Вы находитесь на странице: 1из 10

Column Revamps:

From Outside to Inside


Some of the many things to consider for this complex task are presented here
Mike Resetarits
Separations
Consultant
Tim ReBeau
Gallop Field Services
Terry Thurber
Fractionation
Research Inc.

IN BRIEF
TRAYS AND PACKING

REVAMP TARGETS

MECHANICAL
CONSIDERATIONS

LEVELNESS

GAMMA SCANNING

LARGER COLUMNS

TIDE MARKS

INSPECTIONS

SAFETY

FIGURE 1. Revamping a column is a major undertaking

P
etroleum refineries, chemical-pro- Associated with columns are heat ex-
cessing plants, natural-gas purifica- changers, reboilers, condensers, receivers,
tion plants and other facilities in the pumps, valves, tanks and instrumentation.
chemical process industries (CPI) all Most column revamps necessarily include
contain columns. These columns perform evaluations and modifications of this ancil-
distillations [1], regenerations, strippings and lary equipment.
absorptions. Column diameters range from Unfortunately for us, no two real column
12 in. to 50 ft, and column heights range revamps are identical. They are never easy.
from 10 to 350 ft. And column revamps cannot be boiled down
Prior to about 1970, the majority of the to a step-by-step procedure that can be ap-
column work performed in the U.S. was the plied to most columns. Instead, this article
building and installation of new, grass roots, presents some of the many considerations
columns. Subsequent to that, the workload that are involved in column revamps.
shifted, with many existing columns being
revamped to achieve performance improve- Trays and packings
ments or maintenance targets. When col- Today, globally, approximately one half of
umns are revamped, some columns are re- columns are equipped with trays and the
vamped on the outside; some, on the inside other half contain packings [2]. The pack-
(Figure 1); and some, both. ings can be random or structured. For many
38 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015
Condenser Condenser

Pump Pump

Column Column

Reboiler Reboiler

FIGURE 2. Sometimes the column bottlenecks the unit FIGURE 3. Sometimes the ancillary equipment bottlenecks
the unit
years, the performance of trays was consid-
ered to be more predictable than packing. detrimentally upwards in such columns.
Around 1980, however, work by Fraction- Random packings (for instance, Pall rings)
ation Research Inc. (FRI; Stillwater, Okla.; are still very viable in many columns. Ran-
www.fri.org), and others, showed that suc- dom packings are easy to install and have
cessful packing performance usually hinges low pressure drops. Their optimum perfor-
on proper liquid distribution above packed mance depends upon the liquid distributors
beds. At about that same time, sheet-metal that are feeding the packed beds. Good liq-
structured packing was invented, and such uid distribution is also, of course, required
packing sometimes showed advantages with structured packings.
over both random packings and trays. Regardless of the tower internals, foul-
When compared to trays, the biggest ad- ing is never good. With trays, some parts
vantage attributable to packings is lower get plugged up and are no longer capable
pressure drops. This is particularly true with of passing liquid or vapor. With packings,
columns that are operating at pressures distributors become plugged and liquid
below atmospheric. As an example, prior distributions become non-optimum. Struc-
to about 1985, most ethylbenzene-styrene tured packings are much more prone to
vacuum columns were trayed. Many of those fouling than random packings, because the
columns were soon revamped with struc- metal sheets of structured packings are very
tured packings to reduce the pressure drops tightly spaced.
across the columns, to reduce the bottom The companies that develop and sell trays
temperatures and to reduce renegade po- and packings have been very successful at
lymerization. Generally, the pressure drop improving the performances of those mass-
across a bed of structured packing is about transfer products. Subsequent to about
one-sixth of that across a stack of trays hav- 1960, there have been four generations of
ing the same total height. trays as follows:
On the other hand, there are certainly • Crossflow
some services where packing seems to • Augmented crossflow
be inapplicable. High-pressure distillation • Counterflow
columns, where pure products are being • Cocurrent flow
targeted, have resisted the packing “revolu- Generally, each generation had a higher
tion.” Trays perform better, and much more capacity. Some generations exhibit higher
predictably, in such columns where the vol- efficiencies than others.
umetric liquid-to-vapor ratios are high. Re- Some practitioners divide the history of
garding such packed columns, some dis- random packings into four generations.
tillation theoreticians contend that the high First came Raschig rings and Berl sad-
liquid rates are causing vapor to back-mix dles; then, Pall rings and Intalox saddles;
downward. Some theoreticians contend then, proprietary rings from several ven-
that the low surface tensions of the liquid dors; and then, high-performance rings
phases cause tiny liquid droplets to be from several vendors.
sheared off easily from the downward-flow- Structured packings had the following
ing liquid films; those droplets are entrained history:

CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015 39


been disappointing. When packing replaces
Equilibrium trays, it is usually in pursuit of reduced pres-
stages sure drops.

Revamp targets
High purity/recovery Some columns are revamped on the out-
side. Old insulation is removed. The bare
tower is sand-blasted, re-painted and then
reinsulated. Such work is required to prop-
erly address corrosion under insulation (CUI),
which is an increasing safety problem with
the aged and aging columns of the western
Low purity/recovery world. After painting, some of these columns
are left uninsulated. This allows for easy de-
terminations of future metal-thickness losses
Reflux ratio almost everywhere on the column shell.
Some columns are revamped on the in-
FIGURE 4. Attainment of side, which is the primary topic of this ar-
purity and recovery target • Gauze ticle. The possible targets of such revamps
depend upon the number of
equilibrium stages and the • Corrugated and textured sheet metal are the following:
reflux ratio • High-capacity corrugated and textured • Replacement, in kind, of old, corroded or
sheet metal plugged, internals
High-capacity structured packings gener- • Increased capacity
ally exhibit about 20% more capacity than • Improved separation (better purities,
“conventional” sheet-metal structured pack- recoveries or both)
ings, with no loss in efficiency. • Reduced energy consumption
All of these new generations of trays, ran- In some cases, a column’s service (key sep-
dom packings and structured packings have aration) is changed completely. Such a revamp
made it easily possible, at times, to make can prove to be particularly challenging.
large improvements in column performances A simple replacement of old internals re-
with relatively easy column revamps. quires that details of those internals are avail-
Many column revamps include the chang- able via drawings or purchase orders (POs).
ing out of the column internals. These Such drawings and POs often prove to be
change-outs can be divided into the follow- outdated, and wrong. Whenever possible,
ing broad categories: before such a revamp, the tower should be
1. Trays replace trays entered to ascertain exactly what is presently
2. Trays replace packing residing inside the tower.
FIGURE 5. A simple revamp 3. Packing replaces packing All of the other revamp targets require the
can yield a feedrate increase 4. Packing replaces trays performance of process simulations work.
and there are times when a
complex revamp can yield a When trays replace packings, it is usu- Many such computer programs are avail-
larger feedrate increase [2] ally because the packing performance has able commercially. For distillation columns,
“simple” programs employing equilibrium
stages, or “theoretical trays,” suffice. Car-
Complex revamp
bon-dioxide absorbers and regenerators are
a completely different case. Such columns
Original often exhibit and require very few equilib-
column
rium stages. For example, a carbon-dioxide
absorber might require 0.8, or 3.2, equilib-
rium stages. For such columns, computer
Equilibrium programs that utilize the rate-based (ap-
stages
Simple proach to equilibrium) calculation strategy
revamp will give more satisfying results.
Some engineers might argue that a re-
vamp targeting a simple capacity increase
does not require a process simulation. This
is not true. The highest volumetric flow-
Feedrate rates inside a tower are rarely determin-
able from simple mass balances of the feed
Reflux ratio and product streams. Volumetric flowrate
40 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015
FIGURE 7. Trays can be changed out on
To condenser
a one-for-one basis, or revamps can be
more complex

Revamp
rings
Manhole Reflux
20 Original Revamp Original
rings rings rings

Feed Manhole
10

1-for-1 revamp 3-for-2 revamp


1

Manhole From reboiler


sometimes include a multiplicity of feed
cases, such as near-term, future, worst-
case, best-case or other scenario. A se-
To reboiler
rious revamp study usually begins with
a simulation of the existing operation. In
a perfect world, a perfect vapor-liquid
FIGURE 6. Columns contain nozzles for feeds and equilibrium (VLE) thermodynamic model
draws and also manholes for human entry [2]
is employed in that simulation. A some-
what imperfect model can suffice as
bulges occur inside columns. Also, long as the number of equilibrium stages
stage-by-stage densities, viscosities being exhibited by the existing, old trays
and surface tensions are required. or packings is reasonable. For example,
Feed flashes might cause the above- a process simulation showing that 130
feed tray or packing layer to be the theoretical trays are being exhibited by
most congested. Old, original, process 100 actual trays is not reasonable. The
simulations often prove to be mislead- VLE model is probably wrong and a pro-
ing when employed to evaluate current cess simulation of the future conditions
processing conditions. should not be trusted. For this particular
Computer simulations of columns example, a process simulation showing
will also help to identify bottlenecks in that 90 theoretical trays are being ex-
the columns’ ancillary equipment. Too hibited is reasonable. That VLE model is
often, columns are revamped with su- possibly “good enough.”
perior internals, and eventually, it may be The target of some column revamps
determined that the old internals were is energy reduction. Figure 4 applies to
not bottlenecking the unit; the problem distillation columns. Two curves show
might have been reboiler circuitry pip- the well-known distillation relation-
ing, an under-sized reflux pump, or con- ship between the number of equilib-
denser cooling water temperature, and rium stages (NES) and the reflux ratio.
so on [3]. Figure 2 illustrates a tower that The y-axis of this graph could be re-
is bottlenecked by its internals (trays or labeled as number of theoretical trays
packings). Figure 3 demonstrates that (NTT). The present x-axis shows reflux
the ancillary equipment often bottle- ratio, but this axis could be changed
necks performance. to show energy consumption. Both of
The target of some column revamps the curves of Figure 4 show that as
is an improved separation. Maybe a the staging in a column is increased,
top product needs to be more pure. the energy requirement decreases.
Maybe the losses of that product, out There are minima, however, on staging
the bottom of the tower, need to be and on reflux ratio. Figure 4 includes
decreased. The pursuit of such targets two curves, one for an easy separa-
absolutely requires the performance of tion and one for a difficult separation.
process simulation work. Such work will As expected, the latter requires more

CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015 41


Source: FRI
FIGURE 8. New tray rings can make it possible to increase the feedrate to
be welded to tower walls or the column, as shown in the datum labeled
they can be supported using
posts that are attached to the “complex revamp.” Similarly, high-efficiency
old rings packings could replace less-efficient pack-
ings to achieve the benefits of a complex
column revamp.

Mechanical considerations
Figure 6 shows a very short distillation col-
umn with only 20 trays. Included is a feed
nozzle half-way up the column. Process sim-
ulation work on any distillation column shows
that there is an optimum feed point location,
stages, more energy or both. where energy consumption is minimized.
Most importantly, Figure 4 shows that en- That optimum location could be in the upper
ergy consumption can be reduced with more half or the lower half of the column. During
staging. More staging can be obtained with some distillation column revamps, the feed
more trays, more-efficient trays, more pack- location is changed. The obvious way to
ing or more-efficient packing. One way to move a column’s feed point is to add a new
place more trays or more packing in a col- nozzle to the column. This is not always easy.
umn is to increase the height of the column. Another way to change a feed location is to
Indeed, sometimes, the head is cut off of an use the old, original feed nozzle and then run
old column and a new spool piece is added a pipe up or down through a set of trays (or
to the shell to increase the column’s height. packings) and then terminate that pipe with
Usually, however, increased staging is horizontal distributor piping at the optimum
achieved as follows: feed location. Primarily, this internal piping
1. Adding trays by decreasing tray spacings, strategy avoids welding a new nozzle to the
for example, 100 trays at 24-in. spac- outside of an old column.
ings are replaced by 150 trays at 16-in. An explosion that occurred in 1984 in
spacings Lemont, Ill., served as a wake-up call to
2. Replacing random packing with more-effi- global column-revamp practitioners. When
cient (that is, smaller) packing elements welding work is performed on “old” pres-
3. Replacing structured packing with more- sure vessels, that work must be followed
efficient (that is, higher-surface area) struc- by local or total heat treating (stress relief).
tured packing Such heat treating is expensive when per-
In all of these cases, the new trays or the formed correctly.
new packings must be capable of handling In columns, trays are supported by rings.
the new internal flowrates, without flooding. With a new column, those rings are often
Figure 5 is a three-dimensional graph. The welded to the inside of the column while the
datum labeled “original column” shows the column is in the fabrication shop. Eventually,
“as is” operating point. A feedrate increase the column is shipped to the production site
could be achieved with a simple revamp, for and the column is erected.
example, higher capacity trays or higher ca- Imagine a column with 100 rings and 100
pacity packings. Assuming that there were trays. Imagine a scenario wherein the 100
no changes in the tray or packing efficiencies trays are going to be replaced by 150 trays.
after the simple revamp, the column would This is sometimes called a “three-for-two
be operating at a higher reflux rate, but the revamp” and is shown in Figure 7. One op-
same reflux ratio. With a simple revamp, the tion is to use many of the existing rings and
staging in the column is not changed. then to weld many new rings to the inside of
Now imagine a complex revamp — for the column [4]. This welding will necessitate
example, the replacement of 100 trays with heat treating. Another option is to support
150 trays. Assuming a tray efficiency of 80%, new rings using old rings and vertical posts.
the number of equilibrium stages supplied by As shown in Figure 8, FRI demonstrated the
the trays would be increased from 80 to 120. post-supporting strategy of new rings in one
This has a large impact on the requisite reflux of its test towers. This strategy avoids the
ratio, as shown in Figures 4 and 5. The re- necessity for heat treating, because the new
duced reflux ratio leads to a decrease in the rings and posts are not welded directly to the
reflux rate, a decrease in the reboiler boil-up shell of the pressure vessel.
and decreases in the internal vapor and liq- Referring back to Figure 6, most columns
uid flowrates. The reduced internal flowrates contain manholes. These manholes allow
42 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015
humans to enter columns for inspection, ating companies all have standards regard-
maintenance and revamp work. Figure 9 ing ring levelness tolerances. Usually, larger
is a photograph (side view) of one of FRI’s tolerances are allowed at larger diameters.
manholes. The inside dimensions (IDs) of It is very important that tray and distributor
column manholes are of extreme impor- installation companies adhere to these lev-
tance when planning a revamp and when elness tolerances, regardless of how difficult
designing parts for trays and for packing they sometimes appear to be. In worst-case
distributors. The parts must, of course, fit scenarios, shims can be employed on the
through the manhole, and then the parts rings to install trays and distributors with-
must be “rotate-able” into vertical orienta- out significant out-of-levelness. Again, very
tions, for transporting downward inside the unfortunately, the history of global column-

Before initiating serious column revamp work, a column should


be gamma-scanned especially at processing conditions near its
flood point.
column. Similarly, large blocks of structured revamp work contains numerous cases
packing must fit inside the open manholes. where non-horizontal trays and distributors
In some cases, large parts of trays and dis- performed poorly.
tributors are broken down, in the planning
and drawing stages, into sub-parts. For ex- Gamma scanning
ample, a large central tray downcomer might Before initiating serious column revamp
be designed and fabricated as two pieces. work, a column should be gamma-scanned
In some cases, column-revamp work is fa- especially at processing conditions near its
cilitated by cutting the tops off of columns flood point. Gamma scanning can identify
and then reattaching those tops after the re- the location of any hydraulic bottlenecks in
vamp work is completed. Very unfortunately, trayed or packed columns. Once the loca-
the history of global column-revamp work tion has been identified, tray and packing
includes numerous cases where tray and engineers, especially from the vendor com-
packing parts did not fit into columns after panies, can determine the reason that the
those parts were designed, fabricated and hydraulic bottleneck is occurring. Column
delivered to revamp sites. flooding is often defined as “liquid can-
not get down the column.” When column
Levelness flooding occurs, there are many possible
Some old and new columns are not perfectly reasons including excessive vapor traffic
straight, or upright. Long column shells are and excessive liquid traffic. Column flood-
fabricated in pieces. Sometimes when the ing usually initiates at a single vertical point
shell pieces are welded together, the column in a column. Because the full liquid stream
makes a slight turn. Additionally, long shells is not getting past that point, the section of
can become bowed, especially if left in a hor- the column beneath the bottleneck is often
izontal position in the sun for too long. Once starved of liquid. At the same time, the sec-
a long column is erected, that is, uprighted, it tion of the column above the bottleneck
is difficult to see if the column is bowed, es- is accumulating liquid. This starvation and
pecially because of the column’s insulation, accumulation are observable in thorough
ladders, platforms and piping hook-ups. On top-to-bottom gamma scans. Reboiler and
the other hand, if a column is not perfectly condenser circuitry should also be scanned
upright, that can often be seen from about at those rates where a column appears
100 yards away. A column that is off vertical to be flooded. Also, premature flooding is
by only 1 deg can be seen by eye. often attributable to solids and plugging.
Columns that are not perfectly vertical Sometimes, column internals can simply be
usually have rings that are not perfectly hori- cleaned, rather than replaced.
zontal. When trays or packing distributors
are placed upon those rings, those trays Larger columns
and distributors are prone to malperfor- In 1985, the number of global columns over
mances — sometimes not meeting process 300 ft in height could have been counted on
targets. It is also, of course, possible that one hand. Today, several global columns are
the rings were installed improperly in the approaching 350 ft in height.
shell fabrication shops. Tray and packing In 1985, a propylene column 15 ft in diame-
vendors, engineering companies and oper- ter was considered to be “huge.” Today, pro-

CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015 43


Source: FRI
work elevations, are required. Each team
requires an observer/coordinator at each
manhole and also its own on-the-ground
assistants to keep parts moving down and
up the tower.

Tide marks
As trays and packings are being removed
from a tower, those trays, packings and
packing distributors need to be examined
before they are discarded or reused. Be-
sides plugging, one of the first things to
look for is metal thinning due to corrosion.
Some services are particularly prone to
acid build-ups, and acids eat away at met-
als, including column shells. Sometimes,
so-called “tide marks” can be seen on the
inside walls of trayed columns that have
been running for many years. Those tide
marks show froth heights, and maybe froth
FIGURE 9. Column manholes pylene columns 30 ft in diameter have been height differences. Figure 10 is a photo-
allow humans and equipment commissioned and are being designed. graph from one of FRI’s kettle reboilers [6].
to enter
A column that is 30 ft in diameter has four Tide marks are clearly evident on the inside
times the cross-sectional area of a 15-ft- walls of that kettle. In this case, those tide
dia. column. As a result, with large-diameter marks indicate the average depth of the
trayed and packed towers, the possibilities boiling pool.
for liquid and vapor maldistributions are
greatly increased. With trays, for example, Final post-revamp inspections
long liquid-flow path lengths help to create After any revamp, there comes a point in time
hydraulic gradients in the froths. In response when a column is ready for a final inspection,
to the froth height differences, vapor streams before the manhole covers are closed and
have a natural tendency to flow through the the column is buttoned up. This inspection
deck areas having the shortest froth heights. should always involve a member of the com-
As a worst-case scenario, vapor crossflow pany that owns and operates the column.
channeling (VCC) can occur [5] and tray ef- Trays are usually equipped with manways
ficiencies can suffer. that allow workers and inspectors to climb
Again, very large trays have very large deck vertically through tray stacks. Multi-pass
areas. Such areas are particularly prone to crossflow trays, such as four-pass and
froth stagnations, or even retrograde (back- six-pass trays, are usually equipped with
wards) froth flow. If properly designed and multiple vertical manway paths. The down-
specified, push valves on those deck areas comers and anti-jump baffles of multi-pass
can keep the froths moving toward the out- trays make it impossible to inspect an entire
let weirs. freshly installed tray from just a single set
Regarding packing, the difficulties asso- of vertical manways. Such multi-pass trays
ciated with the attainment of perfect liquid require that each set of vertical manways
distributions at the tops of packed beds are be climbed through so that every area and
increased appreciably with very large column volume of a freshly installed tray can be in-
cross-sectional areas. Some companies, in- spected before those manways and column
cluding vendors, insist that all liquid distribu- manholes are closed.
tors be tested with water at vendor company It is, of course, impossible to climb vertically
test stands. through a bed of packing, whether random
The bottom line is that, with trayed and or structured. Nevertheless, it often happens
packed towers, malperformances are more that liquid distributors are positioned at the
likely to occur before and after column re- same elevations as column manholes. It is
vamp work, when tower diameters are ex- therefore easily possible to inspect most
tremely large. packing distributors before the manholes are
Very large and very tall columns bring up buttoned up.
other issues. Revamping such towers dur- All findings of column inspections need
ing 30-day turnarounds is often excessively to be thoroughly documented, including in-
challenging. A multiplicity of teams, and spector names and dates.
44 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015
Safety considerations way, that all valves leak. Has the column
General. There are many people who per- been steamed out? Aired out? Is the oxygen
form column revamps very regularly. There content going to be monitored continuously
are other people who become involved in while the vessel is occupied?
such work only occasionally, or even just Regarding entry to any confined space,
once in a career. These people include en- a key player is the attendant, sometimes
gineers, technicians, mechanics, welders, called the “hole watch,” who is usually posi-
electricians and so on. The next few para- tioned outside of any manhole where people
graphs are particularly for the people who enter the column. Nobody enters the column
are not already experienced, and expert, at without the attendant’s full permission and
column revamp safety aspects. knowledge. The attendant logs all entries and
Ultimately, you are responsible for your own exits. The attendant has many other respon-
safety. At the plant, you are in your shoes. sibilities, including the blowing of an air horn
Only you go where you go. You should not if any dangers arise outside of the column,
expect to have an experienced safety expert and, the contacting of rescue personnel if
at your side everywhere that you go at a anything goes wrong inside the column. The
plant during a column revamp. attendant must sometimes prevent the res-
The first people to talk to regarding col- cue team from rushing into the column if the
umn revamp safety are the safety profes- rescue team might possibly suffer the same
sionals and the experienced veterans (engi- calamity as what brought the team to the
neers and technicians) where you work. Your column in the first place. Very unfortunately,
company has, or should have, procedures a large fraction of confined-space rescues

Falls are the most common cause of work-related injuries and


deaths.
and policies regarding plant visits. Training involve fatalities and the rescue teams end
classes will possibly be needed. Paperwork up focusing on body retrievals. Most impor-
will need to be attended to, earnestly. A sec- tantly, the attendant should be regarded as
ond group of people to talk to are the safety “the boss.”
professionals and experienced veterans at OSHA Standard 29 CFR 1910 also in-
the plant. This includes engineers, outside cludes chapters regarding falls and fall-
technicians and board operators. On an in- protection equipment. Falls are the most
creasing basis, plants are providing safety common cause of work-related injuries and
training to first-time entrants to those plants. deaths. Climbing up and down the outside of
This training can last an hour or as long as a column involves the risk of falling. Climbing
three days. Sometimes, tests will need to up and down inside the column involves the
be taken at the plant, to assure everybody same risk. As was stated previously, some
that you are fully ready to encounter all of the of these newer columns are 350 ft tall. Body
known and potential hazards that are pres- belts, harnesses, deceleration devices, lan-
ent near and in columns during revamps. yards, lifelines, arrest systems, ropes, lad-
OSHA standards. There are several applica- ders and scaffolds are all available to make
ble federal Occupational Safety and Health the climbs safe.
Administration (OSHA; Washington, D.C.) OSHA Standard 1910.132 applies to per-
standards. Certain states and localities have sonal protective equipment (PPE). For column
their own standards and these must, and revamp work, the following are regarded as
should, be adhered to also. Among the ap- possibly applicable PPE: hard hats, gloves,
plicable federal standards are the following: safety glasses with side shields, steel-toed
OSHA Standard 29 CFR 1910.146 applies boots, shields, barriers, respiratory devices
to entry into confined spaces. During a col- and flame-resistant clothing. Anybody who
umn revamp, some people need to enter the wears PPE needs to be trained regarding
column. Those people need to know what the PPE. PPE should always be regarded
was processed in the column. Were there as the last line of defense against injury. To
any poisons or dangerous hydrocarbons or avoid PPE coming into play at a revamp site,
chemicals? Is the column properly blanked engineering controls, policies and proce-
off so that those chemicals have no possibil- dures need to be in place, and adhered to.
ity to reenter the column? Has the appropri- For example, platforms on the sides of col-
ate equipment been locked out and tagged umns have guardrails and toe guards. These
out (LOTO)? It should be assumed, by the are intended to prevent people or untethered

CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015 45


Source: FRI
changes have occurred, the unit’s process
flow diagrams (PFDs) and P&IDs need to be
updated to include the changes. All operat-
ing units must have up-to-date PFDs and
P&IDs while those units are operating.
PSSR stand for “pre-startup safety re-
view.” After a unit has been modified, and
before the blinds are removed, the valves
are opened and the pumps are restarted,
a meeting should be held to determine
whether the unit is truly totally ready to be
placed back into service. Among the ques-
tions that need to be answered is this one:
Have all affected employees been apprised
or trained regarding the changes that have
been made to the unit?
Miscellaneous. Column owners or operators
rarely do their own revamp work. Some ven-
dors of tower internals have field service or-
FIGURE 10. Tide marks can equipment from falling off of the platforms. If ganizations at their disposal. Otherwise, there
sometimes be found inside equipment does somehow fall from a plat- are very experienced companies that perform
of old vessels, in this case, a
kettle reboiler form, hard hats being worn by the people such work.
underneath will lessen the injuries, if any, sus- Before any column can be entered by hu-
tained by those people. The first line of de- mans it must be steamed-out, especially to
fense is the guard rails and the toe guards. remove chemicals that adhere to the column
Safety – policies and procedures. LOTO wall and the column internals — subsequent
stands for “lock out tag out” and is a policy to the pump-out. Every column and service
and a procedure whereby energy sources is different. Some columns are steamed for
(potential, kinetic, pneumatic, radiation, elec- 24 h, whereas others require three full days.
tric and so on) are totally isolated from hu- Thereafter, air movers are required to es-
mans. Dangerous machines are shut off and tablish breathable atmospheres and to pre-
cannot be restarted easily. Hazardous power vent air from becoming dangerously stale.
sources are isolated and made inoperative Thereafter, the column is still not ready for
often via padlocks. Associated with those full entry. Workers with respiratory equip-
padlocks are cardboard or plastic tags that ment should peer carefully into the column
are easily seen and that identify the source of and take samples of any liquids or solids (for
the padlocks. When two or more companies instance, deposits) that are found. Those
or subcontractors need to be protected from samples require analyses. For example,
an accidental restart of those machines, it is pyrophoric compounds, such as polybuta-
sometimes required that those two or more diene, are sometimes in evidence in olefin
companies each add their own padlocks to plant depropanizers, even after long steam-
the machine. outs. It sometimes takes a full week, after
JHA stands for “job hazard analysis” and shutdown, for some columns to be totally
can be applied to any small or large project. ready for human entries.
Via a JHA, the hazards associated with a Column revamp work, especially for those
project are identified. The means by which people who do not get involved in it routinely,
the dangers are eliminated, or reduced to is very tiring. For example, when climbing up
reasonable levels, are listed and enacted. the outside of a column, a worker’s arms be-
Most JHAs ultimately involve at least one come fatigued before the legs. On very rare
multi-person meeting where the listed haz- occasions, with very tall columns, special
ards and actions are discussed openly. scaffolds are erected and those special scaf-
MOC stands for “memorandum of folds are equipped with elevators. Revamp
change.” Any change to a unit’s piping and workers who have such elevators at their
instrumentation diagram (P&ID) or proce- disposal should consider themselves lucky.
dures needs to be preceded by an MOC, When first entering any plant, notice should
which should also involve an open discus- be taken of the wind sock and the wind di-
sion between many parties. MOCs, including rection. If anything goes wrong in a nearby
the appropriate costs, ultimately need to be operating unit, know where to go to avoid
approved by management before a change any harmful vapors, including smoke.
or changes are actually effected. Once such Column revamps can occur anywhere and
46 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015
during any season. Dress appropriately. Wind Acknowledgements
speeds near the tops of columns can easily The authors express their gratitude to the
be twice those at ground level. Wherever you many staff members of Gallop Field Services
go when you are at a plant, somebody must and Fractionation Research Inc. who con-
know where you are. tributed to the material of this article.
Whenever two or more teams are work-
ing at different elevations inside a column, References
means must be in place to assure that work- 1. Resetarits, M.R. and Lockett, M.J., Distillation, “Encyclopedia of
ers lower in the column are not struck by ob- Physical Science and Technology,” 3rd Ed., Vol. 4, Academic Press
Inc., 2002, pp. 547–559.
jects that fall by accident from above. The
2. Gorak, A. and Olujic, Z., “Distillation: Equipment and Processes,”
fact that all of the people inside the column 1st. Ed.. Elsevier Publishing, Chapter 2 — Distillation Trays; Chapter
are wearing hard hats is insufficient. Nets 3 — Random Packings; and Chapter 4 — Structured Packings,
can be strung horizontally inside columns to 2014.
protect the lower workers. 3. Kister, H.Z., “Distillation Troubleshooting,” AIChE: Wiley-Interscience,
Hoboken, N.J., 2006.
New plants have manholes that are nomi- 4. Resetarits, M.R., Agnello, J., Lockett, M.J. and Kirkpatrick, H.L.,
nally 24 in. in diameter. Older plants often “Retraying increases C3 splitter column capacity,” Oil and Gas Jour-
have manholes that have IDs of only 17 in. nal, June 6, 1988, pp. 54–59.
Some humans simply will not fit through 5. Kister, H., Can valve trays experience vapor cross-flow channeling?,
The Chem. Engineer, June 10, 1993, p. 18.
such small manholes, especially when they
6. Resetarits, M.R., Cai, T.J., Chambers, S., Pless, L. and Carlson, R.,
are wearing full safety gear. Then, even if Gamma Scanning of a Kettle Vapor Line, AIChE Fall Meeting, Oct.
those people fit through those manholes, 30, 2012.
rescue difficulties are exacerbated. 7. FRI Design Practices Committee, Causes and Prevention of Packing
People who enter columns, and especially Fires, Chem. Eng., July 2007, pp. 33–42.
tall columns, for the first time sometimes be-
come petrified — and even dysfunctional. Authors
Attendants must keep an eye out for such Mike Resetarits consults in the areas of dis-
people and such people should not be al- tillation, absorption and extraction, having
worked in those areas for 40 years (Email:
lowed to enter columns until they can dem- mike.resetarits@att.net). He has appreciable
onstrate that their fears are under control. Expert Witness experience. He began his ca-
Structured packing has been known to reer in separations with Union Carbide Corp.
He then worked for UOP and then Koch-
catch fire in dozens of columns [7]. Usually, Glitsch and then as an independent consul-
sparks and slag from welding ignite depos- tant. From 2008 until 2014, Resetarits served
as technical director at Fractionation Re-
its on the structured packing sheets and search Inc. (FRI) in Stillwater, Okla. He holds a B.S.Ch.E from SUNY
then the burning spreads to the sheet metal. at Buffalo and an M.S.Ch.E. from Northwestern University. He also
Once these fires begin, they are very diffi- holds an M.B.A. from Canisius College.
cult to stop. Some revamp companies and
some operating companies insist that struc- Tim ReBeau is vice president and co-owner of
Gallop Tower Field Service (TFS; 1602 Mooney
tured packings be removed from a column Rd. Houston, TX 77093; Phone: 281-449-1051;
before any welding work is performed above Fax: 281-449-4241 Email: tim.rebeau@
those packings. gallopcgi.com). He currently oversees the esti-
mating and sales departments for tray and pack-
General. Very unfortunately, some injuries ing installations, welding and revamp projects for
are permanent. Like they said at IBM — think! distillation columns. He has 20 years of experi-
Like one of DuPont’s safety programs — ence, beginning his career at Cana-Tex (1995–
2005) and, after purchase by Sulzer Chemtech
Take Two minutes before embarking on even (2005–2010), continued there until 2010. In 2010, ReBeau and busi-
the smallest of new adventures. Seek the ness partner Mike Mitchell started the TFS division of Gallop, which is
advice and assistance of safety professionals dedicated to tower internals installations and revamps.
and experienced veterans, including board
operators and outside technicians. Some Terry Thurber is currently the Safety Focal
Point at Fractionation Research, Inc. (FRI;
of those people have made safety-related 424 S. Squires St., Suite 200, Stillwater, OK
mistakes and are eager to tell you about 74074; Phone: 405-385-0354; Fax: 405-
385-0357; Email: safety@fri.org). He has
those mistakes. While at the plant, never be worked in both the pipeline transportation
lulled into a false sense of security. Expect the and storage, and process system sides, of
unexpected — and “unexpect” the expected. the energy industry. He has been involved
in well over one hundred permit-required
It has been estimated that there are confined space entries as either an atten-
100,000 columns in the world. Many of them dant, entrant, entry supervisor, program auditor, or trainer. He is
have already been revamped. All of them are certified through OSHA Training Institute to conduct training of
OSHA 10 and OSHA 30 classes and he is also a certified safety
targets for potential future revamps. If you and health official.
become involved in one, or some, of those
revamps, be totally prepared. Be safe. ■
Edited by Gerald Ondrey

CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM APRIL 2015 47

Вам также может понравиться