PROJECT:- (G+5)STAFF ACCOMODATION ON PLOT NO.

592-154 – JABEL ALI


CLIENT:- DEWA
CONSULTANT :- ARCHDOME CONSULTING ENGINEERS
MAIN CONTRACTOR:- ALI MOOSA & SONS CONTRACTING

No. Material Make Origin

A AC WORKS
1 Centrifugal chiller Carrier - USA & France) (USA & France)
Trane - (USA & France) (USA & France)
2 Cooling Towers (CTI Certified) Balticare Europe
Marley UK
GEA Polacel Europe
3 Chilled water and condenser water Armstrong UK
pumps
ITT Bell & Gosset UK
Lowara Australia
Paco USA
Holden Brooke UK
4 Fresh air handling units / AHU & fan coil Trane Europe
units
Carrier Europe
York Europe
Trosten UAE
5 Fans Greenheck UK
ACME UK
NUAIRE UK
Pen ventilation UK
Twin city fan USA
6 Cooling tower make up water pumps Lowara Australia
ITT Beil & Gosset UK
Ibara Europe
Armstrong UK
7 Valves Crane UK
Hattersley UK
8 Valves (auto flow balancing) Frese Sweden
Flowcon Denmark
Crane UK
9 Pipes (MS piping for chilled water) Nippon Steel Japan
Van Leeuwen Europe
Sumitomo Japan
10 Pipe fittings (MS) Crane UK
Benken Japan
Georg Fisher USA
11 HDPE pipes and fittings Georg Fisher Germany
Uponor Germany
Muller USA
12 Plate type heat echanger Alfa Laval
Sondex
Precision
13 Pressure reducing valve Amtrol Inc
Taco
ITT Bell & Gossett
14 Pump discharge valves Amirrol Inc
Armstrong Pumps Inc
Bell & Gosset ITT; Fuild
Handing DIV
Taco Inc
15 Safety relief valves Amtrol Inc
Bell & Gosset ITT; Fuild
Handing DIV
Spriax Sarco
Watts regulator Co
16 Air separators Amrol
Armstrong Pumps Inc
Bell & Gosset ITT; Fuild
Handing DIV
Taco Inc
17 Pressurization unit Holden & Brooke
Heat Transfer
Pillinger

B DRAINAGE WORKS
1 Sump and sewage pumps Flygt-Sweden or Sweden
equivalent
2 Sanitary ware Toto
Roca
or equivalent
3 Mixers Kludi Germany
Roca
Marion Bongio Italy
Grohe Germany
4 Washroom accessories Bobrick International
Roca
Keuco Germany
5 Water tanks (insulate GRP panel hot Mitsubishi Japan
pressed)
Brigestone Japan
6 Domestic water transfer and booster Grundfos UK or Germany
pumps set
ITT Bell & goSSET
7 Solar water heating system AO Smith USA
Ariston Italy
8 Gate, globe, check, ball and float valves Hattersley

Crane
Pegler
9 Butterfly valves Crane
Pegler

C FIRE FIGHTING WORKS


1 Fire pump set (UL/FM) Peerless USA
R-B USA
ITT Bell & Gossett
Armstrong UK
2 Diesel engine UL Lister-Petter UK
Fire Drive
Clark UK

D ELECTRICAL WORKS
1 LV boards, SMDBs, DBs, MCCs ABB Europe
Schneider Frane
Legrand or equivalent France
2 Public Address System BOSCH Germany
Kenwood Japan
Philips Holland
Audix UK
Panasonic Japan
Millbank UK
Bouyer France
Egi Spain
3 CCTV System BOSCH/DM/Baxall
Vicon Germany/UK/UK
Pelco UK
Panasonic USA
Honeywell Japan
Axis or equivalent USA
4 Access Control System Leinel UK
Imrpo/Biosrypt S. Africa / USA
Watchnet or equivalent
5 TV Antenna & Satellite System Televes/Alcad Spain/Spain
Kathreen Germany
Hershman Germany
Wisi Germany
Bosch/Philips Europe
Televes or equivalent Spain
6 Gate barriers Nice/CAME Italy/Italy
RIB Italy
DESIGNA Germany
LANGE Germany
DEA or equivalent Italy
7 Capacitor controller P&C USA
Circutor Spain
ABB Europe
Schneider China
8 UPS BPC
Liebert UK
Sosmec France
Merlin-Gerin USA
GE or equivalent
9 Light fitting Trilux Germany
Thorn UK
Rovasi Spain
LG or equivalent Korea
10 Ballast Tridonic Italy
LG Korea
GE USA
BAG or equivalent Germany
11 LED lamps LG Korea
GE USA
Soraa or equivalent USA
12 Decorative light poles aluminum (powder Sermito France
coated)
Ekko Australia
Pali Campton Italy
Phosco UK
Alico or equivalent UAE
13 Galvanized steel poles powder coated to Where specified only Local
RAL color (Conical, Stepped or straight) 3
to 4 meters

14 Lifts Mitsubishi Japan


Otis Europe
or equivalent Italy
15 Structural cabling system
a. UTP cables & patch cords a. Systimax from common USA
scope
b. 24/48 port copper patch pane; b. Panduit USA/Canada
c. Fiber patch panel c. Leviton or equivalent USA
d. Fiber optic cable Switzerland
e. Cable manager

Remarks
* All the long lead materials schedule delivery dates are based on the early finish dates of the baseline
NO.592-154 – JABEL ALI

ACTING

Delivery Time (weeks) Order date Delivery date

20 to 24 29/Jul/2016 16/Dec/2016

20 to 24 29/Jul/2016 16/Dec/2016

12 to 16 23/Sep/2016 16/Dec/2016

18 to 20 12/Aug/2016 16/Dec/2016

16 to 18 26/Aug/2016 16/Dec/2016

16 to 20 26/Aug/2016 16/Dec/2016

12 to 14 31/May/2016 23/Aug/2016

12 to 14 31/May/2016 23/Aug/2016

10 to 12 14/Jun/2016 23/Aug/2016
10 to 12 14/Jun/2016 23/Aug/2016

8 to 10 28/Jun/2016 23/Aug/2016

11 to 13 30/Sep/2016 16/Dec/2016

8 to 10 28/Jun/2016 23/Aug/2016

10 to 12 7/Oct/2016 16/Dec/2016

10 to 12 14/Jun/2016 23/Aug/2016

10 to 12 14/Jun/2016 23/Aug/2016

10 to 12 27/Oct/2016 5/Jan/2017

10 to 12 14/Jun/2016 23/Aug/2016

14 to 16 7/Jan/2017 15/Apr/2017

12 to 14 21/Jan/2017 15/Apr/2017

12 to 14 21/Jan/2017 15/Apr/2017
12 to 14 23/Sep/2016 16/Dec/2016

12 to 14 23/Sep/2016 16/Dec/2016

16 to 18 26/Aug/2016 16/Dec/2016

12 to 14 31/May/2016 23/Aug/2016

12 to 14 31/May/2016 23/Aug/2016

16 to 18 26/Aug/2016 16/Dec/2016

16 to 18 26/Aug/2016 16/Dec/2016

16 to 18 3/May/2016 23/Aug/2016

12 20/Jul/2016 12/Oct/2016

12 to 14 20/Jul/2016 12/Oct/2016

12 to 14 20/Jul/2016 12/Oct/2016
12 to 14 20/Jul/2016 12/Oct/2016

12 to 14 10/Jan/2017 4/Apr/2017

16 to 18 9/Oct/2016 29/Jan/2017

16 to 18 9/Oct/2016 29/Jan/2017

20 to 24 30/Sep/2016 17/Feb/2017

20 to 24 14/May/2016 1/Oct/2016

20 to 24 30/Sep/2016 17/Feb/2017

20 to 24 30/Sep/2016 17/Feb/2017

20 to 24 29/Jul/2016 16/Dec/2016

20 to 22 29/Jul/2016 16/Dec/2016

20 to 24 14/May/2016 1/Oct/2016
the early finish dates of the baseline schedule program