Вы находитесь на странице: 1из 56

DEPARTMENT OF THE ARMY

US ARMY CORPS OF ENGINEERS


NEW ENGLAND DISTRICT
696 VIRGINIA ROAD
CONCORD MA 01742-2751

February 16, 2018


Regulatory Division
File Number: NAE-2007-1851

David Veleta, P.E.


City of Northampton, DPW
125 Locust Street
Northampton, Massachusetts 01060

Dear Mr. Veleta:

We have reviewed your application to discharge fill material within approximately 0.91 acres
of waters of the United States including wetlands in order to remove the Upper Roberts Meadow
Reservoir Dam. Impacts include 13,900 square feet (SF) of fill for the installation of
construction access roadways including the removal of the Upper Roberts Meadow Reservoir
Dam and 25,800 SF for the sluicing of accumulated sediment within the Upper Roberts Meadow
Reservoir to downstream areas as part of the new channel formation. The project will be
performed in phases in order to allow the upstream channel to form more gradually. The
purpose of this project is removal of the existing dam and restoration of coldwater fisheries
habitat for brook trout and other coldwater aquatic species as well as normal river processes.
This project is located in Roberts Meadow Brook, Chesterfield Road, Northampton,
Massachusetts. The work is shown on the enclosed plans entitled, “UPPER ROBERTS
MEADOW RESERVOIR DAM BREACH AND ECOLOGICAL RESTORATION PROJECT,
NORTHAMPTON, MASSACHUSETTS,” on 15 sheets and dated February 2018.

Based on the information you have provided, we have determined that the proposed activity,
which includes work and/or a discharge of dredged or fill material into waters of the United
States, including wetlands, will have only minimal individual or cumulative environmental
impacts. Therefore, this work is authorized under the enclosed February 2015 General Permits
for Massachusetts (GPs for MA), specifically GP 14 and 22, under the pre-construction
notification process. This work must be performed in accordance with the terms and conditions
of the GPs and also in compliance with the following special conditions:

1. The permittee shall comply with the enclosed Memorandum of Agreement entitled,
“Memorandum of Agreement Between the U.S. Army Corps of Engineers, the
Massachusetts State Historic Preservation Officer, and The City of Northampton,
Regarding The Upper Roberts Meadow Reservoir Dam Removal Project in Northampton,
Massachusetts.” This is to avoid, minimize and/or mitigate for the adverse effect that the
authorized work will cause to historic properties.
2

2. The work of this project shall be performed in accordance with the attached restoration
and monitoring plan entitled, “Upper Roberts Meadow Reservoir Dam Breach and
Stream Restoration Project, Northampton, MA, Revised Stream Restoration and
Monitoring Plan,” dated November 29, 2017.

3. Your responsibility to complete the required stream restoration as set forth in Special
Condition 2 will not be considered fulfilled until you have demonstrated restoration
success and have received written verification from the U.S. Army Corps of Engineers.
The term “restoration success” means success as defined under “3.0 Restoration Goals
and Success Criteria” in the restoration and monitoring plan this permit requires you to
implement. Demonstration of success under this permit shall consist of the required
restoration, monitoring, contingency plans, and submittal of monitoring reports as
defined in the restoration and monitoring plan.

4. Post-demolition monitoring reports required by the restoration and monitoring plan must
be submitted to the Corps prior to December 31st of the associated monitoring year.

5. If restoration of the Roberts Meadow Brook is not successful as defined in the restoration
and monitoring plan, mitigation in the form of payment into the Massachusetts In-Lieu
Fee program may be necessary. Coordination between the Corps and the City of
Northampton shall take place before a final payment amount is determined.

6. Except where stated otherwise, reports, drawings, correspondence and any other
submittals required by this permit shall be marked with the words “Permit No. NAE-
2007-1851” and shall be submitted via: a) MAIL: PATS Branch - Regulatory Division,
Corps of Engineers, New England District, 696 Virginia Road, Concord, MA 01742-
2751, b) Email: Ruthann.A.Brien@usace.army.mil, or c) FAX: (978) 318-8303. A copy
of the monitoring reports shall also be submitted to the Environmental Protection Agency
via email at reiner.ed@epa.gov. Documents which are not marked and addressed in this
manner may not reach their intended destination and do not comply with the
requirements of this permit.

You are responsible for complying with all of the GP requirements. Please review the
enclosed GPs for MA document carefully, in particular the general conditions beginning on Page
23, to familiarize yourself with its contents. You should ensure that whoever does the work fully
understands the requirements and that a copy of the permit document and this authorization letter
are at the project site throughout the time the work is underway.

This authorization does not obviate the need to obtain other Federal, State, or local
authorizations required by law, as listed on Page 57 of the GP document. Performing work not
specifically authorized by this determination or failing to comply with any special conditions
provided above or all the terms and conditions of the GP may subject you to the enforcement
provisions of our regulations.
3

This authorization presumes that the work as described above and as shown on your plans
noted above is in waters of the U.S. You may submit a request for an approved jurisdictional
determination to this office in writing if you desire.

This authorization expires on February 4, 2020. You must commence or have under contract
to commence the work authorized herein by February 4, 2020 and complete the work by
February 4, 2021. If you do not, you must contact this office to determine the need for further
authorization before beginning or continuing the activity. We recommend you contact us before
this permit expires to discuss a time extension or permit reissuance.

You must contact us immediately to discuss modification of this authorization if you change
the plans or construction methods for work within our jurisdiction. This office must approve any
changes before you undertake them.

We continually strive to improve our customer service. In order for us to better serve you,
we would appreciate your completing our Customer Service Survey located at
htt ://cor sma u.usace.army.mil/cm apex/f?p=regulatory survey.

Please contact Kevin Kotelly of my staff at (978) 318-8703 if you have any questions.

Sincerely,

Barbara Newman
Chief, Permits & Enforcement Branch
Regulatory Division
Enclosures

Copy Furnished

Ed Reiner, U.S. EPA, Region 1, Boston, Massachusetts, reiner.ed@epa.gov


David Cameron, DEP WERO, Wetlands and Waterways, Springfield, Massachusetts;
david.cameron@state.ma.us.us
Sarah LaValley, Conservation, Preservation, and Land Use Planner, 210 Main St., Room 11,
City Hall, Northampton, Massachusetts 01060, SLaValley@northamptonma.gov
Matthew Taylor, GZA GeoEnvironmental, Inc., 249 Vanderbilt Avenue, Norwood,
Massachusetts 02062, matthew.taylor@gza.com
dveleta@northamptonma.gov
GZA GeoEnvironmental, Inc.
Engineers and Scientists
249 VANDERBILT AVENUE
Norwood, MA 02062
PHONE (781) 278-3700

N
Division of Ecological Restoration
0 1000 2000 4000 251 CAUSEWAY STREET, SUITE 400
BOSTON, MA 02114
SCALE IN FEET
PHONE (617) 626-1540

N
UPPER ROBERTS MEADOW RESERVOIR
DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

COVER SHEET

PREPARED BY: PREPARED FOR:


0 500 1000 2000 GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
SCALE IN FEET
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

1
DESIGNED BY: MAT DRAWN BY: EDM SCALE: AS NOTED
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 1 OF 15
N

GRAPHIC SCALE
0 100 200 400

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

OVERAL SITE PLAN AND NOTES

PREPARED BY: PREPARED FOR:


GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

2
DESIGNED BY: MAT DRAWN BY: EDM SCALE: AS NOTED
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 2 OF 15
N

1-A

URMR-4

1-B

3-C
3-B
3-A URMR-1

1-C

2-C URMR-2
URMR-3
2-A

2-B

GRAPHIC SCALE
0 25 50 100

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

EXISTING RESERVOIR BATHYMETRY AND


SEDIMENT SAMPLE LOCATIONS
PREPARED BY: PREPARED FOR:
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
1-C Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

3
URMR-1 DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=50'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 3 OF 15
N

GRAPHIC SCALE
0 5 10 20

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

EXISTING CONDITIONS AT DAM

PREPARED BY: PREPARED FOR:


GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

4
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=10'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 4 OF 15
N

GRAPHIC SCALE
0 20 40 80

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

EXISTING CONDITIONS
FROM DAM TO KENNEDY ROAD
PREPARED BY: PREPARED FOR:
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

5
DESIGNED BY: MAT DRAWN BY: SCALE: 1"=40'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 5 OF 15
N

GRAPHIC SCALE
0 20 40 80

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

MIDDLE ROBERTS MEADOW RESERVOIR


INLET AREA
PREPARED BY: PREPARED FOR:
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

6
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=40'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 6 OF 15
N

GRAPHIC SCALE
0 20 40 80

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

TEMPORARY SITE CONSTRUCTION ACCESS


AND STAGING PLAN
PREPARED BY: PREPARED FOR:
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

7
DESIGNED BY: NYA
MAT DRAWN BY: EDM SCALE: 1"=40'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 7 OF 15
N

GRAPHIC SCALE
0 25 50 100

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

INVASIVE SPECIES CONTROL PLAN

PREPARED BY: PREPARED FOR:


GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

8
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=50'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 8 OF 15
VERTICAL SCALE IN FEET
0 6 12

0 30 60 120
HORIZONTAL SCALE IN FEET

VERTICAL SCALE IN FEET


0 5 10 20

0 10 20 40
HORIZONTAL SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

IMPOUNDMENT PROFILE AND DAM


REMOVAL STAGES - ELEVATION VIEW
PREPARED BY: PREPARED FOR:
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

9
DESIGNED BY: MAT DRAWN BY: EDM SCALE: AS NOTED
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 9 OF 15
N

GRAPHIC SCALE
0 25 50 100

SCALE IN FEET

1-C

URMR-1C
UPPER ROBERTS MEADOW RESERVOIR

14+00
DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

PROPOSED CONDITIONS IN RESERVOIR

PREPARED BY: PREPARED FOR:


GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

10
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=50'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 10 OF 15
UPPER ROBERTS MEADOW RESERVOIR
DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

CROSS SECTIONS IN RESERVOIR


STA. 0+00 TO STA. 6+00
PREPARED BY: PREPARED FOR:
GRAPHIC SCALE GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
SCALE IN FEET Engineers and Scientists DEPT. OF PUBLIC WORKS
0 5 10 20 www.gza.com
0 5 10 20 PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING
SCALE IN FEET

11
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=10'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 11 OF 15
UPPER ROBERTS MEADOW RESERVOIR
DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

CROSS SECTIONS IN RESERVOIR


STA. 7+00 TO STA. 14+00
PREPARED BY: PREPARED FOR:
GRAPHIC SCALE GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
SCALE IN FEET Engineers and Scientists DEPT. OF PUBLIC WORKS
0 5 10 20 www.gza.com
0 5 10 20 PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING
SCALE IN FEET

12
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=10'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 12 OF 15
N

GRAPHIC SCALE
0 20 40 80

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

FINAL CONDITIONS
FROM DAM TO KENNEDY ROAD
PREPARED BY: PREPARED FOR:
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

13
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=40'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 13 OF 15
N

GRAPHIC SCALE
0 5 10 20

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

PROPOSED CONDITIONS AT DAM

PREPARED BY: PREPARED FOR:


GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

14
DESIGNED BY: MAT DRAWN BY: EDM SCALE: 1"=10'
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 14 OF 15
UPPER ROBERTS MEADOW RESERVOIR
DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

DETAILS

PREPARED BY: PREPARED FOR:


GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: MAT CHECKED BY: CWC DRAWING

15
DESIGNED BY: MAT DRAWN BY: EDM SCALE: AS NOTED
DATE: PROJECT NO. REVISION NO.
FEBRUARY 2018 01.0019547.20 SHEET NO. 15 OF 15
WORK-START NOTIFICATION FORM
(Minimum Notice: Two weeks before work begins)

******************************************************************************
* EMAIL TO: cenae-r@usace.army.mil; or *
* *
* MAIL TO: Paul Sneeringer *
* U.S. Army Corps of Engineers, New England District *
* Permits and Enforcement Branch *
* Regulatory Division *
* 696 Virginia Road *
* Concord, Massachusetts 01742-2751 *
******************************************************************************
Corps of Engineers Permit No. NAE-2007-1851 was issued to the City of Northampton,
Massachusetts. This work is located in Roberts Meadow Brook, Chesterfield Road,
Northampton, Massachusetts and authorized the discharge of fill material within approximately
0.85 acres of waters of the United States including wetlands in order to remove the Upper
Roberts Meadow Reservoir Dam.
The people (e.g., contractor) listed below will do the work, and they understand the permit's
conditions and limitations.
PLEASE PRINT OR TYPE
Name of Person/Firm:
Business Address:

Telephone Numbers: ( ) ( )
Proposed Work Dates: Start: Finish:
Permittee/Agent Signature: Date:
Printed Name: Title:
Date Permit Issued: _ _Date Permit Expires:

******************************************************************************
FOR USE BY THE CORPS OF ENGINEERS

PM: Kevin Kotelly Submittals Required: Yes

Inspection Recommendation:
COMPLIANCE CERTIFICATION FORM
(Minimum Notice: Permittee must sign and return notification
within one month of the completion of work.)

Permit Number: NAE-2007-1851


Project Manager: Kevin Kotelly
Name of Permittee: City of Northampton, MA
Permit Issuance Date: February, 2018

Please sign this certification and return it to our office upon completion of the activity and any
mitigation required by the permit. You must submit this after the mitigation is complete, but not
the mitigation monitoring, which requires separate submittals.

************************************************************************ *
* E-MAIL TO: cenae-r@usace.army.mil; or *
* *
* MAIL TO: Permits and Enforcement Branch A *
* U.S. Army Corps of Engineers, New England District *
* Regulatory Division *
* 696 Virginia Road *
* Concord, Massachusetts 01742-2751 *
************************************************************************ *

Please note that your permitted activity is subject to a compliance inspection by an U.S. Army
Corps of Engineers representative. If you fail to comply with this permit you are subject to
permit suspension, modification, or revocation.

I hereby certify that the work authorized by the above referenced permit was completed in
accordance with the terms and conditions of the above referenced permit, and any required
mitigation was completed in accordance with the permit conditions.

________________________________
Signature of Permittee Date

Printed Name Date of Work Completion

( ) ( )
Telephone Number Telephone Number
MEMORANDUM OF AGREEMENT BETWEEN
THE U.S. ARMY CORPS OF ENGINEERS,
THE MASSACHUSETTS STATE HISTORIC PRESERVATION OFFICER, AND
THE CITY OF NORTHAMPTON
REGARDING THE UPPER ROBERTS MEADOW RESERVOIR DAM REMOVAL PROJECT
IN NORTHAMPTON, MASSACHUSETTS

WHEREAS, the City of Northampton (City), the dam owner and proponent, is
proposing the Upper Roberts Meadow Reservoir Dam (URMR Dam) Removal Project (Project)
in Northampton, Massachusetts, in order to reduce the threat of failure of this Poor condition,
high hazard dam and to comply with a 2007 Certificate of Non-Compliance and Dam Safety
Order issued by the Massachusetts Department of Conservation and Recreation — Office of Dam
Safety. The Project will decommission aging public infrastructure, reduce flooding hazards,
improve public safety, and improve ecological conditions of the Upper Roberts Meadow Brook
as shown on the plans attached as Exhibit 1; and

WHEREAS, the Project involves mechanized grading operations at the URMR Dam and
within the upstream impoundment, the installation of temporary construction access roadways,
and the sluicing of accumulated sediment downstream into Roberts Meadow Brook and the
Lower Roberts Meadow Reservoir (the Federal undertaking), and these discharges require a
Department of the Army permit under Section 404 of the Clean Water Act from the United
States Army Corps of Engineers, New England District (Corps); and

WHEREAS, both the Corps and the Massachusetts State Historic Preservation Officer
(MA SHPO) have determined that the URMR Dam and the Edwards-Moody-Hoxie Tannery Site
meet the criteria of eligibility (36 CFR 60) for listing in the National Register of Historic Places
under Criteria A, C, and D; and

WHEREAS, the Corps, in consultation with the MA SHPO, pursuant to the Corps
regulations at 33 CFR Parts 320 through 330 and the 36 CFR Part 800 regulations implementing
Section 106 of the National Historic Preservation Act of 1966, as amended [16 U.S.C. Part
470(f)], has determined that the Federal undertaking will have an unavoidable adverse effect on
the National Register-eligible URMR Dam and a portion of the National Register-eligible
Edwards-Moody-Hoxie Tannery Site; and

WHEREAS, the City has participated in the consultation process and has been invited
to sign this MOA as an invited signatory; and

WHEREAS, the Northampton Historical Commission and the Friends of Upper Roberts
Meadow Dam and Reservoir have participated in the consultation process and have been invited
to sign this MOA as concurring parties; and

1
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
WHEREAS, the Tribal Historic Preservation Officers (THP0s) of the Wampanoag
Tribe of Gay Head (Aquinnah), the Mashpee Wampanoag Tribe, and the Narragansett Indian
Tribe have not responded to a request for comments on the Federal undertaking, and the
Director of the Massachusetts Board of Underwater Archaeological Resources (BUAR) and the
Stockbridge-Munsee Tribe THPO have both responded that this project is unlikely to impact
significant historic resources; and

WHEREAS, in accordance with 36 CFR Part 800.6(a)(1), the Corps has notified the
Advisory Council on Historic Preservation (ACHP) of its adverse effect determination with
specified documentation, and the ACHP has chosen not to participate in the consultation
pursuant to 36 CFR Part 800.6(a)(1)(iii); and

NOW THEREFORE, the Corps and the MEIC agree that the undertaking shall be
implemented in accordance with the following stipulations in order to take into account the effects of
the undertaking on historic properties.

STIPULATIONS

The Corps shall require that the following measures are implemented by the City:

Archaeological Site Avoidance and Protection

A. The City will undertake the "Archaeological Site Avoidance and Protection Plan"
(ASAPP), attached to this MOA as Exhibit 2. The ASAPP provides for the
protection and avoidance of archaeologically sensitive areas including portions of
the Edwards-Moody-Hoxie Tannery Site during the dam removal construction work.

B. Specifically, prior to the commencement of construction activities, the City, with


the assistance of a 36 CFR 61 qualified archaeologist, will flag the construction
areas of avoidance around the Edwards-Moody-Hoxie Tannery Site and other
sensitive areas (refer to Exhibit 1, Sheets #3 and #6), which will be shown in the
construction plan. The Contractor will erect construction fencing and signage
around the avoidance areas which will remain in place for the duration of the
Project construction activities. The City, with the assistance of the Project Engineer
and the 36 CFR 61 qualified archaeologist, will inspect and monitor the installed
construction fencing to ensure that it properly delineates the identified avoidance
areas.

Historic Documentation

Upper Roberts Meadow Reservoir Dam

A. The City, with the assistance of a 36 CFR 61 qualified architectural/industrial


historian, will provide state-level photographic documentation prior to the removal
of the dam and associated components. High-resolution digital photographs will be
2
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
taken that show general views of the dam and its context within the Upper
Reservoir; and details of the dam components including cut granite blocks, stone
masonry retaining walls, earthen embankments, and bedrock abutments. The
photographic documentation will consist of digital photographs captured and
printed according to the MHC Photographic Documentation Technical
Requirements for Digital Images, keyed to an existing conditions project plan where
applicable. Written recordation will consist of copies of historical images and a text
discussing the history and development of the dam based upon information included
in the 2010 MHC Inventory Form (MHC # NTH.964) and the 2011 technical report
on the National Register eligibility opinion of the dam. Additional research will be
conducted to obtain high resolution historical images of the dam for inclusion in the
state-level documentation.

B. A non-archival copy of the documentation will be submitted to and reviewed and


approved by the Corps, Northampton Historical Commission, and the Forbes
Library. If comments are not received within 30 days of submission, it will be
assumed that the documentation is complete and acceptable.

C. An original archival copy of the documentation will be provided the Northampton


Historical Commission for filing at the Forbes Library-Hampshire Room for Local
History. Non-archival copies of the final documentation will be provided to the
Corps, MHC, and the Friends of the Upper Roberts Meadow Dam and Reservoir.

Archaeological Data Recovery and Monitoring

Edwards-Moody-Hoxie Tannery Archaeological Site

A. The City, with the assistance of a 36 CFR 61 and 950 CMR 70 qualified
archaeologist, will undertake an Archaeological Data Recovery Program for a
portion of the Edwards-Moody-Hoxie Tannery Site that is located in the temporary
construction access route downstream of the dam. The archaeological data recovery
program will consist of archival research, field investigations, laboratory processing
and analysis of recovered cultural materials, and the preparation of a technical
report.

B. The Data Recovery Program (DRP) will be implemented under a written Research
Design and Fieldwork Methodology and a State Archaeologist's field investigation
permit. The data recovery work conducted under this permit will be consistent with
the Massachusetts standards for conducting archaeological investigations (950 CMR
70 and 312 CMR 2), and will take into account the Secretary of the Interior's
"Standards and Guidelines for Archeology and Historic Preservation" (48 Fed. Reg.
(190): 44716-42 (1983)) and the ACHP's publication, "Treatment of Archaeological
Properties: A Handbook" (1980), subject to any pertinent revisions of the cited
regulations, standards, guidelines, and publication.

3
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
C. If unforeseen circumstances require the modification of the DRP, the Proponent and
the Principal Investigator (950 CMR 70.04) will consult with the MA SHPO to
develop and implement the required modifications. Copies of the modified DRP
shall be forward to the Corps after this consultation is completed

D. The City will ensure that upon completion of the fieldwork aspect of the DRP, and
any preliminary analyses of the results that may be required, a completion
memorandum shall be submitted by the Principal Investigator to both the MA SHPO
and the Corps that describes the DRP activities completed, a brief description of the
results of the fieldwork and any preliminary analyses, and a schedule for completing
the remaining aspects of the DRP. The Corps and the MHC shall review and
comment on the adequacy of the DRP within thirty (30) days of receipt of the
completion memorandum. The City shall ensure that any inadequacy is addressed
to the satisfaction of the commenting party, whether Corps or the MHC, Prior to
proceeding With remaining aspects of the Project.

Dam, Brook, and Impoundment — Monitoring

E. The City, with the assistance of a 36 CFR 61 and 950 CMR 70 qualified
archaeologist, will monitor the construction of the downstream dam access route in
Roberts Meadow Brook, and the construction, excavation, and stone removal
activities associated with the breaching of the Upper Roberts Meadow Reservoir
Dam. The monitoring effort will include the recordation of any structural elements
(e.g., core of the dam, waterpower elements, and mill stones) exposed during
excavation and stone removal work. Digital photographs and sketch/measured
drawings will be taken as safety considerations allow.

F. The City, with the assistance of a 36 CFR 61 and 950 CMR 70 qualified
archaeologist, will conduct walkover of the upstream impoundment following the
dewatering and removal of the dam to establish an existing conditions baseline in
advance of the natural sediment mobilization in the naturally deep ravine that
characterizes this portion of the original brook drainage. The walkover will consist
of close ground surface inspection to locate and identify potentially significant
archaeological resources. The City, with the assistance of the 36 CFR 61 qualified
archeologist, will consult with the MOA signatories regarding the need for the
protection or mitigation of any resources that may be identified.

Reporting:

G. A technical report will be prepared describing the results of the DRP, monitoring,
and post-dam removal walkover efforts that meets the state permitting standards of
the MA SHPO guidelines for archaeological investigations (950 CMR 70.14).

H. The report will be submitted to, and reviewed and approved by, the MA SHPO and
the Corps. The Corps will consider all comments for incorporation into the final
document. If comments are not received within 30 days of submission, it will be
assumed that the technical report is complete and acceptable.

4
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
I. The City will ensure that two bound copies of the final technical report will be
provided to the MA SHP° pursuant to 950 CMR 70.14, along with updated MA
SHPO archaeological inventory form for the Edwards-Moody-Hoxie Tannery Site,
and an electronic file on a CD-ROM with the final report, bibliographic data and
archaeological abstract. A bound copy of the final report will also be provided to •
the City, the Northampton Historical Commission, the Corps, and the Friends of the
Upper Roberts Meadow Dam and Reservoir.

IV. Preservation of Stone Masonry Dam Abutments and Earthen Dike

The north and south stone masonry dam abu inents and the northerly dike will be retained, to
the extent possible. The extent of the abutments to be retained will be assessed during final
design phase and confirmed during the construction phase of this project. The primary goals
of the undertaking are to remove the hazard caused by the Poor condition of the URMR dam
and to remove the stream flow obstruction. (See Exhibit 1, Sheets #2, #4, and #5).

V. Preservation and Re-use of Historic Materials

Some of the dam's stone masonry blocks will be removed, segregated, and transported by the
Contractor to a City defined location for stockpiling The salvaged blocks may be used by the
City in a future project. Some of the blocks will be kept at the dam site and will be
incorporated as part of the historic signage area (Refer to Stipulation VI below).

If the old mill stone from a former bark grinding mill structure (reported to be at the base of
the dam by the BUAR) is found during construction, a reasonable attempt will be made to
remove it and incorporate it into the on-site interpretive signage area.

VI. Historic Sig-nage and Viewing Area

A historical signage and viewing area will .be created at the dam site near the remnants of the
northern abutment of the dam. The exhibit panel text and images will be prepared with the
assistance of a 36 CFR 61 and 950 CMR 70 qualified historian. A draft of the panel design
and content will be provided to the Northampton Historical Commission for review and
comment. The historic signage area will include an exhibit panel with text and images
explaining and illustrating the history of the URMR dam and Edwards-Moody-Hoxie-
Tannery Site, one or more of the stone masomy blocks from the spillway section and (if
found) the former mill stone. The historical signage will be completed as part of the dam
removal construction project. The City will coordinate with the MOA signatories on the final
design for the historic signage and viewing area. Photographic images that are of sufficient
size and resolution to be legible on the final exhibit panels, and overall images of views of
the installed signage and viewing area, shall be provided to the MHC within thirty (30)
days of the installation of the signage and viewing area.

5
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
Public Access and Path

An existing logging road on the north side of the Roberts Meadow Brook will be used as a
temporary construction access road the project (See Exhibit 1, Sheet #3). Portions of the
construction road will remain as an unpaved walking path to allow for public access,
extending from Kennedy Road to the historic signage and viewing area noted under
Stipulation VI above (See Exhibit 1, Sheet #6). The City will provide the Corps and the
MHC with project plans for the final design of the permanent public access walking pathfor
review and approval within thirty (30) days of receipt.

VIII. Post-Review Discoveries

The Corps and the signatories agree that if previously unidentified historic resources are
discovered and which may be affected by the undertaking, the Corps will notify the MA
SHPO of any findings consistent with 36 CFR 800.13 and Corps regulations. The Corps,
in consultation with the MA SHPO, will apply the National Register criteria and
eligibility and consult with the MA SHP() in order to resolve potential adverse effects
pursuant to 36 CFR 800.4 to 800.6 and Corps regulations.

IX. Duration

This MOA will be null and void if its terms are not carried out within five (5) years from
the date of its execution. Prior to such time, the Corps may consult with the other
signatories to reconsider the terms of this MOA and amend the MOA in accordance with
the provisions in Stipulation XI, below.

X. Dispute Resolution

Should any signatory party to this MOA object in writing to any actions proposed or the
manner in which the terms of this MOA are implemented, the Corps shall consult with
such party to resolve the objection. If the Corps determines that the objection cannot be
resolved, the Corps will:

A. Forward all documentation relevant to the dispute, including the Corps proposed
resolution, to the ACHP. The ACHP shall provide comments to the Corps within
thirty (30) days of receiving the documentation. Prior to reaching a final decision on
the dispute, the Corps shall prepare a written response that considers timely
comments from the ACHP and the signatory parties, and provide them with a copy
of this written response. The Corps will then proceed to a final decision.

B. If the ACHP does not provide comments regarding the dispute within the thirty (30)
day time period, the Corps may make a final decision and proceed accordingly. Prior
to reaching such a final decision, the Corps shall prepare a written response that
considers all timely comments from the signatory parties to this MOA, and provide
them and the ACITP with a copy of such written response.

6
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
C. The Corps responsibilities to carry out all other actions subject to the terms of this
MOA that are not the subject of the dispute remain unchanged.

XI. Amendments

This MOA may be amended when such an amendment is agreed to in writing by all
signatories. The amendment will be effective on the date a copy signed by all the
signatories is filed with the ACHP.XII.Termination

A. If any signatory to this MOA determines that its terms will not or cannot be carried out,
that party shall immediately consult with the other party in an attempt to develop an
amendment per Stipulation XI. If, within thirty (30) days (or another time period agreed
to by all signatories), agreement concerning an amendment cannot be reached, any
signatory may terminate the MOA upon written notification to the other signatories.

B. Once the MOA is terminated, and prior to work continuing on the undertaking, the Corps
must either (1) execute an MOA with signatories pursuant to 36 CFR 800.6 or (2) reques,t,
take into account, and respond to the comments of the ACM' under 36 CFR 800.7. The
Corps shall notify the signatories as to the course of action it will pursue.

Execution of this MOA by the Corps and the MA SHP° and implementation of its terms evidence
that the Corps has taken into account the effects of the undertaking on historic properties and
afforded the ACHP an opportunity to comment.

7
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
SIGNATORIES:

U.S. ARMY CORPS OF ENGINEERS

By: fikii (K70- Date: b_ite


e nifer L. McCarthy", Chief, Regulatory Division

MASSACHUSETTS STATE HISTORIC PRESERVATION OFFICER

By: Date:
Brona Simon, Massachusetts State Historic Preservation Officer
7

INVITED SIGNATORY:

CITY OF NORTHAMPTON
II

By: Date:
David Narkewicz, Mayor

CONCURRING PARTIES:

NORTHAMPTON HISTORICAL COMMISSION

Date:

FRIENDS OF THE UPPER ROBERTS MEADOW DAM AND RESERVOIR

By: Date:
Barbara Pelissier

8
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
EXHIBIT 1
MOA PLAN SHEETS

9
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
GZA INTERCOMPANY PROJECTS\01.0019547.20URMRD Removal Final Design\ 01.0019547.20 CAD\dwg\ HISTORIC MOV EXHIBITS_031116.dwg [EXHIBIT1—OVERALL PLAN]
UPLAND SEDIMENT AND EROSION CONTROL NOTES. GENERAL CONDMONS: GENERAL CONSTRUCTION SEQUENCE;
I. REDWINE AND EROSION CONTROL BARRIERS AND DIRER MEASURES WENDED 10 TRAP I. UNDERGROUND MANY LOCATORS SHOPE HEREON IRE BASED ON SURFACE FEATURES AS ME WENT OF MS ANTHIPATED CONSTRUCTION DESHERTE IS TO PROVIDE GUIDANCE FOR SLUICED SEDIMENT MANAGEMENT NOTES:
soma SHALL BE CONSTRUCTED AS A FIRST STEP IN ANY LAND DISTURBING ACIMIT LOCATED BY SURVEY AND AVMAELE RECORD DATA. AND ARE CONSIDERED APPROMMATE APPLYING BEST MA/MOUE/IT PRACTICES AND FOR MEETING DOMpLEATTE MTH 0110111ONS OF 1
AND SHALL BE PACE FUNCTIONAL BEFORE UPGRAGENT LAND CISTURPANCE TAXES AORTAL LOCATION SHOULD BE VERIFIED WWI THE APPROPRATE MIRY COMPANY AND/OR DIVIRONLIERTAL PEONS ISSUED FOR TIE PROJECT. THE CONSTRuCTON SEQUENCE MAT BE I. $1EDIMENT RELEASED IS INTINNOT ID PARTIALLY SETTLE IN ROBERTS LIENION BROOK MO
PLACS, BEE OR ON NE WEB AT ALTERED BY 105 011 RASED ON TM OINDITIONS 01 AT THE waTTEI RECUEST FOR A PRCMOE ROMEO HAMM REPROTEMER OVER TINE TIE MANNING SEDNENTS ARE
MUNICIPN_ 001111110211. CONTACT 'C/G-SAFE•
PROM.) CHANGE BY TE CONTRACTOR TO BE REAMED NW APPROVE, 01 11)5 ENGINEER. EXPECTED TO SLUICE COOL-STREAM AND SETTLE Di THE 11/01/1 OVER SEVERAL YEARS.
INTIWINOODOSEECOM) AT LONNUM OF 72 BUSINESS HOURS (BUT NOE GREATER WAN ACTJESO FOR =weir
2. ME CONTFACHIR RIMEL CONSTRUCT ALL DROWN 1140 SEDDIENT COMROL MEASURES SHORT-TERII (<2 INRS) 110100I5 II) THE BROOK WILL BE HOMPORED AND RISKS TO
30 DAIS) PRIOR TO BEGNENG AM EXCAVATING CR SUBSURFACE DEPLORATION ACETATES. AMCOR RONNEAYS LOCATED THROUGH NAIVE SEMENE REMOVAL AS HEEDED. 144i4GEMENT
N ACCORDANCE NTH THE MANS AND TIE STORM/TATER POLLUTION PRenNuoti PIATI yAT-JUNE 2015
(SITPPP) PRIOR TO BEGINNING Nff LIND ERSTIARBANCE, SHELL ENSURE THAT ALL 2. ACME MIMES STOLL NOT BE DISTURBED UNLESS DIRECTED 01 1010 GM I. INSPECT OVANSTREAM READHES BERM MR AND INN AND ESTABLISH
RUNOFF FROM MAME° MEM 1. DIRECTED TO TIE SEDIMENT CONTROL DEVICES, AND PHOM-NONTORING POINTS, 2. MOUNT RELEASED IS EMENDED TO PARTIALLY SETTLE IN ROBERTS MEADOW BROOK MO
SHALL NOT REIWIE INY EROSTON OR SEDIMENT CONTROL MEASURES UNTIL TIE AREAS 2, PREPARE TIE ITECESSARY ACCESS REINES TO THE MAN DAM. PROODE BEMPIP HABITAT IMPROVEMENT IN THE IMAM TO LONG TERIL THE ROAMING
S. THE CONTRACTOR'S ATTENTION IS DRAWN TO THE PRESENCE OF OVD01040 PRES WINN REDRAWN ARE EXPECTED TO WIPE OODRISTREATI AND SETRE IN MRIM OVER A PERGO
DIAMOND TO THEM ARE FINAL STABILRED. TIE CONTRACTOR SHALL INSPECT ONLY AND THE VICINITY OF WORK. THE CONTRACTOR SHALL TAKE ALL NECESSARY PREY/AGNS TO
PAINTOLN COMINUOLLSLY DI EFFECTIVE OPERATING c000rnoN ALL EROSION AND AINF-MCSINTER 7010. OF 5E1E0E-YEARS. SPORT TERM (52 YEARS) IMPACTS TO THE BROOK TALL BE MONITORED,
AVOID ME OVERHEAD WIRES OR ANY OTHER UPON SERVICES IMRE PERS/WANG 111E WORK MD RISKS TO AMMER ROADWAYS IA/BOATED THROUGH MARINE SEDDON REMOVAL AS
SEMEN CONTROL MEASURES UNIL SUCH TIME AS 711Ef ARE ROMMEL CONDUCT OF THE PROJECT; 3. CONDUCT LWASIVE SPECIES TREANOR ADJACENT TO OMR AND ON ALUM IRMO AS
INSPECTIONS AND RONNITENG Di ACCORDANCE rani ALL PERMITS PORMITED. NEEDED.
4. BENCHMARKS TOLL BE PREMED BE THE CITY AND SHALL BE WARMED BY THE 4. BEGIN STAGED DNA REMOVAL. BY REWARD TIE UPPER 54 FEET OF THE SPILLITAY SECTOR
3. THE SEDIMENT AND EROSION CONTROL MEASURES AND BEST PANADEVIENT PRACTICES CONTRACTOR MR THE DURATION OF THE PROJECT. PAWED OR 04010000 014034101115 OF THE MN TO BEGOT DERATERNG THE URAR IMPOUNDMENT. 3. THE CONTRACTOR MOLL. NOM THE PROJECT ENGUIM INIEDATELY UPON OESEIVING
(IMPS) SHOWN ON TES PLAN SHALL BE CONSIDERED AS MINNA RECURETIENTS. SHALL BE REESTABURHED BY TE CONTRACTOR, TEMPORARY BENCH MARIS ME MVO ON 5. MONITOR DtWATERNG PROGRESS NW SEDNENT MONLIZATION; DEFECT MAINSTREAM REACHES RENAME ACCUMLAATPN(S) Di THE BROOK- THE PROJECT ENGINEER WILL OETEMONE F
MITEVATELY UPON OSCOIDING LIEFORIMEDI CINCUYSIANCES POSING THE oomovi. THE DRAWINGS, HOMER, THEIR EXISTENCE DR ACCURACY MINOT BE GUARANTEED AT THE AR), AT ERECTION OF THE CRT, ADMITTED' MANAGE SIGNEOCANE REINERT ACCUMULATOR OBSERVED SEDIMENT ACCUI/ULATXIN(S) LS IMPEDING RIMING ARD WEL DRECT THE
AREAS THAT IMINT POSE A F1006010 RE( TO RESEW= ROM. • CONTRACTOR ID REMOVE SEMEN AID DOORS BLOCKMES RUHR ME BROOK.
FOR ACCELERATED EROSION ANIT/OR SECOADEE POWITION, THE CONTRACTOR SHALL 11115 CONSTRUCTION BEGNS. B. REMOVE THE NECT SI FOOT CO 10* FOOT VERTICAL SECTION FOR ITS NEXT STAGE OF OW
IMPLEMENE APPROPRIATE MPS TO ENDOW ME POTENTAL. FEET ACCELERATED EROSIDN RINOVAL. ALLOW RESERVOIR DEBATE/14O MO SINFAII STAMMATON. MO CONTINUE
5. 'ME CONTRACTOR NOEL VERIFY DOMING DNERSINES, ELEVATIONS. DATIONETRY, 310 4. AREAS OF ACCESS TO THE BROOK FOR ADDRESSING SECOTENE ACCUMULATORS ARE SHOWN
AND/OR SEDIMENT POULITPIL 1HE CONTRACTOR MOLL INSTALL MD MAINTAIN AT NO MAINSTREAM MONITORING. ON THE DRAWINGS MO ME LOCATED IN AREAS WHERE SEDDLENT ACCUMULATORS ARE
ADDITTONAL COOT TO ME 051191. ANY ADETIONAL EROSION CONTROL MEASURES DEEMED INCOUT MD SHALL NOTIFY THE ENGINEER OF NET AND ALL INSCRMANCETS N WRMILD
PARR 70 COMPENCING MY WORK. 7. REPEAT SEPS S AND 6 UNTIL THE DAM IS COMPLETELY MOVED. ESTNATED TO OCCUR, HCATIVER CIONGIM AND AMMONS TO BROOK ACCESS MAY BE
NECESSARY FOR PERIN COMPLIANCE BY THE CONTACTOR, THE OWNER, AND/OR THOR B. THE COMPACTOR TO SECURE TIE SATE AND 0E/040M FOR WIRIER. TEDGESSARY TO ACCESS SEDDEENT ACCUMULATIONS NOT ANTKPATED. CHORES OR
REPRESENTATIVES, DR BY FEDERAL/STATE/LOCAL GOVERNMENT INSPECTORS. ADDITIONS TO BROOK ACVSS AREAS WILL BE DETERMINED BY THE PROJECT 0151110 11
B. THE 030I00100 SHALL BE RESPONSBLE FOR MENIS 11110 1.15110115 OF CONSTRUCTOR,
00001 514017 SPECIFICALLY DETAILED IN THE CONTRACT COCA/RENTS. DECI41REELIASE01.21117. ACCORDANCE TOM TILE ORDEN OP 00110111015.
4. STAFAUZED CONSTRUCTION ENTRANCE(S) SHALL BE INSTALLED CONCURRENTLY WWI THE 9. THE CRY TO CONNIVE INSPELTKIN OF THE COANSMEMI REAcHrs IND oolsomi IN-STREAM
INTRADON OF NUM% GRUBBING AND CREATIONS OPEFLATION.S. THE CONTRACTOR 7. AIL ITORIC $HALL COMPLY TOTH ENVIRONMENOL PUNITS ISSUED FOR ME PROJECT. #111101710 56001015 MANAGOIENT ALIMITIM, AS NEEDED, 10 IIRSVOrt 11.1300I10 Of RESERVOIR
SHILL PROTECT NI PORTS OF CONSTRUCTION INGRESS AND EGRESS TO P50100 10 ROAD FOR 3 ID 4 11001S *aim THE CONTRACTOR IS NOT ON-SITE!
DEPOS1T1ON OF MATERIALS DITTO TRAVERSED PUBLIC THOROUGHFARES. ALL MATERIALS B. THE CONTRACTOR SHALL NOT DISTURB OR REMOVE NCO TREES 0-000 DIAMETER AT BREAST
DEPOSITED ONTO PUBUC THOROUGHFARES SHILL BE REMOVED IMMENATELY. HOCK OR GREATER ITIMOUT FEST MARANO ANT SUCH TREES MO RECEMNG WRITTEN MARCH-APRIL 7017 MEATIER PENDINO4,
APPROVAL FROM THE MY. TO. THE 055000101 10 6010012010 1115 SITE,
11. CONTINUE DOWISTIREABI MONEWRING FOR SIEMER ACCUMULATOR ND POTENTIAL FIDOWNG
5. ME COMPACTOR SHALL BENI ID APPLY SOD. SIM AND AJECHORED STRAW vani. RISKS MD MANAGE ANY CONSMCITONS AS NEEDED (ALONG REERYOR ROAD) AT THE
DR OTHER APPROVED STABLEMAN MEASURES TO NI MARRED AREAS IMMEDIATELY B. ON SITE EQUIFIENT AND MATINIALS STORAGE DOLL BE CONFINED ID ME SIMKO MEA(S)
AFTER STOPPING AND GRACING ACITTES HAVE CEASED DLL THAT AREA AND STOLL SHOWN ON THE DRAWINGS AND IN ACCORDANCE WITH THE STIPPP FOR THE PROECT AND DIRECDON OF THE CITY.
COMPLETE STNTLIZATEN ACTIVITIES 111119/1 FOURTEEN (14) CALENDAR DAYS [SEVEN (7) SMALL BE PROPERLY SECURIM AT ALL 10101 111411 PFPSIMILF1 ARE NOT PRESENT ON $ETE 12. RESTORE THE TEMPORARY 0:IN4510010 AREAS (INCLUDI)45 MGM ROUES) TO PRE-DAM
FU340VAL CONDMONS.
CALENDAR DAYS F THE IvsomADGE IS TO AN REPAIRED WATER 541 10 A TER 2/2.5 IS. PREPARE THE TEMPORARY OONSTRUCTION ACCESS ROUTE ID LEFF ODE OF THE MI AS A
EWER). NIAMENNICE SMALL BE PERFORMED TO DOUSE CONTORTED STARTRADON. 10. RIES, LLITINPANIS, OR OTHER WARMS MATERIALS SHALL BE SACRED ONSHORE ONLY PI
A =MIRE METAL $TORAGE CONTAINEFL URCE FUEL/OIL STORAGE TARPS SHALL HAYE PUBLIC PEDESTRIAN ACCESS.
ACIDIC CONSTRUCTION AREAS, SUCH AS BORROW OR MCC/WILE AREAS, ROADWAY 14. COMPLETE HISTORKAL MITGATTON DELORS FOR THE FINAL MEMOMOUIA GP ACREELIENT
11PRINENEMS, AND ARDS WINN 60 FEET OF A MUNN UNDER cotisioucnoti MAY RECOMMIT CONTAINMER NED VNIIAL-PROOF LOCKING DEVICES. THERE SHALL BE 140
SIORAGE OF THE PETROLEUM PRODUCTS TOM WERNIO BUFFER ZONES OR RYER/ROW (EADA) BETWEDI THE U.S. NUN CORPS OF ENGINEERS, CITY CE NORTHALETON, MD
BE DEIFIED FROM TIE RETHMEMENT, PROVIDE) THAT ODER APPROPRIATE EMINENT CONSULTING MIES.
ABED EROSION CONTROL MEASURES ME NSTALLED AND LIANDWED TO PROTECT AND PROTECTION AREAS.
IS. ME CONTRACTOR 11) PERFORM 00111 SETE RESTORATION 1,1.11015.5 'MO RELIEVE SEWER
PROADE SEDIMENT CONTROL FROM THOSE AREAS. ANO EIDSON CONTROLS,
11. RIEUELING DF EQUIPLIENF SNAIL EE PERFORMER WITH TE MLITT TO DOEDATELY ACTUATE
THE APPROVED FUEL/OIL CONTAINMENT AND SRN- RESPONSE PLAN.
R. ALL DISTURBED SLOPES STEEPER TON OR EQUAL 10 37 (ELV) SHALL BE STADIUM
TOM SOD. STEED NED ANCHORED STRUT MULCH, 00 OTHER APPROVED STEILIZATION 12. THE CONTACT COCOONS ED NOT FRONDE ALL ELEMENTS NECESSAFTI FOR SITE SAFLTO N/F
MEASURES. WWI SEVEN (7) CALENDAR DAYS OF ESTABUSINENT. NO AREAS OUTSIDE TIE COMRACTOR SHILL BE RES/TREBLE FOR ESTAELISHING SAFE OPERATIXIS DI AND
HISTORIC FEATURES NOTES' JEN,L.HY D. & DIANA H. GORDON
Of ME PERIMETER 50/0I0E0 CONTROL BARRER OR MT OF WORK SHALL DE MOUND THE SITE. WONG AGRICULTURAL FIELD
DISTLIRETELL 510110415 OF 111E DAM STRUCTURE MD OTTER FEATURES SHALL BE PREMED AND PROTECTED
13. TIE CONTRACTOR DOLL RESTORE AREAS DISTURBED BY CONSTRUCTOR ACTMRES Pi FOR IDSTORIC PURPOSES MLLAMEG THE FOUITIONDI
7. 5100514I10 WHICH 1111 !KIT NE USED FOR A PERIOD OF FIDOITIM (14) OR MORE ACCORDANCE NM TIE ONTINACT DOWNERS WHERE III SPECIFP DESTRUCTOR IS GWEN,
RESTORATION MOLL BE TO ITE ORIGINAL CONDITION AND WEL BE DONE AT 43 ADDITIONAL 1. THE NORTH AND SOUTH (LEFT AND FLIGHT, RESPECT/In) (MN AFAMENTS AND IRE
CALCIUM OATS [SEVEN (7) OR {PRE CALEILIAR DAYS IF THE DISCHARGE IS TO AN NORTHERLY MUNDT DIKE WILL BE REENTER TO THE TIAXIMUM ',OEM POSSIBLE THE
&FARED PATIN OR TO A TER 2/2.5 WATER] SHALL DE MINED STABENED THROUGH 007 10 THE CRT.
ECIEM Of THE ABUTENTS TOT CAN BE SAFELY RETAINED WILT BE DETERANED IN TIE
THE APPUCOTON OR SOO, SEED, AND ANCHORED STRAW MULCH, COVERS, OR ODOM FELD IN THE PROJECT ENGINEER MD DI COORDINATOR TEM THE PoSSACHUSETTS ELISTORICAL
APPROVED STMILFLATION MEASURES. 14. NOT ALL MEM ON SITE ARE SHOWN ON THE DRAWINGS. NO STERNUM TREES (000E04) OMISSION.
$HALL BE DISTURBED OR REMOVED WITIOUF CONTRACTOR FIRST MARKING PROPOSED TREE
REMOVALS AND SEEKING WRETTIN APPROVAL FROM THE CM All NSTORICAL INTERPRETIVE ono STOLL BE INSTALLED NEAR TIE RITHANTS OF THE NORTH
B. SEDIMENT TRAPPING/FILTERING LIMPS SHALL BE CLEANED DUE WHIN TIE REDREW
ALCUMULAM TO ONE HALF THE MOM Cf THE MN, AT?, MNIMUIL DAM ABUTMENE Di COORGINATION NTH THE NORTHAMPTON moon coloomoo.
GENERAL PLAN NOTES: SELECT LARGE RECTANGULAR GRANTEE BLOCKS 04 THE MI SNAIL. TE MGM INTACT A.10
9. THE CONTRACTOR SHALL IE RESPONSIBLE RIN THE CONTROL OF DUST AND DIRE RISING PRESERVED ON ODE OR AT A LOCATION TO BE DETERMINED BY THE 0101 MD AT TIE
AND SCATTERING DI TIE AIR DORM CONSTRUCTION AND SHALL PROVIDE HAM MENTON OF ME PROJECT ENGINEER
SPRINKLING, CAUCTUM CHLORDE AND/OR OMER 31.105101 TEEMS OF CONTROL 1. EASE PAP PLR THE PROJECT PIM WAS GENERATED FROM MUMTAZ SOURCES
A. OVERALL PROJECT AREA FEATURES INCLUNNO NEE!$, PROPERTY BOUNDARIES, A MILLSTONE IS PURPORTED ID LAY AT THE RASE OF THE OM. IF THE MUSTONE
10. ALL WASTE WAIERPLS CEERATED AT THE SITE SHALL BE INMENATELY REITOVED AND ENCOUNTERED, ME CONTRACTOR AT TIE DINECTRE OF THE PROJECi ENONIDER, SHALL MACE
PERMITS OF ROBERIS TEADOW BROM AHD 17IE UPPER ROBERTS MEADOW A REASONABLE 01001 10 RECUMM IT.
=POSED OF OR STORED Di A SECURELY COVERED CONTNNER 01 ACCOIREANCE MTH RESERVOIR WIRE CETTADIED 111041 LOPPRO PROVIDED DT THE CITY OF NORIMPION
PROJECT PERMITS AND LOCAL AND STATE REGULATIONS. CONTNNER SHALL BE MIMED AND AERIAL PHOTOGRAPHY MADE AVNIABLE BY THE MASSACHUSETTS GINGRAPHIC
ON A REGULAR BASIS MO AS NEEDED. NO COMM/CRON ITASIE OR DEBRS SNAIL BROOK ACCESS FOR
INFORMATION 010)011 (PARROTS). SEDDON' 1.4NADEMENT •
BE BLARED LENNIE B. EXISTING CONCETPHS AT IRE DMA AND DOIEDIATE COWART:FM AREA ROE MANED
FROM A PLAN INITTLED .TCPOGRAPHO NMI OF 'AND El NORINALIPION, N_OhD RESERVOIR ROAD
11. POUR 10 RELKIIAL OF SEMENT CONTROL MEASURES, THE CONTRACTOR DOLL MASSACHLISEITS, PREPARED BY HERITME SURVEYS, INC.. 05111111 SEPTEMBER 2007. -NO ma REMOVAL &LOBED
50001/1 All CONTREARCRY CISRMED AREAS USING SOD OR AN APPROVER C. MMHG ITAIHMETRY WENN TIE UPPER ROBERTS MEADOW RESERVOIR WAS
PERMANENT SEED MIXTURE WITH REGIME/ SOO- AMENDMENTS MD AN APPREHED SURVEYED BO GIA CEDEEMRCNITENTAL. NC. DI A.A.T ODOR.
ANCHORED MULCH. AREAS BROWN TO FINISHED GRADE DURING DE SIMINO SEASON D. POSTING CONDMONS FROTA THE MA 10 APPROXIMIELY 1,000 FEET COWNSTREMI
SEOLL BE PERIAMENTLY STABLE= WREN FOURTEEN (14) CALENDAR DAYS [SEVEN (7) Cf TOE DMA WAS OBTAINED FROM A RAN DORM IRAN OF LAND Di
CALENDM DAYS IF THE DISCHARGE IS 10 AN WANED WATER OR TO A 1EI2 2/2.5 NORTINEMN, TOSSAMMETT PREFORETT BY HERITAGE SURVEYS, NC., DATED JULY
TAM) OF COMPLETION OF WORK AREAS BROUGHT TD DRAGE DERNG THE MONTHS 2013.
WHEN PORIAMENT STABILIZATON 5 FOUND TO BE IMPRACTICAL SNAIL BE STADIUM
1010 AN APPROVED TEMPORAM SLED NE ANCHORED ARCH OR OMER ACCEPTABLE
E. COSTING CONCRIXES AT THE NIET AREA OF THE EIDDLE ROBERTS REMOTE dffrOF
NORTHAMPTON
RESERVOIR WERE OBTAINED FROM A PLAN DOTTED 'PLAN OF IMO DI •
1101145 110 PERMANENTLY STABILIZED DUMP THE SEEDING SEASON. NORINALIPTON, WSSACHUSETTS' PREPAIED BY HERITAGE SUREYS, INC. DATE/ JULY
2D14.
12. TEAPOPARY SEDIMENT CONTROL OLTA.E., DOLL BE REMOVED VENN THIRTY (30) DOMING LIATIMETRT WITTIN THE MIDDLE ROBERIS MEADOW RESERVOIR HET AREA
CALOIDAR GAlS FOLLOWNG ESTABLISHMENT' OF PERTIAMEN STABUTATON Di 011 WAS SURVEYED UT CON GECONRIONMENTAL INC. Di JUNE 2014.
CONTRBUTORY ORP111PP AREAS. STORMAATER IONAGETER STRUCTURES USED
TINPORARLY MR SEDDENT CONTROL MALL BE CLEANED MD CONDONED TO WM 2. WETTAND CELLNEATIONS BY VA CEDDNIROMEINAL DEC
PERIANONT CONFIGURATION 511141 THIS TIME PE1000 AS WELL ALL STORM DRAINAGE AUGUST 2007, ONE 2013, AND JURE 2014.
STRUCR/RES, SAWS, AND PIPES STOLL BE CLEANED OF ALL SEDDIENIS MIOR TO TYE
111111 PATIENT. BENCHMARK: SPIKE Di ORLEY POLE LOCATED AT THE SOUTH SPE OF 11161000.0 ROAD
OPPOSRE TIE ay. ELEV..459.01. THE VERTICAL DARN 6 Di FEET AND REFIRDECES ROBERT A. & ANN 11. BORAWSKI
THE EATON& GEODETIC VERTICAL MUM OF 1929 (1111/020). EGSTING AGRICULTURAL FIELD

4. NORMAL UPPER ROBERTS MEADOW RESERANI WATER SURFACE ELEVATION .4 450.21.
S. BASEUNE SHOWN TROUGH UPPER ROBERTS MEADOW RESONDIR FOLLOWS ORNIOL
STREAM 04113110. 10 APPROXIMATED BY BATITMETWO SUR/EY RAMIE,

N/F
MERLE L JR- & MERLEYFJR.
N/F ROTH C. TA
ELTIABETT J. & CARTE G. RUTH C. TAYLOR
ANDERSON
200 FE VERNAL POOL GRAPHIC SCALE
RESOURCE AREA
EDSTING WOODS ROAD ID BE USED FOR
TEMPORARY CONSTRUCTION ACCESS.
0 250 500
TO RE (504004100 10 PEDESTRIAN TRAIL
UPON COMPLETION 037511W REMOVAL
ACRWINES
SCALE IN FEET
TEMPORARY
COKSTRLICRON
71/F ACCESS TO DAV
CITY OF
TADRINAILPTON

00)01110 03W DATE


TO BE REMOVED POTENTIAL BROOK ACCESS NO. ISSUE/DESCRIPTION BY
ON
STAGING AREA FUR MANAGEMENT. UNLESS SPECIFICALLY STATED BY WRITTEN AGREEMENT. THIS DRAWING IS THE SCL PROPERTY OF 5.5./,
UPPER ROBERTS MEADOW -SOME TREE REMOVAL NECESSARY
GEOENVIRONMEINAL, INC. (024). THE INFORMATION 5000/1 ON THE DRAWING IS SOLELY FOR USE BY GZA'S
• 441050,0151 )0 BE CLIENT OR ME CLIENT'S DESIGNATED REPRESENTATIVE FOR THE SPECIFIC PROJECT AND LOCATION IDENTIFIED ON
CONVERTED TO STREAM
© 2016 — GZA GeoEnvironmental, Inc. GZA—A0

THE DRAWING. THE DRAWING SHALL NOT BE TRANSFERRED. REUSED. COPIED, OR ALTERED IN ANY MANNER FOR
UPON RBIOVAL OF aw
.N .0040NSTRUCTION STAGING
N/F
CITY OF
USE AT ANY OTHER LOCATION OR oOR ANY OTHER PURPOSE WITHOUT THE PRIOR WRITTEN CONSENT OF GOA- ANY
TRANSFER. REUSE. OR MODIFICATION TO THE DRAWING BY THE CLIETET OR OTHERS. WEHOUT THE PRIOR 45017511
EXPRESS CONSENT OF CZA. WILL BE AT THE USER'S SOLE RISK AND WITHOUT ANY RISK OR LABILITY TO GZA.
• AREA & BROOK ACCESS NORTHAMPTON
FOR santarr Atimoaferr
TEMPORARY STABILIZED UPPER ROBERTS MEADOW RESERVOIR
CONSTRUCTION ENTRANCE
DAM BREACH AND ECOLOGICAL RESTORATION PROJECT
WF
NORTHAMPTON, MA
CITY OF
NORTHAMPTON
FRANCES IL
I-T
LORRANE CLAPP-O'KEEFE Et OVERAL SITE PLAN
KEVIN O'KEEFE

=FEL
PREPARED BY: PREPARED FOR:
WENN) REROURCE MACAW
200 FT. MEDIAL POOL REVOKE
AREA BOLIN:PRY
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
200 FT, 01,007005 01,401101
Engineers and Scientists DEPT. OF PUBLIC WORKS
• www.gza.com
APPROXMATE P4011040100
EOSTNO OPE OF INTER PROJ MGR: MAT REVIEWED BY: NYA CHECKED BY: MAT EXHIBIT
-'001030 005 OF IMMEENT DESIGNED BY: NYA DRAWN BY: EDM SCALE: 1,
500'
PISTON TREE Leic PROJECT NO. REVISION NO. 1
FEB 2017 01.0019547.20 SHEET NO, 1 OF 6
CONDMONS]
LECEIR
/ DWI BINI 1400
2 l'iats 11' \ \._\ BISEUNE (SEE GENERAL PLAN NOTE #5 ON DWG. 2)

/7/ .
, \
._ --- — —
452 --___ \--... —•--11-01 e. WERAND RESOURCE BOUNDARY 81II1 WETLAND FIAG
___ — 03— — — — DOMING EDGE OF WATER
___- -.(4-2"‘"--
___ --- -____,KA___ -__ ___ -11-1.::- — --- --- ) ) ///
----- ---- TOF\ ABUTMENT EXISTING EDGE OF PAVEMENT
---- ,1
1.
----
--- _----
.-----
/
----- 445
Auguyik.
// / //':zy/ n n EXISTING GUARD RAIL
. . / / z'e EDGE OF WOODS
EX EAR1}IEN E
MOANINENT: DIKE 8 / // / /z EGSTING OVERHEAD WIRES
Cfl mow min POLE

1 / 7 . EXISTING TREES (NOT AU_ TREES ON SITE ARE SHOWN)


/ EOST1NG 5 FT. UPLAND CONTOUR
// — — — — DUSTING 1 FT. UPLAND CONTOUR
7- 2.5.6 — DOMING 2 FT. RESERVOIR BOTTOM CONTOUR
— — — — — — — — — X423.I E0571NO SPOT GRADES
/ ABURIENT7-4 4-.24—
000( A-4+ BORING LOCATION (SEE DAM/AMON NOTES #1 AND
12 BEUOY0
17 --
------
TOP ABUTMENT-454.1
82.0.9
‘ti
SPILLWAY CORE LOCADON (SEE DOROPADON NOTES
#1 AND #3 BELOW)
II / /
/ ----- --
Ogr5

II • olf „--
Pig'k
"-
cii
ATO
ASSORTED
ITERAND RFSOORCE AREA KEY

BORDERING VEGETATED WETLAND


/ /z HOCKS Ac BOULDERS
i PEger;„‘gg..,
\ -9+50
LJJN LAND UNDO WATER

1 / / / z' BANKOMM1/011/1).• BANK (MEAN ANNUAL HIGH WATER LINE/


ORDINARY HIGH WATER)
/ / , ROBERTS MEADOW \ Fwpi nRaoN NcrrFc•
/ UPPER RESERVOIR
// / / ( WATER ELEV \ 4,0 1. DCPLORATION LOCATIONS WERE APPROXIMATELY DETERMINED IN
FIELD BY TAPE MEASUREMENTS FROM EXISTING SITE FEATURES.

/////// // 450.2'
9/7/07
I
THIS DATA SHOULD BE CONSIDERED ACCURATE ONLY TO THE
DEGREE IMPLIED BY THE METHOD USED.
2. BORINGS PERFORMED BY NEW ENGLAND BORING CONTRACTORS OF
• / / / / / 432--
) I 4,15-8
GLASTONBURY, CONNECTICUT ON SEPTEMBER 27 AND SEPTEMBER
28. 2007. OBSERVED AND LOGGED BY GZA GEDENVIRONMENTAL
// INC. PERSONNEL.

zz z / _ 3. SPILLWAY CORE PERFORIAED BY NEW ENGLAND BORING


CONTRACTORS OF GLASTONBURY. CONNECT/CUT ON SEPTEMBER
z ' 'zzz z I 4571 6.0 440
27, 2007. OBSERVED AND LOGGED BY GM GEOENARONMENTAL.
INC. PERSONNF1.

Vvv / z I z
Yyy / z 8, AR\ I \
V V nA
uo(Jslir (Top)
/
/ O
1
43

V 7 TOP DA4-450...65 ____ _ 444 — -____


TOP WI wAU. ,

.7" 445

.-- .----- ----- STON


WING
/ ..---' _44a_
..7 .-•-' .----.
.---' ----- TOP 1111IGIYAU.49 ___-
..-"" ,---' ..----- TOE %INGRAM,- INNGWALL-44111.41
..--' „----- -------
,----- V ------ ,-- 448--
..--' ---/ ------ ,----
----- V 7 ----' -- 449
------- _,•-' 7- ...”' .----
----- V 7- ----- GRAPHIC SCALE
----- -,----- ,---/
,../.' .,--- __--- 0 10 20 40
----
,------- 7- ----- .-----
------ 7 ,----- 7 ---- • SCALE IN FEET
.---- -----" .„----- ----
---- -----. -----
..---- /- ,-----
.---'
----- .---- ,----- ------ ------' ------- B-4 ( PIMPIONNINEEN

----- ---". _., ----- .--- ---- -----


------ .------ • .---* 7 --- ...----
---- \ \-
--- • -- • ,-----. _.,..--- _____, _ _
„„.--- ___..,..
-..---. ----
/
--- --- ) -•:_____ ----:_____, ..--'"
L..'.. IT
____.__ /
,,...'' .../.
NO. IssUE/DESCRIPBON BY
UNLESS SPECIFICALLY STATED BY WRITTEN AGREEMENT. THIS DRAWING IS THE SQL PROPERTY OF GZA
DATE

.--- — --- \ -- ----- ,.___.,. ---- ----


......., \ GEOENVIRONMENTAL, INC. (GZA). THE INFORMATION SHOW( ON THE DRAWING , SOLELY FOR USE BY GZA•S
---- ..---- __ -------- ..,.--'. ,..,-_...- CLIENT OR THE CLIENT'S DESIGNATED REPRESENTATIVE FOR THE SPECIFIC PROJECT AND LOCATION IDENTIFIED ON
.------ ..-- ..----- ....,.•
----" THE DRAWING. THE DRAWING SHALL NOT BE TRANSFERRED, REUSED, COPIED. OR ALTERED IN ANY MANNER FOR
USE AT MY OTHER LOCATION OR FOR MY OTHER PJRPOSE WITHOUT THE PRIOR WRITTEN CONSENT OF GZA. MY
TRANSFER. REUSE. OR MODIFICATION TO THE DRAIVING BY THE CLIENT OR OTHERS. WITHOUT THE PRIOR wRintii
---- --- EXPRESS CONSENT OF GZA, WILL BE AT THE USER'S SOLE RISK AND WITHOUT ANY RISK OR UABIUTT TO OZA.

452 \ ---- ------- \


_ 4' ----,-- ___.— ---- —— UPPER ROBERTS MEADOW RESERVOIR
--- ,--,--- .,-- DAM BREACH AND ECOLOGICAL RESTORATION PROJECT
--1,-----
___._ ----""— --- NORTHAMPTON, MA
-----3>
— —454__ -----j•-• .----- Ae
___--- ---- _,..---
"--
: 2---H EXISTING CONDITIONS AT DAM
____
/

Oe'9
.----
/ / 5'1 " FT PREPARED BY: PREPARED FOR:
45e 03..
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
- --- 457- Engineers and Scientists DEPT. OF Punic Wows
www.gza.com
4,50----
PROJ MGR: MAT REVIEWED BY: NYA CHECKED BY: MAT EXHIBIT 1
---459---
DESIGNED BY: NYA DRAWN BY: EDM SCALE: 1"•=20'

FEB 2017 PROJECT NO. REVISION NO. 2


01.0019547.20 SHEET NO. 2016
TEMPORARY CONSTRUCTION MATS FOR WETLAND TEMPORARY CONSTRUCTION MATS FOR WETLAND 214548
CROSSING ALONG EXISTING LOGGING ROAD CROSSING. REPLACE WITH PEDESTRIAN WETLAND
TEMPORARY TIMBER BRIDGE ALIGNMENT. MATS TO BE REMOVED AT CROSSING AT COMPLE770N OF DAM REMOVAL r 234' ,
FOR SWALE CROSSING. COMPLE770N OF DAM REMOVAL ACTIVITIES. ACTIVITIES.
*IF v1353
REPLACE WITH PEDESTRIAN
SEDIMENT AND EROSION CONTROLS- SHALL
BE COMBINATION SILT FENCE/STRAW BALE SEDIMENT AND EROSION CONTROLS SHALL
05,17
WETLAND CROSSING AT
THRU WETLAND AREAS. BE COMBINATION SILT FENCE/STRAW BALE
COMPLE770N OF DAM REMOVAL
Ntlf 2\11329 ....."- THRU WETLAND AREAS.
ACTIVITIES.
028
‘14v 2\

V•IF 1v 2 \054 445 Site Avoidance Fence Line


'
34 K2.0

— SILT FENCE

20°6

6 z1305 \
TEMPORARY
TURNAROUND
\ \
6V\\vfA ( )
_

Archaeological
Data Recovery
r ----:------ ---
l
'
t
Area La
1:2- ' /
--;,-...:.- -.-
Dam Removal -/-,ll• , _.....
I- -
Monitoring Area
TEMPORARY ACCESS IN BROOK. ltT
USE CONSTRUCTION MATS AND
EXISTING RIVER STONES TO
CREATE/SUPPORT ACCESS ROWE- BOO r• '-x--.-Senve No Impact Area
---- -- F7LL AROUND .- 00'. S••••'
•-
STAGED DAM OR REMOVE A mEAD°W 40 01111
REMOVAL POR770N OF
/K MASONRY FOR ROBERTS
EQUIPMENT
- 432 ACCESS GRAPHIC SCALE
_- -
INFORMATION -
- 434 ---- -- -- 0 25 50 100
DAM
UPPER ROBERTS — —
SCALE IN FEET
MEADOW RESERVOIR — _
: EARTHEN EMBANKMENT DAM AND
440.
STONE MASONRY WING AND
-----TRAINING WALLS TO REMAIN LEGEND
LIMIT Or WORK
AT THE DAM TEMPORARY - - /4 WETLAND RESOURCE BOUNDARY WITH WETLAND FI.AG

448- TEMPORARY -444 SAFE7Y - PORDPRING LAND SUBJECT TO FLOODING (BLSF).


NO. ISSIJE/DESCRIPRON BY DATE
CONSTRUCTION --- r- FENCING (TYP.) -__
_ 200 FT. RIVERFRONT AREA BOUNDARY (RA) UNLESS SPECIFICALLY STATED BY WRITTEN AGREEMENT, THIS DRAWING IS THE SQL PROPERTY OF WA
DEOEIWIRONMENTAL. INC. (c-TA). THE INFORMATION SHOWN CN THE DRAWING IS SOLEL FOR USE BY ALAS
ACCESS ROAD _ 200 FT. VERNAL POOL RESOURCE AREA CLIENT OR THE CLIENT'S DESIGNATED REPRESENTATIVE FOR THE SPECIFIC PROJECT AND LOCATION IDENTIFIED ON
THE DRAWING. THE DRAWING SHALL NOT BE TRANSFERRED, REUSED, COPIED. OR ALTERED IN ANY MANNER FOR
....,„ ...,N, PROTECT - Th SO EXISTING EDGE OF WATER USE AT ANY OTHER LOCATION OR FOR ANY OTHER PJRFOSE WriliOUT THE PRIOR WRITTEN CONSENT OF DOW. ANY
TRANSFER. REUSE. OR MODIFICATION TO THE DRAWING BY THE CJEIR OR OTHERS. WITHOUT THE PRIOR WRITTEN
'' -----.... T--- - EX. TREES' BUSTING EDGE OF PAVEMENT EXPRESS CONSENT OF NA. WILL BE AT THE USER'S SOLE RISK AND WITHOUT ANY RISK OR LIABILIFT TO GZA.
'''',
.....1,
.,...... ...--,..,,, .......--- ..,. 450 EXISTING 5 FT. VAR.) CONTOUR
.,,
UPPER ROBERTS MEADOW RESERVOIR
--._
'..s„ ..
..
,.. ....
...

....
...:::
.--.. .,...,„
....
.....-.
oasmn I FT. UPLAND CONTOUR
DAM BREACH AND ECOLOGICAL RESTORATION PROJECT
.-.....-`..... \ ., ...._. _._, ••• --., ..-
- - - 440 - - - - EXISTING 2 FT. TOP Of SEDIMENT CONTOUR
.
-----
.
...
NORTHAMPTON, MA
-
.7= .T
i. --7--- 01-N FASTING OVERHEAD WIRES
46
--,. ,.__. ....... EOSIN° TREE
-
\----- ----- ..----- --
---- • I • • •••••••• SEDIMENT AND EROSION CONTROL
TEMPORARY CONSTRUCTION ACCESS ALTERNATIVE
--05-2
------- ---
- --..

P --. "IEMPO RY SiABILIZD _- °W'l ----ACCESS ROAD TEMPORARY IMPACTS TO BVW


WETLAND RESOURCE AREA KEY PREPARED BY: PREPARED FOR:
- -- CONS I UCTIOJI ,ff.NIP?ii(N-
CE AS PROPOSED ALTERNATIVE 1
,----/--, (11/10/15) (12/09/15) RA RNERFRONT AREA GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
------ 0 .i - - - - k
EX 2,300 S.F. BVW 4,900 S.F. BVW
BVW BORDERING VEGETATED WETLAND OZ. Engineers and Scientists
mivi.gza.com
DEPT. OF PUBLIC WORKS
LUWW LAND UNDER WATER BODIES AND WATERWAYS
tAi-N G
RUEM
A OD
R VERAIL *FOR PROJ MGR: MAT REVIEWED BY: NYA CHECKED BY: MAT EXHIBIT 1
ACCESS REMOVAL OF 42± MATURE REMOVAL OF 14± MATURE BANK (MAHWL/OHW) - BANK (MEAN ANNUAL HIGH WATER UNE/ORDINARY HIGH WATER)
SCALE: 1"=.50'
DESIGNED BY: PD DRAWN BY: EDM
TREES IN BZ AND RA TREES IN BZ AND RA NW
BLSF
ISOLATED VEGETATED WETLAND
BORDERING LAND SUBJECT ID FLOODING FEB 2017
PROJECT NO. REVISION NO. 3
01.0019547.20 SHEET NO. 3 OF 6
UPPER ROBERTS ANTICIPATED
MEADOW STAGED DAM
(09-07-07) g RESERVOIR DAM REMOVAL
450 sEQUENCE
PROFILE LEGEND
TOP OP AcCUABILATED EXISTING WATER SURFACE (9/7/07)
sEDAVENTS (AS oF AUGUST STAGED REMOVAL
UFT USE
2008)
EXISTING TOP OF SEDIMENT (8/20/08)
440

ORIGINAL GRADE, AS DETERMINED BY PROBINGS


-STAGED REMOVAL
UFT USE M 1-A 2008 SEDIMENT SAMPLE LOCATION (APPROX.)
430
oRfaNAL CRADC
............. UR- 1 A 2014 SEDIMENT SAMPLE LOCATION (APPROX.)
AS DEI519411007 BY
pRoile(Gs
STAGED REMOVAL • ASSUMED POST-DAM REMOVAL STREAMBED GRADE
UFT USE

DASHED ORIGTNAL GRADE Isl.'s


420 INFERRED, AS DEPTH WAS • STAGED REMOVAL
BETUND pROBING UFT LINE
CAPABILITY STOKE MASCWRY 34AI TO BE- BROOK BOTTOM GRADES
REMOVED TO BEDROCK OR TO DOWNSTREAM OF STA
EVSTING BROOK 901701.1 AT 0-30 INFERRED FROM
DOMYSTREAM TOE OF OW VISUAL OBSERVATIONS

410 Z1 10

g Xg
174-co 18+w 15+00 14+00 134-00 12400 11+00 9+00 7+0D 8+0D 5+ 4400 3+00 2+00 1+00 0+00 -04-50 -1+00
VERTICAL SCALE IN FEET
PRE-DAM REMOVAL PROFILE ALONG PROBABLE STREAM ALIGNMENT 0 10 20 40
VERT. 1 "..20'
NOR. 1..•=200' 0 100 200 400
HORIZONTAL SCALE IN FEET

460 TRAINING WALL Az YOPIGWAI LS


460 460
STONE MASONRY IRAJNING TOP OF DAM NE STONE iAASONRY TRNNING TOP OF DAM ONE TO REMAIN TO MAXIMUM STONE MASONRY DAM TO
WALL & WINGWALLS EL- 454.5 AASONRY
ir ------------•••.,...... WALL & WINGWALLS EL 454.5 MASONRY ------•...,.... 1D(ENT PRA CTICABLE REMAIN TO MAXIMUM

IDOSTING
-,,
\

...-• '
0' F
:._
SPILLWAY
NOTCH
...._
.
.-
DAM

9:17
..z-,-.we,

/i

EXISTING ..-••
...- -
15
L
r S RILLWAY
gOTCH
DAM

=MI
,2

ExisTING ..-
--
WENT P RACT1CABLE

450 EMBANKMENT ...s EMBANKM - r"Vir - 450 INBAR


.1 - M1'- 1- 1
FILL FILL OM% F ILL

,.(41/ P-.1 t BEDROCK ••• AL -


rAGM
.- .M--.O II ELVAION VIEWS)
u l
'-er' lo•
- 440
GATEHOUSE
BEDROCK EN 12 t. -...
CIYP. IN ELEVATION VI
I jif& dr ' Lrr
A:AU** 4, la.
430 41r:i..mg,rwir 430 KUBERTSTMEADOW-BROOK
LIMIT OF 0 ••NP '../L. NORMAL STREAM FLOW
1 T•7 EL 425±
REMOVAL WORK A16.1%, AM . 4 _ grAGED AL__, EiL 425*
r?\ d
uFr
I
V (.;') 155
EX. PLUNGE POOL
•• 420
LEGEND : 420
420
W 1.5x2 STAGED AL -, v
ANTICIPATED
DRAIN LFT
BEDROCK/C RIGINAL BROOK ( -
4) STAGED DAM \ --STONE MASONRY DMA TO BE REMOVED
OUTLET BEOF OCK/ORIGINAL
BOTTOM D UNKNOWN ''`' REMOVAL TO BEDROCK OR TOI EXISTING BROOK
BROOK BOTTOM
SEQUENCE
DEPTrl UNKNOWN BOTTOM AT DOWNSTIEAM TOE OF DAM
I
410 410 410
-80 -40 -0 -40 -80 -40 -0 -40 -80 -40 -0 -40
EXISTING CONDMONS STAGES OF DAM REMOVAL PROPOSED CONDITIONS
DOWNSTREAM EIVATION OF DAM VERTICAL SCALE IN FEET
VEST. l=•20' 0 10 20 40
NOR. 1"=40'

0 20 40 80
HORIZONTAL SCALE IN FEET

ANTICIPATED STAGED DAM REMOVAL SEQUENCE NOTES:


NO. LSSUE/DESCRIFTON BY DATE
1. THE CONTRACTOR AND THE ENGINEER SHALL INSPECT THE ROBERTS MEADOW BROOK BLIWEGH UPPER ROBERTS 12. THE CONTRACTOR AND THE ENGINEER SHALL MONITOR THE BROOK BETWEEN 'ME BRIM AM) MRIAR WHILE ME 20. THE CONTRACTOR, ENGINEER, AND CITY WILL CONDUCT A POST-LMJA REMOVAL INSPECDON Of THE FORMER
MEADOW RESERVOR (URIAR) DAM AND THE INLET TO MIDDLE ROBERTS MEADOW RESERANI 4L &TRITR) TO BECOME WATER LEVEL IS BEING LOWERED AT EACH STAGE. AS DIRECTED BY THE ENGINEER, THE CONTRACTOR SHALL IMPOUNDMENT, OF THE BROOK BLITREN THE FORMER URID2 AND THE IARMR. AND OF THE BRIM INLET AREA TO UNLESS SPECIFICALLY STATED BY WRITTEN AGREEMENT, THIS DRAWING IS THE SCL PROPERTY OF CZA
FOR MANIAMING REPCSMON ITATE EXCESS ACCUMULATED SEDIMENT WITHIN THE BROOK TO FACILITATE DOWNGIMDIENT ASSESS THE PROGRESS OF SEDIMENT TRANSPORT THROUGH THE PROJECT REACH. THE ENGINEER WILL INVENTORY GEOEN, IRONMENTAL. INC. (GOD). THE INFORMATION SHOWN ON THE DRAWING IS SOLELY FOR USE BY GZA'S
FAMILIAR WITH POTENTIAL AMISS LOCATIONS AND TO PLAN THE ADAPTIVE MANAGEMENT Api .A
SEDIMENT TRANSPORT TO IMAM. SEDIMENT I , TO PREVENT OVERTOPPING OF THE CHANNEL BANKS, MD TO PREVENT FWODING Of POST-DAM REMOVAL WORK REMAINING MCWDING, BUT NOT NECESSARILY LIMTTED TO REPOSMONINGdAGITATING OR CLIENT OR THE CLIENT'S DESIGNATED REPRESENTATIVE FOR THE SPECIFIC PROJECT AND LOCATION IDENTIFIED ON
2. THE CONTRACTOR SHALL ESTM3USH CONSTRUCTION Accez ROUTES As SHOWN ON THE DRAWINGS. RESERVOIR ROAD. REMOVAL Of SEDIMENTS WITH94 THE BROOK CHANNEL OR WITHIN MRIAR, REMOVAL OF A TEMPORARY THE DRAWING. THE DRAWING SHALL NOT BE TRANSFERRED, REUSED, COPIED, OR ALTERED IN ANY MANNER FOR
CONSTRUCT/ON AC*Fss ROADS, ENTRANCEs, MD WETLAND CROSSINGS, REGRADING OF FORMER CONSTRUCTOR USE AT ANY OTHER LOCATION OR FOR ANY OTHER PURPOSE YdITHOUT THE PRIOR WRITTEN CONSENT OF DUO. ANY
3. THE CONTRACTOR SHALL ESTABLISH THE LOWER IN-STREAM NORTHERN ACCESS ROUTE TO THE DAM USING 13. ONCE THE WATER LEVEL IN ME UPPER RESIDIVOIR HAS REACHED THE BOTTOM OF THE NOTCHED 501,8001 (STAGES TRANSFER. REUSE. OR MODIFICATION TO THE DRAWING BY THE CLIENT OR OTHERS. WTTHOUT THE PRIOR WRITTEN
CONSTRUCTION MATS OR OTHER TEMPORARY STRUCTIJRAL MEASURES YITIHIN ROBERTS MEADOW BROOK. THE 1 AND 2), THE CONTRACTOR SHALL ESTABLISH THE NEXT NOTCH RI THE SPILLWAY, WHICH WILL BE APPROXIMATELY ACCESS ROADS FOR PEDESTRIAN ACCESS, INSTALLATION OF PEDESTRIAN WETLAND CROSSINGS ON FIRMER
CONSTRUCT/0N ACCESS ROAD, INSTALLATION OF HIS RAM sicii AT LEFT SIDE OF FORMER IMM, RaAVIAL Of ANY 'EXPRESS CONSENT OF CIA, WILL BE AT THE USER'S SOLE RISK AND WITHOUT ANY RISK OR LtABILOT TO GZA.
CONTRACTOR SHALL UTILIZE THE RIVER STONES/BOULDERS TO CREATE THE ROADWAY. NO PLACEMENT OF ROCK FILL 5-FEET WIDE 137 10-FEET TALL (STAGE 3).
WITHN THE BROOK OIL BE ALLOWED. 14. THE STAGED DAM REMOVAL SHALL PROCEED BY sl.R.A44110 AND SEQUENTIAL REPERTION OF Era II TO 13. REWANG CONsTRUCTION AND DEMOLMON MATERIALS, REMOVAL OF TEMPORARY FENCING, AND RESTORATION OF
4. THE CONTRACTOR AND ENGINEER SHALL CONFER TO CONSIDER THE AMITY AND SAFETY OF PRESERVING THE LEFT
STONE MASONRY SECTION Of TIE DAM DURING CONSTRUCTION OPERATIONS.
15. PRIOR TO REMOVING A NEW NOTCH IN THE SPILLWAY, THE FOLLOWING MEATS SHALL BE PERFORMED: DISTURBED AREAS.
21. UPON MEETING SUBSTANTIAL COMPLETION, THE CONTRACTOR, ENGINEER. AND CRY WILL PERFORM A SITE WM<
UPPER ROBERTS MEADOW RESERVOIR
0. THE ENGINEER. WITH ASSISTANCE FROM 11-E CONTRACTOR, WILL PERFORM SOUNDINGS WITHIN THE UPPER
B. THE CONTRACTOR SHALL CONDUCT THE INVAsNE SPECIES CONTROL PROGRAM BY A COMBINATION OF NAND CUTTING
All) GLYPHOSATE-BASED HERBICIDE APPLICATIONS, BY A LICENSED HERBICIDE APPLICATOR, ON THE SEDIMENT ISLAND
RESERVOIR AS DESCRIBED IN STEP B. PRIOR TO THE CONTRACTOR DEMOBILIZING FROM THE SITE AND THE ENGINEER WILL PREPARE A PUNCH LIST OF
ITEMS FOR THE CONTRACTOR TO ADDRESS.
DAM BREACH AND ECOLOGICAL RESTORATION PROJECT
b. THE CONTRACTOR AND THE ENGINEER SHALL INSPECT THE LOWER ACCESS ROUTE TO THE DAM AND
WITHIN THE IMPOUNDMENT (-STA. 10+00 TO STA. 14+00), IN ACCORDANCE MTH APPLICABLE PERMITS AND AT THE ADJUST/ADD CONSTRUCTION MATS AS NEEDED TO ENSURE ACCESSIBILITY
22. UPON COMPLETION OF THE PUNCH UST ITEMS, THE CONTRACTOR SHALL FULLY DEMOBILIZE FROM ME SITE AT
WHICH TIME THE CITY WILL ASSUME ALL BROOK MONITORING AND ADAPTIVE SEDIMENT MANAGEMENT RESPONSIBILITIES.
NORTHAMPTON, MA
APPROPRIATE TIME OF YEAR. 0. THE CONTRACTOR AND ENGINEER SNAIL INSPECT THE BROOK BEIYIEEN THE UPPER AND MIDDLE RESERVOIRS.
IL THE CONTRACTOR SHALL ESTABLISH TEMPORARY ACIFSs AREAS FOR ADAPTIVE SEDIMENT MANAGEMENT AT THE d. AT THE DIRECTION OF THE ENGINEER, THE CONTRACTOR STOLL REMOVE ANY LARGE DEBRIS OR SEDIMENT
LOCATIONS SHOWN ON THE DRAWINGS OR WHERE DIRECTED BY THE ENGINEER. ACCUMULATIONS WITHIN THE BROOK THAT COULD NOT BE MOBILIZED BY REPOSTPOINAGOGITAllON.
7. THE ENGINEER, WITH ASSISTANCE Of THE CONTRACTOR, WILL PERFORM PRE-DAM REMOVAL SEDIMENT SOUNDINGS e. THE ENGINEER WILL ASSESS THE PERFORMANCE CIF THE STAGED DAM REMOVAL RESPECT TO SEDIMENT
ALONG THE BASELINE OF THE ANTICIPATED NEW STREAM CHANNEL WITHIN THE IMPOUNDMENT AND AT SPECIFIED
TRANSECT LOCATIONS. SOUNDINGS SHALL BE LOCATED ALONG EACH IRANSECT AT 10-FOOT INTERVALS FROM RANK
1,40BIUZATON FROM THE URIAR IMPOUNDMENT AREA, DOWNGRADIENT SEDIMENT TRAWL:NE IN-STREAM
SEDIMENT RETENTION, AND FLOODING POTENTIAL. THE ENGINEER WILL DETERMINE F ADAM& SEMLER
DAM REMOVAL STAGES
TO BANK AND WILL BE PERFORMED AT STATIONS 1+00, 2+00, 5+00, 7+00, 9+00, 12+00 AND 14+00. AFTER A MANAGELLENT wools ARE NEEDED DOWNSTREAM OF THE DAM PRIOR TO AUTHORIZING THE NEXT STAGE OF
STAGE Of DAM REMOVAL HAS BEEN PERFORMED, FLOW AND SEDIMENT MOBILIZATION HAS STABIUZED, MD PRIOR TO DAM REMOVAL.
THE NEAT STAGE OF DAM REMCNAL, SOUNDINGS WILL BE PERFORMED ALONG TRANSECTS ACCESSIBLE By OPEN 18. REPEAT THE STAGED DAM REMOVAL Si Er UNTIL THE FULL VERTICAL EXTENT OF THE SPLLWAY PORTION OF THE
WATER REMAINING IN THE IMPOUNDMENT AREA. THEREFORE, THE NUMBER OF MANSECTS WILL BE REDUCED AS THE DAM HAS BEEN REMOVED TO BEDROCK OR TO ME EXISTING BROOK BOTTOM AT THE DOWNSTREAM TOE OF THE PREPARED BY: PREPARED FOR:
DAM IS BEING REMOVED MID THE OPEN WATER AREA WITHIN THE IMPOUNDMENT IS REDUCED. DAM.
B. THE STAGED DAM REMOVAL SEQUENCE PLAN IS SHOWN ON DRAWING NO. B. THE CONTRACTOR SNAIL BEGIN BY 17. THROUGHOUT THE PROJECT, THE CONTRACTION SHALL PERIODICALLY INSPECT ALL EROSION CONTROL MEASURES AND GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
REIAMING AN APPROXIMATE 5-FOOT WIDE BY 5-F007 TALL NOTCH OUT Of SOUTHERN ENO (RIGHT SIDE) OF THE REPAIR/REsIDRE THEM AS NECESSARY.
SPILLWAY SECTION OF THE DAM (STAGE 1). THE NOTCH WILL ALLOW FOR CONTROLLED RET FAcF OF WATER (AND 18. FOLLOWING THE FDLAL STAGE OF DAM REMOVAL IN FAL=LYWINTER. 'ME CONTRACTOR SNAIL DEIAGDILIZE FROM
Engineers and Scientists DEPT. OF PUBLIC WORKS
SEDIMENT) FROM THE UPPER RESERVOIR. THE SITE FOR THE WRITER. UNTIL THE CONTRACTOR 90180811 TzA's THE CRY WILL ASSUME BROOK IAONTIORING AND Www.gza.com
B. THE CONTRACTOR SHALL LINNTAIN A SUPPLY OF PRE-FILLED SUPERSACKS, ROAD PLATES, OR OTHER MATERIALS ADAPTIVE SEDIMENT MANAGEMENT RESPONSIBILITIES TO ENSURE FLOW IS MAINTAINED IN THE BROOK As SEDIMENTS
THAT MAY BE PLACED WIER THE NOTCH SHOULD AN FROM THE OMAR IMPOUNDMENT AREA CONTINUE TO MOBILIZE DOWNSTREAM.
10. AS THE RESERVOIR WATER LEVEL DROPS, THE CONTRACTOR SHALL REMOVE THE REMAINING TOP 5 FEET Of THE 19. INNEN DIRECTED BY THE CRY, ME CONTRACTOR SHALL REMOBILIZE TO ME SHE TO PERFORM POST-DAM REMOVAL
PROJ MGR: MAT REVIEWED BY: NYA cHECKED BY: MAT EXHIBIT 1
SPILLWAY SECTION (STAGE 2). ACITYMES. DESIGNED BY: DRAVVN BY: SCALE:

4
NYA EDM AS NOTED
11. SELECT ARCHITECTURAL STONE MASONRY BLOCKS (I.E CAPSTONES AND OTHER CUT STONES TO BE IDEMMED BY
THE CITY) AND MASONRY RUBBLE SHALL BE SEGREGATED AND TRANSPORTED TO AND bRAKrILED AT AN OFF-SITE PROJECT NO. REVISION NO.
LOCATION(S) TO BE SPECIFIED BY THE CITY. FEB 2017 01.0019547.20 SHEET NO. 4 OF 6
onz AzEss
arr
krocai I
t 1FGFND
DiMs Qff ii N
_ -----
( II .1
A
1+00

A
&SEIM (SEE GENERAL RAN NOTE 15 ON MG. 2)
WETLAND RESOURCE BOUNDARY
455 ELISONG EDGE OF WATER
PPROXIIATE RESTORED STREW CHANNEL BOTTOM
APPROXIMATE RESTORED STREAM CHANNEL TOP
77/7 7P7/// ----„---.
--A IDDSTING EDGE OF PAVEMENT
CT EXISTING GUARD RAIL
_• -- \ 0'444; EDGE OF WOODS
A up.k./ DOSING OVERHEAD WIRES
2:PM COSTING UTIUlY POLE
-'"glY
•\

e -- ___
COSTING TREES

7 \\\ \ 445 DaST1NG 5 FT. DRAM CONTOUR

-/ I /_____
7-
/ z ..--_-- ----____ _- — — ____ 1 II ,90v
0E.t
EXISTING 1 FT. UPLAND CONTOUR

( I \ \'I „oz15
EOSI1NG 2 FT. TOP OF SEDIMENT CONTOUR

/V'// _1+00

....-- --- —-- ao.s gOv NOTE*


REFER TO DWG. 8 FOR ELEVATION VIEWS OF DAM REMOVAL
PORARY &ROOK
70 BE REMOVED
/// 0 / / / ,/ 7 v \ \ •
/ / / e 0 / / • • ASSORTED
\ \ DUSTING ROCKS &
1 / // i °P / // / / BOULDERS
/ . • • \ X 419.5 (10 MON
// / ii / ( h o+oo
' / / / / / / / /
1 -- ----
---- / 1 ___ 1 \ \

/7 ///// 4.32---

) /
WATER SURFACE 9.EV
425.4
(8/7/07)
,--"

1 \\ Ix 418.6
A19.6 X
;/ // "BROOK Ti
.. 7 7 7 -RT S.- AiVfEARCAV
/
...---
'
RS:1":° -/
\\
\ /
--- ..-- __06
7 7 7
7 7 V

7
7 V
7 ..
/ _____ 06— — ------- ,_
.777-
.. „„ ....- ____-- , \
/_ ...-- ------ --I
, i
i '4'8.•
445
IIP,

-----
uk
7 7 "-Fratier
7 .7 )' ill• -^
7 --- --''44.0
7 7 .-----

7 7 7 7 -------- Cs I
7

7
7
7
7
„......- V.
7
7
— --=.:..-- :•z---•
------ --- ____ --- — —
e
:-;,
, s----
___ ___ ___ ---__/--
------
.7 7 .,----
7
7 --=
7 _ ____ ___ ___. , GRAPHIC SCALE
------- ,---'- 7 .„./.-
"\ (1 \ \
7 ' --
7 ,...."' 7 „....--- \ I \ o 10 20 40
7 „....--' 7 ....---- TI,\17--------
7 „....--- 7 7
----
- I\ I \ -7 ---'-'
SCALE IN FEET
.-7
.7 7-
7
7 ,...--..-
.7 .,-/-
------
------
/I l I\ \ I /
7 7 ...--'-'
7 7 7 .....----
..----
----- I
\
1006FSMIZION2
„...--- .....---- __--- ------
.7 _.----
7 '--- - ._...--- ------. ------
_----

-
.„..---
..„--'
.7 _,.
..--- ------ ----
REEKNE-TrAmourr-
corrsinuonom \\ RaW
IREESAI3..„..-
L
------' Emmy& RESTORE 117711 LOAM
448--- AND SEED \\N;

- --- NO. ISSUE/DESCRIPTION BY DATE

\ I L UNLESS SPECIFICALLY STATED BY \FRITTER AGREEMENT, THIS DRAWING IS THE SOL PROPERTY OF GZA
GEOEHVIRONMENTAL. INC. (CZA). THE INFORMATION SHOWN ON THE DRAWING .S SOLELY FOR USE Br DZA'S
CLIENT OR THE CLIENT'S DESIGNATED REPRESEMTATIVE FOR THE SPECIFIC PROJECT AND LOCATION IDENTIFIED ori
THE DRAWING. THE DRAWING SHALL NOT BE TRANSFERRED. REUSED. COPIED. OR ALTERED IN ANY 8011108 FOR
USE AT ANY OTHER LOCATION OR FOR ANY OTHER PURPOSE WITHOUT NIE PRIOR FIRRIEll CONSENT OF CZ& STY
TRANSFER. REUSE. OR MODIFICATION TO THE DRAWING BY THE CUENT OR OTHERS. WITHOUT THE PRIOR WRITTEN
1N\J -- EXPRESS CONSENT OF GZA. WILL BE AT THE USER'S SOLE RISK AND WITHOUT ARE RISK OR LIABILITY TO GZA.

--7.,..--
—7-
N . UPPER ROBERTS MEADOW RESERVOIR
__- i ) ..,.....-,-
\,.. _
DAM BREACH AND ECOLOGICAL RESTORATION PROJECT

_ --'2.--
------' NORTHAMPTON, MA
- ------- ...---- ------ i -';, ,00
- \
(-- _- - -_-_._ _....-
-------
,..__- - PROPOSED CONDITIONS AT DAM
..-
- \ 0
_-- ._- _ _ _ _ „. __,- _ . ..___ _- _ - ,-J, _.._. . _ ___. _ .._ - • --)
._. ._... , _..__-__
, _i „w_.--- PREPARED BY:

GZA GeoEnvironmental, Inc.


PREPARED FOR:

I 0'7-- --- CITY OF NORTHAMPTON

___-------- _ - -- - „...... „ __--1,—/___- ---- /


.--- -- \
__.,-____--
OW • \ ,-
Engineers and Scientists
wori.gza.com
DEPT. OF PUBLIC WORKS
St \
---- -,-- ----- ---,--- "") PROJ MGR: REVIEWED BY: NYA CHECKED BY: MAT
.I. .„---• \ MAT EXHIBIT 1
•---- ---:- __--- s--- , DESIGNED BY: NYA DRAWN BY: Eom SCALE: 1,
20'
_---- _--- ,---
, j ....------
---
/ , \ \ \
FEB 2017 PROJECT NO. REVISION NO. 5
01.0019547.20 SHEET NO. 5 OF 6
stv.

EX. LOGGING/R. AD TO ----


REAWN FOR P ESTR
200 FT. RA -- OW
,> AC ESS
01
2.va

/
/ CONSTRUCT PERMANENT
PEDL51 KAN WETLAND W03' , ............
CROSSING I_ ' ____----
411!---
41.1
k4'°9

2,41356 00—
viv 2,04.1
siff 0352 --
APPROX. LOCATION OF
PEDESTRIAN ACCESS FOOT 2029
z
------
ors53 CRUSHED STONE OVER
PATH. (TO BE HEW LOCATED 93152r5 EX. LOGGING ROAD TO F 2W351
AT COMPLETION OF PROJECT). lllE2.14534
REMAIN FOR PEDESTRIAN
4-45
, ACCESS
LU lip- —
INSTALL HISTORIC 243. "-""
z6
INTERPRETATION
ES SIGN az? _
/ 7
/
HA Wit VA
111,
0312- , 70'5/ -”
202_3 21k..
TC1
p!,
t , ....., ,
r A.

*. Sensitive Avoidance _
vi6,06 , ,
( Fence Line
. ,. -
BVW ----- .--:-- ' --
0
, -r--rri-t
,i _r
...
7, e
2,Nske - ,--- ---.,
oval Final D

asEr( Sensitive No Impact Area


; CONSTRUCT PERMANENT
PE -.(- ---( N
PED1 KEAN WETLAND (--(
CROSSING
ES ASSORTED
EXISTING ROCKS &
BOULDERS
re - (TO BE Rtsit1RED 70 / /
4/WY// ORIGIML CI7N807ONS) WATER SURFACE ELEV.
425.4 0,
6

+Go
(9/7/07) 1
C('
• _AIK'PER __ROBERT968---- ,_ 410 0 30 60 120
6 ,.,...„ ,--______ ,.----
----
--- T ------- --- ----
-

. .-,__ __-• ------ ---- 14:- ' ..../ itk I I


--------
_..-- _----- - - ---,,- -----___
------ ,-- ---„=: ,--- /-.,--______-
------
--
_--/-_--____
-____„--=--- SCALE IN FEET
.--- ,- ,--- ---- ,--- ----
.,_ 445----- --
- --- - ____ __,
0GMINTERCOMPANYPROS

------
--__.-- ---- ---- --L.S.v.e ---- — — — ---:"--_.--- —. --.,--
- _—_=-_—_—
-_=!
---=---- --- =
._.-- 7_,,-'-'-' ,-(-(-(
r r-r-
. LEGEND
_--,-.
_,..--..- -- --448-- -- -__ ----- _ _ ------ ENOWWWWW"
.;_-
-_-
__ 3
-- \
---- --- -- ____ /-
\ t
_.--
G c 4"
A A WETLAND RESOURCE BOUNDARY WITH MERANO FLAG

--- \
, 5. L --- I BORDERING WV SUBJECT To FLOODING (BLSF)

----/Ircw _ 200 FT. RNERFRONT AREA BOUNDARY (M) NO. ISSUE/DESCRIPTION BY DATE
e - v,” 200 FT. VERNAL POOL RESOURCE AREA UNLESS SPECIFICALLY STATED BY WRITTEN AGREEMENT, THIS DRAWING IS THE SOLE PROPERTY OF GZA

-::-.__ - • -.- -__—_____—


- 1--
--2-7.--- :--- - - ---'"
-- .- e2-.---------
- \ 2 1/2' (2 3/8' at%) SCHED. COSTING EDGE Of WATER
GEOEIVIRONMENTAL, INC. (GZA). THE INFORMATION SHOWN ON THE DRAWING S SOLELY FOR USE BY GZA'S
CLIENT OR THE CLIENT'S DESICATATED REPRESENTATIVE FOR THE SPECIFIC PROJECT AND LOCATION IDENTIFIED ON
\)‘• 40 PVC COATED GALV. STL THE DRAWING. THE DRAWING SHALL NOT BE TRANSFERRED, REUSED. COPIED, OR ALTERED IN ANY NtAtINER FOR
- - 2 PIPE COLOR-BWK W/PRESSED APPROXIIAATE RESTORED STREAM CHANNEL BOTTOM USE AT ANY OTHER LOCATION OR TOR ANY OTHER PURPOSE WITHOUT THE PRIOR WRITTEN CONSENT OF OTT. ANY
- \REPOCE STL CAP. TRANSFER, REUSE. OR MODIFICATION TO THE DRAWING BY THE CLIENT OR OTHERS. WITHOUT THE PRIOR WRITTEN
APPROMMATE RESTORED STREAM CHANNEL TOP EXPRESS CONSENT OF WAS. WILL BE AT THE USER'S SOLE RISE AND WITHOUT ANY RISK OR LIABILITY TO GZk
) \\7U_A7RALL_V\._ _ — ""\ EMBLEM
COSTING EDGE OF PAVEMENT
UPPER ROBERTS MEADOW RESERVOIR
36-x48" D.08 ALUM. SIGN EXISTING 5 Fr. UPLAND CONTOUR
PANEL-PAINTED ONE SIDE AS DAM BREACH AND ECOLOGICAL RESTORATION PROJECT
SHOWN IN DETAIL SET PANEL IN 4 COSTING 1 FT. UPLAND CONTOUR
SIDED ALUM. CHANNEL. BACKED NORTHAMPTON, MA
0 WI/2' EXT. GRADE A-A PLYWOOD.
PANT BACK 2 COATS FLAT-BLACK-
COSTING 2 FT. 10P OF SEDIMENT- CONTOUR
COVER COMPLETELY (WITHIN THE COSTING OVERHEAD MARES
FRAME) W/3/16' CLEAR ACRYLJC FINAL CONDITIONS ALTERNATIVE
SHEET. ATTACH PANEL TO PIPE DrIST1NG TREE LINE
FRAME W/VANDAL RESISTANT BOLTS.
COSTING 'TREE
FROM DAM TO KENNEDY ROAD

WETLAND RESOURCE AREA KEY PREPARED BY: PREPARED FOR:


SUBMIT SHOP BAGS. FOR
APPROVAL OF MATERIALS. GZA GeoEnvironmental, Inc.
RA CITY OF NORTHAMPTON
ASSEMBLY & VERBIAGE
BWJ
RNERFRONT AREA
BORDERING VEGETATED WETLAND on Engineers and Scientists
www.gza.com
DEPT. OF PUBLIC WORKS

LUWW LAND UNDER WATER BODIES AHD WATERWAYS


CHECKED BY: MAT
PROJ MGR: MAT REVIEVVED BY: NYA EXHIBIT 1
DIA CONC. FOOTING BANK (MAHWL/OHW)- BANK NEAR ANNUAL HIGH WATER LIRE/ORDINARY HIGH WATER)
SET PIPE MI 3' IN CONC. DESIGNED BY: PD DRAWN BY: EDM SCALE: 1"=60'
TO
(1) HISTORIC INTERPRETATION SIGN 1W1 ISOLATED 1itutiATED WETLAND
_., PROJECT NO. REVISION NO. 6
mrs BLSF - BORDERING LAND SUBJECT 10 FLOODING FEB 2017 01.0019547.20 - SHEET NO. 6 OF 6
EXHIBIT 2

ARCHAEOLOGICAL SITE AVOIDANCE AND PROTECTION PLAN


(A SAPP)

10
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
Archaeological Site Avoidance and Protection Plan

Upper Roberts Meadow Reservoir Dam Removal Project


Northampton, Massachusetts

In accordance with Stipulation I of the Memorandum of Agreement (MOA) for the Upper Roberts
Meadow Reservoir Dam Removal Project, this archaeological site avoidance and protection plan
(ASAPP) has been developed to protect the three archaeologically sensitive areas downstream of
the dam including portions of the Edwards-Moody-Hoxie Tannery Site that are not within direct
project construction impact areas. Specific avoidance and protection strategies are detailed below
that will be implemented to ensure that the integrity of the archaeological site and sensitive areas
are maintained throughout the dam removal project.

The Edwards-Moody-Hoxie Tannery Site is recommended eligible for listing on the National
Register of Historic under Criteria A and D, and possibly B and C, at the local and/or state levels
for its potential to yield important information relating to early water-powered tannery operations
and improvements to the tanning process that saved in manual labor and increased profitability.
The site was identified during an intensive (locational) archaeological survey conducted by PAL in
2016, which resulted in the identification of four building foundation remains, two wheel pits, and
a stone-lined raceway that are within and adjacent to the proposed temporary dow'nstream access
route for the dam removal construction work on the north side of Roberts Meadow Brook. There is
also the potential for belowground remains of documented tanning vats or leaches on a broad, flat
terrace to the south and east of the building foundations. A site avoidance fence line and associated
polygon has been established on the south and east sides of the proposed temporary downstream
access route, pursuant to the final design and construction plans (see MOA Exhibit 1, Sheet #3).

The portion of the Edwards-Moody-Hoxie Tannery Site that will be directly impacted by the
Project construction activities (see MOA Exhibit 1, Sheet #3) will be subjected to archaeological
data recovery and monitoring and recordation, in accordance with Stipulation III of the MOA. The
data recovery and monitoring areas have been established to the west of the site avoidance line and
associated polygon, pursuant to the final design and construction plans.

The 2016 archaeological investigations also identified archaeologically sensitive areas on the south
side of Roberts Meadow Brook, including an area containing visible cellar hole/stone foundations
likely associated with the eighteenth and nineteenth-century Edwards-Hoxie family dwelling. This
sensitive archaeological resource area is within 10 feet (ft) of the proposed Kennedy Road
construction staging area for the dam removal project. An impact avoidance fence line and
associated polygon has been established on the north and west sides of the construction staging
area, pursuant to the final design and construction plans (see MOA Exhibit 1, Sheet #6). An impact
avoidance polygon has been established for the other sensitive area on the south side of the brook
closer to the dam (see MOA Exhibit 1, Sheet #3).

11
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
The ASAPP will be implemented to avoid and protect the above- and below ground archaeological
features and sensitive areas on both sides of Roberts Meadow Brook downstream of the Upper
Roberts Meadow Reservoir Dam from inadvertent impacts during the dam removal work. The
following site protection measures shall be implemented prior to contractor construction work for
the removal of the dam and associated components.

1. The site and sensitive area avoidance lines and associated polygons on both sides of
Roberts Meadow Brook will be recorded on the final construction plans available to and for
use by the Contractor. Under the direction of a qualified archaeologist, the construction
areas of avoidance around the Edwards-Moody-Hoxie Tannery Site and other sensitive
areas will be flagged on the ground with wooden surveyor stakes having blaze orange
spray-paint tops. The boundaries will be flagged in accordance with the "site avoidance
fence line" and "sensitive no impact area" clearly labeled on the Final Construction Plans to
be released in the spring 2017 (refer to MOA Exhibit 1, Sheets #3 and #6). The field
delineation and flagging of the archaeological avoidance and protection areas will take
place prior to the start of construction.

2. Under the direction of the qualified archaeologist familiar with the project area, the
Contractor will erect high visibility construction fencing and "No Trespassing" signs
around the avoidance areas which will remain in place for the duration of the Project
construction activities. No construction work, staging, or vehicular access will take place
within the archaeological avoidance and protection areas.

3. The City, with the assistance of the project engineer and the qualified archaeologist, will
inspect and monitor the installed construction fencing during the Work so that it properly
delineates the flagged identified archaeological avoidance areas.

4. Suitable language will be included in contract and construction bid documents to minimize
chances for inadvertent impacts to the ground surface and visible stone features inside the
archaeological avoidance and protection areas.

a. Construction personnel and contractors will be informed verbally and in writing that
the fenced areas are "Sensitive No Impact Areas" where the ground surfaces and
visible stone features are to be protected as indicated above.

b. Construction personnel and contractors will neither perform nor permit any tree
cutting or tree stumping, construction, excavation, grading, filling, dumping, or the
storage or staging of equipment, vehicles, or supplies within the fenced "Sensitive •
No Impact Areas."

c. Any work within the fenced "Sensitive No Impact Areas" will require submission to
and written approval from the City after the US Army Corps of Engineers (Corps)
and the Massachusetts Historical Commission (WIC) have the opportunity to
review and comment on the proposed activities within the fenced area.

12
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
5. No unauthorized artifact collecting or archaeological investigation will be permitted within
the fenced "Sensitive No Impact Areas" or in other areas of the property, other than that for
which the Massachusetts State Archaeologist has issued an archaeological field
investigation pelinit (950 CMR 70).

6. If the contractor or other project personnel observe unexpected cultural resources during
dam removal work, the City should be notified immediately, and work should be halted in
this area. The City will contact the qualified archaeological consultant for review and
evaluation. The qualified archaeological consultant will coordinate with the Corps and the
MHC under Stipulation VIII of the MOA, as necessary.

7. The high visibility construction fencing and signage around the "Sensitive No Impact
Areas" must be removed upon completion of the project.

13
Upper Roberts Meadow Dam Removal Project
Northampton, Massachusetts June 2017
UPPER ROBERTS MEADOW RESERVOIR DAM BREACH
AND STREAM RESTORATION PROJECT
Northampton, MA

REVISED
STREAM RESTORATION AND MONITORING PLAN

to accompany
Section 404 Massachusetts General Permit
NAE-2007-1851

Existing Dam Proposed Condition

May 29, 2015


Revised November 29, 2017
GZA GeoEnvironmental, Inc.
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

1.0 Project Background and Overview

The City of Northampton (City) Department of Public Works (DPW) is proposing to remove the Upper Roberts
Meadow Reservoir (URMR) Dam to comply with a 2007 Certificate of Non-Compliance and Dam Safety Order
issued by the Massachusetts Department of Conservation and Recreation - Office of Dam Safety (ODS). The project
is a Priority Project for river restoration by the MA Division of Ecological Restoration (DER), who is partnering
with the City on the project. In April 2015, the City submitted a Pre-Construction Notification (PCN) pursuant to
the regulatory revisions to the Massachusetts General Permit (MAGP) (eff. February 4, 2015) by the U.S. Army
Corps of Engineers (USACE) under General Permit 22: Habitat Restoration, Establishment, and Enhancement
Activities (GP 22). As stated in the Section 404 PCN application materials (see permit application narrative), the
purpose of the proposed project is to remove the Upper Roberts Meadow Reservoir (URMR) Dam and thereby (1)
protect downstream water supply infrastructure, (2) eliminate future City costs and liabilities associated with an
obsolete structure, and (3) promote ecological restoration of the brook.

During a post-submittal conference call held on May 22, 2015 with members of the project team and the US Army
Corps of Engineers, a request by the USACE was made for the project team to develop a Stream Restoration and
Monitoring Plan (Plan) for the project. The Plan outlined herein includes the project and restoration goals, the
success criteria to determine if the goals have been met; and the adaptive management elements and monitoring
activities associated with the work.

2.0 Project Approach

The proposed methods and follow-up monitoring/documentation include the following:

 Staged removal of dam sections to control stream sediment mobilization. The primary concern about
the in-stream sediment management proposed (and permitted via MA DEP 401 Water Quality Certification)
approach is aggradation downstream and potential flooding of the roadway adjacent to the brook. The
staged dam removal is intended to provide a measure of control concerning the rate of sediment
mobilization so that downstream monitoring for infrastructure impacts can be performed by the City. The
ecological impacts of sediment release to the downstream reach are considered (by state restoration
ecologists and fisheries biologists) to be minimal and short-term in nature. Moreover, the short-term
ecological impacts will transition to long-term and permanent benefits via the infusion of habitat forming
sediment and organic matter. These benefits are well established in the scientific literature and within U.S
Army Corp Nationwide Permit 53 (Low Head Dam Removal).

 A targeted invasive species removal program will be included as part of the project. Invasive plant
species currently exist upstream, within, and downstream of the dam impoundment. In order to reasonably
limit the spread of new invasive plants, the project involves limited plant treatment and/or removal prior to
the dam removal. The work will focus on several targeted areas, including an island of potentially mobile
sediment within the impoundment, and a stand of existing plants downstream at the inlet to the Middle
Reservoir. Refer to the project’s Invasive Species removal plan included in Attachment A. Invasive plants
are also widespread in the surrounding City-owned forest. The City is currently in the planning stages of a
programmatic invasive species control plan for City-owned watershed land. The project site is within City
watershed land and will be incorporated into the invasive species control program as appropriate.

 Adaptive management of downstream sedimentation areas to remove blockages that increase the risk
of roadway flooding. These adaptive management steps are intended to address the potential risk to

1
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

downstream infrastructure, described above. These actions are not related to ecological impacts, as the
accumulation of large wood, organic matter, and sediment would otherwise be considered beneficial.

 Conformance with a construction time-of-year restriction to limit short term impacts to native fish
populations. The project team has been coordinating with state fisheries biologists for years concerning an
appropriate window of construction and sediment release. Accordingly, work will commence after April
1, 2017.

 Restoration of temporary access areas and roads and removal of temporary erosion and
sedimentation controls. The project involves the construction of temporary access routes. Pursuant to the
Massachusetts General Permit, the project will remove these temporary fills and structures and restore the
ground surface to natural forest litter and cover (as exists now).

 Pre- and Post- photographic documentation from defined locations within the URMR basin and
downgradient stream to compare pre-dam removal and post-dam removal conditions. The data collection
will help qualitatively assess the changes to stream habitat post dam removal.

The phased dam removal will gradually dewater the impoundment and initiate sediment release and gradual stream
reformation within the URMR impoundment area. The slow drawdown of the impoundment will also allow
sediment to dewater and stabilize. Of the approximately 27,000 cubic yards of sediment within the URMR
impoundment, approximately 10,000 cubic yards of sediment is expected to be released during the staged dam
breaching. Some of the sediments will be retained within the brook with the remainder mobilized to Middle Roberts
Reservoir. This approach to sediment management was developed in concert MA DEP staff, lengthy consideration
of other options, and selection of this approach as most sensible, least damaging to surrounds lands, and most cost
effective. It is currently permitted via a 401 Water Quality Certification from MA DEP (WE 246-0689).

As the dam vertical sections are incrementally removed, the reservoir sediments will be gradually exposed and de-
watered in-place. During the reservoir dewatering, the sediments within the basin will be allowed to mobilize by
the downward “cutting” of the stream as it begins to re-establish within the reservoir basin bottom. Roberts Meadow
Brook will have the ability to respond naturally to the base flow and storm events, adopting its own equilibrium for
sediment retention and mobilization, eventually achieving a generally stable stream form. The residual URMR basin
sediments will become stabilized as vegetated soils within the former URMR basin. The flows will be elevated
during dam removal assisting with sediment mobilization, with additional temporary and permanent sediment
repositioning occurring during larger rainfall events during and several years after the dam removal. Sediment
mobilization is anticipated to be substantially complete within 1-3 years, consistent with other dam removal projects
completed in Massachusetts, and consistent with the scientific literature. Wetland and upland seed mixes of native
forbs and shrubs may be used at the recommendation of the project engineer and/or the City in coordination with
DER should impoundment sediment and soils not revegetate adequately. Refer to the referenced 404 application
for additional information about the dam and the restoration project.

3.0 Restoration Goals and Success Criteria

3.1 Ecological Restoration Goals

The ecological restoration goals for the dam removal and stream restoration are as follows:

(1) Restore longitudinal connectivity to allow migration of aquatic organisms between the Middle Reservoir
and the upper reaches of Roberts Meadow Brook;
2
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

(2) Restore natural stream processes, including the free movement of water, sediment, and organic matter; and,
(3) Restore stream habitat (now submerged) and stabilize residual exposed sediments within the former URMR
impoundment area.

3.2 Success Criteria

Project success will be achieved by removing the full vertical extent of the Poor condition, High hazard dam, and
limiting short-term construction period impacts. The related ecological restoration benefit of stream connectivity
will be realized immediately upon dam removal, and can be easily confirmed via field observation and survey. In
the months and years following dam removal, other restoration benefits will also be realized, including
transformation of the now submerged channel within the impoundment back to a free-flowing reach. Moreover,
following erosion and natural redistribution of mobile impounded sediment, a natural sediment and organic matter
transport regime will be re-established in the sediment starved downstream brook. The assessment of the Success
Criteria relative to the ecological restoration goals will include active monitoring by the City of Northampton, as
described in Table 1.

Table 1. Restoration Goals and Success Criteria


Restoration Goal Success Criteria Criteria Assessment

(1) Restoration of  Full vertical extent of the dam is  As-built plan of the dam removal
Stream removed. generated post construction.
Connectivity  Increased cold water fish populations.  Fish surveys by MassWildlife at Years 1,
5, and 10 post dam removal.
 GPS-based longitudinal stream bed
profile surveys at Years 1 and 5 post
dam removal

(2) Restoration of  Downstream benthic habitat between the  Photo-documentation by the City at
natural stream dam and Middle Reservoir contains a Year 1, 3 and 5 post dam removal at five
processes, mix of grain sizes and organic matter. (5) monumented cross-sections within
including sediment the stream corridor downstream of the
and organic matter former dam site.
regimes  Water quality monitoring (temperature
and dissolved oxygen) by Hampshire
College, UMass Amherst, MA DER and
MassWildlife

(3) Formation of free-  A natural stream bed – consistent with  Photo-documentation by the City at
flowing stream upstream conditions – reforms within the Years 1, 3 and 5 post dam removal at five
reach and natural restored channel of the former cross sections within the former
riparian habitat impoundment, impoundment.
within former  The banks of the restored stream channel
URMD of the former dam impoundment, in areas
impoundment above estimated Ordinary High Water
(OHW), are at least 90% re-vegetated

3
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

 Exposed sediment landward of the new


stream bank are at least 90% re-vegetated
by herbaceous and/or woody vegetation.

4.0 Project Monitoring

The restoration success of Roberts Meadow Brook will be assessed by monitoring during and post dam removal
construction. The monitoring methods to be used will be as follows:
4.1 Construction Phase Monitoring

The construction phase monitoring will focus on safe implementation of the staged dam removal,
confirmation of removal of the full-vertical extent of the dam, and downstream monitoring of bed
aggradation to address potential roadway flooding risks. Adaptive sediment management
techniques will be implemented downstream as needed to address risks of flooding to adjacent
roadways downstream of the dam. Weekly reports will be generated during the active construction
and will be kept on file with the City.

4.2 Post-Construction Monitoring:

4.2.1 Photo-documentation will be performed before, during and for a period of 5-years
after the dam has been removed. For Roberts Meadow Brook and the residual sediment
areas within the former URMR Basin area, a minimum of five (5) general basin and
instream photo-documentation transverse cross-sections will be established to monitor the
conditions as they stabilize and mature over time. Along Roberts Meadow Brook below
the former dam, at least five (5) photo-documentation transverse cross-sections will be
established along the stream to document the change in conditions over time. The post
construction photo-documentation will occur at years 1, 3, and 5 after the dam has been
fully removed.
4.2.2 GPS-based, longitudinal surveys will be performed through the former
impoundment, through the dam removal location, and downstream to the Middle
Reservoir at years 1 and 5 post-construction. This data will be compared to the existing
conditions longitudinal survey. Lastly, Massachusetts Fish and Game will conduct fish
studies of the restored stream at Year 1, Year 5 and Year 10 post dam removal.
4.2.3 Water quality monitoring (temperature and dissolved oxygen) will be measured within
and downstream of the former impoundment pre- and post- dam removal. Refer to the
detailed description in Attachment B.

5.0 Contingency Plans

The dam removal will require the City to develop and implement a series of contingency responses on an as needed
basis. The contingencies include the following:

5.1 Re-Vegetation Contingency

The City will maintain a contingency provision for “as-needed” re-vegetation of highly
eroded areas that may develop within the newly established stream channel within the former
4
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

impoundment. The project objective is to utilize natural processes to re-establish the stream
channel within the former impoundment. Consequently, sediment will be eroded during the dam
breach process. The intent is for the stream channel to erode its way into the sediment to establish
itself. Once established, the goal is that the sediments beyond the banks will be “stabilized” via the
growth of wetland vegetation. The intent of this contingency provision is to provide a means to
reseed areas that continue to erode post construction due to a lack of established vegetation. It is
anticipated that the re-vegetation contingency will utilize either City forces or a subcontractor to
mobilize to the former impoundment and re-seed eroded areas that lack established vegetation with
appropriate wetland vegetation seed. The identification of these areas will be made during the Post-
construction visual monitoring and photo-documentation to be conducted by the City after the
completion of the dam breaching. The contingency will be used for hand seeding only, no additional
earthwork operations will be performed for this item. The re-vegetation contingency will be
maintained for a period of five (5) years after the completion of the dam breaching.

5.2 Adaptive Sediment Management Contingency – Roadway Flooding Mitigation

The City will implement an adaptive sediment management program geared towards
mitigating flooding to adjacent roadways downstream of the dam. The contingency will
include requiring the contractor and/or the City to have equipment and man power available should
a snag or block develop within the stream channel that could potentially cause a temporary dam
within the stream channel and threaten to flood adjacent roadways. The contractor will be
responsible for this contingency during construction. The City or a subcontractor to the City will
be responsible to implement this contingency on an as needed basis post dam removal.

6.0 Schedule

The dam removal project is scheduled to begin in the spring of 2018 and be completed by the fall of 2018.
Construction phase monitoring will be performed during the work. Post dam removal monitoring will be performed
one year after the dam has been removed at or near the end of the growing season, as well as within years 3 and 5
post-dam removal. If the Success Criteria have been met, the monitoring under this Restoration Plan will cease.
Otherwise, additional bi-annual monitoring events will occur. We anticipate that the project will fully meet the
success criteria within three years of project completion.

7.0 Reporting

Monitoring reports for data collection in years 1, 3, and 5 post dam removal, will be assembled and submitted to
the USACE within 60 days of completion. Monitoring reports will address the success criteria and provide narrative
descriptions, figures, and labeled photographs, as appropriate.

5
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

Attachment A

6
N

GRAPHIC SCALE
0 20 40 80

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

MIDDLE ROBERTS MEADOW RESERVOIR


INLET AREA
PREPARED BY: PREPARED FOR:
GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: NYA CHECKED BY: MAT DRAWING

6
DESIGNED BY: NYA DRAWN BY: EDM SCALE: 1"=40'
DATE: PROJECT NO. REVISION NO.
NOVEMBER 2017 01.0019547.20 SHEET NO. 6 OF 15
N

GRAPHIC SCALE
0 25 50 100

SCALE IN FEET

UPPER ROBERTS MEADOW RESERVOIR


DAM BREACH AND STREAM RESTORATION PROJECT
NORTHAMPTON, MA

INVASIVE SPECIES CONTROL PLAN

PREPARED BY: PREPARED FOR:


GZA GeoEnvironmental, Inc. CITY OF NORTHAMPTON
Engineers and Scientists DEPT. OF PUBLIC WORKS
www.gza.com

PROJ MGR: MAT REVIEWED BY: NYA CHECKED BY: MAT DRAWING

8
DESIGNED BY: NYA DRAWN BY: EDM SCALE: 1"=50'
DATE: PROJECT NO. REVISION NO.
NOVEMBER 2017 01.0019547.20 SHEET NO. 9 OF 16
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

Attachment B

7
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

BACKGROUND

The Upper Roberts Meadow Dam in Northampton, MA is the most upstream of three dams on Roberts
Meadow Brook. At a formidable 9 meters tall and with no form of fish passage, it is a complete barrier to migrating
aquatic species. The aging structure is listed as “high hazard” and in “poor condition” (Figure 1, 2) and could
eliminate 200 homes within the downstream community of Leeds, MA in the event of a failure. The dam is part of
the City of Northampton’s former emergency public water supply and sits in a relatively undeveloped and protected
tract of forest. Upstream of the impoundment, Roberts Meadow Brook is a cold-water, high gradient stream (Figure
3) that runs through steep gorges, over large riffles, and supports a strong cold-water fishery that includes native
brook trout. Downstream of the dam, the brook slowly transitions from a high gradient stream to a channelized, low
gradient one as it heads to the Middle Reservoir on the brook (Figure 4).

METHODS

Continuous data loggers will be used to assess the impacts of Upper Roberts Meadow Dam and associated
impoundment on temperature and dissolved oxygen profiles within Roberts Meadow Brook. The study area
stretches from downstream of the tributary inflow about 660 meters upstream of the dam to the Middle Reservoir
on Roberts Meadow Brook about 1800 meters downstream of the dam (Figure 5). Pools and deep runs will be
prioritized as installation locations to ensure all loggers remain submerged throughout the deployment period.

One upstream, one impoundment, and five loggers downstream of the dam will be used to assess the impact
of the Upper Roberts Meadow Dam on the river’s temperature regime (Tables 1, 3). Onset© HOBO Pro V2
Temperature Data Loggers recording every 15 minutes will collect year-round, continuous temperature throughout
the entirety of the project. Each logger will be visited bi-annually (See “Project Timeline” below) to check the
installation location and to download data off of the logger. The impoundment logger will float beneath a buoy
attached via cabling to a cinder block on the impoundment bottom. Depending on stream substrate, temperature
loggers will be attached to a piece of rebar in the streambed or anchored on the streambed with rocks. All loggers
will be cabled to a permanent structure on the stream bank. More detailed information can be found in the
Continuous Temperature Monitoring SOP.

To assess the impact of the dam on dissolved oxygen, Onset© U26 Dissolved Oxygen Data Loggers will
be deployed upstream of the impoundment, within the impoundment, and downstream of the dam (Tables 2, 4).
The loggers will be deployed for discrete weeklong periods between approximately 2015 and 2018 to capture pre-
and post-dam removal conditions (specific periods to be adjusted based upon dam removal timing). While in the
field, loggers will record dissolved oxygen and temperature readings every 15 minutes. The impoundment logger
will float beneath a buoy cabled to a cinder block on impoundment bottom, and upstream and downstream dissolved
oxygen loggers will be attached to a piece of rebar via zip ties and hose clamps. More information can be found in
the Continuous Dissolved Oxygen Monitoring SOP.

8
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

Table 1. Temperature data logger installation information.


LOGGER
ATTACHED
SITE LOGGER DEPTH STREAM ANCHORING
SITE LATITUDE LONGITUDE BANK
CODE LOCATION (CM FROM FEATURE METHOD
STRUCTURE
BOTTOM)
URM-T-
Upstream 42.337417 -72.734517 River right Bottom Riffle Cabled to tree Rock pile
US
URM-T-
Impoundment 42.338132 -72.728243 Mid channel Surface Impoundment N/A Cinder block
IMP
URM-T-
Downstream 1 42.338150 -72.727700 River right Bottom Riffle Cabled to tree Rock pile
DS1
URM-T-
Downstream 2 42.338633 -72.726300 River left Bottom Riffle Cabled to tree Rock pile
DS2
URM-T-
Downstream 3 42.339433 -72.724600 River right Bottom Riffle Cabled to tree Rock pile
DS3
URM-T-
Downstream 4 42.340300 -72.720283 River right Mid depth Run Cabled to tree Rebar
DS4
URM-T- Cabled to tree
Downstream 5 42.348067 -72.713117 River right Bottom Run Rock pile
DS5 roots

Table 2. Dissolved oxygen data logger installation information.


LOGGER
ATTACHED
SITE LOGGER DEPTH STREAM ANCHORING
SITE LATITUDE LONGITUDE BANK
CODE LOCATION (CM FROM FEATURE METHOD
STRUCTURE
BOTTOM)
URM- Hose clamp
Upstream 42.337417 -72.734517 Mid channel Mid depth Pool N/A
DO-US to rebar
URM-
Impoundment 42.338132 -72.728243 Mid channel Surface Impoundment N/A Cinder block
DO-IMP
URM- Hose clamp
Downstream 42.338247 -72.727670 Mid channel Mid depth Pool N/A
DO-DS to rebar
Table 3. Temperature data logger detailed installation information and rationale.

9
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

METERS
SITE WRITTEN DESCRIPTION OF DEPLOYMENT
SITE D/S OF REASONING FOR DEPLOYMENT LOCATION
CODE LOCATION
DAM
URM-T- 50 meters upstream of gorge, just downstream of Downstream (80 m) of tributary and upstream
Upstream -660
US large riffle. River right. of inaccessible gorge.
URM-T-
Impoundment -28 Center channel. Floating. Kept a safe 25-m buffer from spillway.
IMP
URM-T-
Downstream 1 23 Cabled to birch. River right. Birch was good anchor.
DS1
URM-T- Cabled to oak tree 100 meters upstream of Intermediary position between URM-T-DS1
Downstream 2 149
DS2 Kennedy St. Bridge. River left. and URM-T-DS3.
URM-T- 27 meters downstream of Kennedy St. Bridge.
Downstream 3 325 At start of “middle reach” of downstream.
DS3 Cabled to triple trunk tree. River right.
URM-T- Cabled to roots of enormous two-trunked white Just before homogenous “lower reach” of
Downstream 4 700
DS4 pine. River right. On rebar. downstream.
URM-T- Cabled to hemlock root 75 meters upstream of Just upstream of upper extent of Middle
Downstream 5 1750
DS5 Middle Reservoir. River right. Reservoir.

Table 4. Dissolved oxygen data logger detailed installation information and rationale.
METERS
SITE WRITTEN DESCRIPTION OF DEPLOYMENT
SITE D/S OF REASONING FOR DEPLOYMENT LOCATION
CODE LOCATION
DAM
URM- 50 meters upstream of gorge, just downstream Downstream (80 m) of tributary and upstream of
Upstream -660
DO-US of large riffle. Center channel. On rebar. inaccessible gorge.
URM-
Impoundment -28 Center channel. Floating. Kept a safe 25-m buffer from spillway.
DO-IMP
URM-
Downstream 27 Center channel. On rebar. In pool deeper pool near URM-T-DS1.
DO-DS

10
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

PROJECT TIMELINE (TENTATIVE – TO BE UPDATED BASED UPON DAM REMOVAL SCHEDULE)

March 2018 Install temperature data loggers


March 2018 Deploy dissolved oxygen loggers for 1 week
October 2018 Download and check temperature data loggers
May 2019 Download and check temperature data loggers
June 2019 Deploy dissolved oxygen loggers for 1 week
July 2019 Deploy dissolved oxygen loggers for 1 week
August 2019 Deploy dissolved oxygen loggers for 1 week
September 2019 Download and check temperature data loggers prior to beginning of
dam removal
September 2019 Dam slated for removal
April 2020 Download and check temperature data loggers

SITE CONTACTS

Alex Hackman MA DER alex.hackman@state.ma.us (617) 626-1548


David Veleta City of Northampton dveleta@northamptonma.gov (413) 587-1570
Johanna Stacy City of Northampton jstacy@northamptonma.gov (413) 587-1376

Upper Roberts Meadow Dam is located within the City of Northampton’s former backup public water supply and
either David or Johanna must be contacted 24 hours in advance of a site visit. A monitoring plan was submitted to
the City of Northampton to gain approval for the proposed monitoring associated with this project.

SURROUNDING ENVIRONMENT

Upper Roberts Meadow Dam is located on Roberts Meadow Brook in Northampton. The dam is
approximately 9 meters tall and is built in a steep walled gorge. The stream extends downstream of the dam for about
1800 meters before reaching the Middle Reservoir on the brook. This downstream reach can be divided into three
separate reaches – the high gradient “upper reach” from the dam to Kennedy Road Bridge, the middle gradient
“middle reach” from Kennedy Road Bridge to the intersection of Chesterfield and Reservoir Roads, and the low
gradient “lower reach” from that intersection to the Middle Reservoir. The middle reach is moderately channelized,
and the lower reach has been heavily channelized into a straight segment running between Reservoir Road and a
large berm until it empties into the reservoir. The upstream reach of this study is very high gradient with large riffles
and additional steep walled gorges. The entire study area is located within protected, forested land and was formerly
used by the City of Northampton for emergency public water supply. Kennedy St. crosses the river about 300 meters
downstream of the dam.

ADDITIONAL RESEARCH BEING CONDUCTED ON SITE

Chris Cianfrani of Hampshire College is studying geomorphic changes to Roberts Meadow Brook following
removal of Upper Roberts Meadow Dam.
Allison Roy of UMass Amherst is studying the changes to benthic macroinvertebrate and fish communities
of Roberts Meadow Brook following removal of Upper Roberts Meadow Dam.
Alex Hackman of MA Division of Ecological Restoration is establishing photographic monitoring stations
(hopefully with local neighborhood volunteers).
Rich Hartley of MassWildlife is studying fish community structure and distribution before and after the dam
removal.
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

FIGURES

Figure 1. Under moderate flows (seen here) the number of seeps through the dam that has contributed
to its listing as a “poor condition”, “high hazard” structure can be easily seen. Photo taken downstream
of the dam, center channel, facing upstream.
© Joe Foster

Figure 2. Under very low flows, it is easier to see the “poor condition” of the dam, especially on the river right
abutment with the large number of protruding and slipping granite blocks. Photo taken downstream of the dam,
center channel, facing upstream.
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

Figure 3. Upstream of the dam, the brook is a high gradient (and coldwater, though that cannot be seen here) stream
that runs over large riffles and through steep-walled gorges. Photo taken 5 meters downstream of URM-T-US, center
channel, facing upstream.

Figure 4. Downstream of the dam, the brook slowly transitions into a low gradient stream that has been completely
straightened and channelized by boulders, dikes, and large riprap. Photo taken from URM-T-DS4, center channel,
facing downstream.
Upper Roberts Meadow Reservoir Dam Breach and Stream Restoration Project
Stream Restoration and Monitoring Plan
NAE-2007-1851. GZA File No. 01.0019547.20
Revised November 29, 2017
May 29, 2015

Figure 5. Map of Upper Roberts Meadow Dam sampling locations.

Вам также может понравиться