Вы находитесь на странице: 1из 244

SUMMARY

CONTRACTOR PAYMENT CERTIFICATION


CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: Refer to the individual projects Project No.: Refer to the individual projects

PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: SUMMARY DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00

Deductive $0.00 $0.00 $0.00


3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: 0.00% $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00

(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!
SUMMARY FOR ALL PROJECTS To
Contractor's Name Invoice Date

0 1-Jan-04

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION

CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

REFER TO EACH INDIVIDUAL PROJECT FOR AUTHORIZATION SIGNATURE


Design Consultant's Signature Please print Design Consultant's Name & Company Date

REFER TO EACH INDIVIDUAL PROJECT FOR AUTHORIZATION SIGNATURE


Inspector of Record's Signature Please print Inspector of Record's Name Date

REFER TO EACH INDIVIDUAL PROJECT FOR AUTHORIZATION SIGNATURE


College Project Director's (CPD) Signature Please print CPD's Name Date

REFER TO EACH INDIVIDUAL PROJECT FOR AUTHORIZATION SIGNATURE


PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
SUMMARY
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04
Project Name: SUMMARY FOR ALL PROJECTS Contract No.: 0
Project No.: SUMMARY FOR ALL PROJECTS Payment Req. No.: SUMMARY
Contractor: 0 City
Address: 0 0
Work Completed
Total Value of From Previous Earned This Period Earned To Date
Division Detailed Item of Work
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: SUMMARY FOR ALL PROJECTS Contract No.: 0
Project No.: SUMMARY FOR ALL PROJECTS Payment Req. No.: SUMMARY
Contractor: 0 City
Address: 0 0
Work Completed
Total Value of From Previous Earned This Period Earned To Date
Division Detailed Item of Work
Division % Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment
Process Gas and Liquid Handling, 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Insurance 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
SUMMARY
ED FOR ALL METHODS OF EXECUTION
To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION


College: 0 Performance Dates:
Project Name: SUMMARY FOR ALL PROJECTS Contract No.:
Project No.: SUMMARY FOR ALL PROJECTS Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: SUMMARY FOR ALL PROJECTS Performance Dates:


Project Name: SUMMARY FOR ALL PROJECTS Contract No.:
Project No.: SUMMARY FOR ALL PROJECTS Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: SUMMARY FOR ALL PROJECTS Contract No.:
Project No.: SUMMARY FOR ALL PROJECTS Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

BE USED FOR ALL METHODS OF EXECUTION


1-Jan-04 To 1-Jan-04
0 Invoice Date
SUMMARY 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
SUMMARY 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
SUMMARY 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: 0.00% $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount %
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
01 General Requirements 0.00 0.00% 0.00 0.00% 0.00 0.00%
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00%
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00%
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00%
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00%
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00%
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00%
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00%
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00%
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00%
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00%
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00%
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00%
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00%
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00%
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00%
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00%
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00%
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00%
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00%
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00%
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00%
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00%
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00%

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount %
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00%
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00%
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00%
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00%
41 Material Processing & Handling Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
42 Process Heating, Cooling & Drying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
Process Gas and Liquid Handling, Purification and
43 Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00%

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%


N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%


N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33%
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28%
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00
Pre-Const. / Design Division Total: 0.00 0.00 0.00
Construction Division Subtotal: 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


ACTOR PAYMENT CERTIFICATION
TRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
LED ITEMS OF WORK Sht. 1 of 2
E USED FOR ALL METHODS OF EXECUTION
To
Invoice Date

City State Zip Code

Work Completed Balance of Work to


Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00

Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
TRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
LED ITEMS OF WORK Sht. 2 of 2

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0

Work Completed Balance of Work to


Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00

0.00 100.00% 0.00


0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00

0.00 100.00% 0.00


0.00 100.00% 0.00

0.00 100.00% 0.00


0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 6.67% 0.00
0.00 69.72% 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work ha
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amoun
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been rec

Project Name: 0 Project No.:


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN

1. Original Contract Value $0.00


2. Executed Change Order Value Additive $0.00
Deductive $0.00
3. Current Contract Value $0.00
(a) Total Earned to date (from Original Contract value) $0.00
(b) Total Earned to date on Executed Change Orders $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00
(d) Total Earned This Period $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00
(g) Total Amount Retained or Amount Approved by District $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00
6. Percentage Complete #DIV/0!

0
Contractor's Name

Design Build Contractor's Signature Please print name and title


CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT
To the best of my knowledge and belief, I certify that this progress payment does not exceed the value (less % retained from 'e') of the work completed since th
value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify tha
work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (le

Design Consultant's Signature Please print Design Consultant's Name & Company

Inspector of Record's Signature Please print Inspector of Record's Name

College Project Director's (CPD) Signature Please print CPD's Name

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name

Form CP-0191 Page 1 of 1


N
ED REPRESENTATIVE
EXECUTION

st are correct; that all work has been performed and materials supplied in full
tement of the contract amount up to and including the last day of the period
yment Request" has been received:

CONSTRUCTION TOTAL

$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00

$0.00 $0.00

$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
#DIV/0! #DIV/0!

1-Jan-04
Invoice Date

`
name and title Date
N
ONTRACT
of the work completed since the previous progress payment, if any, plus the
alled, if any. I further certify that this progress payment covers full payment for
does not exceed the value (less % retained from 'e') of the materials.

Date

Date

Date

Date

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount %
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
01 General Requirements 0.00 0.00 0.00% 0.00 0.00%
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00%
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00%
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00%
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00%
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00%
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00%
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00%
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00%
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00%
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00%
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00%
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00%
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00%
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00%
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00%
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00%
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00%
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00%
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00%
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00%
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00%
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00%
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00%

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount %
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00%
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00%
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00%
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00%
41 Material Processing & Handling Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
42 Process Heating, Cooling & Drying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
Process Gas and Liquid Handling, Purification
43 and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00%
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00%

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%


N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%


N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00%
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33%
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28%
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00
Pre-Const. / Design Division Total: 0.00 0.00 0.00
Construction Division Subtotal: 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


ACTOR PAYMENT CERTIFICATION
TRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
LED ITEMS OF WORK Sht. 1 of 2
E USED FOR ALL METHODS OF EXECUTION
To
Invoice Date

City State Zip Code

Work Completed Balance of Work to


Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00

Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
TRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
LED ITEMS OF WORK Sht. 2 of 2

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0

Work Completed Balance of Work to


Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00

0.00 100.00% 0.00


0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00

0.00 100.00% 0.00


0.00 100.00% 0.00

0.00 100.00% 0.00


0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 6.67% 0.00
0.00 69.72% 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04
Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount % Amount
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount % Amount
0 Demolition of Netting Poles 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount % Amount
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Construction Additive CO Totals: 0.00 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
AYMENT CERTIFICATION
OR HIS DULY AUTHORIZED REPRESENTATIVE
ORTING CONTRACT PAYMENT REQUEST
FOR ALL METHODS OF EXECUTION
To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0
ers Approved by Board of Trustees
ESIGN PHASE CHANGE ORDERS
Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
0.00
0.00
0.00
Rev. 02.06.15
AYMENT CERTIFICATION
OR HIS DULY AUTHORIZED REPRESENTATIVE
ORTING CONTRACT PAYMENT REQUEST

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0
ers Approved by Board of Trustees
PHASE CHANGE ORDERS
Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
Rev. 02.06.15
AYMENT CERTIFICATION
OR HIS DULY AUTHORIZED REPRESENTATIVE
ORTING CONTRACT PAYMENT REQUEST

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0
ers Approved by Board of Trustees
PHASE CHANGE ORDERS
Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
0.00
0.00
0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Dat
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Dat
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Dat
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
TOR PAYMENT CERTIFICATION
ACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
SUPPORTING CONTRACT PAYMENT REQUEST
USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
ge Orders Approved by Board of Trustees
ON / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
TOR PAYMENT CERTIFICATION
ACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
ge Orders Approved by Board of Trustees
TION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
TOR PAYMENT CERTIFICATION
ACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
ge Orders Approved by Board of Trustees
TION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in full
accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the period
covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress payment
covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from 'e') of the
materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION

To the best of my knowledge and belief, I certify that all items, units, quantities, and prices of work shown on this Payment Request are correct; that all work has been performed and materials supplied in
full accordance with the terms and conditions of the construction contract on this project; that the following is a true and correct statement of the contract amount up to and including the last day of the
period covered by this estimate and that no part of the "Total Amount Payable This Contract Payment Request" has been received:

Project Name: 0 Project No.: 0


PRE-CONSTRUCTION /
Contract No.: 0 Invoice No.: 0 DESIGN CONSTRUCTION TOTAL

1. Original Contract Value $0.00 $0.00 $0.00


2. Executed Change Order Value Additive $0.00 $0.00 $0.00
Deductive $0.00 $0.00 $0.00
3. Current Contract Value $0.00 $0.00 $0.00
(a) Total Earned to date (from Original Contract value) $0.00 $0.00 $0.00
(b) Total Earned to date on Executed Change Orders $0.00 $0.00 $0.00
(c) Total Earned (sum of 'a' and 'b') $0.00 $0.00 $0.00
(d) Total Earned This Period $0.00 $0.00 $0.00
(e) Amount to be Retained or Amount Approved by District
Enter Percentage (%) to be Retained: $0.00 $0.00 $0.00
(f) Amount Previously Retained ('g' from previous invoice)
If Final Issuance of Retention enter zero $0.00 $0.00 $0.00
(g) Total Amount Retained or Amount Approved by District $0.00 $0.00 $0.00
(h) Total Payment Allowed to Date ('c' minus 'g') $0.00 $0.00 $0.00
(i) Less Previous Payment (item 'h' from prior claim) $0.00 $0.00 $0.00
(j) Total Amount Payable This Contract Payment Request ('h' minus 'i') $0.00 $0.00 $0.00
4. Amount remaining in Contract / Retention / Escrow ('3' minus 'h') $0.00 $0.00 $0.00
5. Contract Value Remaining to be Invoiced ('3' minus 'c') $0.00 $0.00 $0.00
6. Percentage Complete #DIV/0! #DIV/0! #DIV/0!

0 1-Jan-04
Contractor's Name Invoice Date

Design Build Contractor's Signature Please print name and title Date
CONTRACTOR PAYMENT CERTIFICATION
CERTIFIED AND APPROVED AS PER TERMS OF CONTRACT

To the best of my knowledge and belief, I certify under penalty of perjury that this progress payment does not exceed the value (less % retained from 'e') of the work completed since the previous progress
payment, if any, plus the value (less % retained from 'e') of acceptable, prefabricated materials delivered to the job for incorporation into work, but not installed, if any. I further certify that this progress
payment covers full payment for work completed since the previous progress payment, and that any payment for prefabricated materials stored on the site does not exceed the value (less % retained from
'e') of the materials.

Design Consultant's Signature Please print Design Consultant's Name & Company Date

Inspector of Record's Signature Please print Inspector of Record's Name Date

College Project Director's (CPD) Signature Please print CPD's Name Date

PMO Regional Program Liason's (RPL) Signature Please print RPL's Name Date

Form CP-0191 Page 1 of 1 Rev. 02.06.15


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 1 of 2
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: Performance Dates:
Project Name: Contract No.:
Project No.: Payment Req. No.:
Contractor: City
Address:

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
N/A Pre-Construction / Design 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01 General Requirements 0.00 0.00 0.00% 0.00 0.00% 0.00
02 Site Construction / Existing Conditions 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02A Asbestos Abatement 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
03 Concrete 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04 Masonry 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05 Metals 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
06 Wood, Plastic and Composites 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
07 Thermal and Moisture Protection 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
08 Doors & Windows / Openings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
09 Finishes 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
10 Specialties 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
11 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
12 Furnishings 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
13 Special Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
14 Conveying Systems / Conveying Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
15 (Refer to Division 23) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
16 (Refer to Division 26) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
21 Fire Suppression 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
22 Plumbing 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
23 Heating, Ventilating & A/C (HVAC) 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
25 Integrated Automation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
26 Electrical 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
27 Communication 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
28 Electronic Safety & Security 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
31 Earthwork 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
32 Exterior Improvements 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

Form CP-0191 Page 1 of 2


CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
DETAILED ITEMS OF WORK Sht. 2 of 2

College: 0 Performance Dates: 1-Jan-04


Project Name: 0 Contract No.: 0
Project No.: 0 Payment Req. No.: 0
Contractor: 0 City
Address: 0 0

Work Completed
Total Value of
Division Detailed Item of Work From Previous Earned This Period Earned To Date
Division
% Amount % Amount % Amount
33 Utilities 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
34 Transportation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
35 Waterway and Marine Construction 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
40 Process Integration 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
41 Material Processing
Process & Handling
Heating, Cooling Equipment
& Drying 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
42 Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
Process Gas and Liquid Handling,
43 Purification and Storage Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
44 Pollution and Waste Control Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
45 Industry-Specific Manufacturing Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
46 Water and Wastewater Equipment 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
48 Electrical Power Generation 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00

N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
N/A Not Used 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
00610 Payment & Performance Bond 0.00 93.33% 0.00 0.00% 0.00 93.33% 0.00
00610 Insurance 0.00 30.28% 0.00 0.00% 0.00 30.28% 0.00
Pre-Const. / Design Division
Subtotal: 0.00 0.00 0.00 0.00
Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Pre-Const. / Design Division
Total: 0.00 0.00 0.00 0.00

Construction Division Subtotal: 0.00 0.00 0.00 0.00


Overhead & Profit @ 0.00% 0.00 0.00 0.00 0.00
Construction Division Total: 0.00 0.00 0.00 0.00

Form CP-0191 Page 2 of 2


R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 1 of 2
ED FOR ALL METHODS OF EXECUTION
To
Invoice Date

State Zip Code

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

Rev. 02.06.15
R PAYMENT CERTIFICATION
TOR OR HIS DULY AUTHORIZED REPRESENTATIVE
TEMS OF WORK Sht. 2 of 2

To 1-Jan-04
Invoice Date
1-Jan-04
State Zip Code
0 0

Balance of Work to
Complete
% Amount
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00

100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
100.00% 0.00
6.67% 0.00
69.72% 0.00

0.00
0.00

0.00

0.00
0.00
0.00

Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates:
Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
PRE-CONSTRUCTION / DESIGN PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Pre-Const. / Design Additive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design Deductive CO Totals: 0.00 0.00 0.00
Pre-Const. / Design CO Subtotals: 0.00 0.00 0.00
0.00 0.00 0.00
Form CP-0191 Page 1 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Form CP-0191 Page 2 of 3
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST

College: 0 Performance Dates:


Project Name: 0 Contract No.:
Project No.: 0 Payment Req. No.:
Contractor: 0 City
Address: 0 0
List only those Change Orders Approved by Board of Trustees
CONSTRUCTION PHASE CHANGE ORDERS
Work Completed
Change Order
Description Total Value From Previous Earned This Period Earned To Date
No.
% Amount % Amount %
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
0.00 0.00% 0.00 0.00% 0.00 0.00%
Construction Additive CO Totals: 0.00 0.00 0.00
Construction Deductive CO Totals: 0.00 0.00 0.00
Construction CO Subtotals: 0.00 0.00 0.00
Contract Change Order Total: 0.00
Form CP-0191 Page 3 of 3
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST
BE USED FOR ALL METHODS OF EXECUTION
1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
CTION / DESIGN PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
Rev. 02.06.15
ACTOR PAYMENT CERTIFICATION
NTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
ATA SUPPORTING CONTRACT PAYMENT REQUEST

1-Jan-04 To 1-Jan-04
0 Invoice Date
0 1-Jan-04
City State Zip Code
0 0 0
hange Orders Approved by Board of Trustees
UCTION PHASE CHANGE ORDERS
Work Completed Balance of Work to
Earned To Date Complete
Amount % Amount
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 100.00% 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Rev. 02.06.15
CONTRACTOR PAYMENT CERTIFICATION
CERTIFICATION OF THE CONTRACTOR OR HIS DULY AUTHORIZED REPRESENTATIVE
CHANGE ORDER (CO) DATA SUPPORTING CONTRACT PAYMENT REQUEST
THIS FORM IS TO BE USED FOR ALL METHODS OF EXECUTION
College: 0 Performance Dates: 1-Jan-04 To To
Project Name: 0 Contract No.: 0 Invoice Date
Project No.: 0 Payment Req. No.: 0 1-Jan-04
Contractor: 0 City State Zip Code
Address: 0 0 0 0
PRE_CONSTRUCTION & DESIGN PHASE

Amount Due
Total Work Work
Contractual This Period Balance To Retention To
No. Fee - Phase SOV's % Complete Completed & Completed Completed This
% Allocation (Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 Execution of Contract 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 Schematic Design Phase and Validation Phase 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 50% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 100% Design Development Phase 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 50% Construction Document Phase 20% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 100% Construction Document Phase 5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 DSA Approval (Stamp Out) of final Construction Docs 10% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 Construct. Administration 15% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 DSA Certification Completed & Submitted to DSA 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 DSA Final Certification Received 2.5% $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL BASIC DESIGN (Contractual) $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Amount Due
Total Work Work
This Period Balance To Retention To
No. Change Orders SOV's % Complete Completed & Completed Completed This
(Less 0% Finish Date
Stored To Date Previous Period Period
Retention)
1 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
2 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
3 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
4 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
5 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
6 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
7 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
8 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
9 $ - #DIV/0! $ - $ - $ - $ - $ - $ -
10 $ - #DIV/0! $ - $ - $ - $ - $ - $ -

SUBTOTAL DESIGN CHANGE ORDERS $ - #DIV/0! $ - $ - $ - $ - $ - $ -

PRE-CONSTRUCTION / DESIGN PHASE TOTAL $ - #DIV/0! $ - $ - $ - $ - $ - $ -

Form CP-0191 Page 1 of 1 Rev. 02.20.15

Вам также может понравиться