Академический Документы
Профессиональный Документы
Культура Документы
2.0 DEFINITIONS............................................................................................................. 3
8.0 FILTER/COALESCER………………………………………………………………………7
Document No.
Rev
MECHANICAL DESIGN BASIS 11-0290D-02-09-04-001 0
SHEET 2 of 13
1.0 PROJECT DESCRIPTION
M/s Gail Gas Ltd intends to lay 10”/8” City Gas Distribution spurline (from Naya Nohra to Kota)by
taking Tap-off at Naya Nohra, from 16” Gadepan-Naya Nohra Pipeline network of Gail (India) Ltd
to supply the Natural Gas for Kota City Gas Project. The Proposed pipeline as envisaged is of
~40 km length.
The City Gate Station has been proposed near Samcor Glass Factory. Natural Gas from the CGS
is fed into single pipeline supplying gas to the city network. The pressure at the downstream of
CGS shall be 19 bar. A Primary network of steel pipeline shall connect the various CNG stations
and District Regulating Stations (DRS) for further gas supply distribution to automotive and and
PNG consumers. SV Stations are installed at approx every 2.5 km distance. As far as possible,
SV Stations are planned to be installed near CNG stations for prompt maintenance response.
2.0 DEFINITIONS
3.1 The work tendered in this bid package consists of fabrication, installation, testing and
commissioning of the City Gas Distribution Spurline inclusive of City Gate Station, CP works, SV
station, District Regulating Stations & above ground piping including all associated mechanical,
civil, structural, Telecommunication works.
3.2 Contractor will organize equipment and manpower accordingly to meet this requirement as per
instruction of Engineer-in-charge.
4.1 The scope of work shall generally be, but not limited to the following:-
“The Contractor’s scope of work shall consist of preliminary activities like check survey, supply as
required, fabrication, installation, hook-up, testing and pre-commissioning of steel pipeline and
assistance during commissioning along with all associated mechanical, civil, structural, HDPE
conduit laying works and installation of OFC cable works. All such works, which are not indicated
here below but are otherwise required to complete the work in all respects shall form part of
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 3 of 13
Contractor’s scope of work. Further, the scope indicated below shall be read in conjunction with
the schedule of rates, drawings, standards, specifications, and other requirements forming part of
the contract document.”
Design, engineering, fabrication, testing etc. shall be as per the list of codes and standards.
ASME Section - II, Div-1: Boilers and Pressure Vessel Code- Materials
ASME V : Boiler and Pressure Vessel Code - Non Destructive
Testing.
ASME VIII : Boiler and Pressure Vessel Code - Div 1- Pressure
Vessels.
ASME IX : Boiler and Pressure Vessel Code - Welding & Brazing
qualifications
ASME B 31.1 : Power Piping.
ASME B 31.3 : Process Piping.
ASME B 31.8 : Gas Transmission and Distribution Pipeline System.
ASME B 16.5 : Steel Pipe Flanges and Flanged Fittings.
ASME B 16.9 : Factory-made Wrought Steel Butt Welding Fittings.
ASME B 16.11 : Forges Steel Fittings, Socket Welding and Threaded.
ASME B 16.25 : Butt Welded Ends.
ASME B 16.47 : Large Diameter Steel Flanges: NPS 26 through NPS 60.
ASTM A 105 : Forging, Carbon Steel for Piping Components.
ASTM A 181 : Forging, Carbon Steel for General-Purpose Piping.
ASTM A 234 : Piping Fitting of Wrought Carbon Steel and Alloy Steel
for moderated and Elevated Temperatures.
ASTM A 370 : Mechanical Testing of Steel products .
ASTM A 216 : Carbon Steel Castings suitable for Fusion Welding for
High temperature Service.
ASTM A 20 : General requirements for steel plate for pressure
vessels.
ASTM A 516 : Carbon steel pressure vessel plates for moderate and
low temperature service.
ASTM A 106 : Carbon steel seamless pipe for high temperature
service.
ASTM A 193 : Alloy steel and stainless steel bolting materials for high
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 4 of 13
temperature.
ASTM A 194 : Carbon and alloy steel nuts for bolts for high pressure or
temperature.
MSS-SP-6 : Standard Finishes for Contact Faces of Pipe Flanges
and Connecting – End Flanges of Valves and Fittings.
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 5 of 13
6.1.4 Ease of maintenance and convenience of operation
6.1.5 Design for location in outdoor area
6.1.6 Packaged unit shall be furnished as skid mounted fully assembled equipment
6.1.7 Adequate provision for future extension and modification
6.1.8 Fail-safe feature
6.1.9 Suitability for applicable environment factors
6.1.10 Optimized spares inventory
The equipment in general, shall conform to requirements of data sheets, Functional specification
and the latest revision of relevant codes & Standards and shall be suitable for installation and
satisfactory operation in the applicable service conditions. Pressure piping within package shall
be designed and fabricated to ASME B 31.3.
Vendor shall be responsible for thermal and mechanical design and for Obtaining ASME code
stamping. Latest computer programs will be used.
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 6 of 13
7.13 All nozzles shall be welded and flanged.
7.14 Minimum manholes size shall be DN 500 unless restricted by vessel Diameter. Covers shall be
equipped with swinging type davits. Davit Shall be provided for all pressure vessel man ways.
7.15 Vessel shall have 750 MM wide platform at all manholes and at any other identified maintenance
Location.
7.16 To ensure proper fit, level indication and instrumentation directly attached to the vessel shall be
included in the scope of vessel vendor.
7.17 Piping within equipment package should be as per given relevant specs.
7.18 All columns and vessels shall be fabricated at shop and shall be transported in single piece to
site.
7.19 For shop fabricated items, hydro-testing shall be carried out at shop also.
Scope in respect of PRESSURE VESSELS, includes but not limited to the following:
7.20 Design and detailed engineering of all pressure vessels based on data sheets provided as per
“ASME code section VIII, Division – I, Pressure Vessels” ( latest edition ), submission of design
calculations and detailed drawings including foundation drawings for approval by Owner, if any.
7.21 Fabrication of vessels at shop / site including all materials supply as per fabrication drawing duly
approved by Owner / consultant, if any.
7.22 NDT inspection by third party as per relevant standards mentioned in detailed scope
7.23 Transportation of vessels to site if fabricated at shop.
7.24 Construction of civil foundation as per approved drawings with all Materials supplied at site.
7.25 Erection of vessels in respective foundation and hydro-testing at the rated pressure as per
recommendation of relevant code and approved test procedure by owner.
7.26 Hooking-up of vessel to integrate with installation as per P&ID and Approved drawings.
7.27 Trial run and pre-commissioning test with water/ fluid.
7.28 Final commissioning of the system.
7.29 Insulation / Painting of Pressure Vessels
a) Cleaning and insulation / painting as per the requirement as per detail specification for insulation
/ painting.
b) Any other work which may necessary to complete the pressure vessels with respect to integrate
with the Gas GGS in all respects.
8.0 FILTER/COALESCER
Filters / Coalescer shall be complete and operable units comprising of supports, nozzles, flanged
inlet/outlet connections, drain connection, flange cover with pipe davit, filter element, relief valve,
differential pressure indicator and other accessories as required. The filter shall remove solid
particles / moisture content that may be present in the diesel system. Refer process design
criteria and P & ID for capacity and instrumentation requirements. The vessel shall be designed,
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 7 of 13
fabricated and tested in accordance with ASME Section VIII Div-1. As a minimum requirement,
the vessel shall be designed for spot radiography. Dish ends to shell circumferential joints shall,
as a minimum requirement, be fully radio graphed.
Filter shall be provided with Quick opening end end closure with davit assembly for easy
removal / Replacement of filter element. Filter shall be cartridge type. The selection criteria along
with the specifications and other details for the filter elements shall be fully described in the
Tender.
9.0 MECHANICAL DESIGN CRITERIA
9.1 The design criteria give the minimum requirements for mechanical design to be carried out. This
shall be read in conjunction with the specifications attached elsewhere in the bid.
9.2 The equipment proposed to meet the specification shall be designed and manufactured to
achieve the highest possible reliability for design life of 40 years.
9.3.1 All design calculations for pressure requirements, vibrations, considering seismic factors etc.
shall be made in accordance with code requirements and submitted to the OWNER for Approval.
9.4 In the event of conflict, the following order of priority shall govern:
9.4.1 Mechanical Design Basis
9.4.2 P&ID’s
9.4.3 Data Sheet
9.4.4 Drawings
9.4.5 Specifications
9.4.6 Codes and Standards
9.5 LAUNCHERS / RECEIVERS AND HINGED CLOSURE
9.5.1 The Launcher / Receivers shall be supplied along with hinged closure, pig detector and
accessories like trolley, jib crane and other pig handling devices. Launcher / Receiver shall be by
directional type.
9.5.2 The material specification shall be governed by the design conditions of
pressure, temperature, corrosion allowance and compatibility with contained media.
9.5.3 Contractor to calculate thickness / schedule against each size of piping class. Pipe internal
diameter from launcher / receivers shall be critically checked for the safe passage of pig. There
should not be any negative tolerance in internal diameter of Launcher/Receiver barrel.
9.5.4 Pig launchers and pig receivers are important for any pigging systems to ensure safe and efficient
working and handling of pigs. Both Launchers and receivers are required with suitable bandlock
type hinged closure and shall be provided for easy and safe access during pig loading and
unloading. Such closure shall be as per data sheets. Barrel shall be designed to suit the
intelligent pigging. The barrel and hinged closure shall be designed as per latest edition of ASME
Sec VIII Div 1. Launcher / Receiver dimensions shall be suitable for intelligent pigging.
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 8 of 13
9.5.5 The design pressure and temperature for launching / receivers and hinged closure is 49 barg for
and 0 to 60 deg. C respectively.
9.5.6 Pipes, fittings, flanges of size 3/8”, 1 ¼”, 2 ½”, 3 ½”, 4 ½”, 5”, 7” and 9” shall not be used.
However, where equipment is regular supplied by the manufacturer with piping connections of the
above odd sizes, connection shall be made to approve nominal sizes using reducers.
9.5.6 Spectacle blind at the flanged end of Launcher / Receiver to be provided with other spectacle on
kicker line and by-pass line.
9.5.8 The venting arrangement in station should have ball and globe valve combination.
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 9 of 13
All the systems/ equipment required to meet the design conditions as stated shall be
Performance and Function tested preferably at the manufacturer’s works in accordance with
respective codes and functional specifications.The Contractor shall submit for review and
approval by the Company a comprehensive Inspection and Test Plan (ITP) covering all relevant
components, completed equipment and systems. No work by the Contractor or its subcontractors
may commence without prior approval by the owner/consultant of the ITP’s. A detailed test
procedure of shop tests shall be submitted at least two (2) months in advance of any testing and
shall be approved by the Company. A dimensional check of the Package assembly and
components shall be performed for compliance with approved drawings. String tests and site
performance test shall also be carried out as per the requirement.
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 10 of 13
15.1 Battery limits for station shall be as per the drawings attached in the bid.
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 11 of 13
17.8 Procurement of all items shall be done from vendor list approved by OWNER. Necessary
documents such as purchase specifications, test certificates shall be furnished for review /
approval.
17.9 Contractor to plan and carry out suitable isolation, de-pressurization, purging, cleaning, Hydro
testing, Flushing, drying, painting and removal of temporary supports, scaffolding etc. Contractor
to execute the job safely without any operational hazard.
17.10 Any other work not specifically mentioned above but required for completeness of the work as per
specifications / drawings / codes and standards and instructions of engineer- in – charge at site.
17.11 It is the responsibility of the contractor to ascertain space and exact routing for meeting the
requirements of finally approved P&ID’s and design criteria.
17.12 The contractor shall conduct necessary site surveys, prepare additional drawings / data required
which are not parts of the enclosed bid package to ensure proper completion of work. The
contractor shall gather all information from existing facilities in case as-built drawings are not
available.
17.13 Contractor’s scope of work shall include modification / integration as per approved P&ID and other
requirements listed elsewhere in the bid package. For carrying out his scope of work, contractor
may be required to open / dismantle / realign / modify any facilities or instrument or piping or
equipment of the existing facilities and the cost of the same shall be included in the lump sum
price. IT will be contractor’s responsibility to make good, test and pre-commission all such facility
during and after completion of work with minimum period of shutdown. Details of total shutdown if
required for each modification / integration shall be indicated in the bid against each activity.
17.14 Contractor shall perform the necessary modification / integration work on the basis of actual
physical conditions / data / parameters foundduring the site survey during pre-engineering stage.
Contractor shall not be entitle to any cost and time compensation on this account.
17.15 Contractor shall ensure, before submission of his bid, that the space allocated for the various
facilities for the modification is adequate and satisfactory. In case any additional space / facility
such as provision of any walkway / operating platform for maintenance and operation of
equipment is required, the contractor shall indicated the same in his bid and the cost shall be
included in the lump sum price.
17.16 If the bid document / P&ID’s specifically required any existing facility to be altered or reused, the
same shall be done by the contractor after verifying / checking the condition of existing facility. IF
whole or any part of it is found to be defective, contractor, without any extra cost, shall replace
the same.
17.17 In accomplishing the above task the contractor shall take the total responsibility of executing the
project in accordance with this bid document including the supply of all materials and
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 12 of 13
consumables, construction equipment, labour etc. and will adhere to bid document instructions
and requirements in respect of all matter relating to the project.
Document No.
MECHANICAL DESIGN Rev
CRITERIA 11-0290A-02-09-04-001 0
SHEET 13 of 13