Вы находитесь на странице: 1из 3

Save time with

masonry footings
Build the foundation wall immediately after the
footing is laid

T
ired of waiting for concrete preparing the excavation, establish the
footings to cure so you can corner points and string a line between
build the foundation walls? An- them. The layout is square if the diag-
noyed by the concrete subcontractor ’s onals between corners are equal.
schedule or by repairs you have to Place the corner units first. Then in-
make to cracked sidewalks and rutted terlock the stretcher units, leveling the
lawns damaged by concrete trucks? footing as construction continues. The
Then consider building with masonry blocks are placed dry without mor-
footings. tar—or formwork.
Masonry, a common ancient foun- When the footing is completed, the
dation material, is again being used to first course of block for the foundation
build foundations. After World War II, wall can be laid. A bed of mortar can
Europe started using prefabricated ma- be placed on the footing blocks to pro-
sonry footings to make reconstruction vide a level surface for the wall blocks.
faster and easier. Several proprietary
systems are now available throughout How much load can masonry
the world (Figure 1). footings carry?
The National Concrete Masonry The NCMA masonry footing sys-
Association (NCMA) has developed tem was tested by the Department of
an economical masonry footing sys- Civil Engineering at the Virginia Poly-
tem that is now available throughout technic Institute and State University
most of the United States. The NCMA (Ref. 1). Its test results show that con-
system consists of interlocking solid crete masonry footings settle less than
concrete blocks that are slotted on the monolithic concrete footings on both
top to receive reinforcing (Figure 2). loose and moderately dense sand (Fig-
Two stretcher units are available: a ure 3).
4x8x16-inch unit for 8-inch-thick Based on an allowable soil capacity
foundation walls and a 3x8x20-inch of 2,000 pounds per square foot, these
unit for 12-inch-thick foundation interlocking block pieces can carry the
walls. Corner units, 8x8x8 inches, can following loads: The 16-inch-wide
be used with either size stretcher units can carry 2,600 pounds per lineal
block. foot and the 20-inch-wide units can
Figure 1. Commonly used in ancient carry 3,300 pounds per lineal foot.
times, masonry footings were again Constructing a masonry foot- The NCMA block footing system
used in Europe after World War II to ing has been designed to comply with the
speed reconstruction. A system that To build a masonry footing, first ex- requirements of the Uniform Building
complies with the model building codes cavate below the frost line to solid, Code, the Southern Standard Building
was recently introduced in the United undisturbed soil. Using gravel, sand, Code, and the Basic Building Code.
States (see Figure 2). or even mortar, provide a level bearing Check with the NCMA for compliance
surface for the footing blocks. After with other codes and standards.
Figure 2. The block footing system developed
by the National Concrete Masonry Association
(NCMA) is laid dry without mortar on a level
bearing surface, usually gravel or sand. The
blocks interlock, and slots in the top accept
steel reinforcement. Mortar is placed on top of
the blocks to provide a level bed for the
foundation wall blocks.

Benefits of masonry footings contractor can lay up the foundation


Contractors charge the same for ma- wall right after the block footing is
sonry and concrete footings, but ma- built.
sonry footings have many additional Winter construction. Contractors
benefits. who use the footing block system say
Eliminate concrete subcontrac- that is saves money on cold weather
tors. With block footings, work construction. Instead of protecting a
doesn’t have to be scheduled around a concrete footing the extra time re-
concrete subcontractor. Both the foot- quired in winter, then building a ma-
ing and foundation wall can be built in sonry wall and protecting it, they can
the same day. complete the footing and wall and pro-
Eliminate concrete curing time. tect the whole structure at once. Blan-
Even if coordinating with other trades kets, tarps, or even backfilling can pro-
is not a problem, waiting for the con- tect masonry footings.
crete footing to gain strength can be No damage from ready mix
costly. Workers must either move to trucks. Block footings can be very
another job and helpful on remodeling jobs. Cracked
then return, or stay sidewalks and rutted lawns from heavy
Figure 3. Under the same load, masonry footings settle home. The footing concrete trucks are eliminated. The
less than cast-in-place concrete footings. These are the system eliminates footing blocks can be moved from the
results from tests performed on the NCMA footing system waiting time; the truck to the excavation on brick carts.
by the Virginia Polytechnic Institute and State University.
Tips from contractors
Contractors using the footing sys-
tem say it’s easy to construct. The
small units can be strung together to
create or match almost any foundation
layout. The sand or gravel leveling bed
only needs to be within _1/2 inch be-
cause mortar can be used to adjust the
level of the first block course. And no
footing blocks are wasted; extra units
are moved to the next job.
A marketing problem does exist
though. Homeowners don’t always be-
lieve that individual precast footing
blocks are as strong as cast-in-place
concrete. Fortunately, tests indicate
that the footing block system is strong.
Because concrete masonry units are
manufactured under carefully con-
trolled conditions the units are not sub-
ject to the variables that plague cast-
in-place concrete.

Masonry footings in seismic


zones
For strength, the footing system in-
terlocks and can be reinforced with
wire reinforcement or reinforcing bars
placed in the slots in the top of the
blocks. If even greater strength is re-
quired, continuous deformed steel bars
can be placed and grouted within the
first course of the block wall. Vertical
steel dowel bars also can be placed and
anchored into the first foundation
course. Before constructing in seismic
regions, check with the local building
officials for approval of block foot-
ings.

—by Bruce A. Suprenant

References
1. Krebs, R. D., G. W. Clough, and Kim
T. W. Lewis, “Segmented Footing Sys-
tem Evaluation,” Department of Civil
Engineering, Virginia Polytechnic Insti-
tute and State University, Blackburg,
Virginia, 1987.
2. “Segmental Masonry Footings,”
NCMA-TEK 110A, 1988, National
Concrete Masonry Association, 2302
Horsepen Road, Herndon, Virginia
22070.

PUBLICATION #M880306
Copyright © 1988, The Aberdeen Group
All rights reserved

Вам также может понравиться