Method Statement:
WRAPPING OF UNDERGROUND PIPES
Table of Contents
1. METHOD STATEMENT ................................................................... 2
2. PURPOSE ..................................................................................... 2
5. PROCEDURE ................................................................................. 3
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
1. METHOD STATEMENT
In addition, this method statement also covers and defines the material
specifications, method of cleaning, wrapping, testing, handling and storing,
etc., required for the satisfactory completion of the job.
2. PURPOSE
To provide added protection for bolt and nuts and flat washers aside from
currently approved hot dip galvanized bolts and nuts.
3. MANPOWER REQUIREMENT
4. MATERIALS REQUIREMENT
The following materials shall be on site before proceeding with the preparatory
and coating works except for testing apparatus.
1 Ordinary Duct Tape, 2” width
2 Polyethylene Sheet, 6 mils
3 Standard PPE
DCPWTP-2
MS-040 2
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
5. PROCEDURE
1. Wrap the recently installed flange with bolts and nuts with double wrapped of
polyethylene sheet.
2. After wrapping the flange bolt, nuts and washer, seal both ends of the
polyethylene sheet including the horizontal end with duct tape, as shown in
Elevation 1. The tape shall be three wrapped at both ends and one wrap at
horizontal end.
DCPWTP-2
MS-040 3