• Sapura 3500 is at berth 10, Johor PG, Vessel sailing for Zwatika phase II on 09 th Feb.

• Sapura 3000 is at JB anchorage. DP trials completed.


• Sapura 1200 is at Limassol anchorage, standby for further instruction. Physical Name
change/logo works completed.
• SK FLB1 is at at Chiwan yard, Shenzhen for load out of Zawtika jacket which has been
successfully loaded on the barge and expecting to depart for Myanmar tentatively on 10th Feb.
• Sapura 900 continuing with ONGC B127 project, currently engaged in removal of 4” cable at
HJ Platform.
• SK Conquest cleared HRA area and enroute to Galle OPL ETA 12th Feb to drop off arm guards.
Shall continue to Johor, ETA 19th Feb.
• SK Achiever is at Johor port anchorage, undergoing maintenance and readying up vessel for
PCSB project.
• SK Jane is at Johor port anchorage, undergoing maintenance and readying up vessel for PCSB.
Expect to kick start PCSB contract on 26th Feb. Petronas OVID schedule on 12th Feb.
• Sapura Alliance is at Keppel shipyard for DES upgrade project. VFD container expected to
arrive today 15th Feb. Location of new DES at quayside being prepared with foundation
plates. DES estimated arrival date 22th Feb.
• Sapura 390 class reactivation survey completed, received ABS certificate with all class punch
points closed.

• SK Aman is at Kemaman anchorage readying up for EM project. Undergoing 2 x generator


major overhaul, PTO FIFI gearbox overhaul.
• Redang is alongside Johor Port, mobbing for Zawtika. Issue with BT#2 thruster proportional
valve settled with modification done by Wartsila. Meantime 2 valves on order.
• SK Duyong is at LSE shipyard. RS3 inspection 6th Feb. Expected to go for DP trials on after CNY.
Job to commence on 1st week of March for a month at SBO water.
• Sapura 3500 is on Zwatika Project and reached at project site local time 0900 AM 15th Feb.
• Sapura 3000 is at JB anchorage. Bunkering in Singapore completed. Vessel will come alongside
PG.
• Sapura 1200 is at Limassol anchorage, standby for further instruction. Preparatory works for
ABS/Flag state annual inspections in progress.
• SK FLB-1 loaded with WP10 jacket enroute to Zawtika project, ETA Myanmar Mar 3rd ‘18.
• Sapura 900 continuing with ONGC B127 project, installing KOD on BCPA platform.
• SK Conquest cleared HRA area and drop off arm guards at Galle OPL on 12 th morning. Vessel
on passage to Johor ETA 20th Feb.
• SK Achiever is at Johor port anchorage, undergoing maintenance and readying up vessel for
PCSB project. PCSB reps boarded vessel yesterday and were happy with the overall vessel
condition, issued 3 observations.
• SK Jane is at Johor port anchorage, undergoing maintenance and readying up vessel for PCSB.
Expect to kick start PCSB contract on 8th March. Petronas OVID schedule on next week, date
TBA. PCSB requested to upgrade noise insulation at mess room and we are looking at
possibilities attending same.
• Sapura Alliance is at Keppel shipyard for DES upgrade project.DES estimated arrival date
28th Feb.
• Sapura 390 at Pasir Puteh Buoy.

• SK Aman is at Kemaman port alongside undergoing all annual surveys. Readying up for EM
project. Exxon Ovid schedule on 19th Feb. Undergoing 2 x generator major overhaul, PTO FIFI
gearbox overhaul.
• Redang enroute to Zawtika field ETA 16th @ 1100hrs
• SK Duyong is at LSE shipyard. Expected to go for DP trials on after CNY. Job to commence on
1st week of March for a month at SBO waters.
.