Вы находитесь на странице: 1из 16

Navigazione Montanari Spa

M/t Valrossa
Main characteristics:
Chemical/Oil tanker
Date of built: Dec 2007
DWT = 50633 t
Lbp = 174.00 m ; B = 32.20 m ; D = 19.10 m

Work list

Code Work description Notes

1 Dry-dock Docking and undocking Arrangement of keel blocks is included in docking prices.
2 Dry-dock Dry-dock due: first and last day
3 Dry-dock Dry-dock due: second and following days or part thereof
4 Dry-dock Extrashoring and dockblock removal (per block)
5 Wharf Wharfage due (per day)
6 Tug Tug service (per shifting or, if not possible, per tug/hour)
7 Pilot Pilotage (per shifting)
8 Riggers Rigging (per shifting)
9 Gangway Gangway arrangement and afterwards removal including transport and hire.
10 Firewatchman Firewatchman (per man/day)
ISPS code
11 ISPS application Per day of vessel stay at Yard
application
12 Gas free Gas free certificate: first certificate
13 Gas free Gas free certificates: each additional survey onboard (please, specify frequency)
14 Hot work permit Hot work permit, each

15 Shore power supply AC electric power connection and disconnection

16 Shore power supply AC (440V, 60hz) electric power supply per kW

17 Potable water Potable water connection and disconnection


18 Potable water Potable water supply (per ton)
19 Fire fighting Sea water for fire fighting: connection and disconnection
20 Fire fighting Sea water supply for fire fighting (per day)

M/t Valrossa
Rev0 - 14/12/2017 1
Work list

Code Work description Notes

21 Cooling water Sea water for cooling sytems: connection and disconnection
22 Cooling water Sea water for cooling sytems and maintaining under pressure (per day)
23 Ballasting Ballast water connection and disconnection
24 Ballasting Ballasting (per ton)
25 Telephone Telephone to be provided on board (per set)
26 Compressed air Compressed air connection and disconnection (per hose)
27 Compressed air Compressed air supply (per day/hose)
28 Crane use Crane for Owner use (per hour) Usage note to be signed by OR after each use.
29 Cherry pickers Cherry picker for Owner use, operator included (per hour)
3
Staging erection/ removal (per location and per m )
30 Staging
NOTE: please specify different quotation if any (externally, ER, inside tank, etc)
NOTE: Cleaning and waste disposal after completion of Yard works is
31 Cleaning Cleaning operation in areas not involved by Yard repair works.
included in the repair prices.
32 Cleaning HFO / MGO tanks cleaning. Quotation requested as reference, item not confirmed.
33 Garbage Owner garbage disposal (it is intended material extraneous to the repair works). To be quoted per per m³.
34 Deslopping Slop water disposal (per m3)
35 Bilge water Oily bilge water disposal (per m3)
36 Sludge Sludge disposal (per m3)
37 Sewage Sewage disposal (Connection/ Disconnection)
38 Sewage Sewage disposal (per m3)
39 Overtime Overtime (per man/hour)
Temporary lighting for owner use (per location/day)
40 Temporary lighting
NOTE: please specify different quotation if any (ER, inside cargo tank, inside double bottm, etc)
Temporary Temporary ventilation for owner use (per location/day)
41
ventilation NOTE: please specify different quotation if any (ER, inside cargo tank, inside double bottom, etc)
42 Paint bin Paints bin disposal after use (per bin)
Opening of both chain lockers, bottom gratings removal, hand scraping of mud & loose scale, HPFW Owner paint supply.
43 Chain lockers
washing, one coat painting and closing of manholes with new gaskets. Staging included. Chain locker to be inspected by Class surveyor before closing.
44 Chain lockers Water/mud to be collected and disposed off (please quote per ton).
45 Chain lockers Removal and renewal of chain locker sounding pipe caps (material in SS). Please quote 2 pcs.
46 Bottom drain plugs Bottom drain plugs removal and reinstallation. Leaded gaskets to be replaced (per plug). Chief Officer in charge for marking the plugs to be removed.
47 Hull protection Installation of plugs/extension pipes for deck scuppers and overboard discharges. Per unit.

M/t Valrossa
Rev0 - 14/12/2017 2
Work list

Code Work description Notes

Sea chests to be opened up, grids to be removed, both sea chest and grids to be cleaned and painted as Total: 5 sea chests (no.2 S/C in ER, no.2 S/C for ballast system and
48 Sea chests per paint specifcation (4-coats cycle). Sea chests to be closed back with loacking wire. Staging/cherry no.1 S/C for emergency fire pump)
picker for access included. Please quote per sea chest. Please refer to attached "Hull paint spec".
Opening of strainers covers, cleaning inside surface and filter mesh, mechanical cleaning of filter body
49 Sea chests filters Job to be confirmed by OR.
and application of O/S paint, fitting of covers back with new gaskets. Per unit.
Repair of the filter body with inserts, painting with pure epoxy (Min DFT 200µm).
50 Sea chests filters Job to be confirmed by OR after inspection.
Mobilization included, if needed.
Total 11 Aluminum anodes, 10 kg each, bolted type.
Sea chests (2 ER SW P/Ps, 2 Ballast P/Ps, 1 EM fire P/P) anodes supply and replacement.
51 Anodes Please see the attached drawing "Sea chests anodes".
Staging/cherry picker for access included.
To quote per kg.
2
52 Hull cleaning Hull HP (please specify pressure) fresh water hosing (per m )
2
53 Hull cleaning Washing down with LP fresh water (per m )
54 Hull cleaning Washing down with HS Cleaner and consequently with fresh water (per m2)
55 Hull cleaning Removal of oil and grease stains by chemical cleaning (per m2)
56 Hull cleaning Hand scraping (per m2)
57 Hull cleaning Hard scraping (per m2)
58 Hull cleaning Power tooling ST2 (per m2)
59 Hull cleaning Power tooling ST3 (per m2)
60 Hull cleaning Sweeping on hull (per m2)
61 Hull blasting Hull abrasive SPOT blasting to SA 2 (per m2)
62 Hull blasting Hull abrasive SPOT blasting to SA 2.5 (per m2)
63 Hull blasting Hull abrasive blasting to SA 1 (per m2)
64 Hull blasting Hull abrasive blasting to SA 2 (per m2)
65 Hull blasting Hull abrasive blasting to SA 2.5 (per m2)
66 Hull painting Touch-up painting (per m2) - Conventional paint
67 Hull painting Touch-up painting (per m2) - Silicone paint
68 Hull painting Full coat painting (per m2) - Conventional paint
69 Hull painting Full coat painting (per m2) - Silicone paint
Extra precaution and preparation cost for the silicone based paint:
- LPWJ washing of accommodation decks and main deck with fresh water;
Preparation for - LPWJ washing of the dock's main deck and upper decks with fresh water; Please refer to the attached document "Maintenance and Repair of
70
silicone paint - Protection of ICCP and zinc anodes, transducers, stern tube during blasting and coating; SigmaGlide" for the detailed guidelines for silicon paint application.
- Masking with suitable materials all adjacent areas that may be exposed to silcin paint overspray;
- Full cleaning of the painting pumps after application of silicon paint.

M/t Valrossa
Rev0 - 14/12/2017 3
Work list

Code Work description Notes

71 Hull painting Total surface of the flat bottom (m2): 4024 4024
72 Hull painting Total surface of the vertical sides (m2): 5386 3086
73 Hull painting Total surface of fenders area (m2): 1700
74 Hull painting Total surface of bow area (m2): 600
75 Hull painting Total surface of the top sides (m2): 2738 2738
76 High pressure fresh water washing Please refer to attached "Hull paint spec".
77 Top sides Hull abrasive SPOT blasting to SA2 (per m2) - Topside 20%
Hull abrasive SPOT blasting to SA1 (per m2) - Topside 5%
78 2738 Washing down with low pressure fresh water
79 m2 2 x T/U painting by air-less spray on blasted areas
80 1 x F/C painting by air-less spray
81 High pressure fresh water washing (max 150 bar) Please refer to attached "Hull Paint Spec".
82 Fenders area Hull abrasive FULL blasting to SA2 (per m2) - Fenders area (ex silicone scheme)
83 1700 Feathering the boundary by power tooling
84 m2 Washing down with low pressure fresh water
85 2 x F/C painting by air-less spray
86 2 x F/C painting by air-less spray - Silicone paint
87 High pressure fresh water washing (max 150 bar) Please refer to attached "Hull Paint Spec".
88 Bow area Hull abrasive FULL blasting to SA2 (per m2) - Bow area (ex silicone scheme)
89 600 Feathering the boundary by power tooling
90 m2 Washing down with low pressure fresh water
91 2 x F/C painting by air-less spray
92 2 x F/C painting by aire-less spray - Silicone paint
93 High pressure fresh water washing (max 150 bar) Please refer to attached "Hull Paint Spec".
94 Vertical sides Power tooling on damaged spot areas to St-3 and feathering the edges 7%
95 3086 Cleaning the areas subjects to epoxy paint application with alkaline cleaner (HS Cleaner O/S)
96 m2 Fresh water washing (max 150 bar)
97 2 x T/U painting by air-less spray See % treated by power tooling.
98 2 x T/U painting by air-less spray - Silicone paint See % treated by power tooling.
99 High pressure fresh water washing (max 150 bar) Please refer to attached "Hull Paint Spec".

M/t Valrossa
Rev0 - 14/12/2017 4
Work list

Code Work description Notes

100 Flat bottom Power tooling on damaged spot areas to St-3 and feathering the edges 15%
101 4024 Cleaning the areas subjects to epoxy paint application with alkaline cleaner (HS Cleaner O/S)
102 m2 Fresh water washing (max 150 bar)
103 2 x T/U painting by aire-less spray - Conventional paint See % treated by power tooling.
104 2 x T/U painting by aire-less spray - Silicone paint See % treated by power tooling.
105 Hull painting Separation line on shell paints to be properly marked.
Ship name and Port of regisrty to be painted with one (1) coat of paint.
106 Hull painting Ship name: fore P&S and aft transom;
Port of registry: aft transom
Draft marks and Plimsoll marks to be painted with one (1) coat of paint
107 Hull painting Draft marks: fore P&S, amidship P&S, aft P&S and transom;
Freebord marks: amidship P&S;
108 Hull painting Bulbous, bulkheads, pilot, tugs and manifolds marks to be painted with one (1) coat of paint
Fabrication and fitting of drip trays with Mild Steel flat bar dim 100x10mm for spill containments (per
109 Drip trays Work to be confirmed and marked by OR.
running m)
110 LO storage tank Enlargement of drip tray in Engine Room in order to include the space below level gauge. Work to be marked by OR.
111 LO vents on deck Insert of oil tanks vents container walls on poop deck, starboard side. Work to be marked by OR.
112 Light steel works Light steel work price list.
113 Manifold support Renewal of corroded support for manifold no.1 Port. Work to be marked by OR.
Hydraulic pipes Replacement of corroded flat bar suppors for electric cables and hydraulic hoses. Work to be marked by OR after inspection.
114
supports Pipes disconnection and installation to be done by Ship staff. Please quote per pc.
115 Pilot ladders Cutting and renewal of pilot ladders stanchions pins. Please quote 8pcs.

116 Garbage containers Building of containers for garbage and installation on board. Capacity 1m3.

Steel work price list. Estimated: 5 tons (mainly affecting side shell)
117 Steel work
Please specify if any minimum weight is considered. Works on side shell should be completed before any paint application.
Please quote for treatment of new steel up to SA2 or ST2 and coating as per Spec of O/S paint.
118 New steel treatment New welding seams to be properly grinded and strip coat to be applied.
Access, ventilation, lighting and cleaning included.
Renewal of the portside chain locker forward bulkhead iwo bitter end (upper deck). Job to be marked by OR, Estimated 300kg
119 Portside chain locker
Disconnection and reconnection of anchor chain. See the attached "Forebody construction".
120 Piping work Piping work price list
121 Piping work Stainless steel piping price list.
SUS 316L, SCH80, DN40, estimated 15m
122 Dump valve line Renewal of portside dump valve line located in the upper stool and WBT 6P.
Job to be marked by OR,

M/t Valrossa
Rev0 - 14/12/2017 5
Work list

Code Work description Notes

Non-destructive testing on inserts welding seams.


123 NDT
Please quote for radiographic inspection, UTM, Vacuum test, dye penetrate test.
124 Pitting repair Repair of pitting in ballast and cargo tanks by welding build up and grinding.
125 Welding seams Gauging and welding the corroded seams on hull. Work to be confirmed and marked by OR after inspection.
126 Handrail Renewal of handrail: round bars and stanchions (Per m) Work to be confirmed and marked by OR after inspection.
127 Aft mast Renewal of round bar on the aft mast. Staging erection included. Work to be marked by OR after inspection.
128 Cabinets on deck Repair of cabinets doors by building new gasket groove. Work to be confirmed and marked by OR after inspection.
129 Central catwalk Repair cracks in the connection to accommodation platform and welding additional stiffener.
Cargo tanks Renewal of tank cleaning hatch cover (with only one fixed handle), surface preparation as per SA2 and Please refer to the attached "Tank cleaning hatch".
130
port holes application of Interline 704, dft 250 µm. Installation back with new O/S gaskets. Please quote 26pcs.
Cargo tanks Dismantling of tank cleaning hatch cover, cutting old handles, installation of one fixed handle, SA2 surface **This item is alternative to the item above**
131
port holes preparation and application of Interline 704, dft 250 µm. Installation back with O/S gaskets. Please quote 26pcs.
132 Hatches Drilling and renewal of broken stud bolts. Please quote per pc.
133 Ballast tanks Ballast tank internal access ladder replacement. (Per m) Work to be confirmed and marked by OR after inspection.
Replacement of heavy corroded/missing safety bars iwo lightening holes on stringers.
134 Ballast tanks Work to be confirmed and marked by OR after inspection.
No.3 bars for each passage. Bar section: 19x19mm
135 Ballast tanks Renewal of sounding and cable pipes/bars. Work to be confirmed and marked by OR after inspection.

136 High pressure fresh water jet - Not less than 340 bar (per m2)

137 Washing down with low pressure fresh water (per m2)
138 Hammering (per m2)
139 Power tooling ST2 (per m2)
140 Ballast tanks Sweeping on hull (per m2)
treatment
141 Hull abrasive blasting to SA 2.5 (per m2)
142 Stripe coating (per m2)
143 Touch-up painting (per m2)
144 Full coat painting (per m2)
145 Dehumidifiers use during treatment.
Steel renewal should be completed before surface preparation and coating
Treatment of water ballast tanks according to the following surface preparation:
operations.
- SP1 iwo WBT 6P, longitudinal bulkhead, fr. 40-44 from deck to 3rd stringer (ONLY in this area
Ballast tanks All steps of surface preparation will be inspected and approved by OR and
146 Intershield 300 paint to be applied), estimated 40m2;
treatment Paint representative.
- SP3 iwo WBT 1P & S, 1st stringer;
Please refer to attached doc "WBT treatment Spec" and "Guidelines for
- SP3 iwo WBT 6P & S, 3rd stringer.
Interbond 808" for the procedures and curing times.

M/t Valrossa
Rev0 - 14/12/2017 6
Work list

Code Work description Notes

Ballast tank cleaning by collecting mud and loose scales, including lighting and ventilation.
147 Ballast tanks ***Quotation requested only for reference***
Mud weight to be calculated as dry. (Per ton)
148 Ballast tanks Disposal of mud (Per ton). ***Quotation requested only for reference***
Valves inspection: opening-up, seat and disk cleaning and inspection.
149 Valves inspection
Please provide a price list per ND and type, in situ and in workshop.
150 Valves overhaul Valves overhaul: please provide a price list per ND and type, in situ and in workshop.
E/R sea chest suction valve: 2 pcs 10k DN500
Main cooling SW O/B: 10k DN300
Oily water separator O/B: 16k DN40
Scrubber O/B: 10k DN400
Sewage O/B: 5k DN50 (NEW O/S VALVE)
Grey water O/B: no. 2 pcs 5k DN100 (NEW O/S VALVE)
Boiler blow-down O/B: 16k DN40
Valves inspection: opening-up, seat and disk cleaning and inspection.
Bilge, fire and GS pump O/B: 10k DN200
151 Side shell valves Inspection to be done in presence of Class surveyor.
FW generator O/B: 10k DN100
Job to be confirmed by OR after Class inspection.
EM fire pump suction valve: 10k DN100
Ballast suction valve: no. 2 pcs 10k DN350
Ballast O/B: no. 2 pcs 5k DN300
ODME O/B: 16k DN125
Annex II O/B: 16k DN200
Deck seal O/B: 10k DN80
Draft sensors: no. 4 pcs 10k DN80
Ballast tank disc float type pipe air vent to be opened-up and cleaned for internal inspection, gasket and
152 Vent pipes Job to be confirmed by OR after Class inspection.
packing replacement. Please quote per unit and ND.
153 Vent pipes Air vents covers renewal. Installation back with new bolts and flame screen. Job to be confirmed by OR.
154 Sounding pipes Machining and renewal of sounding pipe thread. Job to be marked by OR.
Cargo Tanks P/V valves
Removal, transfering to workshop, maintenance by dismounting, seats lapping and grinding, replacement 12 pcs DN100
155 P/V valves of seal rings, gaskets, flame screen and distance washers. Maker: SE-WON , type: HPV-4
Setting test (pressure 20kPa, vacuum -3,5 kPa) withnessed by Class Surveyor. Pressure test certificate to be provided
Fitting back in place.
Slop Tanks P/V valves
Removal, transfering to workshop, maintenance by dismounting, seats lapping and grinding, replacement 2 pcs DN80
156 P/V valves of seal rings, gaskets, flame screen and distance washers. Maker: SE-WON , type: HPV-3
Setting test (pressure 20kPa, vacuum -3,5 kPa) withnessed by Class Surveyor. Pressure test certificate to be provided
Fitting back in place.
2 pcs DN100
Spare P/V valves
157 P/V valves Maker: SE-WON , type: HPV-4
Transfering to workshop, Setting test (pressure 10kPa, vacuum -3,5 kPa) withnessed by Class Surveyor.
Pressure test certificate to be provided
158 P/V valves P/V valves vacuum side seats machining. Please quote per unit.

M/t Valrossa
Rev0 - 14/12/2017 7
Work list

Code Work description Notes

Opening the top cover, removing the sight glass and internal cleaning for inspection.
159 P/V Breaker Inspection to be withness by OR.
Application of O/S epoxy paint (2 coats) to be confirmed after inspection.
Opening the top cover, renewal of sight glass and internal cleaning for inspection.
160 Deck seal See the attached dwg "Deck water seal"
Application of high solid content epoxy paint (2 coats) for a total DFT of 300µm.
Dismantling of deck seal, transportation ashore, grit blasting of inside only to SA 2.0, application of O/S
161 Deck seal Job to be confirmed by OR.
epoxy paint, delivering back onboard, refitting in place with new O/S sight glass.
Repair by insert of deck seal body and renewal of branch pipes. See attached dwg "Deck water seal".
162 Deck seal repair
Marking of inserts to be done after blasting. Inspection to be withness by Chief Officer.
Renewal of leaking sections of deck water seal overboard pipe inside the WBT 6S. Pipes to be confirmed and marked by OR.
163 Deck seal O/B
SCH80, DN80, Total lenght = 21.5m See the attached dwg "Inert gas pipeline".
164 IGG cover Inert gas generator cover to be disconnected and pressure tested (3 bar). Test to be withnessed by OR.
165 IGG cooling jacket Inert gas generator cooling jacket to be pressure tested (3 bar). Test to be withnessed by OR.
Inert gas generator COMPLETE cooling jacket replacement: old jacket removal, cleaning and fitting of ***Quotation requested only for reference***
166 IGG cooling jacket
new O/S jacket. Material is SS904L, TIG welding requested. Final pressure test at 3 bars. Please refer to the attached dwg "IG generator"
Inert gas generator NOZZLES cooling jacket replacement: old jacket removal, clening and fitting of new ***Quotation requested only for reference***
167 IGG cooling jacket
O/S jacket. Material is SS904L, TIG welding requested. Final pressure test at 3 bars. Please refer to the attached dwg "IG generator"
Inert gas generator: opening the IGG cover, renewal of pilot burner sleeve with new O/S one. New sleeve See attached drawing "Pilot burner renewal".
168 Inert gas system
must be fitted by internal TIG welding 904L and external TIG welding 316L. Pressure test to be withnessed by Chief Engineer.

169 Inert gas system Inert gas generator: renewal of cooling water pipe for IGG cover. L = 2m Please refer to the attached dwg "IG generator"
3
IG storage tanks (N. 2 tanks, 15 m each) internal inspection and pressure test at 45 bars. Job to be confirmed by OR.
170 Inert gas system
Upper deck inert gas main line non return valve removal, cleaning, inspect and fitt back in place. Pressure test certificate to be provided.
IG fan complete overhaul
Fan to be disassembled, E/M and rotor to be carried to ashore workshop for rotor cleaning, E/M open-up,
E/M power: 65 kW
171 IG fans general clening, windings cleaning and drying, ball bearings renewal.
Fan capacity: 3.375 m3/h
Afterwards E/M reassembly, insulation test. Rotor and E/M to be balanced together.
Balance report to be provided. Please quote per unit.
172 Midship crane Hydraulic hoses replacement. Please quote lumpsum, staging included. 64 pcs hoses
See the attached dwg "Midship crane hydraulic cylinder".
173 Midship crane Hydraulic cylinder seals to be renewed.
Quotation is asked only to have a REFERENCE for the price.
174 Midship crane Hydraulic cylinder piston rod chrome plating. ***Quotation requested only for reference***
Pressure test to be witnessed by Class suveyor and OR.
175 Cargo piping system Cargo main lines on deck, manifolds, cargo pump discharge lines, COW lines hydrotest at 18 bar. Pressure test certificate to be provided.
See the attached dwg "Cargo handling system".
176 Bunker line HFO and Diesel bunker line hydrotest at 5 bar.
Pressure test to be witnessed by Class suveyor and OR.
Cargo heating
177 Steam supply line on deck hydrotest at 10.5 bar Pressure test certificate to be provided.
system
See the attached dwg "Steam & condensate system".

M/t Valrossa
Rev0 - 14/12/2017 8
Work list

Code Work description Notes


Pressure test to be witnessed by Class suveyor and OR.
Cargo heating
178 Condensate return line on deck hydrotest at 3 bar. Pressure test certificate to be provided.
system
See the attached dwg "Steam & condensate system".
Draining the steam side of cargo heater, pressure test by air/nitrogen at 3 bar. Maker: Framo; Type: HE 400/1000
Cargo heating
179 After stopping air/nitrogen supply, pressure should hold for 30 minutes. 12 pcs
system
Boxing back with new gaskets. Job to be confirmed by OR.

Cargo heating
180 Slop tanks heating coils hydrotest at 10.5 bar.
system

Pressure test to be witnessed by Class suveyor and OR.


181 Vapour system Vapour return line on deck pressure test at 0.3 bar by air.
Pressure test certificate to be provided.

182 Fire fighting system Fire line on deck hydrotest at 15 bar.

183 Foam system Foam line on deck hydrotest at 15 bar.


Shell&tubes heat exchanger: 215 tubes, AL-BRASS, D16 x t1 x L2175
Heater to be opened up, tubes to be cleaned and pressure tested with fresh water.
Tank cleaning Pressure test: 16,5 bar shell side, 25,5 bar tube side.
184 Please quote apart drilling for tube stuck (per tube). Zinc anodes renewal.
heaters Job to be confirmed by OR.
Heater cover to be closed with new gaskets.
Pressure test to be confirmed by OR after inspection.

Rudder clearances to be taken as per Manufacturer recommendations iwo hull bush, neck bearing, pintle.
To be withnessed by Class surveyor and OR.
185 Rudder Removal of rudder bottom plug for inspection and installation back in place.
Clearances readings to be recorded.
Staging/cherry picker for access included.

Removal and refitting of rudder plugs including vacuum testing, recementing and renewal of lead gasket if
186 Rudder Plug removal and test to be done in presence of Class surveyor.
required. Staging included, if needed.

187 Rudder Rudder building up iwo corroded areas and pitting.

Ranging of both anchors and chains in drydock, washing by HPFW jet, calibration and recording of chain
188 Anchor and chains Please provide record in four copies.
wear down, marking of lengths by O/S paint and kenters with white/red paint and restowing back.

189 Chains Loose link studs rewelding (per stud).


190 Chains Supply and welding of new studs. Per stud.
191 Hawse pipe Visual inspection and dye check of hawse pipe guards and rudder skeg in case of any crack. To be done after blasting before paint application with cherry picker.
Dismantling of brake assembly from the winch and transfer to workshop. Blasting and painting of steel
192 Windlasses band, fitting new O/S brake band with brass bolts, reassembling and fitting back after cleaning the drum Work to be confirmed by OR after inspection.
surface properly. Please quote per unit.
Dismantling of brake assembly from the winch and transfer to workshop. Blasting and painting of steel
193 Winches band, fitting new O/S brake band with brass bolts, reassembling and fitting back after cleaning the drum Work to be confirmed by OR after inspection.
surface properly. Please quote per unit.
194 Winches Brake holding capacity test. Please quote per unit Work to be confirmed by OR.

M/t Valrossa
Rev0 - 14/12/2017 9
Work list

Code Work description Notes

Clutches Contact Surfaces: building up of clutches contact surfaces by welding and grinding.
195 Winches Job to be confirmed and marked by OR.
Please quote per unit.
Cleaning of both windlasses barbotin and building up of worn out surfaces by welding and grinding. Final
196 Mooring equipment
coating with epoxy paint (DFT 200 μm).

197 Chain stopper Bow chain stopper to be permanently marked by welding its certificate number. Job to be marked by OR.

198 Major requirements Mooring equipments to be pemanently marked by welding the SWL. Please quote per equipment. Job to be confirmed and marked by OR.

199 Major requirements Chain blocks and sling wires to be tested at SWL, certificate to be issued. Please quote per pc.

Lenght: 17.0m
200 Portable gangway Construction of new portable gangway with Class approved design. Static load test included.
Please see attached dwg "Wharf ladder".

201 Portable gangway Installation of additional support on deck for proper and safe storage of new gangway. Location of new supports to be marked by OR.

Accommodation Ladders overload test (6 x 75 kg): 2pcs accommodation ladders, 1 pc portable gangway. To be witnessed by OR and Class surveyor and load test certificate to be
202
ladders test Transfer of portable ladder ashore included (if needed). Please quote per unit. issued for each ladders.
Overload test of the following:
- Midship cargo hoses handling crane - Test load: 12,5 t To be witnessed bt Class surveyor.
203 Cranes overload test
- Provision crane - Test load: 3,75 t Test certificate to be issued for each crane.
- E/R overhead crane - Test load: 3,125 t
Lowering the lifeboats (P&S) and recovering them in convenient position for easy access and work. Fitting
204 Lifeboats Job to be done upon arrival of the ship in Yard.
back in place before departure.
205 Lifeboats Dismantiling, overhaul of lifeboats davits pulleys and fitting back. Staging included. Work to be confirmed by OR after inspection.
Repair of the GRP iwo sea side part of forward strong point gripe.
206 Lifeboats See attached dwg "Lifeboat arrangement".
Please quote for both lifeboats, material included.
207 Lifeboats Polishing and painting of both lifeboats with Yard supplied paint. Work to be confirmed by OR.
Overload test with 110% of the full boat weight.
Lifeboat davits Lifeboat and davits (P&S) overload test witnessed by Class surveyor (weight for load test to be supplied by
208 Full boat weight = 5340 kg; Boat weight = 3315 kg; 27persons
overload test shipyard, including movimentation). Please quote for 2 units.
Certificate of overload dynamic test to be provided in four copies.

209 Liferafts embarkation Installation by welding of two pad eyes to secure the embarkation ladder (both sides). Total 4 pcs

210 Accommodation Complete renewal of floor linoleum in Hospital (35m2) and 3rd Engineer cabin (10m2).

211 Accommodation Repair of sofas and armchairs with new leather. Work to be confirmed by OR.

Sewage treatment
212 Repair by insert of the tank wall (stainless steel). Estimated insert 200x200mm.
tank
Rope guard to be removed, cleaned and painted, tailshaft wear down to be taken using vessel gauge,
Gauging to be withnessed by Class surveyor.
213 Tailshaft wear down readings to be recorded and reported. Rope guard to be reinstalled.
Please provide record in four copies
Staging/cherry picker for access included.

M/t Valrossa
Rev0 - 14/12/2017 10
Work list

Code Work description Notes

Normal polishing of propeller by disc grinders and dye penetration test of blade roots and tips. D=6000mm; No. 4 blades
214 Propulsion propeller
Staging/cherry picker included. To be witnessed by Class surveyor and report to be issued.
Silicon paint application as per paint spec. Treatment to be done in the same time as flat bottom. D=6000mm; No. 4 blades
215 Propulsion propeller
Please quote lumpsum. See attached dwg "Propeller paint spec".
Stern tube after and forward seals replacement by Maker's service engineer. Maker: Blohm+Voss
216 Stern tube seals Arrangement of staging and lighting fro easy access. Aft Seal Type : SC 2 M Multisafe – Size: 500
One man assistance to be quoted. Fwd seal type : SC 2 Z – Size: 500
CYLINDER COVER OVERHAUL
Dismantling of cylinder heads, removal to workshop and fitting back upon completion of works.
All subcomponents to be disassembled.
ME WARTSILA
217 Full cleaning, o-rings and gaskets complete renewal. No. 7 units.
7RTA 48T-B
Dye penetration check (in way of injector, starting valve and indicator cock holes) and hydraulic pressure
test.
Please quote per cylinder unit.
CYLINDER COVER COOLING JACKET MAINTENANCE
Dismantling of cylinder head cooling jacket and fitting back upon completion of works.
ME WARTSILA
218 Internal cleaning and o-rings renewal.
7RTA 48T-B
Dye penetration checking and hydraulic pressure test.
Please quote per cylinder unit.
EXHAUST VALVE OVERHAUL
Dismantling and removal to workshop.
ME WARTSILA
219 Cleaning, inspection and clearances taking. Complete overhaul, valve and seat grinding. No. 7 units.
7RTA 48T-B
Dye penetration checking, hydraulic pressure testing.
Please quote per cylinder unit.
STARTING VALVE OVERHAUL
ME WARTSILA Dismantling of the starting air valve on cover, complete overhauling, cleaning, calibration, dye penetration
220 No. 7 units.
7RTA 48T-B checking, reassembling and fitting back.
Please quote per cylinder unit.
SAFETY VALVE OVERHAUL
ME WARTSILA Dismantling of the safety valve on cover, complete overhauling, cleaning, calibration, dye penetration
221 No. 7 units.
7RTA 48T-B checking, reassembling and fitting back.
Please quote per cylinder unit.
INDICATOR COCK
ME WARTSILA
222 Dismantling of the indicator cocks on cover, complete overhauling, cleaning, calibration, dye penetration No. 7 units.
7RTA 48T-B
checking, re-assembling with Owner supplied spares, fitting back.
MAIN SHUT OFF STARTING AIR VALVE
ME WARTSILA Dismantling and removal to workshop, disassembling of all subcomponents including non return valve,
223 Final test to be withnessed by OR.
7RTA 48T-B cleaning all components, replacement of o-rings. tLapping/grinding parts if required.
Overhaul of 3/2-way valve with replacement of o-ring set. Reassembling and fitting back.
STUFFING BOX OVERHAUL
ME WARTSILA Dismantling of stuffing box, removal to workshop and fitting back upon completion of works.
224 ***Quotation requested only for reference***
7RTA 48T-B Cleaning, calibration, spring and lamellas replacement.
Renewal of rings. Please quote per cylinder unit.

M/t Valrossa
Rev0 - 14/12/2017 11
Work list

Code Work description Notes


PISTON OVERHAUL
Withdrawal of piston, removal to workshop and fitting back upon completion of works.
ME WARTSILA
225 Carbon deposits removal and cleaning; piston ring grooves measurement and rings renewal. ***Quotation requested only for reference***
7RTA 48T-B
Measurement and reporting as per Manufacturer recommendations.
Please quote per cylinder unit.
PISTON OPENING
ME WARTSILA Disassembling of head, skirt and rod, cleaning, calibration, dye penetration checking.
226 ***Quotation requested only for reference***
7RTA 48T-B O-rings replacement, hydraulic pressure testing at 7 Bar, reassembling.
Please quote per unit.
ME WARTSILA
227 Piston rod chrome plating. ***Quotation requested only for reference***
7RTA 48T-B
CYLINDER LINER INSPECTION
ME WARTSILA Cylinder liner cleaning and inspection.
228 ***Quotation requested only for reference***
7RTA 48T-B Measurement of cylinder diameter to be taken and reported.
Please quote per cylinder unit.
CYLINDER LINER OVERHAUL
Removal of lubricators from cylinder liner, withdrawal of cylinder liner, cleaning the cylinder frame
ME WARTSILA
229 internally. Cleaning cooling surfaces of liner, calibration, o-rings renewal, fitting back. ***Quotation requested only for reference***
7RTA 48T-B
Reftiing of lubricators in the cylinder liner.
Please quote per unit.
CYLINDER LUBRICATORS
ME WARTSILA Dismantling, cleaning of lubricators, check of non-return valves functionality by compressed air.
230 No. 7 units.
7RTA 48T-B Replacement of diaphram and o-rings (12 lubricators for each unit).
Please quote per cylinder unit.
FUEL INJECTION PUMP
Dismantling of pump block from intermediate frame and transport to workshop.
Disassembling of all subcomponents, cleaning and inspection.
ME WARTSILA
231 Replacement of valves and lapping to the seat (suction, delivery, spill, relief), replace plunger and bush. No. 7 units (3pcs two-pumps block + 1pc single pump block)
7RTA 48T-B
Lapping of valves cover sealing faces on top of the pump block (3 pcs per unit).
Reassembling all components and fitting back in place.
Please quote per cylinder unit.
FUEL INJECTION PUMP SAFETY CUT-OUT DEVICE
ME WARTSILA
232 Removal, overhauling by replacing o-ring and seal. Operational test and fitting back. No. 7 units.
7RTA 48T-B
Please quote per unit.
ME WARTSILA TIMING
233 Record to be issued.
7RTA 48T-B Verification and adjustment of pumps timing according to Maker table.
ME WARTSILA
234 Checking and tightening of cylinder studs, tie rods, holding down bolts as per Manufacturer's instructions.
7RTA 48T-B
BEARINGS INSPECTION
ME WARTSILA
235 Main bearing, crankpin bearing and cross-head bearing inspection. No. of units to be decided in accordance with Class Surveyor.
7RTA 48T-B
Please quote per cylinder unit.

M/t Valrossa
Rev0 - 14/12/2017 12
Work list

Code Work description Notes

ME WARTSILA
236 Main engine bearings clearances measuremnt by filler gauge.
7RTA 48T-B
ME WARTSILA THRUST BEARING INSPECTION
237
7RTA 48T-B Opening of thrust bearing covers, measurement of clearances, fitting back of covers.
WATER SEPARATOR
ME WARTSILA
238 Removal and transportation to workshop, cleaning with HP water or chemicals.
7RTA 48T-B
Fitting back in place.
CHARGED AIR COOLER
ME WARTSILA
239 Removal and transportation to workshop, cleaning with HP water or chemicals to remove foulings. ***Quotation requested only for reference***
7RTA 48T-B
Pressure test (water side), gasket replacement and fitting back.
STARTING AIR DISTRIBUTOR OVERHAUL
ME WARTSILA
240 Opening, cleaning and inspectionof air distributor. Overhauling of pneumatic control valves by replacing o- ***Quotation requested only for reference***
7RTA 48T-B
rings and seals.
ME WARTSILA
241 Replacement of M/E camshaft vibration damper with new O/S.
7RTA 48T-B
MEASUREMENT
ME WARTSILA Deflections before and after overhaul to be taken;
242
7RTA 48T-B Main, crankpin, crosshead bearings clearances to be taken and reported;
Crosshead guide clearances to be taken and reported.
ME WARTSILA FUNCTIONING TEST
243
7RTA 48T-B Sea trial to be carried out, functioning parameters to be taken and reported.
Intermediate shaft Removal of temperature sensor, opening of intermediate shaft bearing upper cap, sliding out lower
244 Diam: 395mm
bearing bearing shells, cleaning and inspection, recording of clearances and re-closing.
E/M complete overhaul
Disassembling the fan, transfer E/M and rotor to ashore workshop for rotor cleaning and E/M opening-up,
245 M/E Electric Blower general cleaning, windings cleaning and drying, renewal of ball bearings . Report to be provided.
Reassembling of E/M and insulation test. Balancing of rotor and e/m together.
Please quote per unit.
DG YANMAR
246 Starting air motor overhaul. No. 3 units.
6N21(A)L-EV
DG YANMAR MAIN BEARING (no.7 pcs bearings for each D/G)
247 No. 21 units.
6N21(A)L-EV Replacement of all main bearing. Deflections mesurement before and after bearings installation.
DG YANMAR LUBE OIL COOLER ***Quotation requested only for reference***
248
6N21(A)L-EV Lube oil cooler to be dismantled, opened up, cleaned, inspected and closed. No. 3 units.
AIR COOLER
DG YANMAR
249 Removal of air coolers to workshop, cleaning by Ultrasonic system, pressure test (water side); gasket No. 3 units.
6N21(A)L-EV
replacement. Please quote per air cooler.
D/G TURBOCHARGER No. 3 units.
DG YANMAR Dismantling, cleaning, inspection, of cartdridge. Nozzle ring and bearings renewal. Maker: ISHIKAWAJIMA
250
6N21(A)L-EV Measurement of clearances, balancing and reassembling. TYPE : IHI RH183
Please quote per T/C. Spare parts supplied by Owner.

M/t Valrossa
Rev0 - 14/12/2017 13
Work list

Code Work description Notes


Governor YANMAR No. 3 units.
DG YANMAR
251 Standard overhauling and adjusting of governor by specialist incl. supply standard overhaul kit and Maker: Yanmar
6N21(A)L-EV
attendance to trials. Model: NZ61
252 Sparks arrestor Main engine exhaust gas sparks arrestor renewal. Staging erection included. DN1000
Aux boiler AALBORG MISSION OL 18000
Opening of fire and water side manholes, cleaning by HPFW jet, disposal of accumulated water and
253 Aux boiler Height: 8314; Diameter: 3220
reclosing of manholes with new gaskets.
Capacity: 18 t/h; Working pressure: 7 bar
Opening of smoke side manholes, cleaning by HPFW jet, disposal of accumulated water and reclosing of Economizer AALBORG XW 1200
254 Economizer manholes with new gaskets. Height: 5.000; Length: 2.627; Width: 1.007
Pressure test at 10 bar to be carried out. Capacity: 1,2 t/h; Working pressure: 7 bar
Aux boiler and exhaust gas boiler safety valves (n. 2 valves DN 65/100 PN 40/16 and n. 2 valves DN
Test to be withnessed by Class surveyor.
255 Boilers safety valves 32/50 PN 40/16) removal, disassembly and overhaul.
Pressure test certificates to be provided.
Pressure test at designed pressure in presence of Class surveyor.
Opening of no.1pc Boiler main steam valve DN250 and 1pc economizer stop valve DN40, dismantling in
256 Boilers valves
situ for cleaning, disc and seat inspection, boxing back.
Replacement of boiler exhaust gas expansion bellow with new O/S. DN800; EX5-2 under C-deck
257 Aux boiler
Staging erection included. See the attached dwg "Gas piping in ER"
Replacement of both inlet and oulet expansion bellows with new O/S. DN1000; EX1-6 under C-deck and EX1-5 under B-deck
258 Economizer
Staging erection included. See the attached dwg "Gas piping in ER"
Combustion air fan E/M complete overhaul. Air flow: 21680 m3/h
Fan to be disassembled, E/M and rotor to be moved to ashore workshop for rotor cleaning and E/M open- E/M Maker: Hoyer
Aux boiler
259 up, general clening, windings cleaning and drying, ball bearings renewal. E/M Type: Y2E2 250 M-2
combustion air fan
Insulation test to be done. Balancing of rotor and E/M together. Balance report to be provided. Power: 62 kW, 3x440V, 60hz
Please quote for 1 unit. Revolutions: 3564 rpm
Atmospheric condenser to be opened up, tubes to be cleaned and pressure tested. Shell&tubes heat exchanger with n. 267 tubes in AL-BRASS
Atmospheric
260 Please quote also apart drilling for tube stuck (per tube). Zinc anodes renewal. Diam=10mm; t=1,0mm; L=1000mm
condenser
Condenser to be closed with new Y/S gaskets. Pressure test: 16 bar shell side, 16 bar tube side.
Atmospheric
261 Clean-thoroughly badly chocked tubes. Per drilled tubes.
condenser
262 Incinerator Renewal of refractory in the furnace. Quote per m2. ***Quotation requested only for reference***
Pressure test of branch pipes (starting air pipe at 45 bar and steam pipe 10,5 bar).
Tests to be done in presence of Class surveyor.
263 Pressure test Branch pipe in ER to be dismantled and carried to the shipyard workshop for being pressure tested at the
Pressure test certicate to be provided in four copies.
presence of Class Surveyor. Please quote per pipe and DN.
.
Air bottles safety valves (n.2) dismantling, opening-up, cleaning and pressure test at 33 bar. Pressure test certicate to be provided in four copies.
264 Safety valves in ER
Air compressor safety valves (n.2) pressure test at 30 bar. Test to be witnessed by Class surveyor.
Shell&tubes heat exchanger - No. 20 tubes
Starting air Removal of air intercooler to workshop, ultrasonic & chemical cleaning and washing of both sides, repair
265 Inner Diam=8mm; t=2,0mm; L=400mm
compressor of leaking tubes, pressure testing, closing with new gaskets and fitting back to place upon completion.
Pressure test: 35 bar
Fresh water Dismantling of evaporator, transport to workshop. Maker: Donghwa Entec
266
generator Chemical cleaning and washing of both sides, pressure testing. Refitting back. Tubular type 25tons/day FW generator

M/t Valrossa
Rev0 - 14/12/2017 14
Work list

Code Work description Notes

Maker: Aalweiler AG
Pump to be open up for in situ internal inspection, to allow Class surveyor to assess the condition of the MCSW 600m3/hx22m; 1750 rpm
Centrifugal pump
267 impeller and casing. Please quote per size/unit. Scrubber 330m3/hx40m; 1750 rpm
inspection
TO BE AGREED WITH OR AFTER INSPECTION WITH CLASS. GS Fire 280m3/hx100m; 3500 rpm
Emercency Fire 72 m3/hr x 70m , 3500 rpm
Maker: Aalweiler AG
Pump to be carried to ashore workshop.
MCSW 600m3/hx22m; 1750 rpm
Centrifugal pump Disassembly; cleaning; impeller and shaft inspection; o-rings, wear rings, ball bearings and mechanical
268 Scrubber 330m3/hx40m; 1750 rpm
overhaul seal renewal. Please quote per type/unit.
GS Fire 280m3/hx100m; 3500 rpm
TO BE AGREED WITH OR AFTER INSPECTION WITH CLASS.
Emergency Fire 72 m3/hr x 70m , 3500 rpm
269 MCSW
270 Scrubber
271 Fire & GS
272 Emergency fire pump
Maker: Svend Hoyer A/S
Electric motor to be removed from position and carried to ashore workshop.
MCSW 64 kW
Electric motor Disassembly, general cleaning, winding cleaning and drying, ball bearings renewal, insulation check. Ball
273 Scrubber 64 kW
overhaul bearings supplied by Owner.
GS Fire 128 kW
Please quote per size/unit.
Emergency Fire 35 kW
274 MCSW
275 Scrubber
276 Fire & GS
277 Emergency fire pump
Disconnecting and removing top half of casing, releasing shaft coupling from motor drive, slinging and
Maker: Allweiler AG; Type: Melo 200-2 L 1850-W202
ME LO pump removing impeller, shaft and wear rings. Withdrawing impeller, shaft sleeve and bearings from shaft,
278 Capacity: 135 m3/h; Rotation: 1740 RPM
(workshop) cleaning all exposed parts, calibrating and reporting. Reassembling and fitting back.
See the attached dwg "ME LO Pump MELO 200"
No.2 units.
Disconnecting and removing top half of casing, releasing shaft coupling from motor drive. Maker: Allweiler AG; Type: Melo 200-2 L 1850-W202
ME LO pump
279 Replacement of ball bearings and oil seal. Reassembling and fitting back. Capacity: 135 m3/h; Rotation: 1740 RPM
(in situ)
No.2 units. See the attached dwg "ME LO Pump MELO 200"
Electric motor to be removed from position and carried to ashore workshop. Maker: Svend Hoyer
ME LO pump electric
280 Disassembly, general cleaning, winding cleaning and drying, ball bearings renewal, insulation check. Power: 87.3 kW; Revolution: 1750 rpm
motors
Please quote per unit. No.2 units
Pipes renewal of E/R sea water discharge line: Schedule 80, galvanized. Please refer to the attached drawing "Cooling SW & service system".
281 E/R SW line
Estimated pipes: 50m Pipes to be confirmed by OR after inspection.
DN25, Estimated lenght: 40m
282 Deck seal SW line Renewal of deck seal sea water pipeline: Schedule 40, galvanized.
Pipes to be confirmed by OR after inspection.
Length: 2m x DN200 + 1m x DN125
283 Scrubber SW line Renewal of scrubber pump discharge line: Schedule 80, galvanized.
Pipes to be confirmed by OR after inspection.

M/t Valrossa
Rev0 - 14/12/2017 15
Work list

Code Work description Notes


Electric motor to be removed from position and carried to ashore workshop. Maker: ABB
284 Framo HPP Disassembly, general cleaning, winding cleaning and drying, ball bearings renewal, insulation check. Power: 420 kW; Revolution: 1787 rpm
Please quote per unit. No.4 units
Dismantling the monitors and transportation to workshop for overhaul.
285 Foam monitors Machining of basements surfaces and sleeves, bearings and o-rings replacement. Please see attached drawing "Deck foam monitor"
Please quote per unit.
Vacuum cleaning, washing and cleaning of all switch gear, cable connections etc. with electro cleaner and
286 Main Switchboard
retighten of any loose connections.
287 Main Switchboard Volt, Ampere and Kwatt meters calibration. Please quote per type and unit.
Emergency Vacuum cleaning, washing and cleaning of all switch gear, cable connections etc. with electro cleaner and
288
Switchboard retighten of any loose connections.
N. 3 DG ACBs control and cleaning as per manufacturer recommendations.
Air circuit breaker:
N. 1 BT ACB control and cleaning as per manufacturer recommendations.
N. 3 ACE MEC LBA-16,3P, AC 450 V (Generators Braker)
N.1 BUS TIE ACB control and cleaning as per manufacturer recommendations.
289 DG ACBs N. 1 ACE MEC LBA-25,3P, AC 450 V (Bus -TIE) N
ACB removal, opening-up, cleaning, checking of connections and contacts, tests of reverse power, over
1 ACE MEC LBA-06,3P, AC 450 V (feeder for em'cy switchboard)
current under voltage in workshop and calibration (trip setting check).
Functional test onboard.

290 Magnetic compass Magnetic compass adjustment during sea trials. Deviation card to be issued.

M/t Valrossa
Rev0 - 14/12/2017 16

Вам также может понравиться