SECTION 1
DESCRIPTION OF WORKS
TABLE OF CONTENS
1 DESCRIPTION OF WORKS ........................................................................................................................ 1-1
1.1. PROJECT BACKGROUND ................................................................................................................. 1-1
1.2. SCOPE OF WORK .............................................................................................................................. 1-2
1.3. SITE LOCATION ................................................................................................................................. 1-3
1.4. SITE ACCESS ..................................................................................................................................... 1-4
1.5. RELEVANT STANDARDS................................................................................................................... 1-4
1.6. SCOPE OF PLANT SUPPLY AND INSTALLATION ........................................................................... 1-7
1.6.1. AYANUNGA POWERHOUSE ............................................................................................... 1-7
1.6.2. 8 DE AGOSTO SUBSTATION .............................................................................................. 1-9
1.7. CONTRACT LIMITS .......................................................................................................................... 1-10
1.7.1. AYANUNGA POWERHOUSE ............................................................................................. 1-10
1.7.2. 8 DE AGOSTO SUBSTATION ............................................................................................ 1-11
1.7.3. AYANUNGA INTAKE, PAN DE AZUCAR INTAKE AND FOREBAY (THREE SITES) ........ 1-12
1.8. DRAWINGS ....................................................................................................................................... 1-12
LIST OF TABLE
TABLE 1: REFERENCED STANDARDS ............................................................................................................. 1-4
LIST OF FIGURES
FIGURE 1- PROJECT LOCATION ....................................................................................................................... 1-3
FIGURE 2 - PROJECT LOCATION (DETAILED) ................................................................................................. 1-3
FIGURE 3 - ACCESS ROUTES ........................................................................................................................... 1-4
1 DESCRIPTION OF WORKS
1.1. PROJECT BACKGROUND
The Ayanunga hydroelectric project (Project) is a 20 MW (nom) run of river scheme located
in the district of Monzón, province of Humalies, and department of Huanuco, Perú.
An intake weir and desander structure on the Ayanunga River. The weir will include:
A 4.1 km long 2.3 x 2.3 m closed culvert, with open channel flow, to the penstock
forebay structure.
An intake weir and desander structure on the Pan de Azucar River. The weir will
include:
A 2.65 km long 2.0 x 2.0 m closed culvert, with open channel flow, to the penstock
forebay structure.
A forebay structure with gravity close, hydraulic open, penstock intake gate and level
and flow measuring equipment.
A 312 m long, 1.9 m internal diameter high pressure GRP surface penstock, a steel
bifurcation, and two branches 20 m long, and 1.2 m diameter to the inlet of the turbines
in the powerhouse.
A surface powerhouse facility located immediately upstream from the Ayanunga and
Pan de Azúcar rivers.
A 4.3 km long single circuit 138 kV transmission line to the existing 8 de Agosto
switchyard.
A new three bay 138 kV outdoor new 8 de Agosto switchyard incorporating the existing
single bay 8 de Agosto switchyard. This new switchyard will be connected to the SEIN at
the existing 138 kV Tingo María substation through an existing 138 kV single circuit
transmission line.
The electromechanical Plant will be located at various locations within the Project area and
are described in more detail later in this specification.
The anticipated access route to be used for major equipment deliveries is by paved
highway from Lima, via the towns of La Oroya, Huánuco and Tingo María. From Tingo
María 65 km of unpaved road extends to the Project site as shown in Figure 3.
Figure 3 - Access Routes
Project
Standard Title
Fundamental Rating Factors and Calculation Methods for Involute Spur and Helical
AGMA 2001
Gear Teeth
ANSI/ASME A13.1 Scheme for the Identification of Piping Systems
ANSI/AWS D1.1 Structural Welding Code – Steel – Welding
ANSI/NFPA 70 National Electric Code
ANSI B49.1 Shaft Couplings, Integrally Forged Flange Type for Hydroelectric Units
ANSI S82.03 Safety Standard for Electronic Test, Measuring Controlling and Related Plant
ANSI B16.104 ANSI/FCI 70-2 Control Valve Seat Leakage
ANSI/IEEE C62.1 IEEE Standard for Gapped Silicon-Carbide Surge Arresters for AC Power Circuits
Overhead and Gantry Cranes (Top Running Bridge, Single or Multiple Girder, Top
ASME B30.2
Running Trolley Hoist) – Safety
ASME HST-4 Performance Standard for Overhead Electric Wire Rope Hoists
ASTM A27/A27M-13 Standard Specification for Steel Castings, Carbon, for General Application
ASTM A36/A36M-14 Standard Specification for Carbon Structural Steel
ASTM A487/A487M-14 Standard Specification for Steel Castings Suitable for Pressure Service
Standard Specification for Pressure Vessel Plates, Carbon Steel, for Moderate-
ASTM A516/A516M-10
and Lower-Temperature Service
Standard Title
Standard Specification for Steel Forgings, Carbon and Alloy, for General Industrial
ASTM A668/A668M-15
Use
ASTM D3487 Standard Specification for Mineral Insulating Oil Used in Electric Apparatus
ASTM A240/A240M- Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate,
15 Sheet, and Strip for Pressure Vessels and for General Applications
ASTM E23-12c Standard Test Methods for Notched Bar Impact Testing of Metallic Materials
BS 148 Reclaimed Mineral Insulating Oil for Transformers and Switchgear
CCH70-3 Specification for Inspection of Steel Castings of Hydraulic Machines
CMAA Specification 74 Single Girder Cranes
COES PR20 Ingreso, Modificación y Retiro de Instalaciones en el Sein
COES PR21 Reserva Rotante para Regulación Primaria de Frecuencia
COES PR40 Procedimiento para la Aplicación del Numeral 3.5 de la NTCSE
DIN 3990 Calculation of Load Capacity of Cylindrical Gears
DIN 19704 Hydraulic Steel Structures
FS SS-W-410 Wire Rope and Strand – Wire Rope
IEC 61131-3 Programmable Logic Controllers – Part 3: Programming Languages
IEC 60034 Rotating Electrical Machines - All Relevant Parts
IEC 60038 IEC Standard Voltages
Field Acceptance Tests to Determine the Hydraulic Performance of Hydraulic
IEC 60041
Turbines, Storage Pumps and Pump-Turbines
IEC 60071 Insulation Co-ordination - All Parts
IEC 60072 Dimensions and Output Series for Rotating Electrical Machines - All Parts
IEC 60076 Power Transformers
IEC 60085 Electrical Insulation - Thermal Evaluation and Sesignation
IEC 60099 Surge Arresters - All Parts
IEC 60193 Hydraulic Turbines, Storage Pumps and Pump-Turbines - Model Acceptance Tests
IEC 60255 Measuring Relays and Protection Equipment - All Relevant Parts
IEC 60228 Conductors of Insulated Cables
Hydraulic Machines, Radial and Axial - Performance Conversion Method from
IEC 62097
Model to Prototype
IEC 60308 Hydraulic Turbines - Testing of Control Systems
Basic and Safety Principles for Man-Machine Interface, Marking and Identification -
IEC 60446
Identification of Conductors by Colours or Alphanumeric
IEC 60364 Low-voltage Electrical Installations
IEC 60534-4 Industrial Process Control Valve - Part 4: Inspection and Routine Testing
IEC 60545 Guide for Commissioning, Operation and Maintenance of Hydraulic Turbines
Hydraulic Turbines, Storage Pumps and Pump-Turbines - Cavitation Pitting
IEC 60609-1 Evaluation - Part 1: Evaluation in Reaction Turbines, Storage Pumps and Pump-
Turbines
Power Cables with Extruded Insulation and their Accessories for Rated Voltages
IEC 60502
from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV)
Industrial-Process Measurement and Control Equipment - Operating Conditions -
IEC 60654
All Relevant Parts
IEC 60870 Telecontrol Equipment and Systems - All Relevant Systems
IEC 60896-22 Technical Requirements for Stationary VRLA Batteries
Guide for Field Measurement of Vibrations and Pulsations in Hydraulic Machines
IEC 60994
(Turbines, Storage Pumps and Pump-Turbines)
Communication Networks and Systems for Power Utility Automation - Part 3:
IEC 61850-3
General Requirements
IEC 61000 Electromagnetic Compatibility
Standard Title
IEC 61116 Electromechanical Equipment Guide for Small Hydroelectric Installations
IEC 61131-2 Programmable Controllers
IEC 61131-3 Programming Languages
IEC 61362 Guide to Specification of Hydraulic Turbine Governing systems
IEC 61439 Low-voltage Switchgear and Controlgear Assemblies
IEC 61850 Power Utility Automation
IEC 61869 Instrument Transformers
IEC 61936 Power Installations Exceeding 1 kV a.c
IEC 62006 Hydraulic Machines - Acceptance Tests of Small Hydroelectric Installations
IEC 62040 Uninterruptible Power Systems (UPS)
IEC 62270 Guide for Computer-Based Control for Hydroelectric Power Plant Automation
IEC 62271 High Voltage Switchgear and Controlgear
IEC 60534-4 Industrial-Process Control Valves – Part 4: Inspection and Routine Testing
IEC/IEEE62271-37-013 Alternating Current Generator Circuit Breakers
IEEE 80 IEEE Guide for Safety in AC Substation Grounding
IEEE 485 Recommended Practice for Sizing Lead-Acid Batteries for Stationary Applications
IEEE 802.1 AB Station and Media Access Control Connectivity Discovery
IEEE 802.1 D Media Access Control Bridges
IEEE 802.1 Q Virtual Bridged Local Area Networks
IEEE 802.3 Ethernet
IEEE 807 Recommended Practice for Unique Identification in Hydroelectric Facilities
Guide for the Application of Turbine Governing Systems for Hydroelectric
IEEE 1207
Generating Units
Standard Environment and Testing Requirements for Communication Networking
IEEE 1613
Devices in Electric Power Substations
ISO 898 Mechanical Properties of Fasteners Made of Carbon Steel and Alloy Steel
Mechanical Vibration - Balance Quality Requirements for Rotors in a Constant
ISO 1940
(Rigid) State
ISO 3046 Reciprocating Internal Combustion Engines
ISO 4301-5 Cranes; Classification; Part 5: Overhead Travelling and Portal Bridge Crane
Mechanical Vibration of Non-Reciprocating Machines – Measurements on Rotating
ISO 7919
Shafts and Evaluation Criteria. Parts 1 and 5
Reciprocating Internal Combustion Engine Driven Alternating Current Generating
ISO 8528
Sets
Cranes; Design Principles for Loads and Load Combinations; Part 5: Overhead
ISO 8686-5
Travelling and Portal Bridge Cranes
ISO 9000 Quality Management Systems - Requirements
Mechanical Vibration - Evaluation of Machine Vibration by Measurements on Non-
ISO 10816-5 Rotating Parts - Part 5: Machine Sets in Hydraulic Power Generating and Pumping
Plants
Hydraulic Fluid Power - Systems Standard For Stationary Industrial Machinery -
NFPA T2.24.1 Supplement to ISO 4413:1998 - Hydraulic Fluid Power - General Rules Relating to
Systems
OSHA Compliance Recommendations for Crane Applications with Motorized Hoist
SAE J514 Metallic Tube Connections for Fluid Power and General Use
UNI EN 10083 Steels for Quenching and Tempering
Colores de Identificación de Tuberías para Transporte de Fluidos en Estado
NTP 399.012
Gaseoso o Líquido en Instalaciones Terrestres y en Naves
Any other ASME/ANSI, IEC, IEEE or ISO Standard may be used for areas of the Plant not
covered by the above list. Other internationally recognised Standards may be accepted by
the Employer provided such standards are not less exacting than corresponding IEC, ASME,
ANSI, IEEE or ISO Standard. In such an instance, a copy of the relevant Standard shall be
forwarded to the Employer.
The Contractor must also comply with any relevant Peru Standards or Regulations. Where
any national Regulations differ from the above requirements, the Regulations shall take
precedence.
1.6.1. Powerhouse
Two Turbine Generator sets each complete with the following:
Horizontal Francis Turbine Unit rated at 10.58 MW output, complete with Francis runner,
turbine shaft, spiral casing, stay ring, head cover, bottom cover, guide vanes, hydraulic
servomotors, draft tube, dewatering, instrumentation and accessories.
Turbine Governor Set, complete with all necessary electronic governor head actuators,
hydraulic oil system, mechanical hydraulic overspeed device, speed monitoring system,
nitrogen cushioned pressurisation plant, instrumentation and accessories.
Counterweight operated butterfly inlet valve with bypass valve, hydraulic servomotors,
instrumentation and accessories.
Pipework between the inlet valve and the turbine.
Horizontal synchronous generator rated at 12.2 MVA 0.85PF, complete with brushless
excitation system and AVR, guide/thrust bearings, bearing lubrication system, cooling
system, compressed air braking system, instrumentation and accessories.
Turbine Generator AC/DC Systems.
Turbine Generator Control and Instrumentation System.
Control Systems for the generator units and station service plant including:
Two generating Unit PLC systems for monitoring and controlling the turbine generators.
One station common services PLC system for monitoring and controlling the
transformers, 6.6 kV switchgear, 138 kV switchgear, powerstation balance of plant, and
for interfacing with the intake and forebay PLC/RIO.
Communication with the 8 de Agosto switchyard PLC (fibre optic communications
provided by others)
Communication with two intake PLCs and one forebay RIO (PLCs, RIO and fibre optic
communications provided by others).
One powerhouse SCADA system complete with two operator interface computers and
ancillary equipment.
All software supply and configuration for the operation of the entire power scheme.
Factory acceptance testing of the software.
Instrumentation.
Protection Systems
Two generating unit protection systems.
One redundant main transformer protection system.
One redundant transmission line protection system with digital fault recorders.
Two auxiliary transformer protection systems.
Other
All necessary piping and cabling.
Equipment grounding connections.
One set of spare parts for all Plant.
One set of special tools required for erection and maintenance of the turbine generator
units.
One set of lifting beams and slings required for the installation of the turbine generator
units and their auxiliaries.
One set of holding down bolts for the entire installation and associated foundation
steelwork such as foundation plates, packers and embedments.
Protection Systems
One redundant transmission line protection system with digital fault recorder.
One bus zone protection system.
Two relocated transmission line protection and digital fault recorder systems
Civil Works
Switchyard site preparation.
Fencing.
Equipment foundations.
Grounding system.
Drainage system.
Other
All necessary piping and cabling.
Equipment grounding connections.
One set of Special Tools required for erection and maintenance of the 138 kV circuit
breakers.
One set of holding down bolts for the entire installation and associated foundation
steelwork such as foundation plates, packers and embedments.
1.7.1. Powerhouse
Civil
Under side of baseplates for major Plant - All holding down bolts and other embedded
materials for all M&E Plant shall be supplied under this Contract.
Grounding - All above ground grounding systems external to concrete foundations and
structures shall be supplied under this contract. Connections to the below ground and
embedded grounding shall be by this Contract.
Control panels and other minor Plant holding down - All anchors shall be
mechanical/chemical drilled type and shall be supplied under this Contract.
Suspended and wall mounted Plant - All supporting anchors shall be
mechanical/chemical drilled type and shall be supplied under this Contract.
Mechanical
Welded connection of turbine inlet valve upstream pipe extension to penstock stub.
Welding, heat treatment and testing by penstock Contractor.
Turbine draft tube discharge.
Electrical
138 kV Transmission Line. Transmission line termination gantry structure by this
Contract. Dropper from transmission line conductor to voltage transformer by this
Contract.
400 V Station Services. Station 400 V services by this Contract. A three phase circuit
breaker rated nominally at 100 A is to be provided in the Station Services switchboard
for the Employer’s use.
This Contract includes for the supply of all unit and services control cubicles. Terminals shall
be provided in these cubicles for the following connections by others:
Remote Control. PLC system by this Contract. Communications from the Station control
to Employer’s main control center is by the Employer. Interface to be RJ45 Ethernet
socket on firewall device supplied by this Contract.
All control and instrumentation cabling to field devices to be provided by this Contract
including those not supplied under this Contract.
All control system software, including data from field devices not supplied under this
Contract.
Fibre optic cabling between the two intakes, forebay and powerhouse, including
termination by the Employer. Contractor to provide fibre optic cabling and patch cords
between the Employer’s termination and the Plant.
Electrical
138 kV Tingo María and Ayanunga transmission line. Transmission line termination
structure gantry by this contract.
Towers required to connection between existing 8 de Agosto bay and new 8 de Agosto
switchyard (including conductor, accessories and civil works) by this Contract.
Replacement or relocation of terminal tower of existing transmission line adjacent to
existing 8 de Agosto switchyard to a new location adjacent to the new 8 de Agosto
switchyard.
138 kV 8 de Agosto switchyard bay. 138 kV bus disconnectors by this Contract.
Droppers to existing bay equipment by this Contract.
400 V Station Services. New Plant 400 V services by this Contract. Supply to be taken
from existing 400 V switchboard at 8 de Agosto switchyard site.
125 V DC Services. New Plant 125 V DC services by this Contract. Two 125 V 16A
(nom) feeders to be provided under this Contract to supply energy to the existing 8 de
Agosto switchyard bay equipment.
Controls and Protection
PLC system by this Contract. Contractor to make provision in the PLC for the later
addition of at least 32 digital inputs, 16 digital outputs and 8 analogue input signals by
the Employer.
138 kV 8 de Agosto Transmission Line Protection and digital fault recorder. Existing to
be relocated by the Contractor. The Contractor is responsible to ensure his activities do
not affect the existing equipment except as prior approved by the Employer.
Fibre optic cabling between the powerhouse and New 8 de Agosto switchyard including
termination is by the Employer. Contractor to provide fibre optic cabling and patch cords
between the Employer’s termination and the Plant.
1.7.3. Ayanunga Intake, Pan de Azucar Intake and Forebay (Three Sites)
Civil
Nil.
Mechanical
Nil.
Electrical
Nil.
1.8. DRAWINGS
The proposed Plant layouts are shown on the following drawings:
General Arrangements
CHA-GRL-PLN-111 Arreglo General Del Proyecto Planta.
CHA-GRL-PLN-200 Bocatoma Ayanunga Arreglo General Planta.
CHA-GRL-PLN-210 Bocatoma Pan de Azúcar Arreglo General Planta.
CHA-GRL-PLN-232 Cámara de Carga Hoya 1 de 2.
CHA-GRL-PLN-234 Cámara de Carga Estructura de Toma Hoya 1 de 2.
CHA-GRL-PLN-246 Tubería Forzada Planta, Perfil y Secciones.
Powerhouse Layouts
CHA-GRL-PLN-250 Surface Powerhouse Horizontal Francis Turbine 20MW - 720 rpm
Configuration Isometric View General Arrangement.
CHA-GRL-PLN-251 Surface Powerhouse Horizontal Francis Turbine 20MW - 720 rpm
Configuration Isometric View Erection Bay Level.
CHA-GRL-PLN-252 Surface Powerhouse Horizontal Francis Turbine 20MW - 720 rpm
Configuration Isometric View Turbine Level.
CHA-GRL-PLN-253 Surface Powerhouse Horizontal Francis Turbine 20MW - 720 rpm
Configuration Isometric View Sheet 1 of 3.