contract forms. CNC Vietnam is proud to briefly introduces the comparison between typical rainbow suits (Red Book,
Yellow Book, and Silver Book) which are reputed as the leading contracts in international engineering and construction
projects for both practitioners, (Employers, Contractor), and professional (Lawyers, legal executive, contract executive
etc.) to have a further acknowledgment, and experience.
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
REGULATION AND WORKS Recommended for building Recommended for the Suitable for the provision
and engineering works provision of electrical on a turnkey basis of a
designed by the Employer and/or mechanical plant process or power plant, of
or his representative, the and for the design and a factory or similar facility,
Engineer. execution of building or or of an infrastructure
engineering works. projector other type of
Under the usual
development, where
arrangements for this type Under the usual
of contract, the Contractor arrangements for this type A higher degree of
constructs the works in of contract, the Contractor certainty of final price and
accordance with a design designs and provides, in time is required, and
provided by the Employer. accordance with the
The Contractor takes total
However, the works may Employer’s requirements,
responsibility for the
include some elements of plant and/or other works;
design and execution of
Contractor designed civil, which may include any
the project, with little
mechanical, electrical
combination of civil, involvement of the
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
1
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
CONTRACT ADMINISTRATION The Contract is The Contract is There is Not Engineer. The
administered by the administered by the Contract is administered
Engineer (appointed by the Engineer (appointed by the directly by the Employer or
Employer) who shall Employer) who shall its representative who
determine any claim for determine any claim for endeavours to reach
extension of time and extension of time and agreement with the
additional payment, certify additional payment, certify Contractor on each claim.
payments and issue taking payments and issue taking The Introductory Note to
over and performance over and performance the Silver Book emphasises
certificates. certificates. that if the Contractor is to
2
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
RISKS ALLOCATION Risks are allocated on a Risks are allocated on a A majority of risks is
fair and equitable basis fair and equitable basis allocated to the
taking account of such taking account of such Contractor under the
matters as insurability, and matters as insurability, and Contract, including any
each party's ability to each party's ability to errors in:
foresee, and mitigate the foresee, and mitigate the
1. Errors in the Setting Out
effect of, the circumstances effect of, the circumstances
data (Sub-Clause 4.7);
relevant to each risk. relevant to each risk.
2. Site data (Sub-Clause
There are a number of There are a number of
4.10);
key risks that the Employer key risks that the Employer
retains, for example: retains, for example: 3. Unforeseeable
difficulties or costs (Sub-
1. Errors in the Setting Out 1. Errors in the Setting Out
Clause 4.12)
data (Sub-Clause 4.7); data (Sub-Clause 4.7);
The Contractor is expected
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
3
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
DESIGN The Contractor shall design The Contractor shall carry The Contractor shall be
(to the extent specified in out, and be responsible deemed to have
-
the Contract), execute for, the design of the Works. scrutinised, prior to the Base
ERRORS IN THE EMPLOYER’S and complete the Works in Date, the Employer's
Design shall be prepared
REQUIREMENTS accordance with the Requirements (including
by qualified designers who
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
4
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Contract and with the are engineers who comply design criteria and
Engineer’s instructions, and with the criteria (if any) calculations, if any). The
shall remedy any defects in stated in the Employer's Contractor shall be
the Works. Requirements. responsible for the design
of the Works and for the
Except to the extent Unless otherwise stated in
accuracy of such
specified in the Contract, the Contract, the
Employer's Requirements
the Contractor Contractor shall submit to
(including design criteria
the Engineer for consent
Shall be responsible for and calculations), except
the name and particulars
all Contractor’s as stated below.
of each proposed designer
Documents, Temporary
and design Subcontractor. The Employer shall not be
Works, and such design
responsible for any error,
of each item of Plant The Contractor warrants
inaccuracy or omission of
and Materials as is that he, his designers and
any kind in the Employer's
required for the item to design Subcontractors have
Requirements as originally
be in accordance with the experience and
included in the Contract
the Contract, and capability necessary for
and shall not be deemed
the design.
Shall not otherwise be to have given any
responsible for the The Contractor undertakes representation of accuracy
design or specification of that the designers shall be or completeness of any
available to attend data or information, except
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
5
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
the Permanent Works. discussions with the as stated below. Any data
Engineer at all reasonable or information received by
The Contractor shall,
times, until the expiry date the Contractor, from the
whenever required by the
of the relevant Defects Employer or otherwise, shall
Engineer, submit details of
Notification Period. not relieve the Contractor
the arrangements and
from his responsibility for
methods, which the Upon receiving notice
the design and execution of
Contractor proposes to under Sub-Clause8.1
the Works.
adopt for the execution of [Commencement of Works],
the Works. No significant the Contractor shall However, the Employer
alteration to these scrutinise the Employer's shall be responsible for the
arrangements and methods Requirements (including correctness of the following
shall be made without this design criteria and portions of the Employer's
having previously been calculations) and the items Requirements and of the
notified to the Engineer. If of reference mentioned in following data and
the Contract specifies that Sub Clause 4.7 [Setting Out]. information provided by (or
the Contractor shall design on behalf of) the Employer:
Within the period stated in
any part of the Permanent
the Appendix to Tender, Portions, data and
Works, then unless otherwise
calculated from the information which are
stated in the Particular
Commencement Date, the stated in the Contract
Conditions:
Contractor shall give as being immutable or
6
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
7
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Prior to the
commencement of the
Tests on Completion, the
Contractor shall submit
to the Engineer the “as-
built” documents and
operation and
maintenance manuals in
accordance with the
Specification and in
sufficient detail for the
8
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Employer to operate,
maintain, dismantle,
reassemble, adjust and
repair this part of the
Works. Such part shall
not be considered to
be completed for the
purposes of taking over
under Sub-Clause 10.1
[Taking Over of the
Works and Sections] until
these documents and
manuals have been
submitted to the
Engineer.
CONTRACT PRICE Unless otherwise stated in Unless otherwise stated in Unless otherwise stated in
the Particular Conditions: the Particular Conditions: the Particular Conditions:
The Contract Price shall The Contract Price shall Payment for the Works
be agreed or be the lump sum shall be made on the
determined under Sub- accepted contract basis of the lump sum
9
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
The Contractor shall pay The Contractor shall pay The Contractor shall pay
all taxes, duties and all taxes, duties and all taxes, duties and
fees required to be paid fees required to be fees required to be
by him under the paid by him under the paid by him under the
Contract, and the Contract, and the Contract, and the
Contract Price shall not Contract Price shallot be Contract Price shall not
be adjusted for any of adjusted for any of these be adjusted for any of
these costs except as costs, except as stated in these costs, except as
stated in Sub-Clause 13.7 Sub-Clause 13.7 stated in Sub Clause
[Adjustments for Changes [Adjustments for 13.7.
in Legislation]; Changes in Legislation]
10
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
11
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
PAYMENT The Employer shall make an The Employer shall make an The Employer shall make an
advance payment, as an advance payment, as an advance payment, as an
interest-free loan for interest-free loan for interest-free loan for
mobilisation, when the mobilisation, when the mobilization and design,
Contractor submits a Contractor submits a when the Contractor
12
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
guarantee. Unless and until guarantee. Unless and until submits a guarantee.
the Employer receives this the Employer receives this
Employer shall pay the first
guarantee, or if the total guarantee, or if the total
instalment after receiving
advance payment is not advance payment is not
stated in the Contract stated in the Contract 1. A Statement;
Data (or Appendix to Data (or Appendix to
Tender), this Sub Clause shall Tender), this Sub Clause shall 2. The Performance
not apply. not apply. Security
The Engineer shall issue an The Engineer shall issue an The Contractor shall submit
Interim Payment Certificate Interim Payment Certificate a Statement in six copies
for the first instalment after: for the first instalment after: to the Employer after the
end of the period of
Receiving a Statement Receiving a Statement payment stated in the
and and Contract (if not stated,
after the end of each
after the Employer after the Employer
month), in a form
Receives: Receives:
approved by the Employer,
1. The Performance 1. The Performance showing in detail the
Security Security amounts to which the
Contractor considers
2. a guarantee in 2. a guarantee in
himself to be entitled,
amounts and amounts and
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
13
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
14
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
will be paid, then unless will be paid, then unless estimated contract
otherwise stated in this otherwise stated in this
If these instalments are not
schedule: schedule:
defined by reference to
The instalments quoted in The instalments quoted in the actual progress
this schedule of this schedule of achieved in executing the
payments shall be the payments shall be the Works, and if actual
estimated contract estimated contract progress is found to be
values. values. less than that on which
the Schedule of Payments
If these instalments are If these instalments are
was based, then the
not defined by not defined by
Employer may proceed to
reference to the actual reference to the actual
agree or determine revised
progress achieved in progress achieved in
instalments, which shall take
executing the Works, executing the Works,
account of the extent to
and if actual progress is and if actual progress is
which progress is less than
found to be less than found to be less than
that on which the
that on which the that on which the
instalments were previously
Schedule of Payments Schedule of Payments
based.
was based, then the was based, then the
Engineer may proceed Engineer may proceed If the Contract does not
to agree or determine toagree or determine include a Schedule of
15
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
16
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
EXTENSION OF TIME Various rights for the Various rights for the The Contractor shall be
Contractor to claim Contractor to claim entitled to an EOT if (and to
ASSOCIATED COSTS
Extension of Time OR Extension of Time OR the extent that)completion
Associated Cost under the Associated Cost under the for the purposes of Taking
Contract for errors: Contract for errors: Over of the Works and
Sections is or will be delayed
In the Setting Out data In the Setting Out data
by any of the following
(Sub-Clause 4.7) (Sub-Clause 4.7)
causes:
In the Site data (Sub- In the Site data (Sub-
A Variation (unless an
Clause 4.10) Clause 4.10)
adjustment to the Time
Unforeseen Site risks (Sub- Unforeseen Site risks (Sub- for Completion has
Clause 4.12) Clause 4.12) been agreed under
Variation Procedure;
Others. Others.
A cause of delay giving
an entitlement to
extension of time under
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
17
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
a Sub-Clause of these
Conditions;
TESTS ON COMPLETION The Contractor shall carry The Contractor shall carry The Contractor shall carry
out the Tests on out the Tests on out the Tests on
Completion. Completion. Completion.
The Contractor shall give The Contractor shall give The Contractor shall give
to the Engineer not less than to the Engineer not less than to the Engineer not less than
21 days’ notice of the date 21 days’ notice of the date 21 days’ notice of the date
after which the Contractor after which the Contractor after which the Contractor
will be ready to carry out will be ready to carry out will be ready to carry out
each of the Tests on each of the Tests on each of the Tests on
Completion. Completion. Completion.
18
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
19
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
20
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
proceed with the Tests at shall give notice to the shall give notice to the
the risk and cost of the Engineer that the Works Engineer that the Works
Contractor. The Tests on are ready for any other are ready for any other
Completion shall then be Tests on Completion, Tests on Completion,
deemed to have been including performance tests including performance tests
carried out in the presence to demonstrate whether the to demonstrate whether the
of the Contractor and the Works conform with criteria Works conform with criteria
results of the Tests shall be specified in the Employer's specified in the Employer's
accepted as accurate. Requirements and with the Requirements and with the
Schedule of Guarantees. Schedule of Guarantees.
Failure to pass tests
Trial operation shall not Trial operation shall not
If the Works, or a Section, fail
constitute a taking-over constitute a taking-over
to pass the Test son
under Clause 10 [Employer’s under Clause 10 [Employer’s
Completion repeated
Taking Over]. Taking Over].
under Sub- Clause 9.3
[Retesting], the Engineer Unless otherwise stated in Unless otherwise stated in
shall be entitled to: the Particular Conditions, the Particular Conditions,
any product produced by any product produced by
Order further repetition of
the Works during trial the Works during trial
Tests on Completion
operation shall be the operation shall be the
under Sub-Clause 9.3;
property of the Employer. property of the Employer.
21
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
If the failure deprives the In considering the results In considering the results
Employer of substantially of the Tests on Completion, of the Tests on Completion,
the whole benefit of the the Engineer shall make the Engineer shall make
Works or Section, reject allowances for the effect allowances for the effect
the Works or Section(as of any use of the Works of any use of the Works
the case may be), in by the Employer on the by the Employer on the
which event the performance or other performance or other
Employer shall have the characteristics of the Works. characteristics of the Works.
same remedies as are As soon as the Works, or a As soon as the Works, or a
provided in Section, have passed each Section, have passed each
subparagraph (c) of of the Tests on Completion of the Tests on Completion
Sub Clause 11.4 [Failure described in sub-paragraph described in sub-paragraph
to Remedy Defects]; or (a), (b) or (c), the (a), (b) or (c), the
Contractor shall submit a Contractor shall submit a
Issue a Taking-Over
certified report of the results certified report of the results
Certificate, if the
of these Tests to the of these Tests to the
Employer so requests.
Engineer. Engineer.
But in this case, the
If the Tests on Completion If the Tests on Completion
Contractor shall proceed in
are being unduly delayed are being unduly delayed
accordance with all other
by the Contractor, the by the Contractor, the
obligations under the
Engineer may by notice Engineer may by notice
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
22
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Contract, and the Contract require the Contractor to require the Contractor to
Price shall be reduced by carry out the Tests within 21 carry out the Tests within 21
such amount as shall be days after receiving the days after receiving the
appropriate to cover the notice. notice.
reduced value to the
The Contractor shall carry The Contractor shall carry
Employer as a result of this
out the Tests on such day or out the Tests on such day or
failure. Unless the relevant
days within that period as days within that period as
reduction for this failure is
the Contractor may fix the Contractor may fix
stated (or its method of
and of which he shall give and of which he shall give
calculation is defined) in
notice to the Engineer. notice to the Engineer.
the Contract, the Employer
may require the reduction to If the Contractor fails to If the Contractor fails to
be carry out the Tests on carry out the Tests on
Completion within the Completion within the
Agreed by both Parties
period of 21 days, the period of 21 days, the
(in full satisfaction of this
Employer's Personnel may Employer's Personnel may
failure only) and paid
proceed with the Tests at proceed with the Tests at
before this Taking-Over
the risk and cost of the the risk and cost of the
Certificate is issued;
Contractor. The Tests on Contractor. The Tests on
Determined and paid Completion shall then be Completion shall then be
under Sub-Clause 2.5 deemed to have been deemed to have been
23
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
24
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
25
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
TAKING-OVER Except as stated in Sub- Except as stated in Sub- Except as stated in Sub-
Clause 9.4 [Failure to Pass Clause 9.4 [Failure to Pass Clause 9.4 [Failure to Pass
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
26
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
The Works have been The Works have been The Works have been
completed in completed in completed in
accordance with the accordance with the accordance with the
Contract, including the Contract, including the Contract, including the
matters described in matters described in matters described in
Sub Clause 8.2 [Time for Sub Clause 8.2 [Time for Sub Clause 8.2 [Time for
Completion] and except Completion] and except Completion] and except
as allowed in as allowed in as allowed in
subparagraph (a) below, subparagraph (a) below, subparagraph (a) below,
and and and
The Contractor may apply The Contractor may apply The Contractor may apply
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
27
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
The Engineer shall, within The Engineer shall, within The Engineer shall, within
28 days after receiving the 28 days after receiving the 28 days after receiving the
Contractor’s application: Contractor’s application: Contractor’s application:
28
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
29
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
If the Engineer fails either If the Engineer fails either If the Engineer fails either
to issue the Taking-Over to issue the Taking-Over to issue the Taking-Over
Certificate or to reject the Certificate or to reject the Certificate or to reject the
Contractor’s application Contractor’s application Contractor’s application
within the period of 28 within the period of 28 within the period of 28
days, and if the Works or days, and if the Works or days, and if the Works or
Section(as the case may Section(as the case may Section(as the case may
be) are substantially in be) are substantially in be) are substantially in
accordance with the accordance with the accordance with the
Contract, the Taking-Over Contract, the Taking-Over Contract, the Taking-Over
Certificate shall be Certificate shall be Certificate shall be
deemed to have been deemed to have been deemed to have been
issued on the last day of issued on the last day of issued on the last day of
that period. that period. that period.
The Engineer may, at the The Engineer may, at the Parts of the Works (other
sole discretion of the sole discretion of the than Sections) shall not be
Employer, issue a Taking- Employer, issue a Taking- taken over or used by the
30
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Over Certificate for any Over Certificate for any Employer, except as may
part of the Permanent part of the Permanent be stated in the Contract
Works. Works. or as may be agreed by
both Parties.
The Employer shall not use The Employer shall not use
any part of the Works(other any part of the Works(other
than as a temporary than as a temporary
measure which is either measure which is either
specified in the Contract or specified in the Contract or
agreed by both Parties) agreed by both Parties)
unless and until the unless and until the
31
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
After the Engineer has issued After the Engineer has issued
a Taking-Over Certificate a Taking-Over Certificate
for a part of the Works, for a part of the Works,
the Contractor shall be the Contractor shall be
given the earliest given the earliest
opportunity to take such opportunity to take such
steps as may be necessary steps as may be necessary
to carry out any to carry out any
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
32
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
33
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Important Notes:
1) This information has been prepared by CNC as a general guide only and does not constitute advice on any
specific matter. We recommend that you seek professional advice before taking action. No liability can be
accepted by us for any action taken or not taken as a result of this information.
2) The materials on this Web site may not reflect the most current legal developments, verdicts or settlements and
should not be considered an indication of future results.
34