for the bidder to select
Employer’s Requirement. 11. Alternative designs are not acceptable

12 Question is not clear


10. Please indicate, Preferred waste water/sludge/odor treatment process if any.
13. These are the conditions imposed by the CEA on

  5 / 6 
 
No Questions Answers
11. Please clarify whether an alternative solution will be accepted such as underground construction and Operation of the plant. Please refer to
environmental clearance letter from the CEA, EMP issued
waste water treatment plant and design landscape and playground or public garden
to the Contractor. Other conditions on environmental
above the plants. protection will be issued by the CEA once the plant is
ready for operation. However, you can discuss with the
CEA on typical requirements of the EPL for operation of
12. Please clarify position for connecting main power and water main sewerage treatment plants.

13. Please clarify Clause 199, requirement list from CEA 14. Question is not clear

15. There is no cost to approval granted by the Employer


14. Please clarify If Job site accessibility must be supplied to Contractor by Employer.

16 You can contact the respective laboratories and obtain


15. Please clarify if Cost of permission and approval required by Employer. their price list for testing.

16. Please clarify if Cost of lab analysis for lab defined by Employer.

  6 / 6 
 
Ministry of Provincial Councils and Local Government
Contract: Wellawatta Wastewater Treatment Plant
Contract No: GCWWMIIP-TR3/ADB/ICB-02/2017
Bid Clarification No. 04 (2 Question Sets)

(1) Responses to questions received from bidders on 21st August 2017


No Questions Answers
1.1 Volume 1, Page 3-8, Clause 2.4.1, As per our understanding of the clause, ‘last 10 years; The Note given at the end of 2.4.2 would also apply for
2.4.1
means ‘last 10 Financial Years i.e. Financial Year ending 31/12/2007 to Financial Year
ending 31/12/2016’. Kindly confirm?
1.2 Volume 1, Page 3-8, Clause 2.4.1, This requirement is in contradiction with the following There is no reference to “substantially completed” in
Clause 2.4.1
condition:
“Both contracts relate to treatment plants that have been fully commissioned and have
been operated successfully by the Bidder for at least two years.”
If a plant is substantially completed, it can’t meet the requirement of being fully
commissioned. Kindly clarify.
1.3 Volume 1, Page 3-8, Clause 2.4.1, For project under ADSB funding there’s generally a Answer not finalized. Will be answered later.
provision to calculate the present Price level of cost of completed and commissioned works
by applying a weightage of 10% per year. We request to kindly allow the same in the
present tender as follows:

Year of Completion Weightage


2016/2017 (on going) 1.00
2015 1.10
2014 1.21
2013 1.33
2012 1.46
2011 1.61
2010 1.77
2009 1.95

  1 / 3 
 
No Questions Answers
2008 2.14
2007 2.36
1.4 Volume 1, Page 3-8, Clause 2.4.1, We request you to kindly allow DBO projects Only DBO contracts have been allowed, where the value
of Design-Build component exceeds USD 32 million
completed in the stipulated duration to qualify against the requirement and not Design-Build
component only.
1.5 Volume 1, Page 3-8, Clause 2.4.1, Kindly clarify what is meant by ‘Bidder’s participation’? The bidder is expected to have been the lead partner in
Is it joint share of all parties or the lead partner of the joint venture? the JV for the qualifying contract with the stipulated
contribution, if it was done by a JV
1.6 We request you to kindly amend the criteria as follows: Answer not finalized. Will be answered later.
…. Where the combined value of Bidder’s participation in both contracts for the
Design-Build component exceeds $ 64 million and value of Bidder’s participation in one of
the contracts for the Design-Build component exceeds $ 32 Million.

1.7 Volume 1, Page 3-8, Clause 2.4.1, As per our understanding of the criteria, ‘Sewage Confirmed
Treatment Plant’ (STP) to treat mixed domestic and trade wastewater’ means STP
designed to treat wastewater in urban city comprising of domestic households and
‘commercial trades’ like hotels, restaurants, institutions, airports etc. and not the Industrial
waste. Kindly confirm?

1.8 Volume 1, Page 3-8, Clause 2.4.1, We request you to kindly make this ‘10 years or Answer not finalized. Will be answered later.
more…’ of O&M as “Cumulative” in last 10 years. Also, request to please make this
separate criterion under 2.4.2 Experience in Key Activities. Further, kindly allow this
criterion to be met by a Sub-Contractor also under MOU.

(2) Responses to questions received from bidders on 23rd August 2017


2.1 Volume 1, Page 3-4, Clause 2, We understand parent/holding company  Please refer the clear note applicable given at the top of
credentials/experience will be considered provided applicant is a subsidiary company or  Page 3-4, which is reproduced below.
similarly the experience of subsidiary company will be considered if the parent/holding 
company is participating in the tender. Request to please confirm the same.
“It is the legal entity or entities comprising the Bidder,
and not the Bidder’s parent companies, subsidiaries, or
affiliates, that must satisfy the qualification criteria
described below”

  2 / 3 
 
No Questions Answers
2.2 Volume 1, Page 3-8, Clause 2.4.1, We request you to consider bidder participations as ‘lead  Answer not finalized. Will be answered later.
partner’ or ‘other partner’ also for at least one contract out of two DBO contracts 
requirements.   
2.3 Volume 1, Page 3-8, Clause 2.4.1, We understand that the project experiences to meet  Confirmed.
these requirements ‘Design & construction cost’ or ‘project value’ should be greater than $ 32 
million. please confirm the same. 

2.4 Volume 1, Page 3-8, Clause 2.4.1, We  request  you  to  consider,  the  two  DBO  contracts  Answer not finalized. Will be answered later.
requirements can be met by water supply projects on DBO, DBOT, DBOO, etc. to demonstrate 
bidder’s execution capability of managing such international projects.       
 
Regarding wastewater plant of 50 MLD experience can be shown separately or as 3rd project 
reference. Request not to be clubbed with above two DBO contracts requirements.
2.5 Volume 1, Page 3-8, Clause 2.4.1, We  request  you  to  consider  50  MLD  wastewater  plant  Answer not finalized. Will be answered later.
experience  requirements  can  be  met  by  water  or  waste  water  treatment  plant  projects 
undertaken on EPC, DBO, DBOT, DBOO, O&M etc.   
We request to consider DBO experience in one contract or also if bidder has Design‐Build & 
O&M experiences in different contracts.
2.6 Volume 1, Page 4-9, Clause 18, In order to familiarize ourselves with the Project and help  Upon bidder’s formal request, we can give a permission to
us to get a useful visit to the site, we kindly request client to provide sufficient details like  visit the site
report, drawings, specifications, etc. of existing pumping station, structures, outfall, network,  Please refer the following Google Drive link.
etc. https://goo.gl/U5PwmT for available drawings and Details.
A list of available drawings is available in the same link
and As Attachment 1 for these replies.
2.7 General, considering that responses by authority to queries could affect the JV agreements,  Extension of deadline will be done through an Addendum
preparation of docs and submission of bid on due date and being an International project,   
we kindly request client to extend bid submission date by at least 2 months from the receipt 
of clarifications.

  3 / 3 
 
Ministry of Provincial Councils and Local Government
Contract: Wellawatta Wastewater Treatment Plant
Contract No: GCWWMIIP-TR3/ADB/ICB-02/2017
Bid Clarification No. 05 (4 Question Sets)

(1) Responses to questions received from bidders on 24th August 2017

No Questions Answers
1.1 Volume 1, Section -07, Sub-Clause 14.7, We understand that in the event that the Bidder Answer not Finalized. Will be answered later.
is a Consortium (non- incorporated JV) of 2 or 3 companies, jointly and severally liable
under the single contract between the Ministry of Provincial Councils and Local
Government, Colombo Municipal Council and the Consortium, please confirm whether
interim payment certificates and payments can be handled as follows:

1) For each payment application, the Contractor issues an interim payment certificates to
the Employer, in line with the Contractual payment terms.
2) The payment claim is supported by separate VAT certificates, one from each consortium
member, with each certificate being under a separate VAT number.
3) The separate interim payment certificates will be compiled by the Leader of consortium
into one single summary as (1) above.
4) After approved by the Employers' representative, The Employer makes one single
payment to a consortium bank account, being the total of the separate VAT certificates.
Please kindly confirm.
1.2 Volume 2, Page 6a-1, Clause 1.1, the Contractor shall be responsible for the disposal of - Answer not Finalized. Will be answered later.
wastewater received under gravity during the Design and Build Period.
- Refer the details available in the following link for
Electricity Bill.
Please kindly provide the following information:
https://goo.gl/U5PwmT in the folder “Wellawatta PS Utility
- Wastewater flowrate for disposal during the design and build period Bills”
- Operation data and electrical bill of the existing pumping station for the last year.

  1 / 9 
 
No Questions Answers
1.3 Volume 2, Page 6a-9/Page 6c, Clause 1.10, the temporary sludge storage facility Answer not Finalized. Will be answered later.
adequate to store the dewatered sludge volume of two days shall be provided at the Site;
However, the minimum volume of on-site storage to be provided is 5 days based on Section
6c Schedule of Guarantees.
Please kindly clarify the discrepancy.
1.4 Volume 2, Page 6c-3, - Sludge Smell Standard, as per the smell standard listed in Answer not Finalized. Will be answered later.
Schedule Guarantee, Hydrogen Sulphide (at side boundary) is 0.0003ppm, and Hydrogen
sulphide (inside any enclosure provided to prevent leakage of odorous gases) is
0.0005ppm.The Odor requirement in the functional guarantee is unrealistic high and
unreasonable. As there is no standard in USA or Europe for the H2S concentration in site
boundary and inside enclosure. As per our previous project experience, we suggest
adopting the following value:-
H2S concentration (at site boundary) less than 0.05mg/m3;-
H2S concentration (inside any enclosure provided to prevent leakage of odorous gases):
Non applicable.
Please kindly clarify.
1.5 Volume 2, Page 6a-10, Clause 1.11, the Contractor shall provide a Service Water Answer not Finalized. Will be answered later.
System for the entire facility which will extract water from a tube well or shallow well for
toilet.
Due to the high salinity of the underground water and the limited service water
consumption, we suggest using the potable water system instead of the service water
system for toilet washing and other service water usage.
Please kindly consider our suggestion.
1.6 Volume 2, Section 6c, Schedule of Guarantees, We understand that the Schedule Answer not Finalized. Will be answered later.
guarantee indicated in Section 6c of ITB are subjected to the preconditions of raw water
quality, Medium Strength listed in Table 3, Clause 3.7 of Section 6a being fully satisfied.
Please kindly confirm.

  2 / 9 
 
No Questions Answers
1.7 Volume 2, Page 6a-85, Clause 6.1.1, the BS or BS EN Standards shall be applied to the BS EN Standards are applicable for the mechanical
Mechanical works, equipment. ISO standard, may be submitted as an
Please kindly conform if other equivalent international standard, i.e. ISO is applicable for alternative for acceptance on case by case basis.
the Mechanical Works.

1.8 Volume 2, Page 6a-92, Clause 7.4, We understand that the additional power supply and No. Cost of obtaining power shall be part of contractor’s
new transformer for the wastewater treatment plant (i.e. incoming HV power supply cost.
electrical substation, step - down transformer and any required connection to the Power
Grid of Ceylon Electricity Board) shall be supply by CEB. The cost for such is subject to
charges by CEB.
As such, we suggest the above said facilities for power from CEB shall be cover under the
Provisional Sum under of Price Schedule No.4.
Please kindly consider our suggestion.
1.9 Volume 2, Page 6a-110, Clause 9.11.3, the Contractor shall be responsible for the Test on Contractor is required to prepare the plan and obtain the
Completion for the Design & Build Period. Please kindly confirm: approval. Issues that you raised in the question should be
- Period for the Test on Completion; addressed in your plan. Employer Representative will go
- The parameters to be tested during this period; through your plan and come to an agreement with the
- The test frequency for above said parameter; Contractor.
- The water and sludge analysis can be tested either by internal laboratory within the plant
or the third-party laboratory.
1.10 Volume 2, Page 6a-93, Clause 7.7, We understand the diesel consumption for the standby Answer not Finalized. Will be answered later.
generator operation during the operation service period due to the CEB electrical
interruption shall be reimbursed by the Employer with escalated rate. Please kindly confirm.
1.11 Volume 2, Page 6b-2, Clause 1.4, the vehicles, trucks, mobile plant, office equipment This applies to vehicles, equipment, etc. that the
and office consumables used for operation service shall be become the property of the Contractor will buy purely to support the O&M functions.
Employer upon delivery to the Site and shall be classified as Employer's Equipment. Quantity, type of vehicles/equipment, etc are for the
Please kindly specify the detailed requirement on vehicles, trucks, mobile plant to be Contractor to determine
handed over to Employer.

  3 / 9 
 
No Questions Answers

(2) Responses to questions received from bidders on 24th August 2017


2.1 General - The bidding documents specified a number of indicators for the discharge No, effluent water quality parameters should meet all the
standards. However, there are only a few inlet water quality standards stipulated. Are the indicators in the discharge standards.
outlet water quality indicators to be met only limited to those stipulated for inlet water?
2.2 General -As the project is at the seaside, please indicate salt content requirements of inlet Question is not clear; inlet received only domestic sewage
water
2.3 General - Is the Project Site Initial Investigation and Report required in the bidding Not with the tender documents
documents to be submitted along with the tender documents or after winning the bid?

2.4 General - As the operation and maintenance of the pumping station is to be covered during Requested details available in the following link
the construction period, please provide the parameters of the existing pumping station e.g. https://goo.gl/U5PwmT in the folders “Wellawatta PS
Pumps & Screens Details” & “Wellawatta PS Utility Bills”.
pump power capacity, local water and electricity price etc.

2.5 General - According to the bidding documents, water is to be drawn from the local tube well Hydrological data is available in the Soil Investigation
Report.
or shallow water wells. Please specify hydrological information of the local available water
Refer the details available in the following link
as well as the costs stipulated by the local water sector.
https://goo.gl/U5PwmT in the folder “Wellawatta PS Utility
Bills”
2.6 General - Is the document submission format stipulation in Clause 2.11.2 of Volume 2, Processing of submittals will be carried out after award of
the contract only
Page No. 6a-28, applicable to the tender documents or the construction documents after
winning the bid? For the tender documents, are A4 or A3 the only sizes allowable for text or
drawing submission?

2.7 General - Please provide the project Environmental Management Plan (EMP) and Copy of EMP which includes Environmental compliance in
the following Google Drive link.
documents showing environmental protection measures consented by the project owner
https://goo.gl/U5PwmT in the folder ‘Environmental
and endorsed by environmental approval authority. Clearance’.

  4 / 9 
 
No Questions Answers
2.8 General -The transportation and disposal of the sludge after dewatering shall be the Please prepare the Technical and Price proposal assuming
responsibility of the bidder. Please specify the transportation distance between the sludge
the disposal site will be as specified in Vol 2 Page 6b-2
disposal site and the sewage treatment plant and provide the cost standard for the sludge
disposal site to receive the sludge Clause 1.2.
GOSL is currently in the process of identifying and
establishing such disposal sites, Most probably such sites
will be operational by 2020.
2.9 General - Will the sewage of the two hospitals only be discharged into the pumping station The wastewater from hospitals are not treated
after treatment through their in-house sewage stations? What is the level and type of the
hospital?
2.10 General - The bidder is responsible for the planning and design from the pumping stations The scope for the contractor is only within the boundary of
the proposed WWTP.
to Wellawatta junction chamber or pump house. Please provide drawings for all peripheral
The drawings available are accessible from the following
pumping stations connected to the Wellawatta junction chamber or pump house and link.
drawings for all pipelines. https://goo.gl/U5PwmT . A list of available drawings is
available in the same link and As Attachment 1 for these
replies.
2.11 General - It is mentioned in the bidding documents, “the contract effluent standards As specified in Volume II – Page :6a – 45, clause 3.8.2 of
stipulated should be more stringent that the proposed new CEA processing standards”. If Bid Document, Final Applicable standards are the
this is true, please provide the new CEA processing standards. standards in “TOLERANCE LIMITS FOR INDUSTRIAL
AND DOMESTIC WASTE DISCHARGED INTO MARINE
COASTAL AREAS".
2.12 General - The bidding documents stipulated "if necessary, the odor control system needs Answer not finalized. Will be answered later.
to be set up". What is the standard for odor of the sewage treatment plant?

2.13 General - Please advise the invert level of old (>50 years) and new (>10 years) pump The drawings of the Old and New PS are accessible from
the following link.
stations.
https://goo.gl/U5PwmT In the Folder “Drawings & Details
of Structures’in Sub Folders ‘Wellawatta NEW PS’ and ’10
Old PS’.
2.14 General - Please advise whether the old and new pump stations are connected They are hydraulically connected via inlet chambers.
Pl refer Schematic diagram in the following Link.
https://goo.gl/U5PwmT under folder ‘Sewer
Arrangement in Wellawatta PS SKETCH’

  5 / 9 
 
No Questions Answers
2.15 General - Please advise, at current setup, whether incoming flow to old pump station can Yes. It is possible to isolate. But the Pump condition
should be taken into consideration since some pumps are
be isolated and divert all flow to new pump station.
not in working condition.

2.16 General - Please advise the top level and invert level of the junction chamber. Please refer the Junction Box drawing available in the
following link.
https://goo.gl/U5PwmT under Folder “Drawings & Details
of Structures’
2.17 General - Please advise the maximum, mean and minimum tidal level. Tidal variation in Sri Lanka is 0.7 meters maximum
2.18 General - Please advise S8 pump station, Dehiwala and Mt. Lavina pump capacity and Please refer the drawings & Details of Dehiwala Mt
Lavinia PSs available in the following link.
head.
https://goo.gl/U5PwmT under Folder “Drawings & Details
of Structures’ in the sub-folder ‘Mount Lavinia Pump
Stations’
Existing capacity of S8 pump Station is 900 l/s at a total
head of 20m.
However, please note at the pumps of this pump station
will likely to be modified soon through an already awarded
contract. The proposed system is to handle a flow of 1,800
l/s at a total delivery head of 32m.
2.19 General -if the EIA study has been done and what the recommendation are from the CCCRMD has already given no objection for the proposed
Central environmental authority, do we need clearance from then coast conversation and works, subjected to submission of details construction
development authority? drawings for final approval as it is a DBO contract.
CEA clearance has already been obtained. However, as time
period for it has been expired, renewal has been already
requested from CEA.
Please refer Item 2.4 of Bid Clarification 01.

2.20 General - Please advise on the import duties and taxes in relation to the equipment for this Please refer Sub-Clause 14.1 in General and Particular
Conditions of Contract in Section 7 and Section 8 of the
project.
Bidding Document

  6 / 9 
 
No Questions Answers

3 Responses to questions received from bidders on 25th August 2017


3.1 General, refer to information gathered during the site visit, it is mentioned that existing It is not under contractor’s scope of works and will be
carried out by CMC. Allocated land Given under the
playground to be relocated. Kindly confirm, whether it is contractor’s scope or not.
“Drawing No. SI 6A in the following Google Drive link.
https://goo.gl/U5PwmT in the Folder “Key Map & Survey”

3.2 General, kindly confirm whether off-shore outfall is a contractor’s scope or not. Unless otherwise the contractor plans to store and release
(batch treatment) treated WW in a higher flow rate, there
is no need to design the outfall.
While the outfall does not require any modifications as per
above description, Junction Box may require
modifications/ shifting according to contractor’s design
and site layout.
3.3 General, please provide piping network diagrams and civil drawings related to Existing Not all the drawings are available.
Please refer the drawings available in the following link.
pumping stations.
https://goo.gl/U5PwmT A list of available drawings is
available in the same link and As Attachment 1 for these
replies.
3.4 General, During the site visit it is identified that, there are some containers, Pipes and Answer not finalized. Will be answered later.
scrap Vehicles within the project limit as well as along the project boundary. Kindly advise
weather, contractor has to dispose those or any.

3.5 General, there are a number of trees are existing in project limits, please advise us whether Permission shall be taken from the Grama Seva Niradari
to fell jack trees. The Contractor can remove other trees
there is any restrictions for removal of trees.
without permission from other agencies but CMC
permission is required. Valuable timber of all the fallen
trees shall be handed over to the CMC.
3.6 Volume 2, Page 6a-73, Clause 2.4.1, Para 400, Earth work sub clause no 400; “Final Consider the distance as not more than 20 kms.
disposal of excavated material shall be to an approved landfill site(s) by the Employer's
Representative “Further to above clause, please provide the approximate distance to
approximate landfill from the project premises.
3.7 Volume 1, Page 4-20, Bidding Forms, Asset replacement Schedule is starting from years Please refer Sub-Clause 14.5 and 14.18(b) in General
Conditions of Contract (FIDIC) in Section 7
6. Our understanding is the asset replacement schedule to be started from Year 1. Kindly

  7 / 9 
 
No Questions Answers
clarify.
3.8 Volume 2, Page 6a-46 & 50, Figures are missing with the document. Kindly provide. Please collect the Figures from the soft copy of the bid
document available in the following link
https://goo.gl/U5PwmT
3.9 Volume 1, Page 2-3, Related to the Schedule no 3, 4, 5a, 5b, 5c and 6; our understanding Yes
is VAT component can be claimed with Contractor's invoices at the time of payment. Please
confirm.
3.10 Volume 1, Section 3, Evaluation and Qualification Criteria, It is mentioned that “at least two It meant that two (two projects) of mixed domestic and
trade wastewater treatment plants
mixed domestic and trade wastewater treatment plants”; our understanding is the
contractor has to show one mixed domestic and one trade wastewater treatment plant
experience . Kindly confirm.

3.11 Volume 2, Page 6a-15, Design Build Requirement, please provide approximate number of Staff strength of 6-10
employer’s staff.

3.12 General, there are two employers in this tender; as per our understanding, it is only need to Please refer to Clarification 01 – Answer No. 1.1
address the Design and build employer’s name in the Tender bond. Please confirm.

3.13 General, Please provide more Design requirements for the Other Associated Please be more specific to provide an answer
infrastructures under the Employer’s requirements. For example, The Floor area of Office
and Operation building.

3.14 Section 3.7of the Employer’s requirements mentioned that heavy metals are not a critical You can base the design on present conditions and if
there will be any change in the influent quality in the future
issue while designing WWTP. But in the future, it may be changed and WWTP will be
the employer will determine how to handle it. However, it
damaged due to heavy metals. So please clarify this matter. is unlikely to change the character of Colombo
Wastewater, away from typical domestic type sewage as
even the small industries currently present are likely to
move out with time.

  8 / 9 
 
No Questions Answers
4 Responses to questions received from bidders on 25th August 2017
4.1 The demolition of the fire brigade building is within the Contractor’s scope. Is the Contractor has the option to demolish or use the existing
buildings.
relocation of the particular building also included in the Permanent works? If so please
No, relocation is not in the scope of contract. This will be
provide the proposed land details and other required information. done by CMC.

4.2 The document indicates the proposed land for relocation of the playground. Is the No, relocation is not in the scope of contract, this will be
particular relocation also a part of the Contractor’s permanent works? If so please provide done by CMC.
the required information
4.3 According to the bidding document electrical and mechanical items of the demolished Those need to be provided to CMC stores. They will
structures should be handed over to the CMC. Please provide the location details of the nominate the place but it will be within the Colombo
handing over procedure to understand the cost for transportation Municipality Area
4.4 Is there any allocated land for the disposal of unwanted building materials of the No
demolished buildings?

4.5 Please provide the information of CMC’s involvement within the period of operation? CMC is the Employer of the contract for Operation Service
period, which is clearly detailed in the bidding document.
4.6 Please provide maximum possible of the following documents/drawings for further Not all the drawings/ reports are available.
Please refer the drawings available in the following link.
reference.
https://goo.gl/U5PwmT
A list of available drawings is available in the same link
 As-built drawings of the two pump stations and As Attachment 1 for these replies.
 As-built drawings of the junction chamber and the sea outfall

 As-built drawings of the fire brigade building

 As-built drawings of the Colombo Sewerage Network

 Any report of recent inspection & repair of the sea outfall section near the junction
chamber

 EIA report used for obtaining the environmental clearance

  9 / 9 
 
Ministry of Provincial Councils and Local Government
Contract: Wellawatta Wastewater Treatment Plant
Contract No: GCWWMIIP-TR3/ADB/ICB-02/2017
Bid Clarification No. 06 (1 Question Set)

(1) Responses to questions received from bidders on 29th August 2017

No Questions Answers
1.1 Volume 1, Section -04, Page 4-30, Price Schedule 5b &5c It is mentioned as "tariff Answer not Finalized. Will be answered later.
charges Kn = Assuming tariffs on date of adjustment are:
Peak rate (18.30-22.30): 24 LKR/KwHr
Day rate (5.30-18.30): 12 LKR/KwHr
Off-peak rate (22.30-05.30): 6 LKR/KwHr
Kn = [(24 x 4hrs) + (12* 13 hrs) + (6 x 7hrs)] /24 = 12.25 LKR/KwHr

Query:
We understand that in the above mentioned tariff charges are only for the variable power
tariff. So we kindly request the employer to please specify the Fixed charges and monthly
demand charges (LKR/Kva/Month) applicable during the O&M tenure of 18 years.
1.2 General, Query: Answer not Finalized. Will be answered later.
We understand that if any change in Fixed charges and monthly demand charges during
the O&M contract period, client shall reimburse the same on submission of documentary
proof. Please confirm.
1.3 Volume 1, Section -03, Page 3-4, Qualification - Please clarify in case bidder is claiming Experience of subsidiaries is not acceptable. Refer note in
the first sentence in Page 3-4 under 2 – Qualification of
experience of its subsidiaries, is any joint venture agreement required or only subsidiary
Volume 1.
confirmation will serve the purpose. “It is the legal entity or entities comprising the Bidder, and
not the Bidder’s parent companies, subsidiaries, or
affiliates that must satisfy the qualification criteria….”

  1 / 1 
 
Ministry of Provincial Councils and Local Government
Contract: Wellawatta Wastewater Treatment Plant
Contract No: GCWWMIIP-TR3/ADB/ICB-02/2017
Bid Clarification No. 07 (5 Question Sets)

(1) Responses to questions received from bidders on 06th September 2017

No Questions Answers
1.1 General – We understand that different few flows coming to the pumping stations Understanding is Incorrect. All the flow coming to
Wellawatta PS & Junction Box should be treated.
and few to the Junction Chamber. However, there is a ambiguity over which flow
Please refer sketches available in the following link
is to be treated under this plant. We understand the flows coming to Pumping https://goo.gl/U5PwmT in the folder “Sewer
Station are only to be treated and flows coming to the Junction Chamber are to be Arrangement in Wellawatta PS SKETCH”.
diverted as it is without treating. Request your clarification.
1.2 Section 6c; Wastewater Effluent Discharge and Testing Standards Not all the parameter values are available for
incoming flow. Please refer the wastewater reports
We understand that there are almost 31 parameters to be guaranteed at the outlet.
available in the Following google drive link
However we do not have the inlet values for the same. Request you to provide https://goo.gl/U5PwmT in the folder ‘Wastewater
the same as it will be easier for us to guarantee and design the plant. Reports’ for available data.

1.3 Section 6a; Volume 2; Page No. 6a-17 – Clause 82: Till the issue of the Commissioning Certificate.
We understand that mobile phones has to be provided and bill has to be paid by
the Contractor. However please clarify till what time Contractor has to bear the
bill as it is not clear from the tender. A defined time period will help us in
estimating the exact cost.
1.4 Section 3; Volume-1, Page 3-4 – Qualification Please note the statement on top of Table 2.1 in
Page 3-4, where it is stated that “It is the legal entity
Please clarify in case bidder is claiming experience of its subsidiaries, is any joint
or entities comprising the Bidder, and not the
venture agreement required or only subsidiary confirmation will serve the purpose. Bidder’s parent companies, subsidiaries, or
affiliates, that must satisfy the qualification criteria
described below.”

  1 / 8 
 
No Questions Answers
th
(2) Responses to questions received from bidders on 17 August 2017
2.1 Section 2; Volume-1, Page 2-5 – ITB 24.1 submission and opening bid, Addendum will be issued regarding Bid submission
date extension.
Due to the nature of the works, we shall require additional 8 weeks for
tender preparation. Please kindly extend 2 months for the bid submission
date, from 6th October 2017 to 6th December 2017.
2.2 Section 2; Volume-1, Page 2-3 – ITB 18.4(a)-ii Custom duty and other Tax Confirmed
In addition, please refer wording in Sub-Clause 14.1
We understand that all imported foreign goods/ materials in Price in Section 8 – Part B Special Provisions.
Schedule 1 will be imported under the name of Employer (i.e. consignee
name shall be the Employer) and any duties, custom dues, port charges
shall be paid by the Employer directly to the Department of Customs or
relevant local authorities on the production of Certified??? Custom Entries
by the Contractor; Any VAT payable (if required) shall be charged to the
Employer in addition to the Contract Price and shall be paid by the
Employer separately as addition to the listed price in Schedule 1.
Please kindly confirm.

2.3 Section 2; Volume-1, Page 2-3 – ITB 18.4(b) ii, ITB 18.4(c), ITB 18.4(d), ITB Confirmed
18.4(e), VAT payable on the Item in Price
We understand that the price quoted locally under Contract in Price
Schedule 2, Price Schedule 3, Price Schedule 4, Price Schedule 5, Price
schedule 6 shall exclude VAT and any VAT payable shall be charged to the
Employer as a separate item in addition to the Contract price and should
be supported with VAT Registration Number. The Employer shall pay
such VAT in addition to the Contract price.

Please kindly confirm.

  2 / 8 
 
No Questions Answers
2.4 Section 3; Volume-1, Page 3-2 – Mobilization of construction equipment & It is left for the Bidder to list the equipment &
Personnel needed by them to execute the Contract
personnel As per Item I of Clause 1.1, Section 3, the capacity to mobilize conforming to the Employer’s Requirements and
key construction equipment and personnel for the contract will be then show their ability to mobilize such equipment as
evaluated. Please kindly suggest the minimum requirement on the needed for the contract.
construction equipment and personnel.
2.5 Section 4; Volume-1, Page 4-22 – Schedule of payment Confirmed as follows:
Reference to the Schedule 3
We understand the schedule of payment for Schedule 3 design service will
20% of the total design service amount as an
be as below: advance payment;
- 20% of the total design service amount as an advance payment; - 60% of the total design service amount upon
- 80% of the total design service amount upon acceptance of design by the acceptance of design by the Employer's
representative (This would mean a total of 80%
Employer's representative;
having paid including the 20% already paid);
- 20% of the total design service amount upon issue of Commissioning - 20% of the total design service amount upon
Certificate; issue of Commissioning Certificate;
Please kindly confirm.
2.6 Section 4; Volume-1, Page 4-23 – Schedule of payment
As per the Price Schedule No.4 of Section 4, ITB document, the operation
and maintenance cost for the existing pumping station during Design-Build
Period is under Price Schedule 4: Installation and other services during the
Design-Build Period.
We wish to request your confirmation of the followings ;
- That the payments for rehabilitation, operations and maintenance of the
existing Wellawatta pumping station during the Design and Build Period - Confirmed
will be by the Ministry of Provincial Council (First Party) and NOT by
Colombo Municipal Council (Second Party)
- We suggest that the payment terms for operation and maintenance of the
- Changes to the terms payment are not possible
existing pumping station during the Design- Build Period shall be based on
monthly fixed payment with automatic price adjustment for any increase in
the electricity tariffs by CEB.

  3 / 8 
 
No Questions Answers
2.7 Section 8; Volume-1, Page 8-6, Sub-Clause 14.3(a), (b) – Deduction for As per Schedule of Payments
In Schedule 1 – Advance Payment is fully recovered
advance payment
at the stage of payment of 90% upon issue of
As per Sub-Clause 14.2 (a), (b) of Section 8 Particular Conditions of Commissioning Certificate
Contract, the deduction for advance payment shall be referred to the In schedule 2 - Advance Payment is fully recovered
at the stage of payment of 90% upon issue of
schedule of payments attached to the price schedule. Commissioning Certificate
In Schedule 3 – Advance Payment is treated as any
According to the Schedule of payments, we understand the advance other part payment
In Schedule 4 - Advance Payment is fully recovered
payment deduction is non-applicable for this Contract. Please kindly at the stage of payment of 90% upon issue of
confirm. Commissioning Certificate.
2.8 Section 8; Volume-1, Page 8-6, Sub-Clause 14.3 – retention Money In Schedule of Payments, a retention is applicable
for payments under Schedule 1, 2, 3, and 4. Please
As per Sub-Clause 14.3 of Section 8 Particular Conditions of Contract, the see the last paragraphs in each such Schedule in
Percentage of Retention and Limit of Retention Money shall be referred to Pages 4-21 & 4.22.
the schedule of payments attached to the price schedule.

According to the Schedule of payments, we understand the retention


money is non-applicable for the Design and Build Part of the Contract.
Please kindly confirm.

2.9 Section 8; Volume-1, Page 8-6, Sub-Clause 19.2(a)(i) – Answer not Finalized. Will be replied later.
As per Sub-clause 19.2(a)(i), the permitted deductible limits is defined as
none. This is contrary to general industrial practice for Contractor All Risk
insurance during D&B period as such insurance policy always have a
deductible limits . As deductible limit is a Contractor's risk, it is in the
interest of Contractor to procure an insurance with reasonable deductible
limit. Typically, this specific sub-clause should provide what is the limit of
deductible limites (i.e. 50,000 USD) allowed and the Contractor can
choose to procure an insurance policy with deductible limit not exceeding
the required amount or lower. Please amend this sub-clause to allowed
for a reasonable deductible limit based on standard industrial practice.

  4 / 8 
 
No Questions Answers
2.10 Section 8; Volume-1, Page 8-7, Sub-Clause 19.2(c) Answer not Finalized. Will be replied later.
As per Sub-clause 19.2(c), the amount of professional liability insurance is
set at 150% of the Accepted Contract Amount which is unusually high and
unheard of in other similar Contracts. Such requirement may not be even
available in the market. Typically, Professional liability insurance cover only
the design amount in the contract. Please amend this sub-clause to be
in line with standard industrial practice for amount to be covered under
professional liability insurance.
2.11 Section 6a & 6c; Volume-2, Page 6c-3, - Peak flow and peak duration Answer not Finalized. Will be answered later.
As per hydraulic capacity standards in Section 6c schedule of guarantee,
the design flow for 2040 in operation is 50MLD (ave. dry weather) and
65MLD (peak flow).For our understanding, 65MLD (peak flow) is
corresponding to 2,708m3/h, which means the peak factor is 1.3. From our
previous experience, the peak duration can be assumed as 4h/day. Please
kindly confirm the hydraulic design basis for the plant will be as following: -
Design flow 50MLD (ave. dry weather) - Peak factor 1.3 - Peak duration
hours: 4h/day
2.12 Section 6a; Volume-2, Page 6a-35, Clause 3.1.7-Existing Utility With present arrangement, the 11/.4 kV transformer
is provided by CEB and power supply for the pump
As per Clause 3.1.7 of Section 6a, at present there is a Ceylon Electricity station is provided at 400V. Approximately 250
Board (CEB) transformer at the Wellawatta new pump station. Please kVA of power is allocated for the pump station.
kindly suggest if the incoming power supply is from 11kV high voltage line Supply at 11kV is also available and the contractor
may decide whether to obtain power at 11kV or
and what's the capacity of the existing transformer. 400V.

2.13 Section 6a; Volume-2, Page 6a-90, Clause 7.3- Applicable Codes and BS 7671- is the wiring regulation applicable in Sri
Lanka. This cannot be changed. BS 1363 for
Standard
socket outlets and similar standards which are
As per Clause 7.3 of Section 6a, the British Standard shall be applied to adopted in Sri Lanka cannot be changed.
the electrical works, however, we noticed that existing electrical works Standards for project specific equipment IEC is
generally acceptable.
e.g.LCP in new pumping station are according to IEC standard during the
site visit.

  5 / 8 
 
No Questions Answers
Please kindly conform if IEC or other equivalent international standard is
applicable for the Electrical Works.

2.14 Section 6a; Volume-2, Page 6a-2, Clause 1.1- Existing Pumping Pump Details are available in the following link.
https://goo.gl/U5PwmT
According to Item 10, Clause 1.1 of Section 6a, Contractor is required to under Folder ‘Wellawatta PS Pumps & Screens
ensure uninterrupted sewage disposal through the sea outfall by Details’
maintaining the existing wastewater pumping. Please kindly suggest the
detail specifications of the existing submersible pump at the old Wellawatta
pumping station (capacity m3/hour, motor kW and make)
2.15 Section 6d; Volume-2, - Supplementary information All available drawings are accessible under the
following link.
We would like to request Civil As Built Drawings for the existing structures https://goo.gl/U5PwmT
indicating the various invert levels and layout arrangements. A list of available drawings is available in the same
- the New Pumping Station; link and As Attachment 1 for these replies to queries
received.
- the Old Pumping Station;
- Outfall Chamber;
- Existing Administration Building
- Existing Firefighting Station
2.16 Section 6d; Volume-2, - Hydraulic profile of the plant This is to be a part of the design by the Contractor
We would like to request hydraulic profile of the plant.
2.17 Section 6d; Volume-2, Page 6d-3, Clause 7- potable water network Water Supply Arrangement of the New PS is
accessible under the following link.
Please kindly suggest the connection point for the potable water. Can https://goo.gl/U5PwmT in the folder ‘Drawings &
provide the potable water network drawings within the plant? Details of Structures’ within subfolder ‘Wellawatta
New PS’
No other drawings of potable water network are
available.

2.18 Section 6d; Volume-2, Page 6d-4, Clause 8- sewer water network Wastewater & Sewage Disposal arrangement of the
New PS is accessible under the following link.
Please kindly suggest the connection point for the sewer system. Besides https://goo.gl/U5PwmT in the folder ‘Drawings &
that, please confirm if there is a sewer system within the plant, if yes, can Details of Structures’ within subfolder ‘Wellawatta
provide the sewer network drawings within the plant? New PS’.

  6 / 8 
 
No Questions Answers
2.19 Section 6d; Volume-2, Page 6d-3, Clause 7- Electrical As built drawing of Single Line Diagram of the
existing new PS is accessible under the following
Can provide the power single line drawing for the existing plant? link.
https://goo.gl/U5PwmT in the folder ‘Drawings &
Please kindly confirm if the existing Short-Circuit breaking current is 25kA. Details of Structures’ within subfolder ‘Wellawatta
NEW PS’
25kA is the minimum considered for CEB supply at
400V. Actual short circuit current will have to be
assessed considering the actual power requirement
for the plant, size of the transformer and the strength
of the utility supply. That is part of the contractor’s
design.

(3) Responses to questions received from bidders on 31st August 2017


3.1 Section 6d; Volume 2; Page No. 6d-4 – Clause 8 – Outdoor discharge main As built drawing of Outfall pipe is accessible under
the following link.
pipe routing:
https://goo.gl/U5PwmT in the folder ‘Drawings &
We would like to request Civil As Built Drawings of the outfall discharge main pipe Details of Structures’ within subfolder ‘Sea outfall’.
indicating the pipe routing and hydraulic level.
3.2 Section 6d; Volume 2; Page No. 6d-4 – Clause 8 – Outdoor discharge main As built drawing of Junction Box is accessible under
the following link.
pipe routing:
https://goo.gl/U5PwmT in the folder ‘Drawings &
We would like to request Civil As Built Drawings of the outfall junction box inlet Details of Structures’
pipe indicating the pipe routing and hydraulic level for the existing catchments.
3.3 Section 2; Volume 1; Page No. 2-1– ITB 2.1 – finance Amount of Finance for the project is available in the
‘Periodic Financing Request Report 45148-008’
as per ITB 2.1, Section 2, The Democratic Socialist Republic of Sri Lanka and
available under ‘Project Documents’ in ADB website.
Asian Development Bank has signed a finance agreement for Greater Colombo The Expiry date of loan is available in the ‘Project
Water and Wastewater Management Improvement. 45148-008’ available under ‘Projects’ in ADB
website.
Please advise us the amount of financing and expiry date of the said finance
agreement for this project.

  7 / 8 
 
No Questions Answers
th
(4) Responses to questions received from bidders on 04 September 2017
4.1 Section 6a; Volume 2; Page No. 6a-43 – Clause 3.7.1 -Influent characteristics No continuous data is recorded for the influent waste
water quality in Wellawatta PS. You may access the
The summary of waste water characteristics at wellawatta outfall is given in table 2
WW reports available in the following link.
clause 3.7.1, Section 6a of ITB documents. We would like to request the detail https://goo.gl/U5PwmT in the folder ‘Wastewater
records of influent water quality for the last year including BOD, COD, TSS, TKN Reports’ for available data.
TP and total coliform.
Please kindly consider our request.

(5) Responses to questions received from bidders on 15th September 2017


5.1 Section 4; Volume 1; Page No. 4-16 – Schedule 5c- Operation Service Answer not finalized. Will be answered later.
It is mentioned as " The COD removal fee shall not be payable for days where the
influent COD concentration measured before treatment is 250 mg/l or less".
Query:
We wish to bring to your notice that "During less COD in the influent (< 250 ppm)
the plant will operate for reduction of other parameters like TSS, BOD etc". We
request the client to kindly clarify how the bidder will be compensated for the
power cost during less COD inflow.
5.2 Section 4; Volume 1; Page No. 4-16 – Schedule 5c- Operation Service Please refer above answer 5.1.
Understanding is confirmed.
It is mentioned as " Estimated weight of COD to be removed through treatment".

Query:
We request the client to clarify how the bidder will be compensated for the power
cost during the first seven years when the estimated weight of COD removal
through treatment is NIL as per the schedule No 5C - item no 3. We also
understand that the in-case COD gets higher than 250 ppm during the first 7
years, the payment will be made based on the calculation mentioned in the
payment schedule. Please confirm our understanding.

  8 / 8 
 
Ministry of Provincial Councils and Local Government
Contract: Wellawatta Wastewater Treatment Plant
Contract No: GCWWMIIP-TR3/ADB/ICB-02/2017
Bid Clarification No. 08 (2 Question Sets)

(1) Responses to questions received from bidders on 18th September 2017

No Questions Answers
1.1 Section 3; Volume 1; Page No. 3-5 – Clause 2.2: Pending Litigation What is required is for the bidder to indicate that a
litigation process is ongoing or not, and if on going
The time period for pending litigation and Arbitration, section 3 evaluation
the amount of claim.
qualification criteria is not mentioned in the tender. Please clarify.
1.2 General; Please clarify the distance from Wellawatta WWTP to Maligakanda About 8 km
central monitoring Station
1.3 General; Please clarify number of circuit of CEB power supply CEB supply is available only at one point presently.

1.4 General; Please clarify Voltage of CEB power supply Present supply is 400/230V. power may also be
obtained at 11KV under different tariff from CEB

1.5 General; Please clarify Model of power supply, which one TN-C, TN-S, TT, IT TT

Section 6a; Volume 2; Page No. 6a-92 – Clause 7.4.: Power from CEB
It is mentioned that the contractor needs to provide HV to LV transformer. While in You have missed “or” condition in Clause 7.4 that
7.5 of same section, it is mentioned that the power from CEB is low voltage power the contractor is free to decide to provide new
1.6 transformer and request CEB to meter at 11KV, or
supply that doesn’t need convert high voltage to low voltage. Please clarify which get CEB to provide new transformer with higher
requirement shall prevail and whether a new transformer is needed? capacity and meter at 400/230V or any other option

Section 6a; Volume 2; Page No. 6a-96 – Clause 7.18.: Harmonics CEB does not have published standards for
It has certain requirement on power quality. Particular for the harmonics. However, harmonics, as it is in the customer’s interest to
reduce harmonics to improve true power factor. CEB
1.7 the specific value and requirements are not clearly given in the technical
will intervene only if there is a complain from third
specifications. Would you please provide relavent CEB technical specification on party. It is generally safe is IEEE- std 519 is
this matter? complied with.

  1 / 2 
 
No Questions Answers

(2) Responses to questions received from bidders on 26th September 2017

Section 3; Volume 1; Page No. 3-8 – Clause 2.4.1: Bidder’s Experience,


Contracts of similar size and nature Characteristics of incoming wastewater are given in
2.1 Employer’s Requirement(ER) and the plant has to
We believe that domestic sewerage and trade effluent are two different streams be designed to cater to such characteristic.
and require different treatment

  2 / 2 
 
Attachment 01

Wellawatta WWTP Supporting Documents
List of Drawings/ Sketches available in Google Drive Folders & Sub‐Folders
Folder in Google Drive Sub‐Folder within Folder Drawing in Folder/ Sub‐Folder
JB‐01 Junction Box (1987)
Directly in Folder
18 Fire Station (2004) (3Dwgs)
Wellawatta PS Foundation Details for Sil & Screen Pits & Sump (1916)
Wellawatta PS Penstock Gate
10 Old PS
Wellawatta PS Sectional Plan Above Floor Level
Wellawatta PS Sections
Wellawatta Old WWTP Detritus & Sedimentation Tanks ‐ Plan (1917)
Wellawatta Old WWTP Detritus & Sedimentation Tanks ‐ Sections (1917)
19 CMC Old Building
Wellawatta Old WWTP Wet Weather Sedimentation Tanks ‐ Plan (1919)
Wellawatta Old WWTP Wet Weather Sedimentation Tanks ‐ Sections (1919)
MLP 1 (5Sheets)
Mount Lavinia Pump Stations MLP 2 (6Sheets)
14 Nos of Sketches
Architectural Details of Super Structure
Beam RF at ‐0.1 A
Beam RF at ‐0.1 B
Beam RF at ‐4.145
Beam RF at ‐8.89
Concrete Outline Layout
Concrete Outline Sections
Control Room Layout & Power Panel (Sketch)
Details of Roof trusses
Electrical Distribution Single Line Diagram
Electrical Lighting & Small Power part 1 Substructure
Emergency Small Pwr & Ligting at existing PS – 1
Emergency Small Pwr & Ligting at existing PS – 2
Equipment & Piping Arrangement B
Equipments & Piping Arrangement C
Equipments and Piping Arrangement A
Drawings & Details of Structures
Fire Detection Alarm & Protection System Layout
Fixing Details of Purlings, Valance board & Bracings
Lightning Protection Layout
Main Feeder & Power Wiring
Manhole at Overflow Line
Wellawatta NEW PS Pipe Support & Stop Log extractor A
Pipe Support & Stop Log extractor B
Pipe Support & Stop Log extractor C
RF at Baseslab ‐11.33
RF at slab ‐7.39
RF details at ‐3.845
RF details at Stop Log Groves at ‐7.39
RF details ground floor columns & corbels
RF details Ground Floor Slab
RF details Sec 1‐1
RF details Sec 2‐2
RF details Sec 3‐3
RF details Sec 4‐4 & 5‐5
RF details Sec 6‐6 & 7‐7
SCADA system contol Wiring & Measuring Devices
Staicase 1 RF details
Staicase 2 RF details
Supporting Bracket Details
Thrust Block Details at Pumping Main
Ventilation System 1 & 2
Water Supply Arrangement
WW & Sewage Disposal Arrangement
Yard Piping
Plan of Wellawatta Outfall
Sea Outfall LS of Wellawatta Outfall
Bedding Backfill & Armour details
FM ML‐1 & ML‐2 (4Dwgs)
Forcemain Drawings Directly in Folder FM‐CFM‐9 & CS 16 (3Dwgs)
FM‐Jpura Layout & LS (3Dwgs)
SI 06 ‐ WELLAWATTA SITE
Key Map & Survey Directly in Folder
SI‐6A DETAIL LIST OF EXISTING STRUCTURES And KEY MAP
Wellawatta Coarse Screens
Wellawatta Fine Screens
Wellawatta PS Pumps & Screens 
Directly in Folder Wellawatta New PS Pump Details
Details
Wellawatta Old PS Flygt Pump
Wellawatta PS Details
Sewer Arrangement in  SK‐01 Existing Sewer Arrangement in Wellawatta PS
Directly in Folder
Wellawatta PS SKETCH SK‐02 Sewer Arrangement in Wellawatta with Proposed Marine Sewer

Page 1 of 2
Attachment 01

Wellawatta WWTP Supporting Documents
List of Other Information
Folder in Google Drive Sub‐Folder within Folder File in Folder/ Sub‐Folder
Environmental Clearance Directly in Folder CEA Environmental Clearance
Dept of Irrigation FL near Mattakkuliya
Flood Level Information Directly in Folder
SLLRDC Flood Map & Levels
1 ‐ Medical Supply Division (Building 1) 13 Photos
2 ‐ Medical Supply Division (Building 2) 1 Photo
3 ‐ Security Hut ‐ 1 1 Photo
4 ‐ Sport Rest Room 3 Photos
5 ‐ Water Board Stores 3 Photos
6 ‐ Water Board Office 3 Photos
7 ‐ Security Hut 2 2 Photos
8 ‐ Electric Room 3 Photos
9 ‐ New Pump Station 11 Photos
10 ‐ Old Pump Station 11 Photos
Site Structure Photos 11 ‐ Container Water Board Stores 3 Photos
12 ‐ Shrine Room 1 Photo
13 ‐ CMC Quarters 3 Photos
14 ‐ CMC Stores 2 Photos
15 ‐ Car Park 1 Photo
16 ‐ Wash Room 5 Photos
18 ‐ Office and Quarters 3 Photos
19 ‐ CMC old Building 3 Photos
20 ‐ Security Hut ‐ 3 2 Photos
21 ‐ Junction Box 2 Photos
General 15 Photos
Directly in Folder Wastewater Quality Survey ‐ UOM ‐ 2011
Water Quality Survey 01
Wastewater Reports Water Quality Survey 02
SGS ‐ Water Quality Survey ‐ 2013
Water Quality Survey 03
Water Quality Survey 04
Bidding Forms Directly in Folder 4_Section 4 Wellawatte DBO
Wellawatta Electricity Bills
Wellawatta PS Utility Bills Directly in Folder
Wellawatta Water Bills

Page 2 of 2