Вы находитесь на странице: 1из 3

ASME B&PV CODE SECTION VIII PRESSURE VESSEL DESIGN

A COMPARISON – DIVISION 1 versus DIVISION 2

Dwight V. Smith
Colt Engineering Corporation
400, 10201 Southport Rd., S.W.
Calgary, Alberta, Canada T2W 4X9
Tel: 403-258-8000
Fax: 403-258-5899
E-Mail: smith.dwight@colteng.com

ABSTRACT stresses now permitted, reduce the thickness advantage of Div. 2


Historically, the ASME B&PV Code, Section VIII, designs, which utilize a design factor of 3.0. However, a current
Division 2, Alternative Rules for Construction of Pressure in-progress ASME review of Div. 2, may also result in higher
Vessels (Div.2), ASME [1], was usually considered applicable allowable design stresses in future editions of that Code, creating
only for large, thick walled pressure vessels. Otherwise, ASME additional opportunities for increased economy through use of
B&PV Code, Section VIII, Division 1, Rules for Construction of Div. 2 vessel designs.
Pressure Vessels (Div. 1), ASME [2], was typically applied. A Div. 1 stresses reflect the simplified design methods of
case can also be made for the application of the Div. 2 Code Div. 1 which are commonly referred to as ‘design by rules’, as
Section for some vessels of lesser thicknesses. Each vessel opposed to Div. 2, where engineering design is referred to as
should be closely evaluated to ensure the appropriate choice of ‘design by analysis’.
Code Section to apply. Div. 2 recognizes the technical progress made over time,
This paper discusses some of the differences between the Canonico [5], with respect to design methods, material
Div. 1 and Div. 2 Code Sections, summarizes some of the main manufacture and non-destructive examination techniques, which
design requirements of Div. 2, and presents a case for considering permit the use of higher allowable design stresses consistent with
its use for design conditions not usually considered by some, to the following:
be appropriate for the application of Div. 2 of the ASME Code. • combined stresses under all loading conditions are calculated
more accurately
• vessel materials undergo more extensive examination and
INTRODUCTION testing
In the past, it was generally accepted that Div. 2 designs • welded joints are subjected to increased non-destructive
could result in considerable cost savings, Lengsfeld [3], through examination
reduced material thicknesses only for large, high pressure ASME Div. 2 generally dictates a more rigorous engineering design
Code vessels. This was primarily because of the higher allowable approach, however, it does provide simplified rules for design in
design stresses permitted for Div. 2, ASME [4], resulting in Part AD. The vessel designer must utilize these rules, as
thinner materials. Savings were realized by lower costs for applicable, in which case some aspects of the design may not be
material, fabrication and associated infrastructure. The reduced much more complex than that of a Div. 1 design.
costs could be substantial where thick materials were involved. Although a Div. 2 design requires additional engineering,
Thus, only where cost savings were large and obvious, was there including Fatigue Analysis evaluation, technical documentation
a tendency to utilize a Div. 2 design. Given an increasingly and inspection, as well as invoking certain in-service restrictions,
competitive market place, and considering the potential for cost the use of thinner materials with the associated cost savings can
savings, Div. 2 designs for lesser thicknesses may be prudent. easily offset the additional costs of these items. When the
Although Div. 1 specifies relatively lower allowable design additional requirements of a Div. 2 design are closely evaluated,
stresses, in recognition of advances over the years in steel making it is apparent that they are not necessarily difficult or expensive
technology and non-destructive examination techniques, Div. 1 to implement. Finally, the availability of computer software
has recently been revised to include a design factor of 3.5, as programs today allow for ease of design of either Div. 1 or Div. 2
opposed to 4.0. As a result, the higher Div. 1 allowable design pressure vessels.
In proposing a Div. 2 design for a given vessel, the end user of Div. 2 vessels will not have problems generating this
must be consulted and the applicable Jurisdictional requirements document, nor should it add significant cost.
must be understood. The requirements for monitoring, for
example of cyclic conditions, as well as for future inspection, can Fatigue Analysis
add costs that are not acceptable to some end users. In addition, Although Fatigue Analysis, where required, can be
some Jurisdictions stipulate more stringent requirements expensive, many vessels consist of conventional carbon steel
regarding field repairs to Div. 2 vessels. For example, detailed materials with simple geometric configurations, where Fatigue
analysis and repair procedure preparation and approvals can add Analysis is not required.
significantly to scheduled shutdown times. A given Jurisdiction The decision as to whether or not a Fatigue Analysis is
may also have more stringent registration requirements, such as required for a particular vessel involves a number of criteria and
stating that the design firm and/or the design engineer be is documented in the User’s Design Specification.
registered in that Jurisdiction. The above should be clarified prior Even in cases where an analysis is required, the cost should
to initiating a Div. 2 design proposal. be evaluated relative to savings in other areas, as an analysis is
It should be noted that the advantages of a Div. 2 design for not necessarily overly complex and may be readily carried out by
SA516-Gr 70 materials are most apparent for design temperatures Engineers experienced in this area. It should be noted that a
of 300°F or less. At higher temperatures, the allowable Div. 2 Fatigue Analysis may also be required for a Div. 1 vessel.
design stresses for SA516-Gr 70 materials are lower, where those
for Div. 1 are fairly consistent up to much higher temperatures. Inspection
Some design condition scenarios can actually result in a Div. 1 Inspection requirements for a Div. 1 vessel may differ little,
design thickness being less than that of a Div. 2 design. if at all, from those invoked by Div. 2. Many industry
This paper relates primarily to SA516-Gr 70 materials. Other specifications, such as those for vessels in sour service, stipulate
types, such as high strength materials may provide much greater inspection requirements exceeding those of Div. 1. In some cases
economy through the use of a Div. 2 design. the specified inspection requirements even exceed those of Div.
It should not be assumed that, because a particular vessel 2. Therefore, the engineering company, or end user specified
design does not require what is traditionally considered ‘heavy inspection details, for a particular vessel, must be evaluated
wall’ material, that a Div. 2 design would not be economically against the requirements of the applicable ASME Code Division,
advantageous. Each case should be individually evaluated. to assist in the decision as to the appropriate Code Division to
Finally, although a Div. 2 design may be considered for apply.
reasons of economy, Rapoport [6], certain specific design
conditions may also dictate its use. These include:
• cyclic temperatures and pressures PURCHASING/FABRICATION
• severe operating temperature gradients The fabrication costs for a Div. 2 vessel can actually be less
• complex geometrical configurations than those for Div. 1. The thinner material requirements may
result in reduced material purchase price, as well as a reduction in
preparation, handling and welding costs.
REQUIREMENTS FOR ASME SECTION VIII, DIV. 2
User’s Design Specification
A “User’s Design Specification” is required for vessels INSTALLATION/INFRASTRUCTURE/SHIPPING COSTS
designed to Div. 2. This document is usually prepared by the Because of the reduced material thickness and weight,
engineering company on behalf of the end user, and contains installation and infrastructure costs can also be reduced.
details such as the operating and design conditions, materials of Therefore, the total installed cost of a vessel may be reduced
construction, Fatigue Analysis evaluation, method of support and further through savings related to concrete foundations, structural
location of installation, along with reference to the fabrication steel and lifting cranes. Shipping costs should also be lower, and
drawings and the process design data. in fact, fabricators who would not otherwise be able manufacture
The Specification is issued to ensure compliance with the or ship a vessel designed to Div. 1, due to weight restrictions,
requirements of the latest applicable Edition and Addenda of the may otherwise be able to provide a quotation for Div. 2 vessel
ASME Code, Section VIII, Div. 2 and must be stamped by a with materials of lesser thicknesses.
Registered Engineer. This document is not usually complicated or
expensive to prepare.
A WORKABLE EXAMPLE
Manufacturer’s Design Report Following is an example of a vessel that historically, might
A “Manufacturer’s Design Report” is also required. This not be considered as a candidate for a Div. 2 design. (ref. Table 1,
document is prepared by the Manufacturer and contains design “WORKABLE EXAMPLE PARAMETERS” and Cost &
and fabrication details/drawings related to the vessel. Thickness Summary Graphs, Figures 1 and 2, respectively):
The information in the report is a compilation of vessel
related data that already exists as a result of the design and Design Conditions:
manufacture of the vessel. This information is also required by Material: SA 516-70 ID: 14 ft.
most Clients for a Div. 1 vessel. This document also requires a Pressure: 450 psi Length: 100 ft.
Registered Engineer’s stamp and Fabricators of Div. 2 vessels Temperature: 300°F Jeff: 1.0
usually have qualified Engineering personnel on staff. A Heads: 2:1 SE CA: 0.1250 in.
Fabricator licensed and experienced in the design and fabrication
Allowable Calc Actual Calc Actual Calc Actual Calc Actual
Calc Cost Actual Cost
Stress t t ∆t ∆t Wt Wt ∆wt ∆wt
Saving* Saving*
(psi) (in.) (in.) (in.) (in.) (lbs) (lbs) (lbs) (lbs)

Div. 1 20,000 2.041 2.0625 482,000 487,100

0.2190 0.1875 51,579 44,100 $128,947.00 $110,250.00

Div.2 22,500 1.822 1.8750 430,421 443,000


* Cost savings based on $2.50/fabricated lb.
TABLE 1
WORKABLE EXAMPLE PARAMETERS

DISCUSSION OF WORKABLE EXAMPLE repairs and monitoring, the use of thinner materials can offset the
Table 1 shows a comparison of Div. 1 versus Div. 2, in additional costs of these items.
terms of the differences in calculated thicknesses (Calc ∆t) and When the additional requirements of a Div. 2 design are
the differences in actual thicknesses (Actual ∆t). Actual thickness closely evaluated, it is apparent that they are not necessarily
(t) values represent commonly commercially available material difficult or expensive to implement.
thicknesses. Similarly, the corresponding differences in calculated Lower weights and thinner materials should reduce
and actual weights, are also shown. Finally, the resulting fabrication and shipping costs, as well as costs for installation and
calculated and actual cost savings are indicated. infrastructure.
Figure 1, “Vessel Cost Summary”, shows the variation in Fabricators who would not otherwise be able to provide a
cost relative to three factors; vessel length, vessel diameter and quotation, due to inability to manufacture or ship a vessel
the Code Div. utilized. It can be seen that, as the diameter for a designed to Div. 1, because of weight restrictions, may be able to
given length increases, the Div. 2 cost benefit also increases. provide a quotation.
Further, as the vessel length increases, the Div. 2 cost benefit also For certain pressure vessels, the use of an ASME Code,
increases. This is because, as the vessel length increases, the Section VIII, Div. 2 design can result in substantial cost savings,
vessel weight increase is greater for a Div. 1 design, than for a
in terms of total installed cost. This is particularly true, for
Div. 2 design. Greater weight corresponds to increased cost.
example, where large vessels will be field fabricated. However,
Figure 2, “Vessel Thickness Summary”, shows the variation
even smaller, lower pressure vessels to be shop fabricated can
in thickness relative to three factors; diameter, pressure and Code
Div. utilized. It can be seen that as the pressure for a given result in significant cost savings, particularly on a cumulative
diameter increases, the thickness also increases. Further, as the basis.
vessel diameter increases, the thickness benefit (cost reduction) Each case should be evaluated on an individual basis to
related to a Div. 2 design also increases. determine the most cost effective design Code, and where
The data shows that even without considering reduced preliminary calculations indicate that a Div. 2 design may result
infrastructure requirements, the capital cost savings can be in significant cost savings, Vendors should be requested to
significant by utilizing a Div. 2 design. In this example, any provide costs for both a Div. 1 and a Div. 2 option.
additional requirements invoked by a Div. 2 design, might be
justified from a cost perspective, even allowing for additional
costs where a Vendor quotes higher pricing for a Div. 2 REFERENCES
engineering design. It should be noted however that the number 1. ASME International, ASME Boiler and Pressure Vessel
of qualified manufacturers for Div. 2 vessel work, is much lower Code, Section VIII, Division 2, 2001 Edition, New York
than that for Div. 1. This means that a less competitive 2. ASME International, ASME Boiler and Pressure Vessel
environment may exist for Div. 2 vessel manufacture. Code, Section VIII, Division 1, 2001 Edition, New York
Smaller vessels or other design conditions may result in less
cost savings per unit. However, individual evaluation of each case 3. Lengsfeld M., Holman R., Lengsfeld P., 1995 “Economic
will maximize commercial benefits. This is particularly true Advantages of Division 2 Design For Vessels Per ASME
where a number of vessels are involved, where the cumulative Code Section VIII”, PVP 313-2, International Pressure
cost savings can be significant. In the example presented here, if Vessels and Piping Codes and Standards: Volume 2 – Current
two vessels were being purchased, the cost savings could Perspectives ASME 1995
approach a quarter of a million dollars, even without considering
4. ASME International, ASME Boiler and Pressure Vessel
infrastructure cost savings.
Code, Section II, Part D, 2001 Edition, New York
5. Canonico D. A., 1999, “Adjusting the Boiler Code”, An
SUMMARY & CONCLUSIONS article based on an address delivered to the 68th General Joint
In addition to large, thick pressure vessels, in some cases Meeting of the National Board of Boiler and Pressure Vessel
significant cost savings may be realized by utilizing an ASME Inspectors and the ASME Boiler and Pressure Vessel Code
Code, Div. 2 design for large carbon steel vessels at lower design
pressures/temperatures, with thinner materials. This is primarily 6. Rapoport A., 1990, “ASME Code, Section VIII, Div.2 & its
Comparison to Div.1”, Colt Engineering Corporation,
true for design temperatures of 300°F or less.
Calgary, Alberta
Although a Div. 2 design requires additional engineering,
including Fatigue Analysis evaluation, technical documentation
and inspection, as well as invoking restrictions on future field

Вам также может понравиться