Академический Документы
Профессиональный Документы
Культура Документы
Planning Guidelines
Disclaimer
This guidebook does not confer legal rights or impose legal obligations upon any member of the
public. While TNB has made every effort to ensure the accuracy of the discussion in this
presentation, the obligations of the regulated community are determined by statues, regulations
or other legally binding requirements. In the event of a conflict between the discussion in this
presentation and any statute or regulation, this presentation would not be controlling.
LV PLANNING GUIDELINES
ACKNOWLEDGEMENT
Our special thanks to Hj. Ismail Mohd Din, Senior General Manager, Asset
Management Department for his full support and motivation to establish
the revision of this guide book.
Our appreciation also goes to Assoc. Prof. Dr. Ir. Au Mau Teng, Ir. Lau
Chee Chong, Ms Teo Siow Kim, Mr Ruslam Hussin, Mr Azmi bin Husin, Ir
Rekha A/P Perumaloo, Ms Fadhlillah Adnan, Mr Fazely Haron and Ir Woo
Chiew Chonng for their guidance and feedback in developing the
guidelines. Special thanks to Dr. Marayati Marsadek for her untiring
efforts in proof-reading this guide book.
Thank you.
Page | i
LV PLANNING GUIDELINES
FOREWORD
With this revised Low Voltage Planning Guidelines, I am confident that TNB
Distribution Planners would be able to produce the most efficient LV network to
meet customer’s service expectation.
Page | ii
LV PLANNING GUIDELINES
TABLE OF CONTENTS
ACKNOWLEDGEMENT......................................................................................................... i
FOREWORD ...........................................................................................................................ii
TABLE OF CONTENTS........................................................................................................... iii
Page | iii
LV PLANNING GUIDELINES
Page | iv
LV PLANNING GUIDELINES
APPENDICES ....................................................................................................................... 58
APPENDIX 1: TYPES OF LOADS AND THEIR CHARACTERISTICS .................................. 59
APPENDIX 2: TRANSFORMER SIZING COMPUTATION.................................................. 60
APPENDIX 3: STANDARD MULTI-TENANTED BUILDINGS DESIGN ................................ 62
Page | v
LV PLANNING GUIDELINES
Page | vi
CHAPTER
1
GENERAL INTRODUCTION
1.0 INTRODUCTION
The design and development of supply system are critical in delivering
quality supply to the customers. The quality of supply includes security,
reliability and power quality.
1.1 SCOPE
The scope of this document covers:
Page | 1
LV PLANNING GUIDELINES GENERAL INTRODUCTION
Page | 2
CHAPTER
2
QUALITY OF SUPPLY
2.0 OBJECTIVE
The objectives of this chapter are to:
Page | 3
LV PLANNING GUIDELINES QUALITY OF SUPPLY
∑C d
i =1
i i
SAIDI = (2.1)
N
∑C
i =1
i
SAIFI = (2.2)
N
∑C d
i =1
i i
CAIDI = n
(2.3)
∑C i =1
i
where:
i = interruption event
n = total number of interruptions
Ci = number of interrupted customers for each interruption event
di = duration of each interruption event
N = total number of customers served for the measured area
Page | 4
LV PLANNING GUIDELINES QUALITY OF SUPPLY
Nominal 400V/230V
Tolerance Under Normal + 10 % to – 6 %
Condition (MS IEC 60038)
Tolerance Under
± 10%
Contingencies Condition
Nominal 50Hz
Tolerance Under Normal
Condition ±1 %
Tolerance Under
47 – 52Hz
Contingencies Condition
Page | 5
LV PLANNING GUIDELINES QUALITY OF SUPPLY
Page | 6
CHAPTER
3
LOADS
3.0 OBJECTIVE
The objective of this chapter is to:
i. Natural growth.
ii. Step growth.
Page | 7
LV PLANNING GUIDELINES LOADS
v. Life styles.
vi. Presence of step loads.
LV systems need to be planned such that it can cater for credible load
growth for the foreseeable future. The area load growth must be taken
into consideration when designing supply infrastructure in a new
development area. Normal load growth pattern in a certain area is
represented by the graph shown in Figure 3.1.
Page | 8
LV PLANNING GUIDELINES LOADS
Table 3.1: Typical range of loads for domestic premises (kW per Unit)
Table 3.2: Typical range of loads for commercial premises (KW per Unit)
Type Of Commercial
Min. Ave. High
Premises
Single storey shop house 5 10 15
Double storey shop house 15 20 25
Three storey shop house 20 30 35
Four storey shop house 25 35 45
Five storey shop house 30 40 55
Table 3.3: Load density with respect to load environment for commercial
complex
Page | 9
LV PLANNING GUIDELINES LOADS
Table 3.4: Load density with respect to load environment for industries
Page | 10
LV PLANNING GUIDELINES LOADS
Table 3.6 summarized the typical values of load factors that can be
used for planning purposes.
Page | 11
LV PLANNING GUIDELINES LOADS
*Source: Development of End User Load Model For Distribution Planning By TNBR
Page | 12
CHAPTER
4
DISTRIBUTION SUBSTATIONS
4.0 OBJECTIVE
The objectives of this chapter are:
4.1 DEFINITION
Distribution substation is defined as the substation that converts power
from medium voltage to low voltage. Some typical distribution
substations are as follows:
i. 33/0.4 kV
ii. 22/0.4 kV
iii. 11/0.4 kV
Page | 13
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
In urban areas, substations are often equipped with more than one (1)
transformer due to the high load density.
i. Public safety.
ii. Less chances of vandalism.
iii. Enable VCB installations.
iv. Reduce exposure to environmental impact on equipment and
operation maintenance personnel (eg: UV ray, rain & moisture
etc).
Indoor type substations can be equipped with SCADA system (RTUs and
other communication equipment), capacitor banks and load monitoring
devices.
All substations in the industrial areas must be planned to use indoor type
substations. For operation and public safety purposes, indoor substations
must also be used in all strategic and critical substations.
Page | 14
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
Page | 15
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
Page | 16
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
Page | 17
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
Step 1:Calculate the minimum installed capacity (a) based on the principle of
85% transformer loading using the following relationship:
MD (in KVA)
a= (4.1)
0.85
Page | 18
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
a
b= (4.2)
1000 kVA
Number of substations = roundup (b) (4.3)
a 1246 kVA
Step 2: b= = = 1.25
1000 kVA 1000 kVA
a 3114 kVA
Step 2: b= = = 3.11
1000 kVA 1000 kVA
Page | 19
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
Step 1:Calculate the minimum installed capacity (a) based on the principle of
60% transformer loading by using the following relationship:
MD (in KVA)
a= (4.4)
0.60
a
b= (4.5)
1000 kVA
Number of substations = roundup (b) (4.6)
Page | 20
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
a 1365 kVA
Step 2: b= = = 1.365
1000 kVA 1000 kVA
Page | 21
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
Based from Table 4.4, supply has to be given through a new substation
with 500kVA transformer capacity. 2 circuits of 300mmp Al 1C PVC/PVC
cable is to be laid in concrete trench from transformer tail to customer
MSB (<30m away).
Page | 22
LV PLANNING GUIDELINES DISTRIBUTION SUBSTATIONS
Customers with high load factor can benefit from MV and HV supply as
their electricity tariff would be lower. Furthermore, they would also have
direct control over their incoming supply.
Page | 23
CHAPTER
5
LOW VOLTAGE NETWORKS
5.0 OBJECTIVE
This chapter addresses the planning design requirements of TNB LV
distribution network, such as:
i. Distribution Transformer.
ii. LV Feeder pillars.
iii. LV feeders, can be underground cables or overhead cables.
iv. Five-foot-way mains.
v. Service cables.
vi. Public Streetlighting.
Page | 24
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
5.2.1 Configuration
The LV tail from a distribution transformer can be connected to TNB
Feeder Pillars or directly connected to customer’s Main Switch Board
(MSB) depending on the connection schemes.
Separate MSB must be installed at the customer’s intake side for the
owner and tenant supply when it involves multiple tenants and owner
intake, such as condominiums, apartments or shopping complexes.
Detailed design scheme is shown in Appendix 3: Multi Tenanted Building
Design. However, multi-tenanted building customers are encouraged to
take bulk supply with Independent Distributor license from Energy
Commission. Independent Distributor is licensed to sell electricity to the
tenants in a building / development.
Page | 25
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
Transformer LV Tail
kVA HT Tail 11/.4 kV
Rating Phase(sq mm) Neutral(sq mm)
5.3.1 Configuration
LV feeder pillars should accommodate a sufficient number of outgoing
feeders in order to allow optimal distribution of LV system to meet the
expected customer demand. The number of outgoing feeder pillars
with respect to feeder pillar current carrying capacity is given in Table
5.2.
Page | 26
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
Typical Number
Feeder Pillar Current Typical Number of
of outgoing
carrying capacity (A) incoming feeders
feeders
400A (Mini) 2 6
800A (Main / Sectional) 2 5
1600A (Main / Sectional) 2 8
Page | 27
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
5.4. LV FEEDERS
The outgoings from main feeder pillars which are used to distribute
supply to customers are called LV feeders. LV feeders include
underground and / or overhead cables.
5.4.2 Configuration
LV network is designed with security level 4. However, higher level of
security can be designed based on consumer request at an additional
cost and with special agreement from TNB.
Page | 28
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
“Mains” along terraced premises are often in the form of Five Foot Way
Mains comprising of PVC single core insulated conductors or ABC
insulated cables.
5.5.1 Configuration
Five Foot Way Mains configuration is currently standardised to three
phase plus neutral in which it consists of four wire layout throughout its
length using 7/.083 (25mm2) for PVC Al. or 3 x 16mm2, 3 x 95mm2 and
3x185mm 2 for ABC cables. Due to the increasing load demand by
customers, it is necessary to use high capacity conductors. To facilitate
the increasing load demand by customers, larger ABC cables are used
instead of single core conductors. Five Foot Way Mains normally do not
include feed back supply features.
TNB has recently extended the provision of street lighting to include such
supply to domestic customers, also at a special tariff.
5.7.1 Configuration
The configurations of street lighting are divided into three categories.
Page | 29
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
Planners should plan for the street lighting supply at the initial stage so
that the distance from the source to the street light meter panel can be
optimized. The distance is restricted by voltage drop and technical loss
of the service cable. Refer Appendix 5 for typical streetlight
configuration.
Meter Board
Customer Type Design requirement
Location
Conductor PVC Al 1C 35mm2
Five Foot
Residential Overhead (19/.064) as the five foot way mains
Way
Services drop Conductor PVC Al
1C 25mm2 (7/.083) into 3 houses
Residential Overhead Pole
(max) with meters installed at the
pole
Page | 30
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
Meter Board
Customer Type Design requirement
Location
Use LV underground service cable
from pole and junction box if
Domestic Overhead looping of service cable is required
Gate Pillar
(with gate pillar) (3 houses max). The bottom of
meter must be >3 feet from floor
level.
UG Cable LV XLPE Al 4C 185mm 2
terminated on the pole with
Domestic Semi- Five Foot
service drop 35mm 2 Conductor
Underground Way
PVC Al 1C 35mm2 (19/.064) as the
five foot way mains
Fully underground design with
Domestic Fully junction box for looping of 3 houses
Gate Pillar
Underground max. The bottom of meter must be
>3 feet from floor level.
Fully underground design where
Domestic Fully
Meter Pillar developers prefer centralized
Underground
metering scheme
Ensure grill gate installations at
Group Commercial staircase is after the centralized
Stair case
(U/G) meter panel (by developer, before
V.P. stage)
Upper front
3 phase & 1 phase meters installed
Group Commercial wall of the
between 0.7m to 1.65m from floor
(U/G) commercial
level
premise
Supporting Aesthetic design by the
Group Commercial vertical developer’s architect. 3 phase & 1
(U/G) pillar of the phase meters installed between
building 0.7m to 1.65m from floor level
Meter Room
C.T. & voltage input to meter
Bulk Commercial in TNB
tapped from transformer tail
Substation.
Upper front
3 phase & 1 phase meters installed
Group Industrial wall of the
between 0.7m to 1.65m range from
(U/G) industrial
floor level
premise
Fully underground design with
Domestic Fully junction box for looping of 3 houses
Gate Pillar
Underground max. The bottom of meter must be
>3 feet from floor level.
Fully underground design where
Domestic Fully
Meter Pillar developers prefer centralized
Underground
metering scheme
Meter Room
C.T. & voltage input to meter
Bulk Industrial in TNB
tapped from transformer tail
Substation.
Page | 31
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
i. Residential Overhead.
ii. Residential Underground.
iii. Commercial Overhead.
iv. Commercial Underground.
v. Industrial Overhead.
vi. Industrial Underground.
vii. LV Multi Tenant and Owner.
viii. LV Ring Circuit.
Services can be distributed mainly using five foot way mains or directly
from poles to individual premises.
Page | 32
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
Page | 33
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
Five foot way mains for commercial lots will not pose a problem
because meters and cut outs are accessible to TNB.
Page | 34
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
Page | 35
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
5.9 ECONOMICS
The decision of selecting a certain network design in a project will have
an economic impact to TNB throughout lifecycle of the installation. The
economic consideration shall include:
Page | 36
LV PLANNING GUIDELINES LOW VOLTAGE NETWORKS
The material used to repair the fault for underground cable is more
expensive compared to overhead line and its accessories.
Page | 37
CHAPTER
6
LOW VOLTAGE PROTECTION
AND EARTHING
6.0 OBJECTIVE
The objective of this chapter is:
6.1 DEFINITION
System protection is the combination of devices and features that
ensure safe operation of the system when abnormal conditions occur by
isolating the fault, or dangerous components to eliminate potentially
dangerous incidents.
Page | 38
LV PLANNING GUIDELINES LOW VOLTAGE PROTECTION
AND EARTHING
Fuses provide low cost and effective protection for short circuit and over
load. The types of fuses used in TNB LV distribution system are of HRC
(high rupturing capacity) J-slotted, HRC NH (or Blade type) and barrel
fuse. Table 6.1 presents the types of fuses used in TNB distribution system
and its respective usage.
The Low Voltage ABC Manual provides detail guidelines on the selection
of fuse sizing and location as well as the examples of short circuit current
calculation. The sizing and location of fuses must satisfy the following
criteria so as to conform to the LV protection philosophy:
Page | 39
LV PLANNING GUIDELINES LOW VOLTAGE PROTECTION
AND EARTHING
1
• × ( Conductor current carrying capacity)
1 .5
- This is with reference to mean HRC fuse time-current
characteristic
Nearest
location Fuse Fuse
Fuse Size
allowed Fuse Size Size Size
Transformer Conductor (J-slotted
for (NH at (NH) (NH)
Size ABC at
1st Substation) 1st 2nd
Substation)
Section Section Section
Fuse
16mm2 Tiang 1 n/a n/a 50 n/a
100kVA
95mm2 Tiang 1 n/a n/a 100 50
H/Pole 2
185mm Tiang 1 n/a n/a n/a n/a
16mm2 Tiang 1 60 50 n/a n/a
100kVA
95mm2 Tiang 1 160 160 50 n/a
G/Mounted
185mm2 Tiang 1 n/a n/a n/a n/a
16mm2 Tiang 1 n/a n/a 50 n/a
300kVA 2
95mm Tiang 2 n/a n/a 125 50
H-Pole
185mm 2 Tiang 3 n/a n/a 200 125
16mm2 Tiang 2 60 50 n/a n/a
300kVA
95mm 2 Tiang 2 160 160 50 n/a
G/Mounted
185mm 2 Tiang 3 200 200 100 50
16mm 2 Tiang 2 60 50 n/a n/a
500kVA 95mm2 Tiang 3 160 160 50 n/a
185mm 2 Tiang 5 200 200 100 50
16mm 2 Tiang 2 60 50 n/a n/a
750kVA 95mm2 Tiang 4 160 160 50 n/a
185mm 2 Tiang 6 200 200 100 50
16mm 2 Tiang 2 60 50 n/a n/a
1000kVA 95mm2 Tiang 4 160 160 50 n/a
185mm2 Tiang 6 200 200 100 50
* Source from LV ABC Manual
Page | 40
LV PLANNING GUIDELINES LOW VOLTAGE PROTECTION
AND EARTHING
Page | 41
LV PLANNING GUIDELINES LOW VOLTAGE PROTECTION
AND EARTHING
Page | 42
CHAPTER
7
LOW VOLTAGE METERING
7.0 OBJECTIVE
The objectives of this chapter are to:
7.1 DEFINITION
Metering of electricity for billing is the measurement of the amount of
electrical energy that is consumed by the installation. Metering in TNB is
based on measurement of active energy as kilowatt-hours (KWH), and
reactive energy as kiloVAR-hours (KVARH), where power factor penalty
applies on the supply tariffs concerned.
TNB customers with C.T. operated meter are classified as Large Power
Customers (LPCs).
In TNB, power factor penalty charge is imposed for all customers’ with
monthly average load at power factor value < 0.85, except for domestic
customers and street lighting.
Page | 43
LV PLANNING GUIDELINES LOW VOLTAGE METERING
i. Mode of supply
ii. Supply voltage
iii. Respective tariff
iv. Magnitude of load fed (i.e. energy consumed)
Meter CT PT
Category Voltage Description
Class Class Class
1 400V CT size 400/5 and below 2 0.5 -
2 400V CT size 500/5 and above 2 0.2 -
3 11kV CT size 50/5 and above 0.5 0.2 0.5
4 33kV and above CT size 100/5 and above 0.2 0.2 0.2
Page | 44
LV PLANNING GUIDELINES LOW VOLTAGE METERING
Page | 45
CHAPTER
8
LOW VOLTAGE TECHNICAL LOSSES
8.0 OBJECTIVE
The objective of this chapter is to:
8.1 DEFINITION
Losses in TNB distribution systems are divided into 2 main categories:-
i. Technical losses.
ii. Non technical losses.
Page | 46
LV PLANNING GUIDELINES LOW VOLTAGE TECHNICAL LOSSES
Capacitor banks used in TNB are rated at 300 kVAR and 150 kVAR with
50 kVAR automatically switched steps.
i. Fix losses due to iron losses : varies with the square of voltage.
ii. Variable losses due to current flowing in the resistive component
( I 2 R ).
i. Overloaded feeders.
ii. Long and extensive LV network.
iii. Low power factor / high reactive customer loads.
iv. Unbalanced load.
v. Under-utilized transformers.
8.4.1 Strategies
There are several main strategies to reduce LV technical losses and they
are listed as follows:
Page | 47
LV PLANNING GUIDELINES LOW VOLTAGE TECHNICAL LOSSES
Page | 48
LV PLANNING GUIDELINES LOW VOLTAGE TECHNICAL LOSSES
Page | 49
CHAPTER
9
POWER QUALITY
9.0 OBJECTIVE
The objective of this chapter is to:
9.1 DEFINITION
In the context of LV network planning, power system quality is the ability
of the LV system to deliver electrical energy to consumers within limits
specified by the Electromagnetic Compatibility (EMC) standards.
Common phenomena related to EMC includes voltage dips/swells,
waveform distortion (harmonics, notching), voltage unbalance,
transients, voltage fluctuation and flicker.
Page | 50
LV PLANNING GUIDELINES POWER QUALITY
9.3 HARMONICS
Harmonics in LV network are produced by nonlinear loads which are
expected to increase in numbers due to advancement in the
application of power electronics to improve energy efficiency level of
electrical loads. Inverter air conditioners, refrigerators, washing machines
are examples of highly nonlinear loads which have penetrated the
electrical loads market recently. Other nonlinear loads are the compact
fluorescent lamps, personal computers, television, etc.
9.5 TRANSIENTS
Transients are caused by capacitor switching or lightning.
Page | 51
LV PLANNING GUIDELINES POWER QUALITY
9.7 REMEDIES
Table 9.1 details the possible remedies for power system
electromagnetic phenomena.
Page | 52
LV PLANNING GUIDELINES POWER QUALITY
Page | 53
CHAPTER
10
DATA MANAGEMENT
10.0 OBJECTIVE
The objective of this chapter is to:
Page | 54
LV PLANNING GUIDELINES DATA MANAGEMENT
iv. Low Voltage feeder load profile covering peak, and off-peak
periods.
(Obtainable from Integrated Load Management System: ILMAS)
v. Local substation voltage profile.
(Obtainable from Integrated Load Management System: ILMAS)
vi. Feeder tail-end voltage profiles.
(Obtainable from Integrated Load Management System: ILMAS)
i. Substations
• Types and sizes of substations
• Locations and capacities of local substation transformers and
their tap settings,
• Types and sizes of substation feeder pillars
• Ratings of fuses at the distribution board and feeder pillar
outgoing units
• Types and sizes of outgoing cable feeders
• Date of commissioning
• Date of last maintenance work done
ii. LV feeder
• Overhead lines and cables routes and section lengths
• Types of poles and pole numbers
• Types and sizes of fuses and their positions
iii. Services
• Types and sizes of service cables
• Types and sizes of service fuses
• Number of customers served
• Types of customers served
Page | 55
LV PLANNING GUIDELINES DATA MANAGEMENT
Page | 56
LV PLANNING GUIDELINES DATA MANAGEMENT
iii. Monitor and manage, load demand and system configuration for
the most reliable system aperation.
iv. Anticipate credible demand growth, and develop the system to
cater for it without violating TNB’s quality and reliability standards.
v. Constantly analyze system performance data details to minimize,
or even eliminate, root causes of supply failures, in a cost effective
manner.
Page | 57
APPENDICES
Page | 58
LV PLANNING GUIDELINES APPENDIX 1
Types Of
No Load Devices Load Characteristics
Loads
Operate at essentially power
Incandescent lamps
factor (p.f.).
Operate at p.f. of 0.5 and
Fluorescent lamps and Neon lights need capacitors to improve
1. Lighting load p.f..
Operate at p.f. of 0.7 to 0.8
Mercury Vapour and Sodium Vapour,
and need capacitors to
Metal Halide lights.
improve load p.f..
Radio, television, X-ray, ;laser
equipment, computers, digital time
Electronic Introduce harmonics to the
2. pieces and timing devices, rectifiers,
Gear system.
oscillators for high frequency current
production.
Essentially operate at unity p.f
Residential (small) cooking, water
heaters, irons, toasters, clothes’ dryers,
house heaters
3. Heating Welding, and some type of
Industrial (large) space heaters, ovens, heaters (arc furnace &
furnaces, welders, and high frequency induction type), create severe
heating harmonics into the system if
not adequately filtered
Single phase fractional horse-
Direct current shunt, series and
power motors operate at p.f.
compound type
of 0.5 to 0.7
Larger motors without suitable
starters cause voltage flicker
disturbance to other customers
on the system
A/C single phase and three phase
4. Motor induction and synchronous type
Induction motors operate at
p.f. of 0.5 to 0.95. At less than
full load operation the p.f. may
drop to 0.5-0.6
Page | 59
LV PLANNING GUIDELINES APPENDIX 2
Domestic
Estimated
Yr % Load Uptake vs % Utilisation of Installed
Average Growth
Declared MD with GCF Transformer Capacity
Rate
1 20% 17%
2 100% 40% 34%
3 50% 60% 51%
4 33% 80% 68%
5 13% 90% 77%
6 5% 95% 81%
7 5% 100% 85%
8 3% 103% 88%
9 3% 106% 90%
10 3% 109% 93%
11 2% 111% 94%
12 2% 113% 96%
13 2% 115% 98%
14 1% 116% 99%
15 1% 117% 100%
Page | 60
LV PLANNING GUIDELINES APPENDIX 2
Commercial
% Load Uptake vs
Yr Estimated Average % Utilisation of Installed
Declared MD with
Growth Rate Transformer Capacity
GCF
1 50% 30%
2 40% 70% 42%
3 29% 90% 54%
4 10% 100% 60%
5 8% 108% 65%
6 8% 116% 70%
7 8% 124% 74%
8 7% 131% 79%
9 7% 138% 83%
10 6% 144% 86%
11 6% 150% 90%
12 5% 155% 93%
13 5% 160% 96%
14 4% 164% 98%
15 3% 167% 100%
Page | 61
LV PLANNING GUIDELINES APPENDIX 3
LANDLORD MSB
Landlord is recommended M1
to install M1 for landlord to
check with individual m m m
tenant bills for any
irregularity m m m
m m m
Supply to Landlord
Tenant Vertical Risers
To tenant units
Figure A3.1: Standard Design for Multi-Tenanted Buildings (< 5 storey) without
Substation
Page | 62
LV PLANNING GUIDELINES APPENDIX 3
M(landlord)
TN B
M1
Landlord is recommended Water pump load
to install M1 for landlord to
Supply to Landlord check with individual m m m Tenant meter at
m m m centralized meter
tenant bills for any
room at ground floor
irregularity m m m
Tenant Vertical Risers
To tenant units
Figure A3.2: Standard Design for Multi-Tenanted Buildings (< 5 storey) with
Substation
Page | 63
LV PLANNING GUIDELINES APPENDIX 3
M(landlord1) M(landlord2)
TNB
M1 m m m
To
M2 m m m
tenant
M3 m m m units
Supply to Landlord
Tenant Landlord is recommended to install M1,
Vertical Riser M2, Mn.. for landlord to check with
individual tenant bills for any irregularity
Figure A3.3: Standard Design for Multi-Tenanted Buildings > 5 storey without
Substation
Page | 64
LV PLANNING GUIDELINES APPENDIX 3
M(landlord)
TNB
M m m m
Tenant Vertical Riser
1
M m m m To tenant
Supply to Landlord units
2
M m m m
3
Landlord is recommended to install M1,
Tenant meter at
M2, Mn.. for landlord to check with
centralized meter
individual tenant bills for any irregularity
room at each level
Page | 65
LV PLANNING GUIDELINES APPENDIX 3
VCB (B2)
With slot for M(Tenant)
M(Landlord) metering CT
TNB
LANDLORD MV PANEL
TENANT MV PANEL
TO
LANDLORD TO TENANT
Figure A3.5: Standard Design for Multi-Tenanted Buildings > 5 storey with
Substation (Landlord & Tenant takes MV supply)
Page | 66
LV PLANNING GUIDELINES APPENDIX 3
Figure A3.6: Standard Design for Multi-tenanted Buildings > 5 storey with
Substation (Development takes MV supply with Landlord load >1600A)
Page | 67
LV PLANNING GUIDELINES APPENDIX 3
Figure A3.7: Standard Design for Multi-tenanted Buildings > 5 storey with
Substation (Development takes MV supply with Landlord load <1600A)
Page | 68
LV PLANNING GUIDELINES APPENDIX 4
Page | 69
LV PLANNING GUIDELINES APPENDIX 4
Page | 70
LV PLANNING GUIDELINES APPENDIX 5
T N B F E E D E R P IL L A R
O U T D O O R M E T E R IN G /
OWN ER : T NB
S U IS B O A R D
M A IN T A I N : T N B
O W N E R : P B T , J K R , ...E T C
M A IN T A I N : P B T , J K R ,
.. . E T C
M A IN R O A D M A IN R O A D
U N D E R G R O U N D S T R E E T L I G H T IN G
C A B L E L AID U N D E RGRO U N D
A N D M A IN T A I N B Y C O N S U M E R S E R V IC E C A B L E L A ID
A N D M A IN T A I N B Y
( P B T , J K R ,. . . E T C )
T NB
D E C O R A T IV E , S IN G L E / D O U B L E A R M
S T R E E T L IG H T
C U S T O M E R : P B T , J K R , . .. E T C
O W N E R : P B T , J K R , . .. E T C
M A IN T A IN : P B T , J K R , .. . E T C
Page | 71
LV PLANNING GUIDELINES APPENDIX 5
MAIN ROAD
Page | 72
LV PLANNING GUIDELINES APPENDIX 5
S T R E E T L IG H T A T T A C H T O T N B P O L E
W IT H O U T M E T E R P A N E L
C U S T O M E R : IN D IV ID U A L ( D O S M E S T IC )
OWNER : T NB
M A I N T A IN : T N B
Page | 73
LV PLANNING GUIDELINES APPENDIX 6
PE D EPO H P E K L IA
E R L (4700m ) N O .2
F /P 1 60 0 A
1 3 5 kW
UN TUK
PE M BAN GUNA N
SE K ITA R A K A N
D ATAN G
4 6 U N I T R T 2 T G K T 1 35 k W
100m
CDGN.
BAN 18 15
Figure A6.1: SAVR with Five Foot Mains for O/H Dom A
Page | 74
LV PLANNING GUIDELINES APPENDIX 7
Figure A7.1: Single Phase Pole Meter Panel for Overhead Dom B
Page | 75
LV PLANNING GUIDELINES APPENDIX 7
ROAD 2B
ROA D 1
ROAD 5
ROAD 6
6
L
AL R OAD 6
W
E
R
Figure A7.2: Site Plan of Single Phase Pole Meter Panel for Overhead Dom B
Page | 76
LV PLANNING GUIDELINES APPENDIX 7
Figure A7.3: Schematic Diagram of Single Phase Pole Meter Panel for Overhead Dom B
Page | 77
LV PLANNING GUIDELINES APPENDIX 8
Figure A8.1: Three Phase Gated Meter Panel for Overhead Dom C
Page | 78
LV PLANNING GUIDELINES APPENDIX 8
Figure A8.2: Site Plan of Three Phase Gated Meter Panel for Overhead Dom C
Page | 79
LV PLANNING GUIDELINES APPENDIX 8
Figure A8.3: Schematic Diagram of Three Phase Gated Meter Panel for Overhead Dom C
Page | 80
LV PLANNING GUIDELINES APPENDIX 9
Page | 81
LV PLANNING GUIDELINES APPENDIX 9
Page | 82
LV PLANNING GUIDELINES APPENDIX 9
Page | 83
LV PLANNING GUIDELINES APPENDIX 10
Page | 84
LV PLANNING GUIDELINES APPENDIX 11
PROPOSED
PEDESTRIAN
BRIDGE
57.80 58.10
57.90 58.00
58.25 58.40 58.55
Page | 85
LV PLANNING GUIDELINES APPENDIX 11
Page | 86
LV PLANNING GUIDELINES APPENDIX 12
Page | 87
LV PLANNING GUIDELINES APPENDIX 12
Page | 88
LV PLANNING GUIDELINES APPENDIX 14
Page | 89
LV PLANNING GUIDELINES APPENDIX 13
Page | 90
LV PLANNING GUIDELINES APPENDIX 14
Page | 91