ARAKAWA CO,.

LTD
BELLEVUE APARTMENT PROJECT

DEMARCATION OF WORK (ARAKAWA / SUB-CONS)


FIRE OTHERS /
NO. WORK ITEM BUILDERS ACMV ELECTRICAL PLUMBING REMARKS
PROTEC'N LIFT
1. Plinth
a) Information (with Shop Drawing) O O O O O Location, size, weight
b) Setting out (marking on site) O
c) Formwork, reinforcement & finish work O
d) Check for dimension & position O O O O O
e) Reinforcement to structure O If require.

2. Opening & sleeves to beam, wall, floor for M & E Services.


a) Information (with Shop Drawing) O O O O O
b) Formwork and reinforcement of openings O
c) Setting out of opening(marking on site) O O O O O O Sleeves by subcon, opening
d) Reinforcement of structure. O by main con.
e) Installation of sleeves with reinforcement bar. O O O O O
f) Hacking and making good to opening O O O O O If the reason is due to the
g). Check to confirm opening size and location. O O O O O sub-contractor

3. Filling to opening & sleeves


a) Back filling (fire barrier, concrete or mortar) O O O O O
to opening and sleeves through walls & floor slab.

4. Machine hatch & hook for equipment delivery and Maintenance


a) Temporary opening to structure wall and O If require.
slab for equipment delivery and handling
b) Information for dimension, position, weight & quantity. O O O O O
c) Installation of temporary hook for machine & O
equipment handling
d) Maintenance hatch and access door. O

5. Hoisting of special heavy equipment. Sub-contractor must follow


a) Hoisting sub-contractor's special heavy O O O O O Arakawa's instruction on the
machinery/Large equipment. usage of facilities avaiable
b). Usage of main contractor hoisting facilities O at site & should inform detail
if load permitted. of hoisting heavy equipment
c). Reinforcement of structure & handling platform if require. O during tender stage. Submit

Arakawa Co,. Ltd Page 1 of 7 F 001, Demarcation of Work.xls


ARAKAWA CO,. LTD
BELLEVUE APARTMENT PROJECT

DEMARCATION OF WORK (ARAKAWA / SUB-CONS)


FIRE OTHERS /
NO. WORK ITEM BUILDERS ACMV ELECTRICAL PLUMBING REMARKS
PROTEC'N LIFT
d). Handling of equipment O O O O O the planing method which
e). Container, hoisting belt/chain for lifting O O O O O include storage, delivery schedule
f). Horizontal movement O O O O O & access within 3 mth of Arakawa
g). Supervising & safety O O O O O O instruction. Access & Delivery
schedule to be discuss regulary.
6. Preparation for delivery of machine & material, etc.
a) Protection to access (material & labour) O O O O O Sub-con is to ensure that all
b). Clearing of access, relocate main contractor O horizontal movement of the
debris, material and equipment. equipment is in accordance to
c). Clearing of access, relocate M&E contractor O O O O O Arakawa predetermined routes.
debris, material and equipment. Sub-con should get approval
d). Temporary support (material & labour) O O O O O for horizontal movement
e). Preparation of common hoisting platform. O method from Arakawa &
f). Information delivery regarding delivery date and time. O O O O O responsible for protection of
g). Cordination of schedule for hoisting. O the floor surface.

7. Site office, storage & workshop shop area.


a) Area for the above O
b) Site office, storage area, work shop area O O O O O
with general lighting and power points.
c) Furniture (desk, table, chair, etc.) O O O O O
d) Telephone, fax, copy machine O O O O O
e) Accommodation of sub-con staff & workers. O O O O O

8. Temporary lighting, power point & water supply


a) Power distribution board, general lighting & power point. O
b) General water supply points O
c) Consumption cost of power and water O
d) Spot light and extension cable O O O O O
e) Extension water supply point O O O O O Power requirement over 20A
f) Power supply for Welding machine. O O O O O O to be provided by sub-con.

9. Temporary scaffolding Sub-con to ensure proper

Arakawa Co,. Ltd Page 2 of 7 F 001, Demarcation of Work.xls


ARAKAWA CO,. LTD
BELLEVUE APARTMENT PROJECT

DEMARCATION OF WORK (ARAKAWA / SUB-CONS)


FIRE OTHERS /
NO. WORK ITEM BUILDERS ACMV ELECTRICAL PLUMBING REMARKS
PROTEC'N LIFT
a) General scaffolding O usage of scaffolding.
b) Special scaffolding for installation work. O O O O O Modification to be approved
c) Responsibility for safety checking of scafolding O O O O O O by Arakawa

10. Cutting builder's finished work


a) Information of dimension, location & quantity. O O O O O To submit drawing.
b) Cutting of plastered ceiling, ceramic tile, O
marble stone, granite, wall clading.
c). Cutting of suspended removeable ceiling O O O O O
for installation of fittings.
d). Cutting, hacking of wall and repair work. O O O O O

11. Waterproofing around penetrating pipes at


roof &roof & external wall.
a) Indication & drawing showing position, number, size. O O O O O To submit drawing.
b) Cast-in pipe & sleeve, etc. O O O O O
c) Installation of the water proofing material. O
d) Caulking for the above O O O O O

12. Anti-vibration & sound proofing for penetration of O O O O O


pipes & ducts, etc.

13. Access panel


a) Information of dimension, location & quantity. O O O O O To submit drawing.
b) Access panel on the ceiling and wall O

14. Roof
a) Roof Drain O
b) Roof Drain Piping O
c) Opening for duct/pipes/cables to the roof O Information of opening to
slab or external wall be provided by sub-con.

15. Site security and protection of material equipment,


fittings and machinery, etc.

Arakawa Co,. Ltd Page 3 of 7 F 001, Demarcation of Work.xls


ARAKAWA CO,. LTD
BELLEVUE APARTMENT PROJECT

DEMARCATION OF WORK (ARAKAWA / SUB-CONS)


FIRE OTHERS /
NO. WORK ITEM BUILDERS ACMV ELECTRICAL PLUMBING REMARKS
PROTEC'N LIFT
a) Overall security except property possessed O Arakawa has no responsibility
by the sub-contractor for any loss/damage. Storing
b) Protection of material, equipment & fitting, etc. O O O O O of equipment & materials on

16. Cleaning of site


a) Taking away packing material from the site O O O O O
b) Removal of debris from site to designated O O O O O
place.(disposal container).
c). Removal of general debris from designated O
place to public rubbish dumpters.

17. Lift & Escalator


a) Hoisting equipment and material O
b) Scaffolding in the shaft O
c) Separator beam in the shaft O
d) Hooks and trolley beam O If required & shown in drawing.
e) Machine beam in lift motor room O
f) Finishing works of external wall of escalator O
g) Essential Electrical Supply to Lift sub-panel O
h). Lift Sub-Switch Board. O
i). Ventilation system at Lift Motor room. O

* The above table states the work to be carried out by the sub-contractors, if they fail to carry out those works as
hereinbefore mentioned, any delay or cost whatsoever is solely the responsibility of the sub-contractor.

Arakawa Co,. Ltd Page 4 of 7 F 001, Demarcation of Work.xls


ARAKAWA CO,. LTD
BELLEVUE APARTMENT PROJECT

(F 001)
DEMARCATION OF WORK (ARAKAWA / SUB-CONS)
NO. WORK ITEM BUILDERS ELECTRICAL REMARKS

1. Plinth
a) Information (with Shop Drawing) O Location, size, weight
b) Setting out (marking on site) O
c) Formwork, reinforcement & finish work O
d) Check for dimension & position O
e) Reinforcement to structure O If require.

2. Opening & sleeves to beam, wall, floor for M & E Services.


a) Information (with Shop Drawing) O
b) Formwork and reinforcement of openings O
c) Setting out of opening(marking on site) O O Sleeves by subcon, opening
d) Reinforcement of structure. O by main con.
e) Installation of sleeves with reinforcement bar. O
f) Hacking and making good to opening O If the reason is due to the
g). Check to confirm opening size and location. O sub-contractor

3. Filling to opening & sleeves


a) Back filling (fire barrier, concrete or mortar) O
to opening and sleeves through walls & floor slab.

4. Machine hatch & hook for equipment delivery and Maintenance


a) Temporary opening to structure wall and O If require.
slab for equipment delivery and handling
b) Information for dimension, position, weight & quantity. O
c) Installation of temporary hook for machine & O
equipment handling
d) Maintenance hatch and access door. O

5. Hoisting of special heavy equipment. Sub-contractor must follow


a) Hoisting sub-contractor's special heavy O Shimizu's instruction on the
machinery/Large equipment. usage of facilities avaiable
b). Usage of main contractor hoisting facilities O at site & should inform detail
if load permitted. of hoisting heavy equipment
c). Reinforcement of structure & handling platform if require. O during tender stage. Submit
d). Handling of equipment O the planing method which
e). Container, hoisting belt/chain for lifting O include storage, delivery schedule
f). Horizontal movement O & access within 3 mth of Shimizu
g). Supervising & safety O O instruction. Access & Delivery
schedule to be discuss regulary.
6. Preparation for delivery of machine & material, etc.
a) Protection to access (material & labour) O Sub-con is to ensure that all
b). Clearing of access, relocate main contractor O horizontal movement of the
debris, material and equipment. equipment is in accordance to
c). Clearing of access, relocate M&E contractor O Shimizu predetermined routes.
debris, material and equipment. Sub-con should get approval
d). Temporary support (material & labour) O for horizontal movement
e). Preparation of common hoisting platform. O method from Shimizu &
f). Information delivery regarding delivery date and time. O responsible for protection of
g). Cordination of schedule for hoisting. O the floor surface.

Page 5 of 7 F 001, Demarcation of Work.xls


Shimizu Corp
ARAKAWA CO,. LTD
BELLEVUE APARTMENT PROJECT

(F 001)
DEMARCATION OF WORK (ARAKAWA / SUB-CONS)
NO. WORK ITEM BUILDERS ELECTRICAL REMARKS

7. Site office, storage & workshop shop area.


a) Area for the above O
b) Site office, storage area, work shop area O
with general lighting and power points.
c) Furniture (desk, table, chair, etc.) O
d) Telephone, fax, copy machine O
e) Accommodation of sub-con staff & workers. O

8. Temporary lighting, power point & water supply


a) Power distribution board, general lighting & power point. O
b) General water supply points O
c) Consumption cost of power and water O
d) Spot light and extension cable O
e) Extension water supply point O Power requirement over 20A
f) Power supply for Welding machine. O O to be provided by sub-con.

9. Temporary scaffolding Sub-con to ensure proper


a) General scaffolding O usage of scaffolding.
b) Special scaffolding for installation work. O Modification to be approved
c) Responsibility for safety checking of scafolding O O by Shimizu.

10. Cutting builder's finished work


a) Information of dimension, location & quantity. O To submit drawing.
b) Cutting of plastered ceiling, ceramic tile, O
marble stone, granite, wall clading.
c). Cutting of suspended removeable ceiling O
for installation of fittings.
d). Cutting, hacking of wall and repair work. O

11. Waterproofing around penetrating pipes at


roof &roof & external wall.
a) Indication & drawing showing position, number, size. O To submit drawing.
b) Cast-in pipe & sleeve, etc. O
c) Installation of the water proofing material. O
d) Caulking for the above O

12. Anti-vibration & sound proofing for penetration of O


pipes & ducts, etc.

13. Access panel


a) Information of dimension, location & quantity. O To submit drawing.
b) Access panel on the ceiling and wall O

14. Roof
a) Roof Drain O
b) Roof Drain Piping
c) Opening for duct/pipes/cables to the roof O Information of opening to
slab or external wall be provided by sub-con.

Page 6 of 7 F 001, Demarcation of Work.xls


Shimizu Corp
ARAKAWA CO,. LTD
BELLEVUE APARTMENT PROJECT

(F 001)
DEMARCATION OF WORK (ARAKAWA / SUB-CONS)
NO. WORK ITEM BUILDERS ELECTRICAL REMARKS

15. Site security and protection of material equipment,


fittings and machinery, etc.
a) Overall security except property possessed O Shimizu has no responsibility
by the sub-contractor for any loss/damage. Storing
b) Protection of material, equipment & fitting, etc. O of equipment & materials on

16. Cleaning of site


a) Taking away packing material from the site O
b) Removal of debris from site to designated O
place.(disposal container).
c). Removal of general debris from designated O
place to public rubbish dumpters.

17. Lift & Escalator


a) Hoisting equipment and material
b) Scaffolding in the shaft
c) Separator beam in the shaft O
d) Hooks and trolley beam O If required & shown in drawing.
e) Machine beam in lift motor room
f) Finishing works of external wall of escalator O
g) Essential Electrical Supply to Lift sub-panel O
h). Lift Sub-Switch Board.
i). Ventilation system at Lift Motor room.

* The above table states the work to be carried out by the sub-contractors, if they fail to carry out those works as
hereinbefore mentioned, any delay or cost whatsoever is solely the responsibility of the sub-contractor.