Financial Proposal for Geotechnical Investigation

Client: BCL Associates Limited Date: 4-Feb-18


Attn: Md. Golam Masud, PEng Designation: Managing Engineer

Project: Widening and Improvement of Road and Construction of Flyover at Mipur Cantonment.

Unit Rate Amount


Sl. Item Description Unit Quantity
(BDT) (BDT)
Mobilisation & Demobilisation: All costs
associated with mobilisation of all
equipment of Soil test, drilling Rigs,
1 Rig 3 30,000 90,000
machinary, manpower etc, undertaking the
work for the duration of the Contract and
demobilisation.
Soil Boring & SPT @ 1.5m interval
-
(Percussion method)
Bridge, Upto 50m (2 BH) BH No. 2 77,000 154,000
2 Road Widening, Upto 10m (8 BH) BH No. 8 13,500 108,000
Flyover, Upto 40m (10 BH) BH No. 10 58,000 580,000
Flyover, Upto 20m (20 BH) BH No. 20 27,500 550,000
3 Dynamic Cone Penetration Test (DCPT) No. 8 9,500 76,000
4 Undisturbed Sample Collection No. Rate only 2,500 2,500
5 Trial Pit Excavation No. 8 8,500 68,000
Laboratory Testing -
a) Particle Size Distribution (Sieve Analysis) No. Rate Only 500 500
b) Particle Size Distribution (Hydometer
No. Rate Only 520 520
Analysis)
c) Natural Moisture Content No. Rate Only 375 375
d) Specific gravity No. Rate Only 520 520
6
e) Atterberg Limits and PI index No. Rate Only 520 520
f) Unit Weight Test No. Rate Only 500 500
g) Direct Shear Test No. Rate Only 1,050 1,050
h) Consolidation Test No. Rate Only 5,500 5,500
i) Unconfined Compression Test No. Rate Only 1,250 1,250
j) CBR Test No. 10 12,500 125,000
Reporting and Submission of draft & final
7 No. 1 150,000 150,000
Report.
N.B.: This rate excludes the Tax and VAT.