Construction Estimates

Project Name: Installation of Jakob Wire Mesh and Safety Net


Project Location:
Contractor: Benedicto Steel Corp Customer:
Start: Scope: Build Only
Date
End: Terms:

Schedule of Activity
Activity Preceeding Succeeding
Activity Name Duration Man Power Cost
Number Activity Activity

A Mobilization - B
B Installation of foundation for Net/Mesh A C,D 2 days 2S, 4L
C Installation of columns for wire mesh B E,F 2 days 2S, 4L
D Fabrication of frames for net/mesh B C 2 days 2S, 4L
E Installation of wire mesh D G 2 days 2S, 4L
F Installation of safety net D G 2 days 2S, 4L
G clearing up E,F -
H
I
J
K
L
M
TOTAL: 6 days 2S, 4L

Estimation of Cost
Unit Total Activity
Quantity Unit Description Activity
Amount Amount Number
Man Power

Total:
Schedule
Project Name: Installation of Jakob Wire Mesh and Safety Net
Project Location:
Contractor: Benedicto Steel Corp Customer:
Date Start: Scope: Build Only
Date End: Terms:

Month
Day 1 2 3 4 5 6
Activity Number Activity Name
A Mobilization
B Installation of foundation for Net/Mesh
C Installation of columns for wire mesh
D Fabrication of frames for net/mesh
E Installation of wire mesh
F Installation of safety net
G clearing up
Bill of Materials
Project Name: Installation of Jakob Wire Mesh and Safety Net
Project Location:
Contractor: Benedicto Steel Corp Customer:
Start: Scope: Build Only
Date
End: Terms: