Академический Документы
Профессиональный Документы
Культура Документы
re LEARNED the BP Process Safety Series: sharing lessons learned from accidents.
Recurring accidents:
inadequate isolations
52 www.tcetoday.com december 2013/ january 2014 For more information and a sample copy of LPB visit: www.icheme.org/lpb
A new series of articles inspired by IChemE’s Loss Prevention Bulletin and LESSONS
the BP Process Safety Series: sharing lessons learned from accidents.
re LEARNED
bleed valve.
If a process isolation deviates
Pump no.2 Plug Pump no.1
from the plan, whether controlled
which had fitted Tank
by PTW or operating procedure, been removed under
then STOP! Re-evaluate the stand
task. In this case, the interlock
arrangements which permitted Layout of phenol pumps, main pipes and valves
the human error to occur should
then have been reviewed with a
An engineering fitter was badly burned by phenol spilling from a pipe attached
view to modification.
to a valve that he was removing.
A phenol transfer system consisted of two pumps, overhead pipework and a
drainage system from the pump bodies as shown in the above figure.
• long delays between atmosphere testing and
work beginning. Number 2 pump was removed for overhaul three weeks prior to the incident
because of a leaking gland assembly. The resulting open pipework was blanked off.
the legal section Maintenance work was planned to coincide with the annual holiday shutdown
Countries with extensive, well-regulated when various pieces of plant were being overhauled. The discharge valve of
industries all have legislation that is similar number 2 pump (“number 5 ball valve”) required overhauling as it was passing.
in principle to that in the UK1,2,3. Factors to Process operators had blown the line clear with inert gas and drained the lines
be considered include the nature of plant to the draindown tank via number 1 pump. Steam was turned off the valve once
to be worked on together with associated the lines had been blown out and electrical heating turned off. The plant was then
hazards that require isolation, contingency handed over from production to maintenance staff and on the following day the full
plant shutdown started.
arrangements, and the need to define safe
systems of work. A fitter was instructed to remove the number 5 ball valve. The bobbin below the
valve was removed and six of eight bolts removed from the top flange of the valve.
In the UK there are no specific regulations
At this moment the joint broke and around 5–10 l of phenol ran out of the pipework
relating to isolation of plant and equipment,
causing burns to the fitter’s shoulder, body, hands and legs. The fitter was, at one
but, as is the case with all UK health
stage, unconscious and critically ill.
and safety legislation, the underpinning
legal requirements are enshrined in the The investigation found that:
Management of Health and safety at Work • the plant had not been handed over to maintenance staff using any formal hand-
Regulations 1999. Practical guidance on safe over procedure;
process isolations is given in HSG253 – The
• the maintenance supervisor lacked knowledge of the precise state of the plant
Safe isolation of Plant and Equipment4. For
and his subsequent verbal instruction to the fitter was inadequate;
electrical isolations, guidance can be found
in HSG85 – Electricity at Work – Safe Working • the line in question had not been drained. The relevant engineering personnel did
Practices5. not recognise that blowing down of this system would be ineffective when number
The following practical guidance is based 2 pump was removed;
on HSG253. • there was no PTW for the job and therefore the possible hazards and risks had
not been recognised;
the detailed legal requirements
• only gloves and goggles had been provided and it is not clear if these had been
Using the UK as an example, a “suitable and
worn by the fitter; and
sufficient” assessment of all the risks for all
work activities for the purpose of deciding • no formal general training on hazard awareness, nor on the hazards of phenol
what means are necessary for safety must be was provided for employees.
carried out in accordance with regulation
For more information and a sample copy of LPB visit: www.icheme.org/lpb december 2013/ january 2014 www.tcetoday.com 53
LESSONS A new series of articles inspired by IChemE’s Loss Prevention Bulletin and
re LEARNED the BP Process Safety Series: sharing lessons learned from accidents.
54 www.tcetoday.com december 2013/ january 2014 For more information and a sample copy of LPB visit: www.icheme.org/lpb
A new series of articles inspired by IChemE’s Loss Prevention Bulletin and LESSONS
the BP Process Safety Series: sharing lessons learned from accidents.
re LEARNED
For more information and a sample copy of LPB visit: www.icheme.org/lpb december 2013/ january 2014 www.tcetoday.com 55
LESSONS A new series of articles inspired by IChemE’s Loss Prevention Bulletin and
re LEARNED the BP Process Safety Series: sharing lessons learned from accidents.
further reading
1. European Framework Directive 89/391/EEC Our Loss Prevention Bulletin (LPB) is the leading source
2. EU-OSHA (2010), Safe Maintenance in of process safety case studies with a 40+ year archive of
Practice lessons learnt.
3. Government of Western Australia,
Department of Commerce. Guidance Note, Take a look at www.icheme.org/lpb
Isolation of Plant, 2010
4. The Safe Isolation of Plant and Equipment
HSG 253. ISBN: 9780717661718
5. Electricity at Work: Safe Working Practices Chemical Engineering Matters
HSG 58 ISBN: 9780717665815 The topics discussed in this article refer to the following lines on the vistas of IChemE’s technical strategy
6. The Management of Health and Safety at document Chemical Engineering Matters:
56 www.tcetoday.com december 2013/ january 2014 For more information and a sample copy of LPB visit: www.icheme.org/lpb