Flexible thinking for capital projects

Conventional project planning and execution may not be the best approach for
gas treating and sulphur recovery installations

Mark Duisters Jacobs Comprimo Sulfur Solutions

T
he most common way be prevented by putting more
to execute gas treat- emphasis on the earliest pro-
ing and sulphur recov- Phase 1 ject phases. This article is writ-
Initiation
ery projects is to follow the ten to inspire decision makers
project steps as laid out by to rethink the approach for
the major global oil and gas executing gas treating and
Phase 2
companies. This means that Conceptual sulphur projects.
after feasibility and concep-
tual studies, technology selec- Project phasing
tion and compiling a process Phase 3 Among projects in almost
design package, the project Definition all technical and engineering
moves to a FEED contrac- driven industries, from food
tor and later on to an EPC and pharma to the entertain-
contractor. The basic line-up Phase 4 ment industry, refineries,
of gas treating and sulphur Engineering and procurement terminals, buildings, govern-
recovery units is pretty well mental infrastructure and
known in the industry which automotive, the thing that
makes it tempting for owners Phase 5 stands out in the oil and gas
Construction
to keep feasibility and concep- industry is the rigid way of
tual phases extremely short. following the capital invest-
This approach leaves a lot of ment work process, mainly
Phase 6
available specialist knowledge Start-up developed for mid-size and
and insights untapped whilst large refinery projects.
asking general engineering Most owners use project
contractors to go to the mar- Phase 7 phasing similar to the exam-
ket for pricing on equipment Close-out ple shown in Figure 1 to
items like columns, main steer their capital investment
burners, mixing chambers, process.
reactors, condensers, and so Figure 1 Conventional project phasing This concept makes a lot of
on. sense for projects where the
This article will provide further background exact configuration is yet to be figured out and
and focus on the execution of gas treating and where combinations of equipment are not part of
sulphur recovery projects, with a view to com- a standard line-up.
parable projects in other industries including However, in gas treating and sulphur recov-
formats like engineering and procurement (EP) ery projects, typically the hardware is pretty
and modular delivery. Also, special features of much similar; the main differences can occur in
gas treating and sulphur recovery projects are the smart use of utilities, catalyst and solvents or
highlighted, including project issues that seem to integration of these systems.
occur over and over again and how they could The line-up, determined by the bidders dur-

www.digitalrefining.com/article/1001364 May 2017 1


ing the bidding phase for the In this period, it will be deter-
technology, rarely changes mined what all other parame-
Pre EPC
during the subsequent phases. <1% ters in the plant’s lifetime will
The various hardware items look like.
have been estimated, bought Engineering Skipping an extra well-test
3-5%
and built many times before. or taking some extra sam-
Therefore a full FEED phase Hardware and ples may save a little time
including obtaining price quo- installation and money during the defini-
20-25%
tations from the market does tion phase of the project, but
not make a lot of sense and the reasoning above makes it
will hardly add any value clear that assumptions taken
compared to estimating infor- instead of those tests or a
mation that could be pro- thorough study will have
vided by the licensors as a huge consequences for the
Consumables
scope item of the technology 40-50% use of consumables (including
package. energy) and effectiveness of
Maintenance and operations
This way of thinking con- 25-30% the installed hardware.
nects to the way more or less
standard units are handled in Lessons learned?
the chemical industry. Units Figure 2 Plant life cycle costs Typically, licensors’ special-
like a sulphuric acid unit or ists are heavily involved in
a regenerative thermal oxida- commissioning and start-up
tion (RTO) unit are bought as of the unit using their pro-
a product rather than a pro- cess licences. In cases where
cess installation. generic engineering contrac-
A lot of information from tors are used for FEED and
previously built installations EPC work, basic mistakes
is available in the licensors’ keep occurring, resulting
databases, provided inputs from lack of real understand-
to preparation of the plant ing of the units. Even when
owners’ investment plans can Figure 3 Modular construction can offer those aspects are clearly
be generated very efficiently, many advantages spelled out and explained
and has the benefit of being during the PDP phase, the
directly connected to specialists in the specific experts at Jacobs Comprimo Sulfur Solutions
technology. keep running into typical errors such as:
Besides the availability of data to support cap- • Feed gas quantity deviates more than 40%
ital estimates, significant quality improvements from design basis.
can also be derived by tapping into the licensor’s • Feed gas composition deviates substantially
knowledge. from design basis.
Thinking of a sulphur recovery unit (SRU) as • Importance of very low pressure drop not
a product automatically leads to putting more understood, resulting in too long pipe routes and
emphasis on what product to buy. Translating equipment not located correctly.
this to the capital investment process highlights • Reactor internals seem simple; risk of damaging
another thing that is noticed in other industries: catalyst not recognised.
significantly more time and effort is put into the • Lines sloping the wrong way, resulting in cor-
earliest project phase, to make sure the right pro- rosion issues.
ject is being scoped. In a typical gas treating and • Connections between reactors and condensers
sulphur recovery project, the money spent on the not designed for (very) high temperatures.
phase before EPC execution is less than 1% of the • Importance of temperature control is not
plant’s life cycle cost (see Figure 2). Time spent always understood, resulting in temperature ele-
on tests and studies to determine the right basis ments mounted the wrong way and/or in the
for process design is only a fraction of that 1%. wrong location.

2 May 2017 www.digitalrefining.com/article/1001364


• Not able to deal with complexity of advanced nected. Each module is fabricated in a workshop
burner control. and contains all the steel, equipment, piping and
• Sample points for proper process monitoring instrumentation. In addition, tracing, insulation,
mounted in inaccessible locations. conduit, cable trays, and cabling are already
The cost of increasing the scope of the PDP installed. Commissioning, inspection and testing
package to make sure critical elements are are completed as much as possible before the
embedded in the design at a very early stage is modules are shipped out.
easily compensated by reduced redo in the field. Next to significant savings in time and money
An extended licensor package can even rule during the front end loading phases, this also
out the need for a FEED phase, saving significant brings the advantage of keeping responsibili-
time and money by ruling out a complete ten- ties in one place and prevents finger pointing
dering sequence. between PMC, FEED contractor, EPC contractor
It almost needs no explanation that when at and licensor. Especially for smaller, add-on units,
the moment of commissioning and start-up it it takes little imagination to understand that the
turns out that feed gas conditions are signifi- advantages of keeping responsibilities in one
cantly different from the design basis, needless place and have the licensing, design and delivery
capital is wasted and a lot of cost and effort is of the skid carried out by subject experts, easily
needed to correct for hasty decisions taken at the outweighs the possible advantages of going for
early stages of project planning. competitive tendering two or three times, intro-
ducing coordination and interfacing tasks to the
Going modular owner’s turnaround organisation.
In cases where the licensor also has capabilities When an SRU is part of a larger capital
to deliver the whole unit or part of the unit, the investment, like a refinery expansion, the ben-
thought of buying a product instead of going efits of this approach become even larger. The
through all the traditional project execution main reason for this is that sulphur recovery
stages can be taken even further. For smaller in most cases is not a core refinery process but
units, a packaged unit or modular approach does require specialist knowledge. By putting
would be the ultimate result of this line of think- the responsibility for such ‘off-plot’ units in the
ing where process guarantees, execution and hands of specialists, the main EPC contractor can
delivery are all in one place. focus on the core process units whilst making
For gas treating and sulphur recovery projects, sure the gas treating and sulphur recovery block
this would apply to smaller treaters and SRUs, receives the attention it deserves.
but especially for add-on units like amine enrich- Advantages of modular construction are many
ment units, extra (Super)Claus stages or scrubber and can be summarised as follows:
type units to lower SO2 emissions. • Using off-site labour that generally is cheaper
Those relatively small add-on units with a total and more readily available. This is especially
investment cost well below $10 million are in relevant when there are big expansion projects
most cases to be integrated during a plant turn- going on in the region.
around of 3-4 weeks. Looking at those units as • Efficient fabrication in a workshop type envi-
package units will make preparation for turna- ronment. Important factors for this are better
round much easier and will shorten the duration controlled working conditions and specialisation
of these projects considerably. in the workshop.
Modular construction can offer many advan- • Enhanced safety because working at heights
tages, including improved safety, lower cost, can be avoided or is well controlled (safe plat-
faster schedules and controlled quality. Sulphur forms), the work area is easily accessible,
recovery plants up to a certain capacity lend weather conditions cannot cause unsafe condi-
themselves well to modular construction because tions and there are no (uncontrolled) dangerous
of their size and geometry. activities near the work area.
In modular construction, a plant is built in • Improved quality with a consistent workforce
smaller parts or modules, typically at an off- in a controlled environment without extraneous
site location. The modules are transported to influences.
the final destination, put in place and intercon- • Time saving by preventing delays due to

www.digitalrefining.com/article/1001364 May 2017 3


weather conditions and permitting issues, and contracts with independent licensors, FEED and
by performing off-site construction and on-site EPC contractors are involved.
preparation in parallel. The ultimate way of tapping all the knowledge
• Reduced cost that arises from the higher effi- available on a technology is to make the licensor
ciency that can be achieved in well-conditioned responsible for the entire delivery. For smaller
and specialised shops. Also standardisation con- and add-on units treating a gas treating or sul-
tributes to lower cost and the cost for capital is phur recovery project, the purchase of a product
lower because of improved schedules. makes sense as those smaller units can be mod-
• Testing, inspection and pre-commissioning will ularised and add-on units can be delivered as
generally be cheaper when done in the shop. packaged units.
• One aspect that is often overlooked is that by The overall conclusion is that allowing some
doing the construction off-site and away from flexibility in the thinking around capital invest-
day to day operations, scope growth can be ment processes can save a lot of time, money
prevented. and effort when a tailored approach is followed
for planning gas treating and sulphur recovery
Conclusion projects.
Established technologies like gas treating, sulphur
recovery and tailgas treating carry the risk of tak-
Mark Duisters is Project Director with Jacobs Comprimo Sulfur
ing the feasibility and concept phase too lightly. Solutions and Petrochemical Technologies. He has been serving
Getting the design basis right is of extreme the industry for more than 25 years and holds degrees in
importance for licensed processes because they engineering and in management and organisation.
are hardly challenged and changed during the
subsequent project phases.
LINKS
Once the licensor is selected, carrying expert
knowledge, this article encourages use of this More articles from: Jacobs Comprimo Sulfur Solutions
knowledge for more than just checking main
More articles from the following categories:
equipment drawings. Lessons learned from Gas Processing and Treatment
many plant checks and start-ups are available; Sulphur Removal and Recovery
too often this knowledge is not used because of