For the facility of irrigation at D/S of ch. 17+988 km the construction of aqueduct is highly
necessary. This proposal is made for the construction of R.C.C. aqueduct at the location
and its estimated cost is NRs. 1,38,58,900.00 . The span of the aqueduct is 16 m and
the discharge of canal is 1.50 cumec and length of canal at D/S of aqueduct is 3.25 km .
Damaged Pipe Aqueduct at Harinagara S14 Canal at ch. 17+988
Span : 16 m.
Command area
Canal Length