PROJECT TITLE: BILL OF ENGINEERING MEASUREMENT AND EVALUATION

FOR CASTING OF POLE BASES FOR DOUBLE ARM SOLAR STREET LIGHT
S/NO. DESCRIPTION QTY UNIT RATE AMOUNT
A. CIVIL WORKS
Casting of poles bases which shall include
the following items of work:
-Pegging/alignment of pole bases
-Excavation of hole
600 x 600 x 1200mm for all types of soil
including hard rock. -Metallic
form work 600x600x600mm to standard
specifications.
-50kg of cement
-25mm diam. HTS foundation bolt &
nuts(to be made available)

- 3/4 (20mm diam)


aggregate granite chippings
- Sharp sand

A1. - Water etc to achieve mix ratio of 1:2:4 1 Sets 22,550.00 22,550.00
A2. Transportation/hiring of working tools Lot sum 1,350.00 1,350.00
GRAND TOTAL/BASE 23,900.00