ADMA/HHI/ETAP Discussions points on Power Energization Relay setting

report

Following points where discussed


Description Action
Generator Input data such as Will be included in the next revision of the
KW, FLA, pf, Xd”, Xd’, Xd etc., relay setting reports(Action by ETAP)
has to include in Annexure in
report. (for Main as well as
Power Energization report)
Attach Load flow and short Will be included in the next revision of the
circuit ETAP Report relay setting reports(Action by ETAP)
Load list and Short circuit study. ETAP confirmed that load flow and short
circuit study for Various phases of
energization has been carried out based on
the load list and SLD submitted by HHI and
same is already been sent to ADMA for
reference. In addition, the same is attached
in this mail.
CRS sheet need to included CRS sheet will be sent along with the report
in next revision. However please note that
most of the comments are pertaining to
permanent settings.
Power System Grounding The report is prepared and submitted to
through NGR HHI/ADMA before the change in the
grounding scheme from NGR to
Ungrounded.

However report shall be revised based on


the proposed ungrounded scheme.
Overvoltage ground relay 59 The setting proposed is 20%. However as
Settings already mentioned in our Email
correspondence dated 6th December 2017,
after energizing 13.8 kV network up to
transformer primary the unbalance voltage
at the open delta VT to be measured and
fine tuned to the next available setting
available.
Maintenance switch for ADMA requested ETAP to check the
Temporary power energization requirement of maintenance switch for the
temporary power energization considering
safety of the operating personnel, Since
ETAP has already recommended to
installation of maintenance switch in Main
relay setting report.
Revision in relay settings for Small feeders connected to HVAC system
small feeders and incorporation having feeder cable lengths more than 20
of Notes in the TCC curves. meters, proposed permanent settings
adopted for the feeders are not sensitive
for operation due to low fault current
caused by high cable lengths. ETAP to
indicate “These settings to be revised to
permanent settings after energization of
Temporary Power supply and
Coordination is not Applicable for these
feeders” in the TCC Curves.
ADMA requested ETAP to check ETAP informed that considering safety of
the proposed Un-grounded personnel and to reduce over-voltages to
arrangement for the Generators ground, as per Industry standard, the
and the proposed ground generator neutral is normally grounded
protection system (OVGR) for solidly or grounded through a resistor or
the temporary Generators reactor depending on the generator design.
considering safety of the Considering the proposed Generators are
operating personal and the meant for Temporary power supply
equipment. energization, and 59/64 sensitive Over
Voltage Ground relays are connected to the
Generator system for Ground fault
detection/protection the proposed
Ungrounded Generators can be connected
in principle to the power system. However,
the suitability of the Generators and the
associated power system to operate as an
Ungrounded Power supply source needs to
be checked and confirmed by HHI thru
proper documentation.