Reference: IQN-17-11-699 Rev 00

IZHAR STEEL (PVT.) LTD.


Dated: December 07, 2017 Head Office:
Izhar House, 35-Tipu Block, New Garden Town, Lahore, Pakistan
Tel: (042) 111 - 323 - 111, 35888000 ~ 3 Fax: (92-42) 35888111
To, http://www.izharsteel.com, Email:info@izharsteel.com
Mr. Talha Munir,
M/s Chenab Engineering Works,
Faisalabad.

SUBJECT: SUPPLY & ERECTION OF PRE − ENGINEERED STEEL BUILDING


Multipurpose Hall with 3T Crane at Faisalabad.

Respected Sir,
Thank you for considering IZHAR STEEL (Pvt) Ltd for this valuable inquiry. On the basis of your
requirement, we are submitting you the Technical & Commercial Proposal. The detailed
parameter for this particular inquiry has been mentioned in Section-I of this quotation.
Highlighted Points;
 0.5mm Thick Bare Zincalume sheets without Insulation are applicable at roof.
 At all wall, 0.5mm Thick Pre-Painted Zincalume sheets without insulation is applicable
above open area & existing civil structure from FFL. (Open area detail is given in the
reference section of this proposal).
 The heights of the proposed building are being varied (at grid 3 & 6); transition frame
(false rafter) is considered. Detail is showing in the proposal drawings.
 Structure frame type is clear span without any intermediate column in the width of the
building.
 At NSW & FSW existing civil structure whose height is 11.278m & 7.926m respectively.
Length of existing building @ FSW is full length along the proposed building & NSW is
18.206m as per provided drawings from REW. The proposed building independent of
any existing building.
 For cranes, ISPL will provide only crane runway girders, Brackets and crane stoppers.
Further, supply & installation of crane along with rail will be in crane supplier’s scope of
work – not in our scope of work.
 This proposal is based on the assumption of crane loads. However, the proposal will be
revised if crane data will revise.
 1 no of 03T cranes will operate in complete width of the building throughout the length
of building.
 The assumed date for 03T crane is as follows, Trolley/hoist weight is 0.58T, Wheel load is
2.04T & wheel base 2.0m and crane hook height is 12.640m from FFL.
 1no of cage ladder is considered in this proposal.
 In building accessories gravity ridge ventilators are considered in this proposal.
 ISPL Quotation and Proposal Drawings (Latest Revision) will supersede all bid
documents, discussions & previous revisions (if any). In case, this Quotation deviates any
Client’s requirements, we shall submit a Revised Quotation accordingly.
 Any change from the Contractual Parameters, if marked by the Client at the stage of
Approval Drawing phase, shall be charged according to the latest rate at that time along
with the revised timelines. Technical and Commercial approval from the Client shall be
required to incorporate that change in the Project.
 Any type of Collateral Load is not been considered in the design of PEB Roof. If there is
such any kind of load then quotation would be revised accordingly.

IQN-17-11-699 Rev 00 December 07, 2017 Page 1 of 12


 For any particular standard requirements regarding Health & Safety, Dispatch & Packing,
Crane, Labors, Scaffolding, Safety Standard Kits etc., our quotation would be revised
with Price & Time.
 All above mentioned points are integral part of “Section 10” of this quotation.
 Any type of civil work & its stability is not included in the scope of ISPL.
 This quotation is prepared on the assumption that the client has both NTN & STRN. In
case, otherwise, the quotation will be revised accordingly.
 Any type of civil work & stability of civil is not included in ISPL scope of work

Important Notes;

 Dimension & Location of the subject Job are being referred by Client/Consultant.
 Confusion regarding inclusions or exclusions of Izhar Steel Scope must be discussed with
our Staff. Any perception about this matter would not be considered valid.

Kindly review the quotation and let us know with your comments.

Regards, Contact Us;

For IZHAR STEEL (Pvt.) Ltd. Haroon.ali@izharsteel.com Cell:+92301-8439997

Adnan Usmani
General Manager
Business Development
Cell: +92301-8497981
E-mail: adnan.usmani@izhar.com

IQN-17-11-699 Rev 00 December 07, 2017 Page 2 of 12


TABLE OF CONTENTS

Sec. No. Description Page No.

1. Building Description 04
2. Design Loads & Applicable Codes 07
3. Material Specification 08
4. Supplied Items 09
5. Exclusions 09
6. Supply Delivery Period 09
7. Proposal Validity 09
8. Payment Terms 09
9. Health & Safety Standards 09
10. Other Terms & Conditions 10/11
11. Supply Prices 12
12. Erection Price 12

IQN-17-11-699 Rev 00 December 07, 2017 Page 3 of 12


Section 1: BUILDING DESCRIPTION

Quantity of Identical Buildings: 00 USAGE: Multipurpose Hall U.O.M: Meter (m) AREA (c/c): 573m2
(o/o will be greater)

1.1 Building Parameters

1 Frame Type Clear Span

2 Width 12.558 center to center of steel columns

3 Width Module Main Frame: - 01 @ 12.558

Left End Wall: -


End Wall Condition & Rigid Frame 01 @ 4.129 + 01 @ 4.300 + 01 @
4
Spacing With Posts 4.129
Right End Wall:-

Side Walls: -
5 Walls Grits Type By - Pass
End Wall: -

6 Length 45.642 center to center of steel columns

01 @ 6.488 + 02 @ 6.619 + 01 @ 6.210 + 01 @


7 Bay Spacing
5.046 + 01 @ 5.381 + 01 @ 4.609 + 01 @ 4.670
At Grid 1 to 3 & 6 to 9 =14.00m from FFL.
8 Clear Height
At Grid 3 to 6 = 17.00m from FFL.
9 F.F.L 0.000

10 Roof Slope 1 : 10
At NSW: N/A, except existing Building height
11.278m with 18.206m length.
Height of Block Masonry At FSW: Existing Building height 7.925m with
11
(Not By IZHAR STEEL) 45.642m length.
At LEW & REW: N/A, open area upto 3.353m
from FFL.
Near Side Wall:- X – Diagonal 1st, 3rd, 5th & 9th Bays are cross
Bracing Braced.
Far Side Wall:-
12 Bracing Type
Left End Wall:-
N/A
Right End Wall:-

13 Storm Water Drainage System Eave Gutter and Down Spouts

Gable type (both Ways Sloping For Water


14 Building Shape
Drainage)

IQN-17-11-699 Rev 00 December 07, 2017 Page 4 of 12


1.2 Roof & Wall Conditions

1 At Roof Single Skin sheet without Insulation is applicable.

2 Left End Wall “Grid 9”

Single skin sheet without insulation is applicable above 3.353m


3 Right End Wall “Grid 1” from F.F.L, below will remain open.
At NSW & FSW, sheeting will also be applicable above existing civil
4 Near Side Wall “Grid D” structure.
At grid 3 & 6, sheeting will also applicable above transition frame.

5 Far Side Wall “Grid A”

1.3 External Roof & Wall Panels

Sr. No. Location Thickness Description Color Profile

1 At Roof XRW Bare Zincalume Bare Galvanized


0.5mm S-Type
XRW Pre – Painted To be selected from ISPL
2 At Walls
Zincalume Available stock

1.4 Building Accessories

Quantity
Sr. No. Description Location Dimension (mm)
(Nos.)

1 Gravity Ridge Ventilator 08 “as per proposal drawings” 300 x 3,000

1.5 Surface Preparation & Paint Specification

All primary Steel members will be cleaned and painted at our factory with two
coats of Red Oxide Primer which attains the Paint Thickness of 35 ~ 40
Primary & Secondary Steel Microns.
(Included in this Proposal)
IZHAR STEEL includes in its scope two (02) coats of Enamel Paint which
attains the Total Paint Thickness (Including primer) of 70 ~ 80 Microns.

Note: Final color shall be chosen by client from available stock of ISPL.

IQN-17-11-699 Rev 00 December 07, 2017 Page 5 of 12


1.6 CRANE SYSTEM

Sr No. Critical Required Information for Each Crane System Unit Crane System No

1 CMAA Classification ( A, B, C, D, E or F ) D

2 Loading Category ( 1, 2, 3 or 4 ) 2
3 Crane Capacity MT 01 x 03T

4 Location ( Between Grids ) From Grid A to D

5 Crane Type ( Top running, Under hung or Jib, Monorail ) TR

6 Crane Manufacturer MORRIS

7 Crane Run Length m From Grid 9 to 6

8 Crane Hook Height from FFL m 12.640


Wheel Base ( Dist. Between End Track Wheels Along
9 m 2.0
Runway Beam )
10 Operation Type ( Pendant or Cab ) Pendant

11 Crane Wheel Load ( W/O Impact ) T 2.04

12 Crane Trolley/Hoist Weight ( W/O Impact ) T 0.58

13 No. of cranes operating on single crane runway beam 01


Crane Supporting Columns (Independent / on Proposed
14 On PEB
PEB)
15 Crane Runway Beam BY ISPL

16 Crane Brackets BY ISPL

17 Clear distance between two adjacent operating cranes m N/A

18 Crane Stoppers BY ISPL

19 Crane Rail & Crane System Not by ISPL

IQN-17-11-699 Rev 00 December 07, 2017 Page 6 of 12


SECTION 2: DESIGN LOADS & APPLICABLE CODES
Design Loads

1 Design Dead Load (kN/m²) Self-Weight

2 Roof Live Load (kN/m²) 0.57

3 Live Load on Frame (kN/m²) 0.57

4 Co-lateral Load (kN/m²) 0.00

5 Wind Speed (km/h) 130, Exp B

6 Earthquake Zone Zone 2B

7 Rain Fall Intensity (cm/hr) 15

8 Load of Crane Yes (as per section-1)


9 Provision For Future Expansion Nil
10 Design Software Metal Building System (MBS)

Design Codes for Primary & Secondary Structural Members:

Loads on buildings are applied in accordance with:


‘Metal Building System Manual (MBSM)’; 1996
Metal Building Manufacturers Association, Inc. (MBMA) 2006
1300 Summer Ave., Cleveland, Ohio 44115, USA

‘Uniform Building Code’ (UBC); 1997 (Seismic Loading)

Hot rolled sections and built up sections are designed in accordance with:
‘Manual of Steel Construction’ – Allowable Stress Design; 1989
American Institute of Steel Construction, Inc. (AISC) 2005
1 East Wacker Drive, Suite 3100, Chicago, Illinois 60601-2001, USA
Cold–formed members are designed in accordance with:
‘Cold Formed Steel Design Manual’; 2002
American Iron and Steel Institute (AISI) 2007
1000 16th Street, NW, Washington, DC 20036, USA
Welding is applied in accordance with:
Structural Welding Code Steel Manual’; 2006
American Welding Society (AWS)
550 NW LeJeune Road, Miami, FL 33126, USA
Design Code: Metal Building System (MBS-2006)
Note::
The Design Loads/Codes mentioned in Section-2 of this Proposal have been considered as per the
prevailing norms. The Client may require any amendments which would be incorporated in Revised
Proposal.

IQN-17-11-699 Rev 00 December 07, 2017 Page 7 of 12


SECTION 3: MATERIAL SPECIFICATION

No. Components Specifications Strength


Built–up for Main Frames
1 ASTM A572M Grade 345 Type 1 (Grade – 50)
(Rafters & Columns)
Cold Formed for
2
Purlins/Girts ASTM A653M SS Grade 340 Class 1 Coating, Z275
Fy = 34.5 kN/cm2
(Grade – 50)
3 Mezzanine Deck Panels

Exterior/Interior Roof & ASTM A792M Grade 345B Coating AZ150


4
Wall Panels (Grade – 50)
Rods ASTM A36 Fy = 27.7kN/cm2
5 X–Bracing HR Angles ASTM – A – 36 Fu = 24.5 kN/cm2
Cables ASTM A475 - Extra High Strength Class A
6 Sag Rods Grade 4.6 Electro Galvanized, Threaded With 4 Nuts Fy = 24.5 kN/cm2

7 Anchor Bolts Grade 4.6 Hot Dip Galvanized, J-shape With 2 Nuts Fu = 24.5 kN/cm2

Primary & Secondary


8 ASTM A325 M Type-1 Threaded Hot Dip Galvanized
Connection Bolts
9 Self Drilling Fasteners High Grade Carbon Steel With Washers and EPDM Seal

10 Pop Rivets Small Headed Pin With An Expandable Shank For Fixing Gutters

11 Bead Mastic

12 Roof & Walls Insulation

13 Sliding Doors Accessories As Per Approved Standards


(Literature could be provided on demand).
14 Motorized Roll-Up Door

15 Skylights

16 Power Ventilators

17 Ridge Ventilators Factory Fabricated, Site Assembled, Mounted As Single Unit


Note:
 Material with above or Equivalent specifications could be supplied depending upon the source
availability.

IQN-17-11-699 Rev 00 December 07, 2017 Page 8 of 12


SECTION 4: SUPPLIED ITEMS:
1. Anchor Bolts for Columns & Post.
(Grouting/supervision is not in the scope of IZHAR STEEL)
2. Bracing For Primary & Secondary Structural Members.
3. Roof & Wall sheeting without Insulation (As per Section 1)
4. Building Accessories (As per Section 1)
5. Crane beams, bracket & Stoper.
6. Eave Gutter & Downspouts
7. All Necessary Flashing & Trims, Sheeting, Fasteners & Connection Bolts.
8. Foam Closures, End Lap and Bead Mastic.
SECTION 5: EXCLUSIONS:
Any Item which is not mentioned in this quotation is excluded.
SECTION 6: SUPPLY DELIVERY PERIOD:
Our current Delivery Period for supply is 12 to 14 weeks from the latest date of receipt
and acceptance of the following (whichever comes latest):
 Signed contract (Any change must be noted and initialed by both parties).
 Advance Payment.
 Final change order.
 Signed Approval Drawings.
NOTE: Erection Time Span would be communicated to you after inspecting the Job Site.
SECTION 7: PROPOSAL VALIDITY:
This proposal is valid for 07 days from the mentioned date. After that IZHAR STEEL
reserves the right to revise the proposal.
SECTION 8: PAYMENT TERMS:

a). For Supply Price (Section – 11)


 Advance upon confirmed work order 50%
 Before Material Supply 50%
b). For Erection & Painting (Section – 12)
 Advance – before Erection. 50%
 After Completion of Erection. 50%

SECTION 9: HEALTH & SAFETY STANDARDS:


 The quoted Prices (for Supply & Erection) and Delivery period are based on Izhar Steel
Health & Safety standard with regular crane and tools specifications.
 For any other particular requirement regarding crane certification/Brand restriction,
Labour clearance, Safety Tools/Kits, Life Line, Limited working hours and any other
requirement which may affect cost and/or Time, this quotation would be revised.

IQN-17-11-699 Rev 00 December 07, 2017 Page 9 of 12


SECTION 10: TERMS & CONDITIONS:

a). For Supply Price (Section – 11)

1. Manufacturing and Supply of building would be initiated only after receipt of complete
Engineering Package duly approved by the client/consultant and Advance Payment.
2. Both parties agreed that the price quoted in this quotation is based on a lump sum basis
calculated according to the building descriptions as well as the required loading and
codes shown above and not as a re-measurable basis.
3. Any change and/or revision to the above stated scope of supply may lead to a variation
in the price and the delivery period. A change must not hold payment for work
completed in the original contract.
4. Civil work like footings, Brick wall, Flooring is not included in the scope of Izhar Steel.
Hence accuracy in civil work is to be assured by Client. The Footings must fulfill the
Loading Capacity of our Column Reactions and sizes of our Base Plates & Anchor Bolts.
Any fault in civil construction related to Pre-Engineered Building shall not be borne by
ISPL in any aspect.
5. Anchor Bolt Plan (By IZHAR STEEL) needs strictly be followed by Client regarding critical
measurements and clearance requirement as per Drawings.
6. Accuracy in final measurements / dimensions of PEB is the responsibility of the client.
7. IZHAR STEEL shall only supply Standard Anchor Bolts (J-Bolts) but it’s grouting in civil
foundations and supervision is not in the scope of IZHAR STEEL. Also, any other types
(Chemical/Expansion Bolts) of Bolts are not included in this Proposal.
8. Space for storage of material will be provided near the work area and covered store for
small parts, insulation and T&P will also be provided nearby.
9. We have based our offer on present day market prices (Raw Materials & Dollar Rates)
and present Government Taxation (4.0 % Withholding Tax & 17% Sales tax). Any
variation in the above will be claimed to Client.
10. Sales Tax Invoice shall be submitted within 07 days of Building/Material Dispatch.
11. We shall be compensated for any change in building parameters/extra works.
12. Transportation of the Complete Material till site is included in our Supply Price (Section –
11). However, Erection Cost of Structure is separately quoted in this Proposal (Section –
12).
13. If the job is “On Hold” from client due to payment or Approval Drawings or any reason
before release to engineering & production for over a period of 20 days, Izhar Steel
reserves the right to re-price the project according to the rates valid at the time of
release.
14. All the structural steel members will be fabricated in the prime facility of IZHAR STEEL
PVT Ltd at 36-Km Multan Road Lahore.
15. Any Additional Charges like Stacking charging in ISPL Workshop, Transportation in Partial
Shipment, Idol Labor for Delayed Material Supply etc., if caused by Delay in Payments or
any other reason at client’s ends, shall be paid by Client.
16. Any type of E.O.B.I and Employee’s Social Security charges are not included in IZHAR
STEEL’s quote and shall be borne by client (if any)
17. To schedule this project in the efficient manner, return the approval drawings (which
will be submitted after project awarding) with your comments marked in RED within 10
days. Any changes made after the approval of these drawings may delay the fabrication
and delivery process.
18. All undefined Jobs arise by the Client later which is not included in Contract Proposal
and/or Signed Approval Drawings shall have Additional Impact on Agreed Cost and
Agreed Timelines.

IQN-17-11-699 Rev 00 December 07, 2017 Page 10 of 12


19. Any fault in civil construction related to PEB Shall not by borne by ISPL in any respect.
20. Loading and packing of material at trailer for transportation will be done as per trailer
loading capacity by following ISPL standards.
21. As per the Standard norms of PEB, Earthing/Grounding of the Building must be
conducted by the Client to be safe and protected from Natural Lightening and other
relevant incidents.
22. ISPL Quotation and Proposal Drawings (Latest Revision) will supersede all bid documents,
discussions & previous revisions (if any). In case, this Quotation deviates any Client’s
requirements, we shall submit a Revised Quotation accordingly.
23. Any change from the Contractual Parameters, if marked by the Client at the stage of
Approval Drawing phase, shall be charged according to the latest rate at that time along with
the revised timelines. Technical and Commercial approval from the Client shall be required
to incorporate that change in the Project.
24. “To avoid leakage, Outer face of brick work must be confined within the outer steel line of
PEB”.

b). For Erection (Section – 12)

1. Separate contract will be added for Erection favoring Izhar Steel (Pvt.) Ltd.
2. Adequate supply of water and power will be given to us at construction site free of any cost
from the very beginning.
3. Space for accommodation of our staff & labor will be provided to us at site free of any cost.
4. We have based our offer on present day government taxes (Sales Tax 16%) for erection
is included in the quoted Price.
5. Health & Safety considerations will be as per IZHAR STEEL Standards. For any special
requirements regarding Health & Safety, our quote will be revised.
6. Client needs to provide smooth and flat surface (obstruction free) site. Clearance of site
does not come under the scope of IZHAR STEEL. The clearance of site for off-loading of
material must be ensured by client at time as off-loading will be done by IZHAR’s
erection team and hence immediate after off-loading, erection will start.

IQN-17-11-699 Rev 00 December 07, 2017 Page 11 of 12


SECTION 11: SUPPLY PRICE:

No. of Total Covered Total Price


Description
Buildings Area (ft2) (Pak Rs.)

Supply of Pre-Engineered Steel Building


Excluding Accessories & Crane Beams 01 6,170 (c/c) 6,774,000/-
(o/o will be greater)
(Excluding Sales Tax)

Crane Beams
Length From Grid 9 to 6 313,900/-
(Excluding Sales Tax)

Gravity Ridge Ventilators


Quantity = 08 No’s 171,100/-
(Excluding Sales Tax)
Total Amount for Supply of Pre- Engineered Steel Building
Including Crane Beams & Accessories 7,259,000/-
(Excluding Sales Tax)

Sales Tax @ 17% 1,234,030/-

Total Amount for Supply of Pre- Engineered Steel Building


Including Crane Beams & Accessories 8,493,030/-
(Including Sales Tax)

SECTION 12: ERECTION PRICE:

No. of Total Covered Total Price


Description
Buildings Area (ft2) (Pak Rs.)

Price for Erection of Pre - Engineered Steel Building 6,170 (c/c)


01 1,354,500/-
(Excluding Sales Tax/PRA) (o/o will be greater)

Sales Tax/PRA @ 16% 216,720/-

Total Price for Erection of Pre - Engineered Steel Building


1,571,220/-
(Including Sales Tax/PRA)

IQN-17-11-699 Rev 00 December 07, 2017 Page 12 of 12