COST ESTIMATE GUIDELINES AND REFERENCES

How to Avoid Bidding Errors

A. Read thoroughly plans, specifications, and general conditions of

contract, addendums, and invitation to bid. Study carefully the following terms

and conditions.

1. Bid bond – 5% to 10% Cash or manager’s check

2. Time of completion – number of working days or calendar days

3. Performance bond – all risk insurance 10% to 20% of contract.

a. Work Guarantee Bond – 20% to 30% of contract

4. Construction Bond for Residential – Subdivision Requirements

5. City Tax or Contractor’s Tax

6. Contractor’s insurance – Verify approved insurance company

7. Liquidated damages for 1% of 10% of bid

8. Price Escalation/ Time Extension

9. Revisions, changes, extra works

10. Last minute addendums, bid bulletins, time and date of the bid

submission

11. Owner-supplied materials

12. Terms of Payments – Check Dpayments

13. Permits

Construction Permits (Architectural, Structural, Plumbing, Mechanical &

Electrical

Occupancy Permits

Demolition & sidewalk Permits

City tax new codes

14. Building Code Requirements/Boundaries

1
B. Look for confusing requirements or any discrepancies in plans

and specifications. Refer to architect and owner in writing ( black & white)

C. Look for notations on plans – general scope of work, changes,

alterations, impossible requirements, Building code requirements

D. Evaluate & study carefully specifications

1. Make list of trades, brand, type that can fulfill the contract

2. Subdivide each trade list if needed

3. Ask quotations from subcontractors

4. Electrical, plumbing and mechanical if required.

Make sure you know the subcontractor suppose to quote on you. Set forms

to avoid gaps and mistakes

E. Set procedures for preparing bids

1. Plan the bid like a project with checklist, target date and project checklist

2. Check if bid required itemized cost breakdown/ unit cost of materials.

F. Check and double check take-off estimate. It might have been

overlooked. Spot check subcontractor proposals if complete. Take note of scope

of works. Verify items not included, unit cost of materials.

G. Site inspections – Verify thoroughly the following conditions.

1. Existing facilities to be demolished – wood, concrete steel.

2. Hauling In/ Out of matls– Disposal of debris. Location. Tools and

Equipment to be Used

3. Sources of Materials – Verify materials unit cost of nearby suppliers.


Major materials from existing supplier and minor materials from new supplier.

Verify terms of payment. Prepare materials checklist. Always check Current

Cost of materials, prepare checklist.

2
4. Geographical conditions of site. Slopes, verify on plans, if backfilling is
required. Check if adobe, soil of backfill. Note depth of excavation requires.

Hauling in/out of backfilling, Dumping of debris from site.

5. Ideal location of bunkhouse, temporary warehouse or storage.


Temporary utilities. Dumping of materials to site must not have conflict with

the layout of proposed building.

6. Sources of manpower, technical expertise, tools and equipment

7. Temporary facilities- power, water, telephone

8. Future tapping of the following:

- Power

- Water

- Telephones

- Sewer and Drainage

Verify if in conformity with the plans. Check utility company

requirements. Project Study. Roads, sidewalks to be demolished.

Permits and payments.Deposits c/o Owner

H. Use the “RULE OF THUMB” method. Check the most contentious

items of bid. Recheck addition of subcontractors.

I. Analyze the bid even if it is not successful. Update cost of

materials. Check file records and other historical data. Get result of bidding and

prepare feedback for future references.

J. Major error in bid. Determine whether or not to continue work on the

project. Determine if you are willing to live with the error. Know the bid of other

contractor.

K. Take note of indirect cost, VAT and other government taxes and

requirements.

Subdivision requirements, construction bonds, insurance, city tax, performance bond.


3
L. You may wish to withdraw the bid.

Reminders before Estimating

A. Read first plans, specifications and general conditions of contract to familiarize


yourself with the general scope of works.

B. Spot check nebulous requirements if available in local market. Verify if imported,


suppliers, type of materials

C. Rough estimate to try. It must be 30-50% of what might be the ultimate cost.

D. Preliminary estimate. Unit cost obtained from past project. Recheck verify current
unit cost.

E. Always use the rule of thumb in the final estimate

F. RE-check your estimate. Let someone do it. Spot check multiplications and
additions of subtotal

G. Ask for quotations of suppliers or subcontractors of specialty works

H. Use different techniques in estimate

1. By volume method

2. BY area method – sq. m.

3. By direct count

Be systematic. Breakdown estimate or use the area method.

Schedule organized breakdown.

I. Begin estimate with fresh mind. Difficult items first, easy items like addition of total
cost can be done when you are tired

J. Always use your imagination, observation, take note of items lacking or errors in
plans and specifications. Do not leave items. Immediately look for unforeseen

requirements before continuing to other portion.

4
Estimate Checklist

A. Site Development/General Requirements

1. Mobilization/Temporary facilities

a. Temporary Fence – Total linear meter

 Sawali 4’ x 5’ or GI sheets

 Coco lumber – 2x3/2x4

 C.W. nails

 Check if corr. GI sheet temp. fence

2. ID / Uniforms/ Biodatas

3. Workers Quarters – Verify number of workers

a. Temporary Field Office

 Plywood

 2 x 4 lumbers

 Roofing G.I. sheets or Lona – 20’ x 40’

 Emergency Kit

 Drums

 Tools and Equipment

b. Temporary Power, Water and Telephone – Cost of utilities


during construction. Contractor or Owner

B.1 Checklist Temporary Power (Residential Only)

Description Qty Unit Unit


Cost
RSC pipe ½ x 10’ 1 Piece
Entrance Cup ½ 1 Piece
RSC Conduit Nipple
Safety Switch 60 A 2p 1dia 1 Set
THW wire # 12 (5.5 mm²) 1 Roll
Electric Tape (big) 1 Roll
One way switch 2 Piece
Duplex Convenience Outlet 2 Piece
5
Fluorescent 40 w 2 Piece
Meter base 1 Set
4 X 4 X 8’ coco lumber or 1 Piece
equal

B.2 Temporary Toilet/Waterlines/Sewer

Description Qty Unit Unit


Cost
PVC pipe 3”ρ x 10’ 2 Pieces
PVC wye 3 x 3 3 Pieces
PVC bend 4 Pieces
PVC bend 2 Pieces
PVC Cement 100 cc 1 Qrt
G.I. pipe ½ x 20’ 2 Pieces
G.I. tee ½ 4 Pieces
G.I. Elbow ½ 4 Pieces
Taplon Tape 3 Rolls
Flush Type Water Closet 1 Set
Drums 3 Set
Water Hose ¾” x 15 lm

B.3 Checklist of tools and equipment to be used

 Concrete Mixer (1 bugger)

 Bar Cutter/Circular Cutter or Hacksaw Blade

 Shovel

 Pick Mattock

 Leveling Hose

 Bareta/Pointed bar

 Angle Grinder

 Vibrator

 Compactor

 Plastic Container

B.4 Manpower Transportation/Cash Advance for Mobilization

B.5 Temporary Bunkhouse for Workers and Storage of Materials

B. Siteworks

1. Demolition of Existing Structure

2. Hauling out/in

6
Verify the following:

a. Slab, beams, footing, etc.

b. Materials that can be utilized – wood/steel/doors/etc.

c. Hauling out of usable materials and debris (labor+delivery


charges) – location of disposal

d. Storage of usable materials

3. Clearing and Grubbing – 3.00 m around building

a. Uprooting of trees and shrubs

b. Soil stripping if required

4. Sheet Piling – Verify adjacent existing structures

a. Near creek, beside high-rise building, etc

b. Piles to be used – Concrete pre-cast, steel or apitong lumber – 2

x 10 x 12’ for property walls

5. Verification of monuments, lot boundaries, slopes and topographical

conditions. Prepare fixed reference above the street level, building

elevations.

- Check if soil test is required for 4 storey buildings up.

6. Excavation

a. Manually

b. By machine – Calculate number of hours required

Verify Soil Conditions

Description Qty Unit Unit


Cost
Soil Cu.m. 150
Adobe Cu.m. 200
7.

Earthfill/Backfilling works
7
a. Backfill – Excavated portion of footing, wall footing

b. Earthfill

– Slope of existing lot

– Elevations of Proposed finished flooring from

street line or other reference point.

c. Type of filling materials

Description Qty Unit Unit


Cost
Escombro T/L*
Banda’y Banda or Lastillas T/L*
Garden Soil for landscape/
Ordinary soil

Dump truck Or Ten Wheeler Truck

d. Tamping by Manual or Machine

Formula: LOOSE VOLUME or VL =Length x Width x Depth


Compact Volume in Place or VC = VL + 25%

Hauling In of Backfill Materials


Description Capacity Unit Unit
(soil) Cost *
6 wheeler truck 4-6 cu.m T/L
10 wheeler or dump 12-16 cu.m T/L
truck
Depending on the type of Backfill – escombro, soil, and lastillas?

8. Gravel Fill
a. 0.05 m thickness below slab on fill and footing
b. G.I. gravel or ¾” gravel

TOTAL AREA OF SLAB = Length x Width x .05 m =


Total Volume of Gravel Fill

Description Capacity Unit Unit


(soil) Cost
6 wheeler truck 4-6 cu.m Per
10 wheeler or dump 12-16 cu.m cu.m.
truck

9. Soil Poisoning – For application before pouring of footing and slab

a. Type of Soil Poison – Lentrex/Chlordane or F3D14

8
10. Polyethylene Sheet under slab on fill – for Ground floor S lab

0.006 Thickness Polyethylene sheet approximately 9 kgs/sq.m. Specially for

narra parquet and vinyl tile floor finish

Reference Checklist: Foundation

a. Soil Bearing Capacity

1,500 – 2,000 psf (pounds per sq. ft.) Most commonly used

assumptions at city engineer’s office

3,000 to 4,000 psf

- if adobe or hard soil depending on soil test done by

geotechnical Engineers

b. Soil Test – For high rise building (Boring Test)

Cost P15,000 – P20,000.00 per hole depending on the

requirement of structural engineer

c. Seismic Analysis if required

11. Other Outside Building Development Checklist

a. Fence – Verify height and total length

b. Special Fence for Slope Area – shear wall with perforated


pipes ( verify detail)

c. Concrete curb and gutter, roads, walk, sidewalk

d. Parking Area

e. Rip rapping if required

f. Water Tank/Genset Rooms/other base foundations

g. Landscaping

9
Note: Provide during construction permanent benchmark for elevation references.

C. Concreting Works

Checklist – check strength required

2,500 psi slab on fill

3,500psi to 4000 psi for footing/ column/beam/slab/residential for high rise

building

1. Manual or concrete mixer – Actual Site conditions if 2 – storey

building

2. Ready Mixed Concrete – for high rise building

a. Interval of Delivery of Truck - 30 to 45 minutes

b. Capacity of One truck – 4 to 6 cu. mts.

c. Retarder or additives fast curing if required

d. Verification of scaffolding work before pouring-safety precautions

e. Dumping of excess cement if necessary

f. Emergency Scaffolding/tools and equipment

Checklist of Concrete Works for Estimate

a. Footing, wall footing, footing tie beam

b. Columns per floor schedule

c. Last Floor to roof or deck

d. Shear Walls

e. Concrete stairs

f. Floor Beams and Girder – per floor

g. Suspended slab

h. Parapet walls and canopy

i. Elevator shaft

j. Slab on fill (includes driveways and walks

k. Cistern Tank and Septic tank


10
l. Kitchen and Lavatory counter

m. Lintel beam for doors and windows

n. Electrical and Plumbing lines embedded in concrete, pullboxes

and catch basins

o. Concrete Curb and gutter

p. Fence/electric post

q. Others as per plan

- Computations shall be scheduled systematically to

above items not included in the estimate. Itemized per

floor

Volume = Length x Width x Depth

Note : To include all portion below natural grade line (footing, column, walls, etc..

depth)

Estimate References for Concrete Works

Ratio : 1 part cement

2 part sand

3-part gravel

Compressive Strength of Concrete = Fc’ Psi- Pounds per square inch

Class Fc’@28 days Ratio Cement Sand Gravel


AAA 4000 psi (281 kgs/sq.cm) - 1:2:3 11 bags .40 m 3 .40 m 3
ready mixed concrete
AA 3,500 psi (special) 1:2:4 ½ 10 bags .41 m 3 .82 m 3
A 3000 psi(regular –211 1:2:4 9 bags .42 m 3 .84 m 3
kgs/sq.cm.)
B 2,500 psi (176 kgs/sq.cm) 1:2 ½:5 8 bags .44 m 3 .87 m 3
11
For estimate use .50 m 3 1.0 m 3

Example :

3,000 psi = Total Volume ( Concrete per computations) = 35 cu.m


Cement = 35.00 m3 x 9.0 m3 = 315  = 315 bags

Sand = 35.00 m3 x .42 m3 = 14.7  = 15 m3

Gravel = 35.00 m3 x .84 m3 = 29.40  = 29.40 m3

Note: Use only Local Brand Cement – Portland cement

Brand : Dragon, Northern Cement, and Island Cement

Get one (1) concrete sample for every 10.00 cu. mts. of concrete during

pouring of concrete on 12” concrete cylinder for testing of strength as required

for occupancy permit.

Capacity of Truck

1 bag of cement = 1 cubic foot

Note: pump cute interval of delivery of concrete every 30 min. capacity of truck 4 – 6.00m³

Cement

Description Capacity (bags) Cost


6 wheeler truck 100-200 bags
10 wheeler or dump truck 500 bags

Gravel/ Sand

Description Capacity Unit Cost


6 wheeler truck 2-4 m3
10 wheeler or dump truck 12-14 m3

S-1 - for concreting works


White Sand - for plastering/topping

Concrete Mixed

12
For one bag of Cement = 40 kgs (weight)

Gravel

G – 1 ¾ “ to 1 ½” gravel for foundations

Slab on fill

¾ gravel – 3/8 to 3/14” for all structural members

verify if crushed gravel or washed gravel

D. Formworks

1. Estimate form lumber using 2x3/2x4/2x6 coco lumber per total volume of

concrete to be used. Estimate first total concrete volume as per guidelines.

Coco lumber supplier – to order coconut bark, avoid lumber at center

2x3/2x4 - for vertical lateral ties and braces

2x6 - for beam support and footing

cost of coco lumber 12.5 to15.50 per bd. Ft.(jan ’06)

2. Normal coco lumber requirements

150 board feet per cubic meter of concrete

1 truckload of coco lumber – Elf, -1,800 to 2,500 bd. Ft.

Ten-wheeler -4,000 to 5,000 bd. Ft.

Cost of cocol umber 6.50 to 7.50 per board foot

3. Assorted C.W. Nails

C.W. nails 1½“ For scaffoldings


C.W. nails 2”
C.W. nails 3”
C.W. nails 4”

Commercial Sizes

1 box = 20-25 kgs (small)

1 box = 30-38 kgs ( large)

13
Estimate Guide : 1 kilo per 50 board foot or lumber

QTY = Total board foot / 50 = N o s. of kilos / 25 = No. of

box

50 bd. Ft. 25 or 38 kgs/box

4. Concrete Nails – 3 “ & 4” for CHB filing guide, concrete walls ceiling joist
and cabinet frames. Quantity depends on the actual requirements

NAILS CHART

CW Nails Pieces per kilo Usage


2D 1” 1,680 pcs Forms Plywood
4D 1 ½” 705 pcs Forms plywood
6D 2” 380 pcs T & G flooring
8D 2 ½” 260 pcs Ceiling joist
10 D 3” 120 pcs Trusses/Rafters
20 D 4” 55 pcs Floor Joist

Size Usage
Finishing nails 1” ceiling
1½“ T & G flooring
2” Cabinet frames

5. PLYWOOD - Use 3/8” to ½” plywood. Normal market/commercialize


of ¼ is too thin

Solve for Contact Surfaces. Columns/Beams/slabs as per plan. See checklist


for concrete works.

Column Example:
4 sides or Perimeter
(.20 + .20 + .40 + .40) x height
area required for formsa
= sq.m.

Beam Example
3 sides
(.15 + .40 + .15) x height = sq.m.

Slab = Length x Width = Sq.m.

Summarize all required formworks


area required for formsa
Total Contact Surface in Sq. Mts. = Nos. of
Pieces
14
2.88 or 1.20 x 2.42 Plywood Size of Plywood Required
Note : Check if you can use it again if building is large. Small buildings assume as per
estimate.

Formoil – Normally to use USED oil – Quantity approximate; 1 ltr. per 15 sq. mts.

If steel scaffolding is to be used check rental per day of steel accessories. Verify to supplier.

Note : For residential, use good lumber for scaffolding, to be used later for rafters, purlins, ceiling
joist, etc.

E. Steel Reinforcement/Bars
Steel forms – rental per piece /day. As per plan

REBARS DESIGNATION
American Philippine Yield Point Tensile Usage
Society for Standard Strength Strength
Testing Kgs/ Psi Kgs/ Psi
Materials mm2 mm2
(ASTM)
Structural Grade 24.452 33,000 39.77 55,000 For
Grade 230 reside
ntial
only
Intermediate Grade 28.042 40,000 48.95 70,000 Depen
Grade 275 d on
(Grade 40) structu
ral
design
Grade 60 Grade 41.80 60,000 63.22 90,000 For
410 high-
rise
buildin
g

Standard Length of Bars


Feet Meter Most commonly used available in hardware
6.00m
20’ 6.00 m Special Length, per order to supplier
26’ 7.50 m
30’ 9.00 m
35’ 10.50 m
40’ 12.00 m

15
20’ (6.00m) – 9mmd, 10mmd, 12mmd
20’ and above – 16mmd, 20mmd, 25mmd

Commercial Sizes of Rebars


Cross
Secti
Unit weight onal
Nominal Diameters Designation per meter area
(metric) (English) (Kilos per in
meter) sq
Inch
8 mm Substandard
9 mm (2.3 kgs) Commercial Sizes
10 mm (standard) 3/8 #3 0.616 0.11
12 mm (standard) ½ #4 0.888 0.12
16 mm (standard) 5/8 #5 1.579 0.31
20 mm (standard) ¾ #6 2.466 0.44
25 mm (standard) 1” #8 3.854 0.79
28 mm (standard) 1 1/8 #9 4.833
32 mm (standard) 1¼ # 10 6.313

Example:

20 pcs – 16 mm dia. X 6.00 bars


20 x 1.576 x 6.0 = 189.46 kgs.

To get quantity of G.I. wire # 16

a. G.I. wire # 16, through use of Concrete Volume

2 kilograms per cu. m. of concrete = NO. OF ROLLS


25 – 30 kilos per roll
(Check commercial weight to supplier)

b. Estimate thru Rebars

20 kilos of G.I. wire per metric tons


1 metric ton = 10,000 kilos
1 kilo of wire = + 53 linear meter
1 roll = 35-40 kilograms
or current commercial kilos per roll = 38 kgs/roll

c. G.I. wires for CHB walls


4” chb - 10” length of tie wires
5” or 6 “chb - 12” length of tie wires
Spacing of rebars

16
Vertical  @ 0.60 m. o.c.
Horizontal  every third layer

GI wires Kilos per sq. mts – 0.04

Example : Total Area of CHB walls – 230 m2 x 0.04 = 9.2 kilos, or 10 kilos of G.I. wire # 16

d. Welding Rods
e. Rust Proofing
f. Post Tensioning – per plan special Construction, quotation per suppliers

Rebars substitution

Say 12-16 Ø To 20 mm Ø

Reinforcement/Rebars Data
How to Determine Bar Splicing Length
Type Minimum Splice Length
1. Tension Bars 25 x bar size +150 mm
2. Compression Bars 20 x bar size + 150 mm

Example : Column
20 mm = 20 x 20 mm + 150 mm
Compression = 550 mm or .55 m

NO FOOTING SHALL REST ON FILLING MATERIALS


“Y” – spacing of bars 1 @ 0.05
2 @ 0.10
3 @ 0.15
rest @ 0.20 m on center
F. Masonry Works

17
Estimating CHB walls
4” chb – interior chb partition
6” chb – exterior chb partition for buildings
5” chb – exterior chb partition for residential

Example :

A1 = LXH
= SQ. M. GROSS AREA
A-1 LESS (A-2+ A-3)
= SQ. M. NET AREA

A-1 = 3.0 X 4.0


= 12.0 SQ.M

A-2 = 1.60 X 1.20 Take note of


portion below grade line
= 1.68
A-3 = 0.80 X 2.10 = 1.92

A-2 + A-3 = 3.60

A-1 LESS (A-2 + A-3) = 12.00- 3.60 =


8.40 SQ. M. = NET TOTAL AREA

FORMULAS
1 cubic foot 0.0285 cu. mts
1 cubic meters 35.28 cu. Feet
1 bag of cement 1 cu. Foot

1. CHB Filler
Ratio 1: 3 or 1 part cement to 3 parts sand

Cement Sand
4 “ chb 25 pcs. Per bag 0.0855 m3 per bag
6 ” chb 20 pieces per bag cement

Example:
2,200 pcs. 4” chb = 88 bags cement
-----------------------
25

88 bags x 0.0855 = 7.52: say 8.00 cu. mts. sand

2. CHB Plastering
Ratio 1: 2 or 1 part cement to 2 part sand

Cement 0.50 bags per sq. m.


½ - ¾ “ thk plastering
Sand 0.057 cu. mts per bag

Example:

18
Say, 200 sq. m x 2: both face
--------------------------------
0.50
= 200 bags cement

200 x 0.057 = 11.4 says, 12 cu.m.

3. CHB Type/ Strength

NLB or non load bearing 400-500 psi Available


in local
market
LB or Load Bearing (Jackbuilt), etc. 700-1000 psi Locally
available
special
chb

Note : Verify delivery cost within Metro Manila or outside Metro Manila

4. Floor Topping

Mortar Per cu.m . Volume Sand Usage


Class A 1:2* 16 bags/cu.m. 0.80 cu.m. For topping,
finishing
works, tiles,
etc.
Class B 1:3** 12 bags/ cu.m. 0.89 cu.m For topping
over slab to
level flooring
after pouring

*1:2 Ratio 1 part cement for every 2 part sand


** 1:3 Ratio 1 part cement for every 3 part sand

5. Rebars for CHB

4” chb 10 mm diameter at every 3rd layer horizontal bars


10 mm diameter at 0.80 m vertical bars
6” chb 12 mm diameter at every third layer horizontal bars
12 mm diameter at 0.80 m. vertical bars

Assume : 4.25 LM per sq.m. of chb


Say : 210 sq.m. x 4.25 lm
= 892.50 LM
---------------------------
6.00 m: standard length of bars
= 148.75 pieces,
19
say 150 pieces – 10 mm dia.x 6.0 m def bars

6. G.I. wire Masonry works Ga # 16

Tie Wire 10” to 12“ length. Included in rebars wire computation (see checklist)

7. Firewalls/ Toilets. Floor Topping


a. Requirement for waterproofing
Sahara Compound – 1 pack per bag of cement for plastering of firewalls

b. Plaster Board –. Assume 5 sq. meters per gallons for floor topping

G. Steel Trusses. Verify details as per plan.


1. Type of trusses
Steel trusses
Open Web Rigid Frame Built Up

2. Checklist for Estimate per Plan. Always verify if roof framing is correct/ economical.
Angular Bars

Top and bottom chords


Web Members
Cross Bracing
Turnbuckles
Baseplate (Thickness)
Bolts and nuts
Sag rod
Hanger or support for ceiling with
bolts
Welding rod
Oxygen Acetylene
C Purlins 2 x 4/ 2 x 6 1.5 mm
thickness
Angular bars for fascia board
connection

* Preferable to get quotation from qualified subcontractor

Wooden Trusses. Checklist per plan

Top Chord/ Bottom Chord

Web Members/ Collar Plate/ Struts

Wood Plate

20
Girters

Fascia Board – Tanguile KD S4S

Wood Braces

Purlins

Machine Bolts, nuts and washers

Eaves ventilation – wood slots with US Aluminum Screen

Tension Rod and Sag Rods

Special Trusses – Fabricated for Low Cost Gang nail/Others

To get board foot of lumber

Example:

1 pc 2 x 3 x 16  2 x 3 x 16 1 pc 8 bf/pc
12 8 bf

5 pcs 2 x 5 x 14  2 x 5 x 14 11.66 bf x 6 pcs


12 58.33 bf

6 pcs 1 ½ x 2 x 14  1.5 x 2 x 14 3.50 bf / pc x 6 pcs


12 21 bf

Conversion Factors
Cu.ft x 0.02832 Cu. mts.
Bf ft. x 0.0833 Cu. ft.
Cu. mts x 35.314 Cu. ft.
Cu. ft x 2.8317 x 10-2 Cu. mts.

H. Roofing Works
Ordinary Corrugated GI sheet Ga.# 16

Standard Market Sizes Width Standard


Length
Corr. GI sheet Ga # 26 x 32” Standard 7 feet
-do- 8 feet
-do- 9 feet
-do- 10 feet
-do- 12 feet
0.30 meters – standard overlap

21
11.50 = 16.42, say
0.70 side lapped 2 ½ “ 17 pcs. X 2 side
or 2 corr.
= 34 pieces
Ga# 26 x 32 x
10’ Corr GI
sheet

5.40 m. = 18’
2 pcs.- 10’ length

2. Plain GI sheet Ga. # 26 x 32” x 8’

standard. Solve for flashing and counter flashing for firewalls and parapet. Verify actual

plan.

3. G.I. gutter Ga. # 26 x 8’ -

Standard Gutter

- Special Gutter ( Spanish type)

4. Ridge Rolls x 8’

5. Valley gutter. Verify if outside gutter or

inside gutter

6. Others per plan. To include fascia board

for estimate.

7. Accessories

a. GI roof nails 3 ½ “ - kilos

b. Lead Washer - kilos

c. GI washer ( medium or thick)- kilo

d. GI rivets ¼ x 3/16

e. GI strap Ga # 26

f. Nicolite Bar

g. Muriatic Acid
22
h. Roof Cement ( Vulcanized)

i. Red Oxide or red lead primer

j. Silicon Sealant

For Color roof – Verify type to be used. Ask for quotation of supplier. Standard Sizes
Brochures

Type 1 – Rib type long span ; most common for residential

Checklist
Ga. # 26 Width Length
(Thickness)
a. 0.40 mm X 1.040 m X ___ LM Rib Type roof
b. 0.40 mm X 0.610 m X 2.44 S type gutter
c. 0.40 mm X 0.610 m X 2.44 V type gutter – valley
d. 0.40 mm X 0.610 m X 2.44 Ridge roll
e. 0.40 mm x 0.915 m x 2.44 Capping/Flashing

Accessories

a. Tek Screw (Metal Screw) 12 pcs per sq m

b. Blind Rivets

c. Silicon Sealant Per tube

d. Touch Up Paint

e. Vulcaseal – gallon

Take note of delivery charge – Around P 2,000.00 – 2,500 per trip, within Metro Manila or

outside Metro Manila

Order roofing one month in advance. Delivery is 2 – 3 weeks after order and payment.

Always estimate as per actual plan.

Formulas

A2 = c2 – b2

23
B2 = c2 – a2

C2 = a2 + b2

Roofing by area method


a. Determine total flat area required
L x W + pitch factor solve for linear feet required
Roof pitch Add to total flat area
(Height) meters (Percent)
0.32 2%
0.40 4%
0.45 5%
0.50 6%
0.55 7%
0.60 8%
0.70 11%
0.80 14%
0.90 18%
1.00 21%

b. Verify type of roofing as per plan

Tegula – 11.50/m²

Rib type

Banaue type

Others per brochures or specifications

I. Windows as per plan

1. Verify if the window jambs are required

2. Checklist on type of windows to be used

K. Jalousie windows 7/32” thk clear or smoked glass

- Verify if operator type

- Jalousies with steel grilles or aluminum

- Grilles with or without design normally grilles shall be

10mm square bar (3/8”) or 12 mm square bars (1/2”)

To compute: L x W= area in m² x 10.76

= area in ft²

24
Jalousie Windows Specifications

Hoover alloy 6063-T-5 Anodized natural Anodized natural color lever

type operator with 7/32” clear glass 4” blade

Standard Single control


No. of blades Standard height
In meters
4 0.378
5 0.466
6 0.566
7 0.644
8 0.733
9 0.822
10 0.910
11 1.00
Width
12 1.080
Minimum of 0.80 m
13 1.178
14 1.266
15 1.355
16 1.444
17 1.533
18 1.622
19 1.710
20 1.800
21 1.888
22 1.978
23 1.060
Note: verify of aluminum screen for windows is included in contract

L. steel casement windows (casement or awning type)

1/8” x 7/8” or ¾” T & 2 mild steel section

1/8” thick clear or smoked glass

12mm square bar grilles with or with out design or as specified

aluminum screen if with u frame or detached

A= L x H= area in m² x 10.76= ft²

M. aluminum frame windows (sliding or fixed)

verify if anodized (white), analok (brown) or powder coated

25
7/32” or ¼” thick glass bronze or clear glass green or blue

weather strip vinyl (mohair)

N. French type windows(wood or steel)

7/32”thick glass

hinges

special

locks and bolts

O. Window casing if required on plans(wood or concrete)

P. Other special type windows(local or imported)

I. Doors and Jambs

1. Door jambs –4” – 2” x 6” yakal or quijo

2. Door casings per plan/ mouldings 1x 5 / 1 x 6

3. Wood preservatives –solignum or black coal

4. Flush type doors 1.3/4” thick or height per plan

1. Hollow core ordinary both face

2. Hollow core 1 face marine

3. Hollow core both face narra

4. Hollow core with glass for kitchen

5. Narra panel floor solid core 1-3/4” thick per plan

1. Tang. KD panel door solid core 1-3/4 thick per plan

6. 1 ¼” louver door for toilets tang. Kd/aluminum, door.

7. metal louver door for pump room, electrical etc.

8. accordion door

1. metal with or with out plates GA # 14

2. wooden accordion
26
9. aluminum doors

1. anodized – kawneer finish

2. analok finish

3. with or with out grilles

10. roll-up door

1. metal – manually operated/machine operated

11. sliding doors/windows per design

12. aluminum screen doors

13. metal clad doors

14. special doors for vaults

B. Accessories

1. 3 ½ x 3 ½” loose butt hinges us or local

2. 3” x 3” double action hinges

3. door track and hanger set

4. lockset per specification-local or imported

5. door closer

6. door bumper and stopper

7. master keys for buildings 2 sets

8. barrel bolts

9. foot bolts / head bolts

10. padlocks

11. peepholes

12. night-latch / privacy lock for toilets

J. Miscellaneous hardware

1. stair nosing- brass or non slip/ carborandum

2. Washington hinges or hettich hinges piano hinges

27
3. closet/cabinets, handles and pulls roller catches an magnetic catches

4. finishing nails and concrete nails

5. railing for stairs

K. Thermal and moisture protection

1. vapor barrier – polyethylene sheet 4 width - > 7.8 m²/kgs. 107.8 kgs. Per roll

2. Sahara cement – 1 pack per bag of cement for firewall plastering

3. ceiling insulation (thickness to verify)1 roll = 5’ x 15mts

1. sisalation or aluminum foil

2. fiberglass

3. styropor boards

4. cauling and sealants

5. fireproofing materials

1. elastomeric

2. membrane

3. asphalt (hard) 30kgs. / bags

note : guarantee 5 to 10 yrs

preparation and cleaning of surface before application

L. Carpentry works

A. WALLS

a. Vertical & horizontal studs 2x3 / 2x4 S4S

b. Plywood panel - per plan ord. Or narra

c. Baseboards 1x6 with or without design

d. C.W, Nails 2" and finishing nails 1 "

e. Concrete nails 3"I rat proofing PLN GI SHT

1. Ordinary or narra or marine for ext.

2. Danarra 1 tempered lawanit

28
3. 5-cut KD LBR

4. Wood lattice with design

2.Wooden Post 4"x4" per plan

Post strap - 3116 x 1 1/2x 24"

3. Special Walls - Corkboard

B. CEILING WORKS
1. 2x2 Apitong RO or S4S @ 0140 x0.60 / 140 x 140
Ordinary or treated - Wolmanized tanalized

2. 2x3 / 2x4 Runner

3. Hanger 1/2 " PLN Round bar with thread and nuts

4. Concrete Nails

5. Exterior Ceiling
a. 1x1TANGKDWoodSlats
b. 1/4" x 4' Screen wire (welded)
c. 1x2 Frame

6. Ceiling niouldings size Per plan


¼ Ordinary - 1" to 1 112," to 3" special design

7. False beam per design

8. T and G or S-cut for ceiling

9. Cover lights ½ " - 1/4 “ plywood

Acrylic diffusers .30 x 1.20 / .60 x 1.20 per plan

10. Special ceiling design


a. Mirror
b. architectural Glass
c. Acoustic board - T runner

C. FLOORING
1. Wood girter and corbel plates
29
2. Machine bolts with nuts and washer

3. Floor Joist Apitong Ro

4. T and G Flooring
a. Sanding of T & 0
b. Wood Filler and Paints

D. CLOSETS & HANGING CABINETS PER DESIGN

1. Plywood

2. Hardwares - drawer slides / handles / hinges

3. Weldwood glue

4. Hanger rod and bracket

5. Drawer locks / bolt

6. Secret drawer

E. HANGING CABINETS

1. Bar counter per design


2. Kitchen Hanging cabinet
F. WOODeN STAIRS

1. Handrails 3x8 narra or guijo S45 2. Riw

3. Threads

4. Balusters

5. Flat bars and screw

G. KITCHEN COUNTERS PER DESIGN

1. Wood / Concrete
a. Frame 2x3

b. Plywood 3/4

c. Cabinet louver door

d. Formica top / Adhesives

f. Tiles inside counter white

30
2. Marble/Granite tiles
a. Countertop 1
b. Splashboard 4" to 6"

A. Area method

1. board ft of studs / m² @ 0.60 m.o.c.b.w.

2. 2 x 3 – 5.38 bf/m²

3. 2 x 4 - 7.30 bf/m²

B. wooden partition

1. 2 x 3 – 9 bf/m²

2. 2 x 4 – 12bf/m²

C. ceiling plywood – joist

1. 2” x 2” @0.60m o.c b.w = 7bf/m²

2. 2” x 2” @ 0.40 m o.c. b.w.=9bf/m²

D. plywood ceiling by sheet method (bf/sheet)

@0.60 B.W. @0.60 & 0.40 @0.40


2”x2” 12bf/sheet 15bf/sheet 18 bf
2”x3” 18bf/sheet 22bf/sheet 27bf
2”x4” 24bf/sheet 30bf/sheet 36 bf
E. T & G flooring / V-cut

Nos. of
Bf/m²
T&G/meter run
1x4 12.11 pcs. 13.85
1x6 7.70 pcs. 13.20
F.

G.

H. C. W. nails

Usage Unit Required Size Kind


kilos
Floor joist 1000 10.35 CWN
4”
bf
Flooring 1000 14.34 f

bf
V/H studs 1000 10.43 2½ CWN
31
bf
Rafters/Purlins 1000 18.38 CWN
4
bf
Trusses 1000 7.93 CWN
4
bf
Facia BD 1000 9.57 CWN

bf
Ceiling joist 1000 16.30 CWN

bf
1000 12.93 f
4
bf
Plywood 8 pcs. 1.00 f
1
ceiling
Baseboard 1000 6.08 CWN

bf
scaffolding 1000 25.00 CWN
3
bf
4 CWN
I. Bolts

Wooden columns

bolt length L = w + 2(t) – 1”

Example: L = 4 + 2 (3 ) – 1”

=4+5

= 9 bolts take note of commercial sizes of lumber

J. Trusses

L = thickness of lumber in layer + 1”

32
FLOOR JOIST (WASTE FACTOR & BRIDGING CONSIDERED)

Per m² method

Spacing @ 0.30 O.C.


2” x 6” 16.10bf/m²
2” x 8” 21.33bf/m²
2” x 10” 26.73bf/m²
Girter, corbel; plate by direct count

M. Specialty roofing Verify discount for Archt.

A. SHIN YEE METALGA # 0.40 /GA # 0.50mm

1. length maximum or 60 feet

2. width = 30” (760mm)

3. minimum roof 3%

B. accessories

1. gutter with design 0.50 x 0.914x_______

2. ridge roll 0.40mm x 0.577x________

3. ridge wall flushing – 0.40m x 0.577m x 3.30m

4. end flushing

5. End flushing wall

6. counter flushings

7. Counter nails

8. blinds rivets 1/8”

9. type 17 – self drilling screw no. 12x2” (50mm)

10. tek screw #10x1/8”

33
11. wire basket strainer

12. silicon rubber sealant / acrylic paints

C. for walls – spandrel

1. Rib

2. Plain

3. V – spandrel

N. Downspouts, catch basins, manholes, septic tank and cistern tank

A. Downspouts

1. 3” or 4” per plan

2. 1/8” x _______PVC bend

3. ¼ x_______PVC bend

4. PVC coupling

5. epoxy and PVC cement

B. catch basins/ drainage per plan

1. .4” to 10” concrete pipe x1.00 non-reinforced or reinforced

2. perforated PVC pipe for basement walls

3. cement

4. sand

5. gravel

6. steel grating if required – angular bars

C. manholes for electrical or plumbing

*Concreting for embedded electrical and PCBG Lines

O. Finishes

A. Walls- exterior and interior

1. plain cement finish

2. tooled finish (plaster)

3. patch on joints

B. synthetic adobe / adobe rubble finish


34
1. with or without shells

2. with or with out grooves

3. color scheme

C. pebble or boracay washout bohol or ordinary

1. white or ordinary cement

2. size #5, 10, 15

D. anay finish

1. with pebbles

2. fissured finish

E. bricks tiles finish / cal-tiles

F. mactan stone 2x8”

G. marble tiles 4”x8” / 6”x12” etc – Bulacan or Romblon

H. wall tiles 4x8

1. colored or white 4 ¼” x 4 ¼”

2. with or without design 6”x6” / 8” x 8”

3. white cement – 350 pcs/kilo

4. tile adhesive

I. marble ashlar finish 2”x8”

1. flooring per plan

a. plain cement finish or colored red green cement 1:2 5 m² / kilo

b. marble tiles

c. vinyl tiles 1.5mm thick x 1’x 1”

3.6mm thick x 1’x1”

Adhesive: gallons per m² x 0.042 = gallons

d. stone inlay finish 2” to 3”

e. wood parquet per design sanding

f. mosaic tile 1” x 1”

g. narra wood planks 1” x 6” to 8” nailers/insulation/c. winnails


35
h. floor tiles 4” x 8” class a or class b

6” x 6” colored light or dark

i. terrazzo finish or marble chips washout

j. others per design

2. Ceiling Finishes

a. acoustic boards with or without design

aluminum T-runner/if plywood with adhesives

b. 1” x 4” t&g

c. S-cut or v-cut finish 1”x6”

d. Acrytex finish

e. Mirror

f. False beams

3. FLOOR FINISHES verify specs & Plan

4 ¼ tiles – 86 pcs. Per sq. m

white cement – 0.80 kilo/m² or 250 pcs. / kilo

cement – 0.076 bags /m²

cement tiles:

Tiles/m² Cement Sand


Bag/m² M³/m²
¾ x 6’” x 6” 45 pcs, 0.3375 0.019
1” x 8” x 8” 25 pcs. 0.3400 0.019
1” x 10” x 10” 16 pcs. 0.3400 0.019
Vinyl adhesive x gals /m² x 0.042 =

Or 200 pcs. Per gallon =

P. Grille works

A. Fence grilles with or with out design

½” to ¾” square bars or 1 ½” x ¼” flat bars

B. gate with mailbox GA # 16 or per design

C. window grilles – ordinary or pregnant grilles

D. fire escape ladder

36
E. air con frames / manhole cover

F. open court grilles – flat bars and angular bars

G. stair railings with design

H. cyclone or interlink wire

G.I pipes/ Welding rod

I. others per plan

brass nosing for stair / screws

Q. Electrical works

Note : if floor plan has no electrical layout

Assumption

Nos. of c.o Nos. of light outlet


Residential 0.38/m² 0.18/m²
Commercial 0.42/m² 0.22/m²
Industrial 0.60/m² 0.40/m²

1. Get total nos. of C.O. outlet x unit cost

2. Get total nos. of ceiling outlet x unit cost

R. Add 30% of 1 & 2 for load center and panel boards

1. Add 40% of 2 for lighting fixtures

2. Add 15% of 1 & 2 for wiring devices

3. add 12% of 1 & 2 for fire alarm

4. add 12% of 1 & 2 for telephone

5. add 10% of 1 & 2 for music and paging system

6. add 8% of 1 to 8 for miscellaneous and contingencies

note: verify MeRalCo / PLDT for tapping

1. Transformer

37
2. Tel. House cable

3. Single phase or three phase

ELECTRICAL COMPUTATIONS:

SINGLE PHASE

Total load x 80% demand factor = LOAD

FOR 110 / 220V

C.O. x 0.75 A =__________total amps

Ground Wire – size =TOTAL LOAD WIRE


3

or 75% if lights & C.O.

ELECTRICAL LOAD COMPUTATION (STANDARD)

# OF
WATTS AMPERE
DESCRIPTION WIRE SIZE
PER LOAD
UNIT
English Metric
Convenience 180watts- TW #
Outlets 200watts 12 3.5mm² 20A
Lights:
Fluorescent TW #
Lights 20 watts 14 2.0mm² 15A
TW #
Halogen lights
40 watts 14 2.0mm² 15A
TW #
Incandescent
100 watts 14 2.0mm² 15A
TW #
Track lights
150 watts 14 2.0mm² 15A
Air con unit 1,980 TW #
1.0 HP watts 10 5.50mm² 30A
2,200 TW #
1.5 HP
watts 10 5.50mm² 30A
2,640 TW #
2.0 HP
watts 10 5.50mm² 30A
Water heater 1,000 TW #
SPO watts 10 5.50mm² 30A
8,000 TW # 40A /
Range outlet
watts 08 8.00mm² 50A
Water pump
TW #
½ HP
880 watts 10 5.50mm² 30A
1,780 TW #
1HP
watts 10 5.50mm² 30A
2,000 TW #
Electric stove
watts 10 5.50mm² 30A

38
1,000
Chandelier
watts
Refrigerator 320 watts
Freezer 200 watts
Washing
machine 585 watts
3,000
Dryer
watts
Jacuzzi 1 HP
Water heater 6,000
centralized watts
Ampacity Of Conductors
solid stranded
AWG mm² TW THW IN. Conduit
mm²

16 For wire
stereo
14 2.0 15 15 ½ 15
12 3.5 20 20 ½ 20
10 5.5 30 30 ¾ 20
8 8.0 40 45 ¾ 20
6 14.0 55 65 1’ 25
4 22 70 85 1½ 32
2 30 90 110 1¾ 32
1 38 100 125 1½ 40
0 50 120 145 2” 50
00 60 135 160 2” 50
3/0 80 160 195 2” 50
4/0 100 185 200 2½ 65
250 125 210 255 2½ 65
300 150 240 280 2 ½ 65
400 200 280 330 3” 80
500 250 315 375 3½ 90
650 325 370 435 3½ 90
750 400 405 485 4” 100
1000 500 445 540 4” 100

ELECTRICAL LOAD COMPUTATIONS (RESIDENTIAL)

CKT OTHER
LIGHTS SW VOLTS WATTS AMPS
NOS. LOAD
1 10 11 220 1,000 4.54
2 9 9 220 900 4.09
39
3 6 6 220 600 2.72
4 5 220 1,000 4.54
5 11 220 2,200 10.00
6 2 220 400 1.81
Stove 3
7 1-SPO 220 3,000 13.63
KW
Bell or
8 1-SPO 220 50 0.22
buzzer
Total 41.55 A

Computations:

TOTAL FLOOR AREA = 135m²

135m² @ 24 W / SW 3,240 W

Small Appliance load 3,000 W

6,240 W

First 3,000 W @ 100% DF 3,000 W

Renaming 3,240 W @ 35% DF 1,134 W


4,134 W

4,134 = 18.79 A
220 V

1 Electric stove 3W 13.63


1 Buzzer 0.22 A
IT = 32.64 A

Use 2 # 14.0 mm² THW wire in 25 mmd RSC 4.55 A / 65 A

Watts = Volts x Ampere W=EI

Ampere = watts I= W
Volts V

1 horsepower = 746 watts

volts = volt
ampere

CARRIER AIR CONDITION

MODEL NOS BTV/HR HORSE POWER Suggested room


space
WC 90 RCY 9,000 1 hp Up to 18 m²

40
WC 120 RCY 12,000 1 ½ hp 18 to 24 m²
WC 120 RCY 12,000 1 ½ hp 18 to 24 m²
WC 150 RCY 15,000 1 ½ hp 24 to 30 m²
WC 180 RCY 18,000 2 hp 30 to 36 m²

Cabinet Dimension H (40mm) x (w) 658 mm

Split type air con /package = 20m² / tons

B. Rough- in

1. PVC pipes

a. ½” to 3” SCH. 40 Neltex, Atlanta, super

b. PVC cement

c. PVC coupling ½” to 3”

d. PVC Elbow ½” to 3”

2. RSC pipe and fitting per plan/brand –Maru– ichi ,setsuyo

a. 3/4” to 3” – entrance / up to panel verify

b. RSC elbow

c. RSC coupling

d. LB /LR

e. Entrance cup

f. Locknuts and bushing

3. secondary rack – power and telephone

4. Solderless connector

Angle connector

Straight connector

5. RSC conduit clamp

6. metal moulding

7. circular loam ¼” to ¾”

8. THW, THHN, TW wires solid or stranded 150 LM/roll

9. G.I. k#16 – guide wires

41
10. P.D. jacketed telephone wires #22/3 flat cord

11. BX wire #12/2 / #123/2 / #8/2’

12. Intercom wires

13. telephone steel cabinets GA # 16 or GA #18

telephone cable wires for 3 storey building

14. pull box (steel ) per plan

15. wire gutter per plan (distribution panel)

16. utility box local or imprinted, plastic or metal GA #16 -#18

17. junction box 4” x 4”

18. 4 11/6 x 4 11/16 square box with ½” and ¼” K.O.

19. PVC Tape or rubber tapes

20. Wiring devices

a. Switches – National , Veto or Mikosha

Flush mounted

a. One gang switch with cover complete

b. Two gang switch with cover complete

c. Three gang switch with cover complete

d. Three way switch

e. Dimmer switch

b. Convenience outlets – ordinary duplex

a. Weather proof outlet

b. Water heater

c. Floor c. outlet

d. Range outlet

e. Air con outlet

f. Microwave oven outlet

c. Door bell and buzzer /chime

d. Telephone outlet cover


42
e. Blank cover

f. Fire alarm bell and station

g. Intercom set band- air phone

h. Smoke detectors

i. Camera monitor

j. CATV antenna – “Winegard” w/ splitter, booster an accessories

k. Lighting panel – “Flush-type or flush mounted enclosure” circuit

breaker plug in or bolt-on

l. Safety switch

m. Double throw switch – emergency generator

n. AVR – automatic voltage regulator

o. Emergency lights.

p. Lighting fixtures

Note: most often owner supplied materials installation done

by contractor

q. Lighting arrester Verify Brand

S. Plumbing works

A. Cold water consumption

Type of building gallons/person/day


Residence – average 50
Residence – average 100
Apartment – low rent 75
Apartment – high rent 100
Hotels 100
Office buidings 25

MWSS WATER METER TAPPING

43
Size of Nos. of units per connection
¾” ½” ¾”
1” 1-2
1 ¼” 3-5 1-2
1 6-9 3-4 1-2 1-2
½” 10-15 5-6 3 3 1-2
2 16-32 7-11 4 4 3 2 1

B. Rough –in

1. PVC pipes and fittings S-40

2. Cast iron pipes and fittings

C. Checklist PVC PIPES OR OTHER TYPES

1. Pipes x 10’ length

2. Cast iron x 5’ (length)

3. WYE

4. TEE

5. Double TEE

6. ¼ bend

7. 1/8 bend

8. P-trap with or without clean out hole

9. coupling

10. Double WYE

11. Tap Tee

12. PVC cement

13. Lead sheet

14. Epoxy A and B set

15. PLBG. Oakum

D. Waterlines: Check hot or cold lines

1. GI pipe and fittings local or japan

1. ½ - 12mm

44
2. ¾ - 15mm

3. 1” – 25mm

4. 1 ¼” – 32mm

2. Fittings

1. GI elbow

2. St. Elbow

3. TEE

4. Union Patente

5. TEE – reducer

6. GI bushing

7. GI nipple

3. Water tank fittings per plan

4. septic tank and cistern tank

V= L x W x H x 264 gals.= Cu. Meter

Septic tank – design standard (minimum)

National Plumbing Code

Nos. of persons Inside depth of chamber


Served Depth Width Length
10+5 1.20 1.10 1.80
20 1.20 1.25 2.50
25 1.20 1.40 2.80
30 1.30 1.50 3.00
35 1.30 1.60 3.20
40 1.40 1.65 3.30
45 1.40 1.75 3.50
50 1.50 1.80 3.60
60 1.50 1.95 3.80
70 1.50 2.00 4.00
80 1.60 2.20 4.40
90 1.80 2.30 4.60
100 1.80 2.50 5.00
Note: leaching well is aproximately ½ of volume of digestion chamber

Capacity of cylindrical tanks

Diameter 2 x 0.7854 x length = volume

If cubic feet x 7.4805 = nos. of gallons

45
1. Cement

2. Sand

3. Gravel

4. Forms

5. 4 ¼” tiles (white)

5. Water heater

6. Shower values and heads

1. Single shower valve

2. Three valve diverter

7. Lavatory centerset faucet

8. Kitchen sink faucet

9. hosebibb – faucet with or without HB

10. Gate valves ½” ¾”

11. Angle valves / check velves

12. Siamese twin (fire hydrant) 3”x2 ½ x2 ½

2½x2½x2½

13. Fire hose cabinet with F. extinguisher

14. Water meters – main, branches

Note verify MWSS tapping of waterline to building

15. Accessories

1. floor drain/ strainer

2. roof drain

3. grease traps

4. drinking fountain and other per plan

5. special equipment

16. PLUMBING FIXTURES Verify Specs

1. waterclosets
46
2. lavatories

3. bidet

4. urinals

5. kitchen sink

6. bathtub

7. soap holder

8. paperholder

9. toilet

10. dispenser

11. shampoo & tooth brush holder

12. towel bar

13. mirror

14. medicine cbinet

15. curtain rods

T. Painting works

A. Painting works
47
1. Masonry Surfaces – latex

2. finishes washout and others – repellent

3. wood surfaces – cabinets/ closets/ceiling/walls

4. wood preserver

5. steel windows/ grilles – qde

6. varnish

7. automotive lacquer finish

8. natural oil finish

9. special finishes

1. acre – cast

2. spraytex

3. Alladin finish

10. roofing – Portland cement paintor Acrylic Paint

B. Overhead/ Contingencies

- note: contractor’s tax

- insurance

- permits – locational clearances

- power and water for construction

- barangay clearance

Updated Jan 12, 2006 FOR RESEARCH & IMPROVEMENTS