Вы находитесь на странице: 1из 10

Barbara Jeroncic

Improved Utilization of Self-Inspection


Programs within the GMP Environment–A
Quality Risk Management Approach
Barbara Jeroncic

Self-inspection is a well-established and vital part of Irish Medicines Board (IMB) published in the Journal
the pharmaceutical quality system. The development of GXP Compliance (3) identifies some of the issues
of the International Conference on Harmonisation with current self-inspection programs of pharma-
(ICH) Q9 and Q10 guidance documents have intro- ceutical manufacturing companies. A major issue
duced an opportunity to improve the design of the discussed was that significant and critical deficien-
self-inspection program by application of the qual- cies observed during regulatory inspections were
ity risk management (QRM) principles and concepts. not identified and corrected by the companies them-
Self-inspection can be designed as a QRM tool used selves via their own self-inspection programs. This
to assess the management of current and potential could be due to the fact that for many companies
risks to quality and to drive forward continual improve- self-inspection comprises little more than a review of
ment. The application of QRM also allows more effi- compliance with current standard operating proce-
cient inspection workload and resource management dures (SOPs). Furthermore, its low priority is coupled
focusing on those areas within the quality system that with insufficient resources and lack of commitment
present higher risk to quality. This article provides from senior management. The interview (3) identifies
examples of how QRM could be introduced to main the opportunities for self-inspection to be designed
activities within the self-inspection program. The as a formal quality risk management tool capable of
article also explores the application of QRM in the identifying and managing risks and driving forward
area of self-inspection by pharmaceutical companies tangible and realistic continual improvement. Self-
based in Ireland. inspection programs designed in this way can help to
demonstrate the effectiveness of the quality system,
INTRODUCTION and thus can play an important role in the achieve-
Self-inspection is a well-established part of the phar- ment of the reduced regulatory oversight in the in-
maceutical quality system. Companies have tradi- spection area (3).
tionally been using it as a method for monitoring the This article introduces an innovative self-inspec-
implementation and compliance with good manu- tion program design, as a part of quality risk man-
facturing practice (GMP) principles, as well as for in- agement, aimed at risk identification and manage-
troducing appropriate corrective measures. This role ment as tools for continual improvement. As a part
of self-inspection is promoted by the current GMP of the design process, a survey of pharmaceutical
legislation and guidance (1). Development of the In- manufacturing companies in Ireland was conducted;
ternational Conference on Harmonisation’s (ICH) the findings are reported in this paper. The survey
Q10 guide has expanded the role of self-inspection to goal was to explore the practical application of qual-
that of an important performance indicator used for ity risk management to self-inspection programs and
monitoring the effectiveness of processes and activi- the pharmaceutical industry interest in seeking re-
ties within the pharmaceutical quality system. ICH duced level of direct regulatory oversight in the area
Q10 promotes the use of self-inspection results as of regulatory inspections.
an important input for periodic management review
performed to manage, evaluate, and continually im- REALIGNING SELF-INSPECTION AS A QUALITY RISK
prove the quality system’s performance (1, 2). MANAGEMENT TOOL
An interview with a senior GMP inspector at the Many parts of the European GMP guide (1) are cur-

22  Special Edition: A Roadmap to GMP Compliance Part 2


Barbara Jeroncic

rently undergoing revision to incorporate the prin- that can provide the regulators with greater assur-
ciples and concepts of the quality risk management, ance of a company’s ability to deal with potential
such as chapters one, three, and five. There is a simi- risks and can beneficially affect the extent and level
lar opportunity with respect to chapter nine (“Self- of direct regulatory oversight.
inspection”). ICH Q9 is already taking initiative in its
drive to define the frequency and scope of inspections ISO 31000 standard entitled “Risk Management–
by taking into account various risk indicators. ICH Q9 Principles and Guidelines” provides even further de-
also provides guidelines for the application of quality tail of benefits of the application of effective quality
risk management to regulatory inspections aimed to risk management (5), as follows:
assist with: resource allocation including inspection • Increasing the likelihood of achieving quality
planning, frequency, and intensity; evaluation of qual- objectives
ity defect significance, recalls, and inspection find- • Encouraging proactive management
ings; assessment of the scope and type of post-inspec- • Awareness of the need to identify and treat risks
tion follow-up; and identification of risks that should throughout the organization
be communicated between inspectors and assessors to • Improving the identification of opportunities and
facilitate better understanding of risk control (4). threats
ICH Q9 states, “quality risk management is a sys- • Improving compliance with legal and regulatory
tematic process comprising of assessment, control, requirements and international norms
communication, and review of risks impacting the • Improving governance
drug (medicinal) product quality across the product • Improving stakeholders confidence and trust
lifecycle.” Organizations manage risk through identi- • Establishing a reliable basis for decision making
fication, analysis, and evaluation of the most suitable and planning
risk mitigation strategy. This process further encom- • Improving controls
passes risk monitoring and review aided by commu- • Effectively allocating and use of resources
nication and consultation with stakeholders in order • Improving operational effectiveness
to ensure that no further risk control/treatment is re- and efficiency
quired (4, 5). • Improving loss prevention and
There is a potential to apply a quality risk manage- incident management
ment approach to the area of self-inspection that can • Minimizing losses.
be integrated into the organization’s quality risk man-
agement framework. The purpose is two-fold as fol- Elements Of Quality Risk Management
lows: The following are elements of quality risk management.
• To design self-inspection as a quality risk manag- Risk assessment. Risk assessment is the process of
ment tool that can provide the objective evidence to risk identification, analysis, and evaluation (4, 5). Its
the management about whether or not the current application within the self-inspection program can be
and potential risks to quality are effectively man- tailored to the risk assessment output purpose, the de-
aged to acceptable levels. Management then can sired level of detail, and the available information. For
judge the effectiveness of processes and functions example, the estimate of risk associated with an area
within the quality system within the quality system, for the purpose of defin-
• Efficient inspection workload and resource man- ing a scope and frequency of self-inspections, can be
agement focusing on those areas within the quality based on the general evaluation of risk factors, without
system that present higher risk to the quality of a detailed risk assessment, as this will be performed
medicinal product, with aim of meeting the qual- during self inspections. ISO 31010 standard describes
ity objectives. different methods and tools that could be used when
performing risk assessment. Examples of the methods
Benefits Of The Application Of Quality Risk and tools are provided in the following sections.
Management To Self-Inspection Programs Risk identification. The purpose of the risk identi-
ICH Q9 lists the following main benefits of the ap- fication process is to identify the causes and sources of
plication of an effective quality risk management ap- hazards, events, situations or circumstances that could
proach to various processes and activities within the have an impact upon the quality of the medicinal prod-
quality system, including self-inspection (4): uct, the quality objectives, and the nature of that impact
• Ensuring high quality of the medicinal product by (4, 5, 6). There is a variety of tools and techniques that
proactively identifying and controlling potential could be chosen for risk identification, such as: reviews
quality issues of historical data, checklists, theoretical analysis, system-
• Improving decision making if a quality issue arises atic team approaches (e.g., structured “what-if” technique
• Facilitation of better and more informed decisions [SWIFT]), primary hazard analysis, hazard operability

Special Edition: A Roadmap to GMP Compliance Part 2 23


Barbara Jeroncic

analysis (HAZOP), fault tree analysis (FTA), cause and ef- and techniques are: consequence-probability matrix,
fect analysis, and supporting techniques (e.g., brainstorm- SWIFT, FMEA/FMECA, etc. (6).
ing, Delphi method) (4, 6). Risk evaluation. Risk evaluation involves compar-
Risk analysis. Risk analysis is an estimate of the ing the identified and analyzed risks against estab-
risk associated with an identified hazard. It consists lished risk criteria in order to determine their signifi-
of linking the consequences and their likelihoods for cance. The purpose of risk evaluation is to assist in
the identified hazard (can also link detectability of the making decisions, based on the outcomes of risk anal-
hazard) to determine the level of risk. The purpose ysis, on the requirements and priorities of treatment
of the risk analysis is to develop risk understanding implementation (4, 5, 6). Risk criteria should reflect
(4, 6). the organization’s values and objectives, legal, regula-
The analysis of consequences determines the nature tory, and other requirements (5). ISO 31000 standard
and type of impact that could occur (6). suggests consideration of the following factors when
It can involve the following (6): defining risk criteria:
• Relating the consequence to the achievement of • The nature and types of causes and consequences
the quality objectives of risks that can occur and their measurement
• Taking into consideration existing controls to • Definition of likelihood
mitigate the consequence, together with all rel- • The timeframe(s) of the likelihood and/or
evant contributory factors consequence(s)
• Considering both immediate consequences and • How the level of risk is to be determined
those that may arise after a certain time has • The views of stakeholders
elapsed, if this is consistent with the scope of • The level at which risk becomes acceptable
assessment or tolerable
• Considering secondary consequences (i.e., those • Whether combinations of multiple risks should
impacting on associated processes, activities, be taken into account, and how and which com-
equipment, etc.). binations should be considered.

The examples of methods and tools that are suitable Risk control/treatment. Risk control/treatment is
for consequence analysis are: HAZOP, hazard analysis the process of decision making in order to reduce and/
and critical control points (HACCP), failure mode ef- or accept risks, identify risk control/treatment solu-
fects analysis (FMEA), cause and consequence analy- tions and implement these solutions aiming to reduce
sis, cause and effect analysis, etc. (6). the risk to an acceptable level. Decisions can take into
The probability analysis estimates the likelihood account a wider context of the risk and include con-
of a particular hazard, using one of the following ap- sideration of the risk tolerance borne by stakeholders,
proaches (6): cost-benefit analysis and the legal, regulatory, and other
• Use of relevant historical data to extrapolate or requirements (4, 5, 6).
predict the probability of occurrence of similar Risk communication. Risk communication refers to
events or situations in the future. It should be information sharing regarding risks and risk manage-
noted that if historically there is a very low fre- ment between stakeholders. It is important that this
quency of occurrence, the estimate of probability information is accurately and regularly communicated
will be very unreliable through reporting channels established by the organi-
• Probability forecasts using predictive techniques zation in order to ensure the success and effectiveness
such as fault tree analysis and event tree analysis. of the quality risk management process. This can take
When historical data are unavailable or inade- place at any stage of the quality risk management pro-
quate, the probability can be estimated by analy- cess (4, 5, 6). The communication and reporting mecha-
sis of a relevant process, activity, equipment, etc. nisms should ensure that key components of the quality
and its associated failure or success states risk management approach to self-inspections, and any
• Expert judgements that can be facilitated by subsequent modifications, are appropriately and timely
formal methods (i.e., Delphi approach, category communicated to all interested parties; that there is ad-
ranking, paired comparison, etc.). equate reporting of the risk assessment outcomes; that
relevant information on the application of quality risk
The consequence and likelihood can be linked by management is available at appropriate levels and times;
using a variety of qualitative, semi-quantitative, or and that there are established processes for consulta-
quantitative methods to determine the level of risk. tion with stakeholders (6). Communication between
The degree of detail depends upon the particular ap- stakeholders can assist the development of appropriate
plication, the availability of reliable data, and the quality risk management approach to self-inspection
decision-making requirements. Examples of methods and integration of self-inspection into the organiza-

24  Special Edition: A Roadmap to GMP Compliance Part 2


Barbara Jeroncic

tion’s quality risk management framework. It can fur- The risk associated with an area can be estimated by
ther ensure that the interests of stakeholders are under- analysis of selected risk factors that indicate or identify
stood and considered when developing self-inspection the risk. ICH Q9 suggests the following various risk
programs; bring together different areas of expertise factors that can be used:
to ensure that the risks are adequately identified and • Complexity of the site, manufacturing process,
analyzed through the use of risk assessment methods and product
and techniques; ensure that different views are appro- • The number and significance of quality defects
priately considered when defining risk criteria and in • Results of previous audits/inspections
evaluating risks; and can help to secure endorsement • The overall compliance status and history of the
and support for a mitigation plan (5, 6). company or facility
Risk review and monitoring. Regular review of the • Robustness of a company’s quality risk manage-
quality risk management ensures that any new knowl- ment activities
edge and experience is taken into account (4, 5, 6). • Major changes of building, equipment, processes,
For example, it ensures verifying that the assumptions and key personnel
about risks remain valid, obtaining further informa- • Experience with product manufacturing process
tion to improve risk assessment, analyzing and learning • Existing legal requirements
from events, including near-misses, changes, trends, • Official laboratory test results.
successes and failures, verifying that risk assessments Some additional factors the companies could con-
are properly applied, verifying that risk treatments are sider might be the following:
effective, detecting changes which could influence risk • Criticality of an area. This factor considers the
criteria and upon which risk treatments need to be re- effect of failure of a particular area and the influ-
vised, identifying emerging risks, etc. (5, 6). ence of potential or identified issues with this
area on areas downstream
Application Of Quality Risk Management To The Activi- • Coupling of an area. Tightly-coupled processes
ties Within The Self-Inspection Program or systems could be those having time dependent
The following sections discuss quality risk manage- processes/activities that cannot wait; those hav-
ment applications to main activities. Examples of ing rigidly ordered processes or activities (i.e.,
quality risk management within the self-inspection sequence A must follow sequence B); those having
program include the following: only one path to a successful outcome; those hav-
• Self-inspection planning—defining the scope ing very little slack in the system, as the system
(inspection units), frequency, and level of self- requires precise quantities or specific resources
inspections, and allocation of the inspectors for successful operation, etc. (3)
• Detailed plan preparation for self-inspections of the • Adequacy of resources associated with an area.
individual inspection units
• Conducting self-inspections The risk associated with an area can be estimated
• Adequate response to self-inspection results—deter- by using different risk ranking methods or tools. For
mining the type of actions for the issues identified example, a simple approach could be assigning a nu-
within self-inspections, determining the timeframe merical descriptive value of 1 (low) to 3 (high) to es-
for the implementation of actions, and assessing the tablished categories for the selected risk factors. An
associated risks. example is provided in Table I.
The estimated values for all risk factors can then be
Planning Of Self-Inspections linked together in an appropriate way to yield a risk
Risk management can be applied to self-inspection level associated with an area (e.g., low, medium, and
planning with the intent to direct the inspection effort high). The estimated values for risk factors could also
to the areas within the quality system that represent be multiplied by significance-weighting factors to give
higher risk to the quality of the medicinal product and a total. This assessment of risk associated with the ar-
the achievement of the quality objectives. The applica- eas within the quality system can be seen as a prelimi-
tion of the quality risk management allows the estima- nary risk screening with the intention to direct the in-
tion of the risk associated with areas within the quality spection effort to those areas that represent higher risk.
system and determining the scope (inspection units), It is important that this evaluation of risk is appro-
frequency and level (time, number of inspectors) of priately communicated to the interested parties (e.g.,
self-inspections, and allocation of inspectors to partic- management, inspectors, etc.). Furthermore, it should
ular self-inspections (considering their experience and be regularly reviewed to take into account any new
skills) based on the estimated levels of risk. This forms information including the results of self-inspections
the basis for a risk-based inspection planning and en- and the risk control/treatment process. Based on this
ables better utilization of available resources. information, the frequency of self-inspections can be

Special Edition: A Roadmap to GMP Compliance Part 2 25


Barbara Jeroncic

Table I: Example of categories for a risk factor and their numeric values.
Risk factor Category (impact X likelihood) Value
(based on data for a given time period)
< 5 minor observations, no major or critical observations 1
Results of previous
< 15 minor observations, no major or critical observations 2
self-inspections
> 15 minor observations or any major or critical observations 3
< 20 minor deviations not affecting the number of released batches 1
per month. No major deviations affecting batch release
> 20 minor deviations not affecting the number of released batches per month 2
Number and significance
< 10 major deviations resulting in delay of batch release 2
of deviations
no major deviations resulting in batch reject or reprocessing
> 10 major deviations resulting in delay of batch release 3
Any major deviations resulting in batch reject or reprocessing

reviewed and adjusted if required. • Are those controls suitable for adequate risk mitiga-
tion, resulting in a tolerable risk levels?
Preparation And Conduct Of Self-Inspections • In practice, are the controls operating in the intend-
Preparation for self-inspections of a particular inspec- ed manner and can they be demonstrated to be
tion unit can include preparing detailed plans for in- effective when required?
dividual self-inspections with the intention to direct
self-inspection activities. These plans could be based For example, during the assessment of the inspec-
on the risk assessment of the inspection unit with the tion unit production process A, it was identified that
purpose to focus on those elements that represent there were several occasions of the delays in the pro-
higher risk to the quality and the achievement of the cess A as the purified water was not available due to
quality objectives and can, therefore, have a higher out-of-specification test results. Table II provides an
impact on the effectiveness of the activity, process, or example of how risk associated with this hazard could
function of that unit. The elements with higher asso- be assessed.
ciated risk can be inspected more thoroughly during The assessed risk increased from Category 3 to Cat-
self-inspections and can be included into future as- egory 4 in a given time period, thus it was decided that
sessments more frequently. purified water system would be inspected more fre-
Risk assessment performed at this stage can be seen quently and new potential controls would be assessed.
as the initiation of assessment of risks associated with The output of the risk assessment performed during
elements of the inspection unit based on the available the preparation of detailed plans for self-inspections of the
information. Risk assessment can then be completed inspection unit could include the following elements to
during conduct of self-inspections based on the ad- help ensure the effectiveness of self-inspections:
ditional information gathered during self-inspections. • A process map of the inspection unit providing vis-
Risk assessment of the inspection unit can be continu- ibility of the inspection unit elements and their interac-
ously updated during subsequent inspections of the tion, and the interaction with other areas of the quality
inspection unit based on new knowledge and experi- system
ence. The purpose of the risk assessment is to provide • A list of identified hazards coupled with description of
an understanding of risks, including their causes, con- methods and type of data used for hazard identification
sequences, and probabilities, and the understanding of • An analysis of consequences of those hazards and their
the adequacy and effectiveness of existing controls to likelihood, including a description of methods and
mitigate these risks (6). After the conduct of each self- type of data used for this analysis
inspection, an objective report can be presented to the • Estimated levels of risk associated with the inspection
management regarding the adequacy and effectiveness unit elements
of risk management of the inspection unit. • Criteria for risk evaluation based on the management
The level of risk depends on the adequacy and effec- tolerance of risk
tiveness of existing controls, which can be addressed • Objectives for self-inspections of the inspection unit
using following criteria (6): (or their recommendation) to direct inspection effort
• What are the existing controls for a particular risk? to those elements that represent higher risk for the

26  Special Edition: A Roadmap to GMP Compliance Part 2


Barbara Jeroncic

Table II: Example of the initial risk analysis of one of the identified hazards associated with an inspection unit.
Identified hazard: Purified water (PW) not available due to out-of-specification
results of conductivity, TOC, microbial content or endotoxin
Impact factors:
• Number of days PW was out of use in a given time period
• Impact on batch release—delay, reject, or reprocessing
Impact categories:
1 PW out of use < 2-day intervals—interruptions and delay in process A
No impact on the number of batches released per month
2 PW out of use >2-day intervals
Reduced number of batches released per month for < 2%
3 Reduced number of batches released per month for > 2%
Any batch rejects or reprocessing
Likelihood factors:
• Number of out-of-specification results in a given time period–conductivity, TOC, microbial content, endotoxin
Existing controls: UV disinfection system, series of water filters (purified water system map)
Risk analysis:
Risk category Impact X Likelihood
1 < 15 out of specifications resulting in interruptions and delay in process A
but not impacting the number of batches released per month
2 > 15 out of specifications resulting in interruptions and delay in process A
but not impacting the number of batches released per month
3 Reduced number of batches released per month for < 2%
4 Reduced number of batches released per month for > 2%
< 2 batch rejects or reprocessing
5 > 2 batch rejects or reprocessing

achievement of the quality objectives associated with lar area, function, or department. It examines all
the unit. inputs and activities required to produce an output.
Selection of this approach is useful when performing
Detailed plans can be prepared just before the indi- departmental or functional self-inspections.
vidual self-inspections, or can be prepared periodical- • Horizontal approach to self-inspection involves
ly, in which case the risk assessment should be revisited examination of an aspect of the quality system that
just before individual self-inspections to include any is applied to, or involving, different functions, areas,
relevant new information. It is very important that the or departments. This type of approach is useful when
relevant information is appropriately communicated to performing self-inspections of systems implemented
inspectors who are conducting self-inspections (if not across various areas or processes, involving different
the same person) to ensure the effectiveness of the risk areas or functions (e.g., change management sys-
assessment. tem, deviation investigation, training of personnel,
Based on the outputs of the initial assessment, the and calibration of equipment). It is also useful for
inspectors can identify additional information required self-inspection of projects and products. Horizontal
for efficient completion of risk assessment of the in- approach can be a powerful tool to test the interfaces
spection unit, and identify methods for obtaining this between different parts of an organization involved
information including various inspection techniques in the system, process, project, etc.
(e.g., interviews, observation, review of documenta-
tion, etc.) and approaches. For example, the inspectors The inspection unit risk assessment outputs after the
could decide to use vertical or horizontal approach to conduct of self-inspections could include the following:
self-inspection, as follows (7) (see Figure 1): • The updated list of hazards
• Vertical approach to self-inspection involves an • The updated analysis of risk, based on the informa-
examination of all aspects of the quality system that tion obtained during the self-inspections, including
contribute to the output (result) within a particu- analysis of risk associated with any identified issues

Special Edition: A Roadmap to GMP Compliance Part 2 27


Barbara Jeroncic

Figure 1. assessment of the inspection unit can be revisited,


Example of vertical and horizontal self-inspection.
reviewed, and updated before and during each sub-
sequent self-inspection. Results of self-inspections are
also important input into periodic senior management
review as they provide objective evidence of suitabil-
ity, adequacy, and effectiveness of the quality system
and identification of opportunities for improvement of
the quality system and the performance of the organi-
zation (2, 8, 9).
Producon Process 1

Producon Process 2

Producon Process 3

QC department 1

QC department 2
Response To The Self-Inspection Results
Warehouse

Based on the results of self-inspections, the respon-


sible management can make decisions on whether the
identified risks can be accepted or reduced and how
to reduce the risks. If self-inspection identifies op-
portunities for improvement of the inspection unit,
these decisions could also include the assessment of
the identified opportunities and plans for their realiza-
Deviaon
tion. Risk control/treatment process could be seen as a
Invesgaon
cyclical process involving the following (5):
• Review of self-inspection findings, including issues
Vercal self-inspecon approach: Example, (e.g., a non-conformity or an ineffective control) or
self-inspecon of acvies within a QC department. identified opportunities for improvement
Horizontal self-inspecon approach: Example, • Risk assessment of the identified issues to facilitate
self-inspecon of deviaon invesgaons in the decision on their mitigation, for example:
producon area. • An immediate correction eliminating an existing
non-conformity or undesirable situation—simple
or non-conformances tools can be used to investigate the cause for the
• Evaluation of risks against established risk criteria non-conformity or undesirable situation, such as
• A self-inspection report including the findings and brainstorming, 5 Whys, etc.
conclusions that allow the management to judge the • A corrective or preventive action eliminating the
adequacy and effectiveness of the inspected unit risk cause(s) of an existing or potential non-conformity
management, recommended actions for identified or undesirable situation in order to prevent recur-
issues, and identified opportunities for improvement rence or occurrence. For corrective actions, tools
of risk management and efficiency of the inspected for root cause analysis can be used to identify the
unit elements. cause(s) of the issue. For the potential issues, the
prevention can include FMEA or FTA analysis
The common approach that can be used when evaluat- to determine potential risk associated with the
ing analyzed risks against the established risk criteria is to identified issue
divide risks into the following tree bands (6): • A trend that will be monitored
• An upper band, where the level of risk is regarded • Selection of possible risk control/treatment solu-
as intolerable and risk treatment is essential tions for the identified issues or improvements in
• A middle band, where the management can decide, areas where the opportunity has been identified:
based on the established treatment criteria (e.g., • Identification of possible risk treatment solutions
“As low as reasonably practicable” [ALARP] criteria or improvement solutions (i.e., use of simple tools
system), as to whether or not take any actions such as brainstorming, etc.)
• A lower band, where the level of risk is regarded • Assessment of risks associated with the risk treat-
as negligible, or so small that no risk treatment ment solutions or improvement solutions (i.e.,
measures are needed. residual risks, new introduced risks, etc.)
• Determining the criteria for selecting or pri-
The results of risk assessment of the inspection unit oritizing a particular risk treatment solution or
should be appropriately communicated to the respon- improvement solution (e.g., risk context, stake-
sible management, enabling appropriate actions. They holders concerns, cost-benefit analysis, legal,
should also be communicated to those responsible regulatory, and other requirements)
for planning of self-inspections to allow review of the • Solution confirmation providing proof, through
risk levels associated with the inspection unit. Risk objective evidence, that the selected risk treatment

28  Special Edition: A Roadmap to GMP Compliance Part 2


Barbara Jeroncic

solution will solve the problem, or that improve- vey, self-inspection is structured as a stand-alone and
ment solution will improve the effectiveness of the independent component of a quality system used to
inspection unit and will not adversely affect the monitor compliance with current GMP regulations
quality of the medicinal product and achievement and standard operating procedures. In 31% of the
of the quality objectives companies it is structured as a part of quality risk
• Defining the project plan for the implementation of management used to proactively and systematically
the selected risk treatment or improvement solution, identify, evaluate, and manage current and potential
including the following: risks to quality and non-compliances. The structure
• Project goal and responsibilities (e.g., “specific, mea- in the remaining 19% is in between the previous two.
surable, attainable, relevant, time-specific” [SMART] The majority of the companies, 63%, do not use self-
criteria can be used to define a project goal) inspection as one of the main activities for identifying
• Verification. How will the effectiveness of the selected the opportunities for continual improvement.
risk treatment solution/improvement solution be
verified? How frequently and for how long before The Application Of Quality Risk Management To
the implementation? Self-Inspection
• Implementation. How will the risk treatment solu- The survey tried to establish whether companies apply
tion or improvement solution be implemented and the quality risk management principles and tools out-
in what timeframe? lined in ICH Q9 in the various high-level areas of the
• How will the effectiveness of the implemented quality system. According to the survey, 44% of the
risk treatment solution or improvement solution companies apply them in the area of self-inspection
be monitored, how frequently and for how long? (see Figure 2).
• Implementation of the selected risk treatment solu- The most commonly used formal quality risk man-
tion/improvement solution agement tools are failure mode effects analysis (FMEA)
• Monitoring and assessment of the risk treatment and process mapping and cause and effect diagrams,
solution and improvement solution (i.e., including used by 69% of respondents. Furthermore, 50% of the
through subsequent self-inspection) effectiveness. respondents use hazard operability analysis (HAZOP)
and flow charts; 44% use risk ranking and filtering;
It is important that the outcomes of the risk control/ 38% apply hazard analysis and critical control points
treatment process are appropriately communicated to (HACCP); 31% implement fault tree analysis (FTA);
the interested parties; including those responsible for and 19% use failure mode, effects and criticality analy-
planning of self-inspections and those responsible for sis (FMECA).
planning and conducting self-inspections of the in- Companies were asked to estimate to what extent
spection unit; as any actions taken can influence the their self-inspection program was risk based, and
risks associated with the inspection unit. The output the results are presented as follows. The majority of
of risk control/treatment process should also be input the companies design their self-inspection programs
into the periodic senior management review. based on assessed risks at least to some extent (see
Figure 3).
SURVEY OF PHARMACEUTICAL MANUFACTURING When planning the frequency and the scope of self-
COMPANIES IN IRELAND ON THE QUALITY RISK MAN- inspections, the results of previous self-inspections and
AGEMENT APPLICATION IN SELF-INSPECTIONS regulatory inspections are the factors most frequently
A survey was sent to the quality assurance managers taken into account by the companies who responded
or audit managers of 40 pharmaceutical manufactur- to the survey (88%). In addition, 81% of the companies
ing companies based in Ireland with the intent to ex- take into account the number and significance of qual-
plore whether and how the pharmaceutical companies ity defects associated with an activity/process; 69% con-
apply quality risk management to their self-inspection sider the specific areas mentioned in chapter nine of the
programs. The survey also assessed the companies’ European GMP guide and the complexity of the spe-
understanding of, and their interest in, reduced level cific activities and processes; and 63% of the surveyed
of direct regulatory oversight in the area of regulatory companies take into account major changes in building,
inspections. The survey included drug product manu- equipment, processes, key personnel, etc. Only 38% of
facturers and manufacturers of active pharmaceutical the companies consider experience with the activity or
ingredients. Eighteen companies responded to the process and just 19% take into account specific arrange-
survey (45%), and the results are presented as follows. ments and agreements associated with the activity or
process.
The Role Of Self-Inspection Within The Quality Half of companies report that the same amount of
System time and personnel are typically devoted to all self-
In 50% of the companies who responded to the sur- inspections included in the annual self-inspection pro-

Special Edition: A Roadmap to GMP Compliance Part 2 29


Barbara Jeroncic

gram. Fifty-six percent of the companies who respond- do so.


ed to the survey do not have documented guidance
for different types of self-inspections (e.g., horizontal, CONCLUSION
vertical, systems-based, process-based, departmental- ICH Q10 and ISO 9000 standard series view self-
based, etc.). Only half of the respondents review results inspection as a vital and integral part of the quality
of self-inspection as a part of the periodic management system, providing an independent tool for monitor-
review. ing and assessment of the effectiveness of the activities
and processes within the quality system, and for driv-
The Potential For Reduced Level Of Direct Regulatory ing forward their continual improvement. In order to
Oversight In The Area Of Regulatory Inspections be efficient and complete, this process should include
ICH Q9 and Q10 promote the potential for reduced the evaluation of the risks hindering the achievement of
regulatory oversight. There is an opportunity to in- the quality objectives placed on activities and processes
crease the use of risk-based approaches for regulatory potentially affecting the quality of the medicinal prod-
inspections for companies that can demonstrate an ef- uct. There is an opportunity to design self-inspection
fective quality system is being in place, including ef- as a quality risk management tool identifying and as-
fective use of quality risk management principles. In sessing risks associated with areas of the quality system
the inspection area, reduced regulatory oversight can and providing objective evidence on the effectiveness of
take a form of less frequent or less intensive regulatory their management. Self-inspection designed in this way
inspections, or inspections where some areas are not could potentially identify issues and non-conformanc-
inspected or are less thoroughly inspected based on es before they occur by allowing the management to
the risk considerations (2, 3). take the appropriate risk-reducing actions; and further
Of the companies who responded to the survey, recognise the opportunities for improvement of risk
56% are familiar with the potential opportunities for management and effectiveness of the quality system ar-
a reduction in the level of direct regulatory oversight eas. Application of principles and concepts of quality
that may be applied as envisaged by the ICH Q8, Q9, risk management also enables more efficient organiza-
and Q10 guidelines. Further 38% are partially familiar tion and planning of self-inspections by directing the
and only 6% are not familiar at all. Importantly, 44% of inspection effort to those areas of the quality system
the companies are interested in seeking some level of that represent higher risk to the quality of the medicinal
reduced regulatory oversight from the Irish Medicines product and the achievement of the quality objectives.
Board, and the same percentage of the companies are The application of quality risk management in different
not interested. The remaining 12% of the respondents areas of the pharmaceutical industry, including self-in-
have not answered this question. spection, is strongly supported by ICH Q9. This article
A significant majority, 81%, of the companies think presents innovative approaches to self-inspection as a
that the best way to demonstrate to the regulatory in- quality risk management tool, with the potential for in-
spectors that an effective quality management system troduction of a risk-based approach to self-inspection
is in place within the company is proactive discussion planning in pharmaceutical manufacturing.
of the company’s quality management system elements The results of the survey of the pharmaceutical man-
with the regulatory inspectors. Furthermore, 75% of ufacturing companies in Ireland demonstrate that the
the companies consider a good regulatory inspection companies have started to apply quality risk manage-
outcome (e.g., no major or critical deficiencies) an im- ment to their self-inspection programs. Whilst half of
portant factor in demonstration of an effective man- the companies still view self-inspection as an isolated
agement system; 50% assign equal significance to no and independent component of the quality system used
recalls and a low number of complaints over a certain to monitor compliance with current GMP regulations
period, whilst 44% are satisfied with no for-cause reg- and standard operating procedures, the remaining re-
ulatory inspections carried out at their company. spondents have structured it as a part of the quality
The majority of respondents, 63%, would like to see risk management used to identify and manage current
a formal program of communications with regulators and potential risks to quality and non-compliances, at
with respect to the potential applications of regulatory least to some extent. The majority of the companies es-
flexibility and reduced regulatory oversight. A consid- timated that their self-inspection program was based
erable 31% are not interested in this, and 6% did not on the assessed risk at least to some extent. The most
answer this question. The majority of the respondents, frequently used factors for determining the frequency
88%, are willing to consider open sharing of self-in- and scope of self-inspections envisaged by ICH Q9 are
spection reports with a regulatory inspector in some the results of previous self-inspections and regulatory
way, in order to demonstrate that an effective quality inspections, and the number and significance of quality
management system is in place within their company, defects associated with an activity or process. The sur-
whilst 12% of the companies would not be willing to vey identified three main areas of self-inspection pro-

30  Special Edition: A Roadmap to GMP Compliance Part 2


Barbara Jeroncic

gram improvement within the pharmaceutical companies: struc- 4. ICH, Q9 Quality Risk Management, 2005.
turing self-inspection as an integral and vital part of the company’s 5. ISO 31000 Risk Management—Principles and Guidelines, First Edition, No-
quality system and risk quality management strategy; designing vember 13, 2009.
self-inspection in a way it could be used as one of the main activi- 6. ISO 31010 Risk Management–Risk Assessment Techniques, first edition,
ties for identifying the opportunities for continual improvement; 2009-12-01.
and including self-inspection results as an input into periodic man- 7. Wealleans D., The Quality Audit for ISO 9001:2000: A Practical Guide, 2nd
agement review. edition, Gower Publishing, 2005.
With respect to the potential for reduced level of direct regula- 8. ISO 9001 Quality Management System—Requirements, Third Edition, De-
tory oversight in the area of regulatory inspection promoted by ICH cember 15, 2000.
Q10, the results of the survey showed that the majority of compa- 9. ISO 9004 Quality Management Systems—Guidelines for Performance Improve-
nies are interested in this idea and would welcome a formal pro- ments, Second Edition December 15, 2000. GXP
gram of communications with regulators. The surveyed companies
consider proactive discussion of the company’s quality manage- ARTICLE ACRONYM LISTING
ment system elements with the regulatory inspectors to be the best ALARP As Low As Reasonably Practicable
way to demonstrate that an effective quality management system FMEA Failure Mode and Effects Analysis
is in place within the company. The majority of the companies are FTA Fault Tree Analysis
willing to consider some form of open sharing of self-inspection GMP Good Manufacturing Practice
reports with regulatory inspectors in order to demonstrate that an HACCP Hazard Analysis and Critical Control Points
effective quality management system is in place. The survey identi- HAZOP Hazard Operability Analysis
fied a need for further regulatory guidance and recommendation in ICH International Conference on Harmonisation
the area of the reduced regulatory oversight, as envisaged by ICH IMB Irish Medicines Board
Q8, Q9, and Q10. ISO International Organization for Standardization
QP Qualified Person
QRM Quality Risk Management
REFERENCES SMART Specific, Measurable, Attainable, Relevant, Time-Specific
1. EudraLex, GMP Directive 2003/94/EU, Good Manufacturing Practice SWIFT Structured “What-If” Technique
(GMP) Guidelines, Vol. 4, Part I-Basic Requirements for Medicinal Prod- TOC Total Organic Carbon
ucts, Chapter 9-Self-inspection. Retrieved from: http://ec.europa.eu/enter-
prise/sectors/pharmaceuticals/files/eudralex/vol-4/pdfs-en/cap9_en.pdf. ABOUT THE AUTHOR
2. ICH Q10 Pharmaceutical Quality System, 2008. Barbara Jeroncic has worked in the pharmaceutical industry for several years in
different roles, including working in quality departments. She may be reached
3. O’Donnell K., “Self-Inspection and its Potential Benefits via ICH Q9,” Jour-
by e-mail at barbara.jeroncic@imb.ie.
nal of GXP Compliance, Summer 2008, Vol.12 No. 4.

Originally published in the Summer 2011 issue of Journal of GXP Compliance

Special Edition: A Roadmap to GMP Compliance Part 2 31

Вам также может понравиться