EVENT NO (1) DELAY CAUSED BY ADVERSE PHYSICAL CONDITION (OBSTRUCTIONS) 590 25-May-16 07-May-18 25-May-16 A 14-Jun-18 4
DELAY-EVENT-1000 Misc.001 Obstruction in the proposed route 18 100% 27-Aug-16 20-Sep-16 27-Aug-16 A 20-Sep-16 A
DELAY-EVENT-1090 Misc.118 Obstrution due to DEWA pillar box 10 100% 17-Nov-16 01-Dec-16 17-Nov-16 A 19-Nov-16 A
DELAY-EVENT-1100 Mis.503 obstruction due to fence in area 7 100% 22-Dec-16 01-Jan-17 22-Dec-16 A 27-Dec-16 A
DELAY-EVENT-1040 Misc.175 the route having obstruction an work was put 42 100% 14-Mar-17 02-May-17 14-Mar-17 A 02-May-17 A
on hold for 2 times
DELAY-EVENT-1120 Misc.854 the Line is Obstructed DN1200 & DN300 water 10 100% 04-May-17 18-May-17 04-May-17 A 09-May-17 A
line
DELAY-EVENT-1110 Misc.213/1 Obstruction due fence, due existing DB and 23 100% 16-Apr-17 18-May-17 16-Apr-17 A 18-May-17 A
constrution material in the proposed route
DELAY-EVENT-1160 Misc. 636 the route obstructed by building materials 4 100% 03-Jun-17 07-Jun-17 03-Jun-17 A 14-Jun-17 A
DELAY-EVENT-1140 Misc.257 work obstructed by fence and materials 25 100% 29-May-17 04-Jul-17 29-May-17 A 29-Aug-17 A
DELAY-EVENT-1200 Misc. 860 obstruction caused by palm tree 14 100% 24-Aug-17 13-Sep-17 24-Aug-17 A 12-Sep-17 A
DELAY-EVENT-1230 Misc.902, Obstruction due tree in the proposed line 10 100% 07-Sep-17 21-Sep-17 07-Sep-17 A 21-Sep-17 A
DELAY-EVENT-1220 Misc.276 obstruction due to fence 14 100% 07-Sep-17 27-Sep-17 07-Sep-17 A 27-Sep-17 A
DELAY-EVENT-1170 Misc.1094, Obstruction due trees and signboard 30 100% 18-Jun-17 31-Jul-17 18-Jun-17 A 25-Nov-17 A
DELAY-EVENT-1190 Misc.447, the villa owner objected on connections 15 94.67% 24-Aug-17 14-Sep-17 24-Aug-17 A 31-Jan-18 -20 Misc.447, the villa owner objected on conn
DELAY-EVENT-1030 Misc.760 route has obstruction and Objected by locals 30 0% 01-Jun-17 15-Jul-17 01-Jun-17 A 15-Mar-18 -25 Misc.760 route has obstruction and Ob
DELAY-EVENT-1270 HC.192, Obstruction to scaffolding and fence 5 100% 24-Sep-16 01-Oct-16 24-Sep-16 A 25-Sep-16 A
DELAY-EVENT-1280 HC -582obstruction due to concrete block 4 100% 06-Oct-16 11-Oct-16 06-Oct-16 A 08-Oct-16 A
DELAY-EVENT-1290 HC. 168, Obstruction due to scaffolding and fence 6 100% 18-Oct-16 26-Oct-16 18-Oct-16 A 20-Oct-16 A
DELAY-EVENT-1320 HC-814, Obstruction due temporary fencing and 6 100% 07-Nov-16 15-Nov-16 07-Nov-16 A 07-Dec-16 A
materials in area
DELAY-EVENT-1330 HC.526, Obstruction due scaffolding 4 100% 07-Dec-16 12-Dec-16 07-Dec-16 A 12-Dec-16 A
DELAY-EVENT-1340 HC-861 Obstruction due scaffolding 7 100% 22-Dec-16 01-Jan-17 22-Dec-16 A 07-Jan-17 A
DELAY-EVENT-1300 HC-615, Obstruction due to scaffolding and fence 6 100% 27-Oct-16 05-Nov-16 27-Oct-16 A 10-Jan-17 A
DELAY-EVENT-1390 HC.672, Obstruction do existing fence, scaffoldin & 7 100% 03-Jan-17 12-Jan-17 03-Jan-17 A 17-Jan-17 A
electrical BD
DELAY-EVENT-1420 HC. 478 Obstruction due to scaffolding 4 100% 30-Jan-17 04-Feb-17 30-Jan-17 A 04-Feb-17 A
DELAY-EVENT-1380 HC.907, obstruction to existing fence 4 100% 27-Dec-16 01-Jan-17 27-Dec-16 A 06-Feb-17 A
DELAY-EVENT-1400 HC.1035 Obstruction due to scaffolding 6 100% 25-Jan-17 02-Feb-17 25-Jan-17 A 09-Feb-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 1 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
DELAY-EVENT-1370 HC.465, Obstructin due exisiting fence 5 100% 03-Jan-17 10-Jan-17 03-Jan-17 A 11-Feb-17 A
DELAY-EVENT-1410 HC.973, Obstruction due to scaffolding 6 100% 28-Jan-17 05-Feb-17 28-Jan-17 A 13-Feb-17 A
DELAY-EVENT-1350 HC.458 obstruction due existing trees 8 100% 25-Dec-16 04-Jan-17 25-Dec-16 A 18-Feb-17 A
DELAY-EVENT-1440 HC-1133, obstruction due over flow meter 5 100% 23-Feb-17 02-Mar-17 23-Feb-17 A 26-Feb-17 A
DELAY-EVENT-1450 HC.652, obstruction due to garden and owner strictly 4 100% 14-Mar-17 19-Mar-17 14-Mar-17 A 19-Mar-17 A
disallow to execute work
DELAY-EVENT-1430 HC.867,Obstruction due to existing fence 7 100% 31-Jan-17 09-Feb-17 31-Jan-17 A 04-Apr-17 A
DELAY-EVENT-1470 HC.922 obstruction due to building materials 7 100% 10-Apr-17 19-Apr-17 10-Apr-17 A 23-Apr-17 A
DELAY-EVENT-1310 Misc.173, 336 Obstructed due to idle parked vehicle 7 100% 07-Nov-16 16-Nov-16 07-Nov-16 A 14-May-17 A
DELAY-EVENT-1520 HC.1325, Obstruction due to fence and materials 6 100% 13-May-17 21-May-17 13-May-17 A 15-May-17 A
DELAY-EVENT-1530 HC. 1469, Obstruction due to scaffolding 4 100% 22-May-17 27-May-17 22-May-17 A 27-May-17 A
DELAY-EVENT-1560 HC.1436, obstructed due to existing materials 7 100% 25-May-17 04-Jun-17 25-May-17 A 30-May-17 A
DELAY-EVENT-1590 HC.1466, obstruction due to materials 7 100% 28-May-17 06-Jun-17 28-May-17 A 06-Jun-17 A
DELAY-EVENT-1570 HC.1636, obstructed due to existing materials and fence 6 100% 27-May-17 04-Jun-17 27-May-17 A 12-Jun-17 A
DELAY-EVENT-1630 HC.1418, obstruction due scaffolding and fencing 4 100% 21-Jun-17 26-Jun-17 25-Jul-17 A 30-Jul-17 A
DELAY-EVENT-1500 HC.1140 & 1435, obstruction due to fence and materials 5 100% 27-Apr-17 04-May-17 27-Apr-17 A 07-Aug-17 A
DELAY-EVENT-1510 HC.1269, obstruction due to fence and materials 8 100% 06-May-17 16-May-17 06-May-17 A 21-Aug-17 A
DELAY-EVENT-1730 HC.1735 Obstruction due to construction materials 5 100% 06-Sep-17 13-Sep-17 06-Sep-17 A 12-Sep-17 A
DELAY-EVENT-1740 HC.1605, obstruction due to electrical panel & fence 11 100% 07-Sep-17 23-Sep-17 07-Sep-17 A 23-Sep-17 A
DELAY-EVENT-1710 HC.1736, Obstruction due water tank to in proposed line 6 100% 02-Aug-17 10-Aug-17 02-Aug-17 A 10-Oct-17 A
DELAY-EVENT-1660 HC.1246, obstruction due fence and concret blocks 5 100% 01-Aug-17 08-Aug-17 01-Aug-17 A 14-Oct-17 A
DELAY-EVENT-1770 HC.1811, Obstruction due to material and fence 4 100% 11-Oct-17 16-Oct-17 11-Oct-17 A 14-Oct-17 A
DELAY-EVENT-1780 HC.1921, obstruction due to commercial vehicle in 2 100% 11-Oct-17 14-Oct-17 11-Oct-17 A 14-Oct-17 A
proposed area
DELAY-EVENT-1620 Hc.1336, obstructed due to materials and fence 10 100% 21-Jun-17 05-Jul-17 21-Jun-17 A 19-Oct-17 A
DELAY-EVENT-1650 HC.1592, obstruction due sign board and materials 5 100% 25-Jul-17 01-Aug-17 25-Jul-17 A 21-Oct-17 A
DELAY-EVENT-1540 HC.780,obstructed due to existing materials 6 100% 22-May-17 30-May-17 22-May-17 A 11-Nov-17 A
DELAY-EVENT-1670 HC.1135, Obstruction due DP near FIC 6 100% 01-Aug-17 09-Aug-17 01-Aug-17 A 22-Nov-17 A
DELAY-EVENT-1800 HC.1342, Obstruction caused by Carvan Materials 6 100% 11-Oct-17 19-Oct-17 11-Oct-17 A 05-Dec-17 A
DELAY-EVENT-1640 HC.1714, obstruction due sign board and fencing 8 100% 06-Jul-17 17-Jul-17 06-Jul-17 A 31-Jan-18 34 HC.1714, obstruction due sign board and
DELAY-EVENT-1790 HC.1860, obstruction due to existing fence and 7 100% 22-Oct-17 31-Oct-17 22-Oct-17 A 31-Jan-18 A
temporary labour shelter
DELAY-EVENT-1360 HC.674, obstruction due existing fence and signbarod 277 100% 25-Dec-16 01-Feb-18 25-Dec-16 A 31-Jan-18 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 2 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
DELAY-EVENT-1610 HC.1546, obstruction due to villa owner 8 100% 11-Jun-17 21-Jun-17 11-Jun-17 A 31-Jan-18 A
DELAY-EVENT-1480 HC.625 obstruction due to existing fence & materials 4 0% 25-Apr-17 30-Apr-17 25-Apr-17 A 05-Feb-18 30 HC.625 obstruction due to existing fence
DELAY-EVENT-1720 HC.1749, obstruction due to temporary toilet in the 16 75% 12-Aug-17 03-Sep-17 12-Aug-17 A 05-Feb-18 30 HC.1749, obstruction due to temporary to
proposed route
DELAY-EVENT-1490 HC.811, Obstruction due to scaffolding 8 100% 26-Apr-18 07-May-18 26-Apr-18 A 14-Jun-18 A
DELAY-EVENT-1930 PCO.260, Obstruction cause by Construction materials 6 100% 15-Jun-16 23-Jun-16 15-Jun-16 A 16-Jun-16 A
DELAY-EVENT-1820 PCO.049, Obstruction due material in the route 9 100% 10-Aug-16 22-Aug-16 10-Aug-16 A 22-Aug-16 A
DELAY-EVENT-1840 PCO.010 Obstruction caused by debris wood and 5 100% 21-Sep-16 28-Sep-16 21-Sep-16 A 12-Oct-16 A
surplus
DELAY-EVENT-1850 PCO.047, Obstruction due to temporary toilet in the 6 100% 04-Oct-16 12-Oct-16 04-Oct-16 A 17-Oct-16 A
proposed route
DELAY-EVENT-1910 PCO233, obstruction due to mateials and fence 7 100% 19-Jun-16 28-Jun-16 19-Jun-16 A 30-Oct-16 A
DELAY-EVENT-1860 PCO-160Obstruction due Green built 6 100% 31-Oct-16 08-Nov-16 31-Oct-16 A 17-Nov-16 A
DELAY-EVENT-1870 PCO.156, obstrution due to existing fence and 4 100% 22-Dec-16 27-Dec-16 22-Dec-16 A 27-Dec-16 A
scaffolding
DELAY-EVENT-1880 PCO.149, obstruction due to trees in proposed route 6 100% 25-Dec-16 02-Jan-17 25-Dec-16 A 27-Dec-16 A
DELAY-EVENT-1890 PCO.032, Obstruction due to existing fence 4 100% 25-Dec-16 29-Dec-16 25-Dec-16 A 17-Jan-17 A
DELAY-EVENT-1250 PCO-135, the site has obstructions 7 100% 22-Dec-16 01-Jan-17 22-Dec-16 A 16-Apr-17 A
DELAY-EVENT-1900 PCO.271 obstruction due to materials and fence 5 100% 02-May-17 09-May-17 02-May-17 A 08-Jun-17 A
DELAY-EVENT-1020 PCO-292 Obstruction were recored due change in FIC 5 100% 11-Jun-17 18-Jun-17 11-Jun-17 A 22-Jun-17 A
locations
DELAY-EVENT-2000 PCO.268, Obstructon due to construction materials 6 100% 19-Jun-17 27-Jun-17 19-Jun-17 A 15-Jul-17 A
DELAY-EVENT-2050 PCO.241, obstrution due scaffolding in ther route 4 100% 10-Sep-17 14-Sep-17 10-Sep-17 A 13-Sep-17 A
DELAY-EVENT-2040 PCO.431, obstruction due to palm tree 6 100% 07-Sep-17 16-Sep-17 07-Sep-17 A 04-Oct-17 A
DELAY-EVENT-1990 PCO.112, obstruction due to villa owner refuse to remove 5 100% 24-May-17 31-May-17 24-May-17 A 26-Oct-17 A
the tree
DELAY-EVENT-1950 PCO.122, obstruction casued by materials and fence 6 100% 25-May-16 02-Jun-16 25-May-16 A 31-Jan-18 A
DELAY-EVENT-1960 PCO.227, obstruction caused by trees and fence 8 100% 24-May-17 04-Jun-17 24-May-17 A 31-Jan-18 A
DELAY-EVENT-1980 PCO.115, obstruction due existing trees 7 100% 25-May-17 04-Jun-17 25-May-17 A 31-Jan-18 A
DELAY-EVENT-2030 PCO.229, Obstruction due to building materials 6 100% 07-Aug-17 15-Aug-17 07-Aug-17 A 31-Jan-18 A
DELAY-EVENT-2010 PCO.218, obstruction due to palm tree 4 0% 21-Jun-17 26-Jun-17 21-Jun-17 A 05-Feb-18 30 PCO.218, obstruction due to palm tree
DELAY-EVENT-1830 PCO.013, Obstruction due Palm trees falling in the area 4 0% 08-Sep-16 13-Sep-16 08-Sep-16 A 21-Feb-18 18 PCO.013, Obstruction due Palm trees
EVENT NO (2) DELAY CAUSED BY AMENDMENT IN DESIGN SEVERAL TIMES 383 02-Jul-16 11-Jan-18 02-Jul-16 A 24-Apr-18 -32
DELAY-EVEN2-1000 Mis.001,Design amended several times 190 100% 02-Jul-16 04-Apr-17 02-Jul-16 A 04-Apr-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 3 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
DELAY-EVEN2-1070 Misc.343, Drawing approval for DEWA 14 100% 28-Sep-17 18-Oct-17 28-Sep-17 A 18-Oct-17 A
DELAY-EVEN2-1010 Misc.002, Hotel management not agree with intial layout 22 100% 24-Sep-17 25-Oct-17 24-Sep-17 A 25-Oct-17 A
DELAY-EVENT3-1000 Misc.007 Design amended several time and still From 221 100% 23-Feb-17 11-Jan-18 23-Feb-17 A 31-Jan-18 -183 Misc.007 Design amended several time a
MH6- MH10 Design yet not finalized
DELAY-EVEN2-1020 Misc.003, Drawings approval 14 0% 12-Dec-17 01-Jan-18 12-Dec-17 A 20-Feb-18 -86 Misc.003, Drawings approval
DELAY-EVEN2-1050 Misc.213/1 Drawings approval/Changed 58 0.69% 22-Jul-17 14-Oct-17 22-Jul-17 A 24-Apr-18 -179 Misc.213/1 Drawings approval/Cha
EVENT NO (3) DELAY IN NOC 'S APPROVAL (OBJECTION/REJECTION) 260 15-Nov-16 04-Oct-17 15-Nov-16 A 10-Jan-18 A
DELAY-EVENT3-1080 Mic.008 some portion of the work was put on hold 92 100% 15-Nov-16 05-Mar-17 15-Nov-16 A 05-Mar-17 A
DELAY-EVENT3-1050 Misc.148 NOC approval in pending 10 100% 25-May-17 11-Jun-17 25-May-17 A 10-Jun-17 A
DELAY-EVENT3-1060 Misc.140, NOC approval in pending 139 100% 09-Apr-17 04-Oct-17 09-Apr-17 A 04-Oct-17 A
DELAY-EVENT3-1070 Misc.007, NOC for NDRC section Section is recently 15 100% 23-Feb-17 12-Mar-17 23-Feb-17 A 10-Jan-18 A
approved and some portion of the work is still not yet
finalized
PRECONSTRUCTION 584 21-Mar-16 31-Jan-18 21-Mar-16 A 31-Jan-18 42
PRE-MOB-110 Setup Site accommodation & facilities 30 100% 29-Mar-16 02-May-16 29-Mar-16 A 02-May-16 A
PRE-INS-110 General recurring requirements 512 100% 21-Mar-16 07-Nov-17 21-Mar-16 A 31-Jan-18 -34 General recurring requirements
MISC-008 IRRIGATION MAIN LINE FOR AL QUDRA ROAD 632 02-Apr-16 09-Apr-18 02-Apr-16 A 23-Apr-18 -28
DEFINED WORKS-MISC-008 632 02-Apr-16 09-Apr-18 02-Apr-16 A 09-Apr-18 -18
PRECONSTRUCTION 574 02-Apr-16 31-Jan-18 02-Apr-16 A 31-Jan-18 -34
NOI/NOCs SUBMISSIONS 21 02-Apr-16 25-Apr-16 02-Apr-16 A 25-Apr-16 A
SUBMITTALS 11 02-Apr-16 13-Apr-16 02-Apr-16 A 13-Apr-16 A
QUD-NOC-100 Prepare & Submit NOC-DEWA 7 100% 02-Apr-16 09-Apr-16 02-Apr-16 A 09-Apr-16 A
QUD-NOC-110 Prepare & Submit NOC-ETISALAT 7 100% 02-Apr-16 09-Apr-16 02-Apr-16 A 09-Apr-16 A
QUD-NOC-120 Prepare & Submit NOC-DU 7 100% 03-Apr-16 10-Apr-16 03-Apr-16 A 10-Apr-16 A
QUD-NOC-130 Prepare & Submit NOC-DUBAI MUNICIPALITY 7 100% 03-Apr-16 10-Apr-16 03-Apr-16 A 10-Apr-16 A
QUD-NOC-140 Prepare & Submit NOC-TOWN PLANNING 7 100% 04-Apr-16 11-Apr-16 04-Apr-16 A 11-Apr-16 A
DEPARTMENT
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 4 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
QUD-NOC-150 Prepare & Submit NOC-TABREED 7 100% 04-Apr-16 11-Apr-16 04-Apr-16 A 11-Apr-16 A
QUD-NOC-160 Prepare & Submit NOC-GHQ ARMED FORCES 7 100% 05-Apr-16 12-Apr-16 05-Apr-16 A 12-Apr-16 A
QUD-NOC-170 Prepare & Submit NOC-CIVIL DEFENCE 7 100% 05-Apr-16 12-Apr-16 05-Apr-16 A 12-Apr-16 A
QUD-NOC-180 Prepare & Submit NOC-ENVIRONMENTAL AGENCY 7 100% 05-Apr-16 12-Apr-16 05-Apr-16 A 12-Apr-16 A
QUD-NOC-190 Prepare & Submit NOC-RTA 7 100% 06-Apr-16 13-Apr-16 06-Apr-16 A 13-Apr-16 A
QUD-NOC-200 Prepare & Submit NOC-DUBAI TRAFFIC POLICE 7 100% 06-Apr-16 13-Apr-16 06-Apr-16 A 13-Apr-16 A
DEPT
APPROVALS 14 10-Apr-16 25-Apr-16 10-Apr-16 A 25-Apr-16 A
QUD-NOC-210 NOC Approvals-DEWA 10 100% 10-Apr-16 20-Apr-16 10-Apr-16 A 20-Apr-16 A
QUD-NOC-250 NOC Approvals-TOWN PLANNING DEPARTMENT 10 100% 12-Apr-16 23-Apr-16 12-Apr-16 A 23-Apr-16 A
QUD-NOC-270 NOC Approvals-GHQ ARMED FORCES 10 100% 13-Apr-16 24-Apr-16 13-Apr-16 A 24-Apr-16 A
QUD-NOC-310 NOC Approvals-DUBAI TRAFFIC POLICE DEPT 10 100% 14-Apr-16 25-Apr-16 14-Apr-16 A 25-Apr-16 A
QUD-MOB-110 Setting out / Exposing existing Services 21 100% 13-Apr-16 08-May-16 13-Apr-16 A 08-May-16 A
QUD-SPD-110 Review & Approve Shop Drawings 14 100% 19-Apr-16 05-May-16 19-Apr-16 A 05-May-16 A
QUD-MTR-110 Review & Approve Material Submittals 14 100% 30-Apr-16 16-May-16 30-Apr-16 A 16-May-16 A
QUD-MTS-110 Review & Approve Method Statements 7 100% 19-Apr-16 27-Apr-16 19-Apr-16 A 27-Apr-16 A
QUD-CH-120 Base Units & Walls 11 100% 24-May-16 06-Jun-16 24-May-16 A 06-Jun-16 A
QUD-CH-130 Installation of Valves & Fittings 11 100% 29-May-16 11-Jun-16 29-May-16 A 11-Jun-16 A
QUD-CH-180 Base Units & Walls 10 100% 15-Jun-16 27-Jun-16 15-Jun-16 A 27-Jun-16 A
QUD-CH-190 Installation of Valves & Fittings 10 100% 20-Jun-16 02-Jul-16 20-Jun-16 A 02-Jul-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 6 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
QUD-CH-220 Excavation 10 100% 23-Jun-16 05-Jul-16 23-Jun-16 A 05-Jul-16 A
QUD-CH-240 Base Units & Walls 10 100% 27-Jun-16 09-Jul-16 27-Jun-16 A 09-Jul-16 A
QUD-CH-250 Installation of Valves & Fittings 10 100% 02-Jul-16 13-Jul-16 02-Jul-16 A 13-Jul-16 A
QUD-CH-300 Base Units & Walls 10 100% 09-Jul-16 20-Jul-16 09-Jul-16 A 20-Jul-16 A
QUD-CH-310 Installation of Valves & Fittings 10 100% 13-Jul-16 25-Jul-16 13-Jul-16 A 25-Jul-16 A
QUD-CH-360 Base Units & Walls 10 100% 21-Jul-16 01-Aug-16 21-Jul-16 A 01-Aug-16 A
QUD-CH-370 Installation of Valves & Fittings 10 100% 23-Jul-16 02-Aug-16 23-Jul-16 A 02-Aug-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 7 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
QUD-CH-390 Covers & Frames 10 100% 30-Jul-16 09-Aug-16 30-Jul-16 A 09-Aug-16 A
QUD-CH-420 Base Units & Walls 10 100% 20-Nov-17 02-Dec-17 20-Nov-17 A 07-Dec-17 A
QUD-CH-430 Installation of Valves & Fittings 10 100% 25-Nov-17 06-Dec-17 25-Nov-17 A 12-Dec-17 A
QUD-PL-400 Dewatering (if required) 20 0% 31-Jan-18 22-Feb-18 31-Jan-18 22-Feb-18 -7 Dewatering (if required)
QUD-PL-420 Bedding and Pipelaying 20 0% 03-Feb-18 25-Feb-18 03-Feb-18 25-Feb-18 -4 Bedding and Pipelaying
QUD-PL-440 Testing and Backfilling 20 0% 07-Feb-18 01-Mar-18 07-Feb-18 01-Mar-18 -4 Testing and Backfilling
QUD-CH-470 Formation & Blinding 11 0% 06-Feb-18 19-Feb-18 06-Feb-18 19-Feb-18 -7 Formation & Blinding
QUD-CH-480 Base Units & Walls 11 0% 08-Feb-18 21-Feb-18 08-Feb-18 21-Feb-18 -7 Base Units & Walls
QUD-CH-490 Installation of Valves & Fittings 11 0% 13-Feb-18 25-Feb-18 13-Feb-18 25-Feb-18 -7 Installation of Valves & Fittings
QUD-CH-510 Covers & Frames 4 0% 27-Feb-18 04-Mar-18 27-Feb-18 04-Mar-18 -7 Covers & Frames
QUD-PL-450 Dewatering (if required) 20 0% 24-Feb-18 18-Mar-18 24-Feb-18 18-Mar-18 -22 Dewatering (if required)
QUD-PL-470 Bedding and Pipelaying 20 0% 26-Feb-18 20-Mar-18 26-Feb-18 20-Mar-18 -6 Bedding and Pipelaying
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 8 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
QUD-PL-490 Testing and Backfilling 20 0% 03-Mar-18 25-Mar-18 03-Mar-18 25-Mar-18 -6 Testing and Backfilling
QUD-CH-530 Formation & Blinding 11 0% 01-Mar-18 14-Mar-18 01-Mar-18 14-Mar-18 -22 Formation & Blinding
QUD-CH-540 Base Units & Walls 11 0% 04-Mar-18 17-Mar-18 04-Mar-18 17-Mar-18 -22 Base Units & Walls
QUD-CH-550 Installation of Valves & Fittings 11 0% 08-Mar-18 20-Mar-18 08-Mar-18 20-Mar-18 -22 Installation of Valves & Fittings
QUD-CH-570 Covers & Frames 4 0% 21-Mar-18 25-Mar-18 21-Mar-18 25-Mar-18 -22 Covers & Frames
QUD-PL-500 Dewatering (if required) 8 0% 24-Feb-18 04-Mar-18 24-Feb-18 04-Mar-18 -34 Dewatering (if required)
QUD-PL-520 Bedding and Pipelaying 8 0% 26-Feb-18 06-Mar-18 26-Feb-18 06-Mar-18 -14 Bedding and Pipelaying
QUD-PL-530 Pipe Surround 8 0% 28-Feb-18 08-Mar-18 28-Feb-18 08-Mar-18 -14 Pipe Surround
QUD-PL-540 Testing and Backfilling 8 0% 03-Mar-18 11-Mar-18 03-Mar-18 11-Mar-18 -14 Testing and Backfilling
QUD-CH-590 Formation & Blinding 5 0% 26-Feb-18 04-Mar-18 26-Feb-18 04-Mar-18 -34 Formation & Blinding
QUD-CH-600 Base Units & Walls 5 0% 28-Feb-18 06-Mar-18 28-Feb-18 06-Mar-18 -34 Base Units & Walls
QUD-CH-610 Installation of Valves & Fittings 5 0% 03-Mar-18 07-Mar-18 03-Mar-18 07-Mar-18 -34 Installation of Valves & Fittings
QUD-CH-630 Covers & Frames 2 0% 10-Mar-18 12-Mar-18 10-Mar-18 12-Mar-18 -34 Covers & Frames
QUD-MIS-130 Connection to the Existing Line 4 0% 19-Mar-18 24-Mar-18 19-Mar-18 24-Mar-18 -34 Connection to the Existing Line
QUD-MIS-100 Overpumping Works 12 0% 10-Mar-18 24-Mar-18 10-Mar-18 24-Mar-18 -34 Overpumping Works
QUD-POS-100 Cleaning & Final Inspection 2 0% 04-Apr-18 07-Apr-18 04-Apr-18 07-Apr-18 -34 Cleaning & Final Inspection
QUD-POS-110 Handing Over 2 0% 05-Apr-18 09-Apr-18 05-Apr-18 09-Apr-18 -34 Handing Over
WO02-NOC-440 Prepare & Submit NOC-ETISALAT 7 100% 25-Jun-16 03-Jul-16 25-Jun-16 A 03-Jul-16 A
WO02-NOC-450 Prepare & Submit NOC-DU 7 100% 26-Jun-16 04-Jul-16 26-Jun-16 A 04-Jul-16 A
WO02-NOC-460 Prepare & Submit NOC-DUBAI MUNICIPALITY 7 100% 26-Jun-16 04-Jul-16 26-Jun-16 A 04-Jul-16 A
WO02-NOC-470 Prepare & Submit NOC-TOWN PLANNING 7 100% 27-Jun-16 05-Jul-16 27-Jun-16 A 05-Jul-16 A
DEPARTMENT
WO02-NOC-480 Prepare & Submit NOC-TABREED 7 100% 27-Jun-16 05-Jul-16 27-Jun-16 A 05-Jul-16 A
WO02-NOC-490 Prepare & Submit NOC-GHQ ARMED FORCES 7 100% 28-Jun-16 06-Jul-16 28-Jun-16 A 06-Jul-16 A
WO02-NOC-500 Prepare & Submit NOC-CIVIL DEFENCE 7 100% 28-Jun-16 06-Jul-16 28-Jun-16 A 06-Jul-16 A
WO02-NOC-510 Prepare & Submit NOC-ENVIRONMENTAL AGENCY 7 100% 28-Jun-16 06-Jul-16 28-Jun-16 A 06-Jul-16 A
WO02-NOC-520 Prepare & Submit NOC-RTA 7 100% 29-Jun-16 07-Jul-16 29-Jun-16 A 07-Jul-16 A
WO02-NOC-530 Prepare & Submit NOC-DUBAI TRAFFIC POLICE 7 100% 29-Jun-16 07-Jul-16 29-Jun-16 A 07-Jul-16 A
DEPT
APPROVALS 18 03-Jul-16 24-Jul-16 03-Jul-16 A 24-Jul-16 A
WO02-NOC-330 NOC Approvals-ETISALAT 14 100% 03-Jul-16 19-Jul-16 03-Jul-16 A 19-Jul-16 A
WO02-NOC-350 NOC Approvals-TOWN PLANNING DEPARTMENT 14 100% 05-Jul-16 21-Jul-16 05-Jul-16 A 21-Jul-16 A
WO02-NOC-380 NOC Approvals-GHQ ARMED FORCES 14 100% 06-Jul-16 23-Jul-16 06-Jul-16 A 23-Jul-16 A
WO02-NOC-420 NOC Approvals-DUBAI TRAFFIC POLICE DEPT 14 100% 07-Jul-16 24-Jul-16 07-Jul-16 A 24-Jul-16 A
WO02-SPD-130 Review & Approve Shop Drawings 12 100% 09-Jul-16 23-Jul-16 09-Jul-16 A 23-Jul-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 10 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WO02-MTR-130 Prepare & Submitt Material Submittals 12 100% 03-Jul-16 17-Jul-16 03-Jul-16 A 17-Jul-16 A
WO02-MTR-140 Review & Approve Material Submittals 12 100% 10-Jul-16 24-Jul-16 10-Jul-16 A 24-Jul-16 A
WO02-MTS-130 Review & Approve Method Statements 6 100% 09-Jul-16 16-Jul-16 09-Jul-16 A 16-Jul-16 A
WO02-250 Shuttering,Reinfrocement & Casting of Foundation 6 100% 11-Aug-16 18-Aug-16 11-Aug-16 A 18-Aug-16 A
WO02-260 Shuttering,Reinfrocement & Casting of Base Slab 7 100% 18-Aug-16 27-Aug-16 18-Aug-16 A 27-Aug-16 A
WO02-270 Shuttering,Reinfrocement & Casting of Walls 7 100% 27-Aug-16 05-Sep-16 27-Aug-16 A 05-Sep-16 A
WO02-280 Construction Joints,Sealants & inserts for Openings 5 100% 05-Sep-16 10-Sep-16 05-Sep-16 A 10-Sep-16 A
WO02-290 Waterproofing / GRP Liner to exposed concrete surfaces 3 100% 06-Sep-16 10-Sep-16 06-Sep-16 A 10-Sep-16 A
WO02-300 Backfilling & Installation of DI Surface Box with chain & 4 100% 10-Sep-16 14-Sep-16 10-Sep-16 A 14-Sep-16 A
lifting Hooks
MEP Works 11 14-Sep-16 28-Sep-16 14-Sep-16 A 28-Sep-16 A
WO02-310 Installation of MEP Works 11 100% 14-Sep-16 28-Sep-16 14-Sep-16 A 28-Sep-16 A
WO02-MIS-130 Fitting and Assembling of Tanks 7 100% 02-Oct-16 10-Oct-16 02-Oct-16 A 10-Oct-16 A
WO02-POS-150 Cleaning & Final Inspection 2 100% 13-Oct-16 17-Oct-16 13-Oct-16 A 17-Oct-16 A
WO:MISC-159 AL QUDRA 500 mm DIA IRRIGATION LINE DIVERSION FOR ENDURANCE CITY 560 25-Jun-16 09-Apr-18 25-Jun-16 A 23-Apr-18 -28
PRECONSTRUCTION 560 25-Jun-16 09-Apr-18 25-Jun-16 A 23-Apr-18 -34
NOI/NOCs SUBMISSIONS 25 25-Jun-16 24-Jul-16 25-Jun-16 A 24-Jul-16 A
SUBMITTALS 11 25-Jun-16 07-Jul-16 25-Jun-16 A 07-Jul-16 A
WO03-NOC-320 Prepare & Submit NOC-DEWA 7 100% 25-Jun-16 03-Jul-16 25-Jun-16 A 03-Jul-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 11 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WO03-NOC-330 Prepare & Submit NOC-ETISALAT 7 100% 25-Jun-16 03-Jul-16 25-Jun-16 A 03-Jul-16 A
WO03-NOC-340 Prepare & Submit NOC-DU 7 100% 26-Jun-16 04-Jul-16 26-Jun-16 A 04-Jul-16 A
WO03-NOC-350 Prepare & Submit NOC-DUBAI MUNICIPALITY 7 100% 26-Jun-16 04-Jul-16 26-Jun-16 A 04-Jul-16 A
WO03-NOC-360 Prepare & Submit NOC-TOWN PLANNING 7 100% 27-Jun-16 05-Jul-16 27-Jun-16 A 05-Jul-16 A
DEPARTMENT
WO03-NOC-370 Prepare & Submit NOC-TABREED 7 100% 27-Jun-16 05-Jul-16 27-Jun-16 A 05-Jul-16 A
WO03-NOC-380 Prepare & Submit NOC-GHQ ARMED FORCES 7 100% 28-Jun-16 06-Jul-16 28-Jun-16 A 06-Jul-16 A
WO03-NOC-390 Prepare & Submit NOC-CIVIL DEFENCE 7 100% 28-Jun-16 06-Jul-16 28-Jun-16 A 06-Jul-16 A
WO03-NOC-400 Prepare & Submit NOC-ENVIRONMENTAL AGENCY 7 100% 28-Jun-16 06-Jul-16 28-Jun-16 A 06-Jul-16 A
WO03-NOC-410 Prepare & Submit NOC-RTA 7 100% 29-Jun-16 07-Jul-16 29-Jun-16 A 07-Jul-16 A
WO03-NOC-420 Prepare & Submit NOC-DUBAI TRAFFIC POLICE 7 100% 29-Jun-16 07-Jul-16 29-Jun-16 A 07-Jul-16 A
DEPT
APPROVALS 18 03-Jul-16 24-Jul-16 03-Jul-16 A 24-Jul-16 A
WO03-NOC-430 NOC Approvals-DEWA 14 100% 03-Jul-16 19-Jul-16 03-Jul-16 A 19-Jul-16 A
WO03-NOC-460 NOC Approvals-TOWN PLANNING DEPARTMENT 14 100% 05-Jul-16 21-Jul-16 05-Jul-16 A 21-Jul-16 A
WO03-NOC-490 NOC Approvals-GHQ ARMED FORCES 14 100% 06-Jul-16 23-Jul-16 06-Jul-16 A 23-Jul-16 A
WO03-NOC-530 NOC Approvals-DUBAI TRAFFIC POLICE DEPT 14 100% 07-Jul-16 24-Jul-16 07-Jul-16 A 24-Jul-16 A
WO03-SPD-120 Prepare & Submitt Shop Drawings 12 0% 20-Jul-16 03-Aug-16 20-Jul-16 A 23-Apr-18 -34 Prepare & Submitt Shop Drawings
WO03-MTR-140 Review & Approve Material Submittals 12 100% 27-Jul-16 10-Aug-16 27-Jul-16 A 10-Aug-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 12 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WO03-MTS-130 Review & Approve Method Statements 6 100% 26-Jul-16 02-Aug-16 26-Jul-16 A 02-Aug-16 A
WO03-QUD-CH-180 Base Units & Walls 8 100% 20-Sep-16 29-Sep-16 20-Sep-16 A 29-Sep-16 A
WO03-QUD-CH-190 Installation of Valves & Fittings 8 100% 24-Sep-16 03-Oct-16 24-Sep-16 A 03-Oct-16 A
WO03-QUD-MIS-160 Connection to the Existing Line 4 100% 17-Oct-16 22-Oct-16 17-Oct-16 A 22-Oct-16 A
WO03-QUD-MIS-170 Abandonment / Demolishing of Existing Line 4 100% 22-Oct-16 26-Oct-16 22-Oct-16 A 26-Oct-16 A
WO03-POS-150 Cleaning & Final Inspection 2 100% 26-Oct-16 29-Oct-16 26-Oct-16 A 29-Oct-16 A
FALCON HANGER SEWERAGE SYSTEM 687 21-Mar-16 30-May-18 21-Mar-16 A 30-May-18 -61
CONSTRUCTION 687 21-Mar-16 30-May-18 21-Mar-16 A 30-May-18 -61
SEWERAGE NETWORK 286 21-Mar-16 18-Feb-17 21-Mar-16 A 09-Apr-18 -16
FALCON HANGER,LOC MH 1 to MH 1-3 208 21-Mar-16 19-Nov-16 21-Mar-16 A 19-Nov-16 A
PIPELINE,LENGTH=222 m 16 31-Oct-16 19-Nov-16 31-Oct-16 A 19-Nov-16 A
FAL-SEW-PL-100 Dewatering (if required) 4 100% 31-Oct-16 05-Nov-16 31-Oct-16 A 05-Nov-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 13 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
FAL-SEW-PL-120 Bedding and Pipelaying 6 100% 07-Nov-16 14-Nov-16 07-Nov-16 A 14-Nov-16 A
FAL-SEW-MH-120 Base Units & Shafts 5 100% 30-Mar-16 05-Apr-16 30-Mar-16 A 05-Apr-16 A
FAL-SEW-MH-130 Water Proofing and Protection 5 100% 31-Mar-16 06-Apr-16 31-Mar-16 A 06-Apr-16 A
FAL-SEW-MH-140 Internal Finishing and Backfilling 5 100% 03-Apr-16 09-Apr-16 03-Apr-16 A 09-Apr-16 A
FAL-SEW-MH-150 Placing Covers & Frames 3 100% 06-Apr-16 10-Apr-16 06-Apr-16 A 10-Apr-16 A
FAL-SEW-MH-180 Base Units & Shafts 15 100% 13-Nov-16 30-Nov-16 13-Nov-16 A 30-Nov-16 A
FAL-SEW-MH-190 Water Proofing and Protection 15 100% 14-Nov-16 01-Dec-16 14-Nov-16 A 01-Dec-16 A
FAL-SEW-MH-200 Internal Finishing and Backfilling 15 100% 16-Nov-16 04-Dec-16 16-Nov-16 A 04-Dec-16 A
FAL-SEW-MH-210 Placing Covers & Frames 8 100% 26-Nov-16 05-Dec-16 26-Nov-16 A 05-Dec-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 14 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
FAL-SEW-MH-240 Base Units & Shafts 4 100% 01-Dec-16 06-Dec-16 01-Dec-16 A 06-Dec-16 A
FAL-SEW-MH-260 Internal Finishing and Backfilling 4 100% 05-Dec-16 10-Dec-16 05-Dec-16 A 10-Dec-16 A
FAL-SEW-MH-250 Water Proofing and Protection 4 100% 22-Dec-16 26-Dec-16 22-Dec-16 A 26-Dec-16 A
FAL-SEW-MH-270 Placing Covers & Frames 3 0% 07-Dec-16 11-Dec-16 07-Dec-16 A 09-Apr-18 -16 Placing Covers & Frames
FAL-SEW-MH-300 Base Units & Shafts 9 100% 07-Dec-16 18-Dec-16 07-Dec-16 A 18-Dec-16 A
FAL-SEW-MH-310 Water Proofing and Protection 9 100% 08-Dec-16 19-Dec-16 08-Dec-16 A 19-Dec-16 A
FAL-SEW-MH-320 Internal Finishing and Backfilling 9 100% 11-Dec-16 21-Dec-16 11-Dec-16 A 21-Dec-16 A
FAL-SEW-MH-330 Placing Covers & Frames 5 100% 17-Dec-16 22-Dec-16 17-Dec-16 A 22-Dec-16 A
FAL-SEW-MH-360 Base Units & Shafts 8 100% 19-Dec-16 28-Dec-16 19-Dec-16 A 28-Dec-16 A
FAL-SEW-MH-370 Water Proofing and Protection 8 100% 20-Dec-16 29-Dec-16 20-Dec-16 A 29-Dec-16 A
FAL-SEW-MH-380 Internal Finishing and Backfilling 8 100% 22-Dec-16 01-Jan-17 22-Dec-16 A 01-Jan-17 A
FAL-SEW-MH-390 Placing Covers & Frames 5 100% 27-Dec-16 02-Jan-17 27-Dec-16 A 02-Jan-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 15 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
FAL-SEW-PL-350 Dewatering (if required) 15 100% 26-Dec-16 12-Jan-17 26-Dec-16 A 12-Jan-17 A
FAL-SEW-MH-420 Base Units & Shafts 14 100% 29-Dec-16 15-Jan-17 29-Dec-16 A 15-Jan-17 A
FAL-SEW-MH-430 Water Proofing and Protection 14 100% 31-Dec-16 16-Jan-17 31-Dec-16 A 16-Jan-17 A
FAL-SEW-MH-440 Internal Finishing and Backfilling 14 100% 02-Jan-17 18-Jan-17 02-Jan-17 A 18-Jan-17 A
FAL-SEW-MH-450 Placing Covers & Frames 6 100% 12-Jan-17 19-Jan-17 12-Jan-17 A 19-Jan-17 A
FAL-SEW-MH-480 Base Units & Shafts 4 100% 16-Jan-17 21-Jan-17 16-Jan-17 A 21-Jan-17 A
FAL-SEW-MH-490 Water Proofing and Protection 4 100% 17-Jan-17 22-Jan-17 17-Jan-17 A 22-Jan-17 A
FAL-SEW-MH-500 Internal Finishing and Backfilling 4 100% 19-Jan-17 24-Jan-17 19-Jan-17 A 24-Jan-17 A
FAL-SEW-MH-510 Placing Covers & Frames 4 100% 21-Jan-17 25-Jan-17 21-Jan-17 A 25-Jan-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 16 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
FAL-SEW-MH-530 Formation & Blinding 5 100% 19-Jan-17 25-Jan-17 19-Jan-17 A 25-Jan-17 A
FAL-SEW-MH-540 Base Units & Shafts 5 100% 22-Jan-17 28-Jan-17 22-Jan-17 A 28-Jan-17 A
FAL-SEW-MH-550 Water Proofing and Protection 5 100% 23-Jan-17 29-Jan-17 23-Jan-17 A 29-Jan-17 A
FAL-SEW-MH-560 Internal Finishing and Backfilling 5 100% 25-Jan-17 31-Jan-17 25-Jan-17 A 31-Jan-17 A
FAL-SEW-MH-570 Placing Covers & Frames 3 100% 29-Jan-17 01-Feb-17 29-Jan-17 A 01-Feb-17 A
FAL-SEW-MH-600 Base Units & Shafts 4 100% 29-Jan-17 02-Feb-17 29-Jan-17 A 02-Feb-17 A
FAL-SEW-MH-610 Water Proofing and Protection 4 100% 30-Jan-17 04-Feb-17 30-Jan-17 A 04-Feb-17 A
FAL-SEW-MH-620 Internal Finishing and Backfilling 4 100% 01-Feb-17 06-Feb-17 01-Feb-17 A 06-Feb-17 A
FAL-SEW-MH-630 Placing Covers & Frames 3 100% 04-Feb-17 07-Feb-17 04-Feb-17 A 07-Feb-17 A
FAL-SEW-MH-780 Base Units & Shafts 6 100% 04-Feb-17 11-Feb-17 04-Feb-17 A 11-Feb-17 A
FAL-SEW-MH-790 Water Proofing and Protection 6 100% 05-Feb-17 12-Feb-17 05-Feb-17 A 12-Feb-17 A
FAL-SEW-MH-800 Internal Finishing and Backfilling 6 100% 07-Feb-17 14-Feb-17 07-Feb-17 A 14-Feb-17 A
FAL-SEW-MH-810 Placing Covers & Frames 3 100% 12-Feb-17 15-Feb-17 12-Feb-17 A 15-Feb-17 A
FAL-SEW-MH-660 Base Units & Shafts 13 100% 12-Feb-17 27-Feb-17 12-Feb-17 A 27-Feb-17 A
FAL-SEW-MH-670 Water Proofing and Protection 13 100% 13-Feb-17 28-Feb-17 13-Feb-17 A 28-Feb-17 A
FAL-SEW-MH-680 Internal Finishing and Backfilling 13 100% 15-Feb-17 02-Mar-17 15-Feb-17 A 02-Mar-17 A
FAL-SEW-MH-690 Placing Covers & Frames 8 100% 26-Feb-17 07-Mar-17 26-Feb-17 A 07-Mar-17 A
FAL-SEW-MH-720 Base Units & Shafts 12 100% 01-Mar-17 15-Mar-17 01-Mar-17 A 15-Mar-17 A
FAL-SEW-MH-730 Water Proofing and Protection 12 100% 02-Mar-17 16-Mar-17 02-Mar-17 A 16-Mar-17 A
FAL-SEW-MH-740 Internal Finishing and Backfilling 12 100% 05-Mar-17 19-Mar-17 05-Mar-17 A 19-Mar-17 A
FAL-SEW-MH-750 Placing Covers & Frames 8 100% 14-Mar-17 23-Mar-17 14-Mar-17 A 23-Mar-17 A
FAL-PS-110 Excavation for Foundation 14 80% 19-Nov-17 04-Dec-17 19-Nov-17 A 03-Feb-18 -61 Excavation for Foundation
FAL-PS-120 Filling with selected materials 10 40% 26-Nov-17 06-Dec-17 26-Nov-17 A 07-Feb-18 -61 Filling with selected materials
FAL-PS-130 Preparation of Excavated surfaces to recieve permanent 7 0% 01-Feb-18 10-Feb-18 01-Feb-18 10-Feb-18 -61 Preparation of Excavated surfaces to rec
works
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 18 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
CONCRETE WORKS 37 10-Feb-18 25-Mar-18 10-Feb-18 25-Mar-18 -61
FAL-PS-140 Concrete blinding 8 0% 10-Feb-18 19-Feb-18 10-Feb-18 19-Feb-18 -61 Concrete blinding
FAL-PS-150 Shuttering, Reinforcement & Casting Base Slab 12 0% 18-Feb-18 04-Mar-18 18-Feb-18 04-Mar-18 -61 Shuttering, Reinforcement & Casting B
FAL-PS-160 Shuttering, Reinforcement & Casting Walls 14 0% 27-Feb-18 15-Mar-18 27-Feb-18 15-Mar-18 -61 Shuttering, Reinforcement & Casting W
FAL-PS-170 Shuttering, Reinforcement & Casting Roof Slab 12 0% 11-Mar-18 25-Mar-18 11-Mar-18 25-Mar-18 -61 Shuttering, Reinforcement & Casting
FAL-PS-190 GRP Lamination 12 0% 26-Mar-18 09-Apr-18 26-Mar-18 09-Apr-18 -61 GRP Lamination
FAL-PS-200 Masonary works 21 0% 28-Mar-18 22-Apr-18 28-Mar-18 22-Apr-18 -61 Masonary works
FAL-PS-210 Epoxy painting 10 0% 12-Apr-18 24-Apr-18 12-Apr-18 24-Apr-18 -61 Epoxy painting
FAL-PS-220 Covers & Frames for clear openings 9 0% 14-Apr-18 24-Apr-18 14-Apr-18 24-Apr-18 -61 Covers & Frames for clear opening
FAL-PS-260 Doors & Windows 10 0% 15-Apr-18 26-Apr-18 15-Apr-18 26-Apr-18 -61 Doors & Windows
FAL-PS-240 MEP Works 30 0% 22-Apr-18 27-May-18 22-Apr-18 27-May-18 -61 MEP Works
FAL-PS-250 Other related Ancillaries works 14 0% 14-May-18 30-May-18 14-May-18 30-May-18 -61 Other related Ancillaries works
FAL-MIS-110 Construction of a new port 7 0% 11-Apr-18 19-Apr-18 11-Apr-18 19-Apr-18 -30 Construction of a new port
FAL-MIS-120 Abandonment / Demolishing of Existing Line 10 0% 14-Apr-18 25-Apr-18 14-Apr-18 25-Apr-18 -30 Abandonment / Demolishing of Exis
FAL-MIS-140 Overpumping Works 18 0% 09-Apr-18 30-Apr-18 09-Apr-18 30-Apr-18 -34 Overpumping Works
KHA-SEW-MH-120 Base Units & Shafts 6 100% 09-Apr-17 16-Apr-17 09-Apr-17 A 16-Apr-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 19 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
KHA-SEW-MH-130 Water Proofing and Protection 6 100% 11-Apr-17 18-Apr-17 11-Apr-17 A 18-Apr-17 A
KHA-SEW-MH-140 Internal Finishing and Backfilling 6 100% 13-Apr-17 20-Apr-17 13-Apr-17 A 20-Apr-17 A
KHA-SEW-MH-150 Placing Covers & Frames 2 100% 19-Apr-17 22-Apr-17 19-Apr-17 A 22-Apr-17 A
KHA-NDM-110 Preparation of Driving & Receiving PIts 3 100% 12-Apr-17 15-Apr-17 12-Apr-17 A 15-Apr-17 A
KHA-NDM-140 Laying NDM Pipes by Microtunelling 9 100% 30-Apr-17 09-May-17 30-Apr-17 A 09-May-17 A
MISC-061 MIRDIF SEWER CONNECTION FOR PLOT NO.251-4410 91 19-Oct-16 02-Feb-17 19-Oct-16 A 02-Feb-17 A
PRECONSTRUCTION 34 19-Oct-16 28-Nov-16 19-Oct-16 A 28-Nov-16 A
NOI/NOCs SUBMISSIONS 30 19-Oct-16 23-Nov-16 19-Oct-16 A 23-Nov-16 A
SUBMITTALS 17 25-Oct-16 13-Nov-16 25-Oct-16 A 13-Nov-16 A
MIS061-NOC-100 Prepare & Submit NOC-DEWA 7 100% 25-Oct-16 02-Nov-16 25-Oct-16 A 02-Nov-16 A
MIS061-NOC-110 Prepare & Submit NOC-ETISALAT 7 100% 25-Oct-16 02-Nov-16 25-Oct-16 A 02-Nov-16 A
MIS061-NOC-120 Prepare & Submit NOC-DU 7 100% 26-Oct-16 03-Nov-16 26-Oct-16 A 03-Nov-16 A
MIS061-NOC-130 Prepare & Submit NOC-DUBAI MUNICIPALITY 7 100% 26-Oct-16 03-Nov-16 26-Oct-16 A 03-Nov-16 A
MIS061-NOC-140 Prepare & Submit NOC-TOWN PLANNING 7 100% 27-Oct-16 05-Nov-16 27-Oct-16 A 05-Nov-16 A
DEPARTMENT
MIS061-NOC-150 Prepare & Submit NOC-TABREED 7 100% 27-Oct-16 05-Nov-16 27-Oct-16 A 05-Nov-16 A
MIS061-NOC-170 Prepare & Submit NOC-CIVIL DEFENCE 7 100% 29-Oct-16 06-Nov-16 29-Oct-16 A 06-Nov-16 A
MIS061-NOC-180 Prepare & Submit NOC-ENVIRONMENTAL AGENCY 7 100% 29-Oct-16 06-Nov-16 29-Oct-16 A 06-Nov-16 A
MIS061-NOC-190 Prepare & Submit NOC-RTA 7 100% 30-Oct-16 07-Nov-16 30-Oct-16 A 07-Nov-16 A
MIS061-NOC-200 Prepare & Submit NOC-DUBAI TRAFFIC POLICE 7 100% 30-Oct-16 07-Nov-16 30-Oct-16 A 07-Nov-16 A
DEPT
MIS061-NOC-160 Prepare & Submit NOC-GHQ ARMED FORCES 7 100% 06-Nov-16 13-Nov-16 06-Nov-16 A 13-Nov-16 A
MIS061-NOC-250 NOC Approvals-TOWN PLANNING DEPARTMENT 14 100% 05-Nov-16 21-Nov-16 05-Nov-16 A 21-Nov-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 20 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIS061-NOC-260 NOC Approvals-TABREED 14 100% 05-Nov-16 21-Nov-16 05-Nov-16 A 21-Nov-16 A
MIS061-NOC-270 NOC Approvals-GHQ ARMED FORCES 14 100% 06-Nov-16 22-Nov-16 06-Nov-16 A 22-Nov-16 A
MIS061-NOC-310 NOC Approvals-DUBAI TRAFFIC POLICE DEPT 14 100% 07-Nov-16 23-Nov-16 07-Nov-16 A 23-Nov-16 A
MIS061-SPD-110 Review & Approve Shop Drawings 10 100% 13-Nov-16 24-Nov-16 13-Nov-16 A 24-Nov-16 A
MIS061-MTR-110 Review & Approve Material Submittals 8 100% 19-Nov-16 28-Nov-16 19-Nov-16 A 28-Nov-16 A
MIS061-MTS-110 Review & Approve Method Statements 6 100% 13-Nov-16 20-Nov-16 13-Nov-16 A 20-Nov-16 A
MIS061-NDM-110 Preparation of Driving & Receiving PIts 2 100% 30-Nov-16 03-Dec-16 30-Nov-16 A 03-Dec-16 A
MIS061-ST-MH-120 Base Units & Shafts 2 100% 12-Jan-17 15-Jan-17 12-Jan-17 A 15-Jan-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 21 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIS061-ST-MH-130 Water Proofing and Protection 2 100% 16-Jan-17 18-Jan-17 16-Jan-17 A 18-Jan-17 A
MIS061-ST-MH-140 Internal Finishing and Backfilling 2 100% 19-Jan-17 22-Jan-17 19-Jan-17 A 22-Jan-17 A
MIS061-ST-MH-150 Placing Covers & Frames 1 100% 22-Jan-17 23-Jan-17 22-Jan-17 A 23-Jan-17 A
MIS061-MIS-120 Connection to the Existing Line 2 100% 26-Jan-17 29-Jan-17 26-Jan-17 A 29-Jan-17 A
MISC-060 MIRDIF SEWER CONNECTION FOR PLOT NO.251-4410 93 25-Oct-16 11-Feb-17 25-Oct-16 A 11-Feb-17 A
PRECONSTRUCTION 29 25-Oct-16 28-Nov-16 25-Oct-16 A 28-Nov-16 A
NOI/NOCs SUBMISSIONS 25 25-Oct-16 23-Nov-16 25-Oct-16 A 23-Nov-16 A
SUBMITTALS 11 25-Oct-16 07-Nov-16 25-Oct-16 A 07-Nov-16 A
MIS060-NOC-100 Prepare & Submit NOC-DEWA 7 100% 25-Oct-16 02-Nov-16 25-Oct-16 A 02-Nov-16 A
MIS060-NOC-110 Prepare & Submit NOC-ETISALAT 7 100% 25-Oct-16 02-Nov-16 25-Oct-16 A 02-Nov-16 A
MIS060-NOC-120 Prepare & Submit NOC-DU 7 100% 26-Oct-16 03-Nov-16 26-Oct-16 A 03-Nov-16 A
MIS060-NOC-130 Prepare & Submit NOC-DUBAI MUNICIPALITY 7 100% 26-Oct-16 03-Nov-16 26-Oct-16 A 03-Nov-16 A
MIS060-NOC-140 Prepare & Submit NOC-TOWN PLANNING 7 100% 27-Oct-16 05-Nov-16 27-Oct-16 A 05-Nov-16 A
DEPARTMENT
MIS060-NOC-150 Prepare & Submit NOC-TABREED 7 100% 27-Oct-16 05-Nov-16 27-Oct-16 A 05-Nov-16 A
MIS060-NOC-160 Prepare & Submit NOC-GHQ ARMED FORCES 7 100% 29-Oct-16 06-Nov-16 29-Oct-16 A 06-Nov-16 A
MIS060-NOC-170 Prepare & Submit NOC-CIVIL DEFENCE 7 100% 29-Oct-16 06-Nov-16 29-Oct-16 A 06-Nov-16 A
MIS060-NOC-180 Prepare & Submit NOC-ENVIRONMENTAL AGENCY 7 100% 29-Oct-16 06-Nov-16 29-Oct-16 A 06-Nov-16 A
MIS060-NOC-190 Prepare & Submit NOC-RTA 7 100% 30-Oct-16 07-Nov-16 30-Oct-16 A 07-Nov-16 A
MIS060-NOC-200 Prepare & Submit NOC-DUBAI TRAFFIC POLICE 7 100% 30-Oct-16 07-Nov-16 30-Oct-16 A 07-Nov-16 A
DEPT
APPROVALS 18 02-Nov-16 23-Nov-16 02-Nov-16 A 23-Nov-16 A
MIS060-NOC-210 NOC Approvals-DEWA 14 100% 02-Nov-16 19-Nov-16 02-Nov-16 A 19-Nov-16 A
MIS060-NOC-250 NOC Approvals-TOWN PLANNING DEPARTMENT 14 100% 05-Nov-16 21-Nov-16 05-Nov-16 A 21-Nov-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 22 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIS060-NOC-270 NOC Approvals-GHQ ARMED FORCES 14 100% 06-Nov-16 22-Nov-16 06-Nov-16 A 22-Nov-16 A
MIS060-NOC-310 NOC Approvals-DUBAI TRAFFIC POLICE DEPT 14 100% 07-Nov-16 23-Nov-16 07-Nov-16 A 23-Nov-16 A
MIS060-SPD-110 Review & Approve Shop Drawings 10 100% 13-Nov-16 24-Nov-16 13-Nov-16 A 24-Nov-16 A
MIS060-MTR-110 Review & Approve Material Submittals 8 100% 19-Nov-16 28-Nov-16 19-Nov-16 A 28-Nov-16 A
MIS060-MTS-110 Review & Approve Method Statements 6 100% 13-Nov-16 20-Nov-16 13-Nov-16 A 20-Nov-16 A
MIS060-NDM-110 Preparation of Driving & Receiving PIts 2 100% 30-Nov-16 03-Dec-16 30-Nov-16 A 03-Dec-16 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 23 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIS060-SEW-PL-140 Testing and Backfilling 7 100% 15-Jan-17 23-Jan-17 15-Jan-17 A 23-Jan-17 A
MIS060-SEW-MH-120 Base Units & Shafts 6 100% 14-Jan-17 21-Jan-17 14-Jan-17 A 21-Jan-17 A
MIS060-SEW-MH-130 Water Proofing and Protection 6 100% 14-Jan-17 21-Jan-17 14-Jan-17 A 21-Jan-17 A
MIS060-SEW-MH-140 Internal Finishing and Backfilling 6 100% 15-Jan-17 23-Jan-17 15-Jan-17 A 23-Jan-17 A
MIS060-SEW-MH-150 Placing Covers & Frames 2 100% 22-Jan-17 24-Jan-17 22-Jan-17 A 24-Jan-17 A
MIS060-MIS-120 Connection to the Existing Line 4 100% 01-Feb-17 06-Feb-17 01-Feb-17 A 06-Feb-17 A
MISC-001, SEWER WORKS -NAD AL SHIBA 418 08-Feb-17 10-Jun-18 08-Feb-17 A 10-Jun-18 -70
CONSTRUCTION 418 08-Feb-17 10-Jun-18 08-Feb-17 A 10-Jun-18 -70
EX. MH V/19-MH V/19/1 37 08-Feb-17 23-Mar-17 08-Feb-17 A 23-Mar-17 A
NDRC WORKS 31 08-Feb-17 16-Mar-17 08-Feb-17 A 16-Mar-17 A
NAD-MIS-001-PL-1000 Excavation for Driving Pit 6 100% 08-Feb-17 15-Feb-17 08-Feb-17 A 15-Feb-17 A
NAD-MIS-001-PL-1005 Excavation for Receiving Pit 6 100% 08-Feb-17 15-Feb-17 08-Feb-17 A 15-Feb-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 24 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-1070 Backfilling 2 100% 14-Mar-17 16-Mar-17 14-Mar-17 A 16-Mar-17 A
NAD-MIS-001-PL-1050 Excavation for Receving Pit 6 100% 15-Feb-17 22-Feb-17 15-Feb-17 A 22-Feb-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 25 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MANHOLE CONSTRUCTION 23 06-Mar-17 02-Apr-17 06-Mar-17 A 02-Apr-17 A
NAD-MIS-001-MH-1220 Excavation and Blinding 2 100% 06-Mar-17 08-Mar-17 06-Mar-17 A 08-Mar-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 26 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-1430 Cover and Frames 2 100% 07-Dec-17 09-Dec-17 07-Dec-17 A 09-Dec-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 27 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-1560 Casting/Placing of Base Slab 3 100% 07-Jan-18 09-Jan-18 07-Jan-18 A 09-Jan-18 A
NAD-MIS-001-PL-1400 Excavation for Receivng Pit 5 0% 31-Jan-18 05-Feb-18 31-Jan-18 05-Feb-18 -51 Excavation for Receivng Pit
NAD-MIS-001-PL-1430 Pipe Surround 2 0% 18-Feb-18 19-Feb-18 18-Feb-18 19-Feb-18 -47 Pipe Surround
NAD-MIS-001-MH-1670 Casting/Placing of Base Slab 2 0% 15-Feb-18 17-Feb-18 15-Feb-18 17-Feb-18 -51 Casting/Placing of Base Slab
NAD-MIS-001-MH-1680 Casting/Placing of Walls 2 0% 18-Feb-18 19-Feb-18 18-Feb-18 19-Feb-18 -51 Casting/Placing of Walls
NAD-MIS-001-MH-1690 Casting/Placing of Reducer Slab 2 0% 20-Feb-18 21-Feb-18 20-Feb-18 21-Feb-18 -51 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-1700 Cating/Placing of Shafts 2 0% 22-Feb-18 24-Feb-18 22-Feb-18 24-Feb-18 -51 Cating/Placing of Shafts
NAD-MIS-001-MH-1710 Construction of Backdrop 2 0% 25-Feb-18 26-Feb-18 25-Feb-18 26-Feb-18 -51 Construction of Backdrop
NAD-MIS-001-MH-1720 External Water Proofing 2 0% 25-Feb-18 26-Feb-18 25-Feb-18 26-Feb-18 -51 External Water Proofing
NAD-MIS-001-MH-1740 Cating/Placing of Cover Slab 2 0% 27-Feb-18 28-Feb-18 27-Feb-18 28-Feb-18 -51 Cating/Placing of Cover Slab
NAD-MIS-001-MH-1750 Internal Finishing 2 0% 01-Mar-18 03-Mar-18 01-Mar-18 03-Mar-18 -51 Internal Finishing
NAD-MIS-001-MH-1760 Cover and Frames 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 -51 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 28 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-1460 Lowering 4 0% 06-Feb-18 10-Feb-18 06-Feb-18 10-Feb-18 -70 Lowering
NAD-MIS-001-PL-1470 Install Dewatering system 4 0% 06-Feb-18 10-Feb-18 06-Feb-18 10-Feb-18 -48 Install Dewatering system
NAD-MIS-001-PL-1480 Excavation to Formation Level 3 0% 11-Feb-18 13-Feb-18 11-Feb-18 13-Feb-18 -48 Excavation to Formation Level
NAD-MIS-001-PL-1500 Pipe Surround 3 0% 17-Feb-18 19-Feb-18 17-Feb-18 19-Feb-18 -46 Pipe Surround
NAD-MIS-001-MH-1780 Casting/Placing of Base Slab 2 0% 14-Feb-18 15-Feb-18 14-Feb-18 15-Feb-18 -48 Casting/Placing of Base Slab
NAD-MIS-001-MH-1790 Casting/Placing of Walls 2 0% 17-Feb-18 18-Feb-18 17-Feb-18 18-Feb-18 -48 Casting/Placing of Walls
NAD-MIS-001-MH-1800 Casting/Placing of Reducer Slab 2 0% 19-Feb-18 20-Feb-18 19-Feb-18 20-Feb-18 -48 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-1810 Cating/Placing of Shafts 2 0% 21-Feb-18 22-Feb-18 21-Feb-18 22-Feb-18 -48 Cating/Placing of Shafts
NAD-MIS-001-MH-1820 Construction of Backdrop 2 0% 24-Feb-18 25-Feb-18 24-Feb-18 25-Feb-18 -48 Construction of Backdrop
NAD-MIS-001-MH-1830 External Water Proofing 2 0% 24-Feb-18 25-Feb-18 24-Feb-18 25-Feb-18 -48 External Water Proofing
NAD-MIS-001-MH-1850 Cating/Placing of Cover Slab 2 0% 01-Mar-18 03-Mar-18 01-Mar-18 03-Mar-18 -51 Cating/Placing of Cover Slab
NAD-MIS-001-MH-1860 Internal Finishing 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 -51 Internal Finishing
NAD-MIS-001-MH-1870 Cover and Frames 2 0% 06-Mar-18 07-Mar-18 06-Mar-18 07-Mar-18 -51 Cover and Frames
NAD-MIS-001-PL-1540 Install Dewatering system 4 0% 11-Feb-18 14-Feb-18 11-Feb-18 14-Feb-18 -53 Install Dewatering system
NAD-MIS-001-PL-1550 Excavation to Formation Level 6 0% 15-Feb-18 21-Feb-18 15-Feb-18 21-Feb-18 -53 Excavation to Formation Level
NAD-MIS-001-PL-1570 Pipe Surround 2 0% 25-Feb-18 26-Feb-18 25-Feb-18 26-Feb-18 -49 Pipe Surround
NAD-MIS-001-MH-1890 Casting/Placing of Base Slab 2 0% 22-Feb-18 24-Feb-18 22-Feb-18 24-Feb-18 -53 Casting/Placing of Base Slab
NAD-MIS-001-MH-1900 Casting/Placing of Walls 2 0% 25-Feb-18 26-Feb-18 25-Feb-18 26-Feb-18 -53 Casting/Placing of Walls
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 29 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-1910 Casting/Placing of Reducer Slab 2 0% 27-Feb-18 28-Feb-18 27-Feb-18 28-Feb-18 -53 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-1920 Cating/Placing of Shafts 2 0% 01-Mar-18 03-Mar-18 01-Mar-18 03-Mar-18 -53 Cating/Placing of Shafts
NAD-MIS-001-MH-1930 Construction of Backdrop 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 -53 Construction of Backdrop
NAD-MIS-001-MH-1940 External Water Proofing 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 -53 External Water Proofing
NAD-MIS-001-MH-1960 Cating/Placing of Cover Slab 2 0% 06-Mar-18 07-Mar-18 06-Mar-18 07-Mar-18 -53 Cating/Placing of Cover Slab
NAD-MIS-001-MH-1970 Internal Finishing 2 0% 08-Mar-18 10-Mar-18 08-Mar-18 10-Mar-18 -53 Internal Finishing
NAD-MIS-001-MH-1980 Cover and Frames 2 0% 11-Mar-18 12-Mar-18 11-Mar-18 12-Mar-18 -53 Cover and Frames
NAD-MIS-001-MH-2000 Casting/Placing of Base Slab 2 0% 25-Feb-18 26-Feb-18 25-Feb-18 26-Feb-18 -53 Casting/Placing of Base Slab
NAD-MIS-001-MH-2010 Casting/Placing of Walls 2 0% 27-Feb-18 28-Feb-18 27-Feb-18 28-Feb-18 -53 Casting/Placing of Walls
NAD-MIS-001-MH-2020 Casting/Placing of Reducer Slab 2 0% 01-Mar-18 03-Mar-18 01-Mar-18 03-Mar-18 -53 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2030 Cating/Placing of Shafts 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 -53 Cating/Placing of Shafts
NAD-MIS-001-MH-2040 Construction of Backdrop 2 0% 06-Mar-18 07-Mar-18 06-Mar-18 07-Mar-18 -53 Construction of Backdrop
NAD-MIS-001-MH-2050 External Water Proofing 2 0% 06-Mar-18 07-Mar-18 06-Mar-18 07-Mar-18 -53 External Water Proofing
NAD-MIS-001-MH-2070 Cating/Placing of Cover Slab 2 0% 08-Mar-18 10-Mar-18 08-Mar-18 10-Mar-18 -53 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2080 Internal Finishing 2 0% 11-Mar-18 12-Mar-18 11-Mar-18 12-Mar-18 -53 Internal Finishing
NAD-MIS-001-MH-2090 Cover and Frames 2 0% 13-Mar-18 14-Mar-18 13-Mar-18 14-Mar-18 -53 Cover and Frames
NAD-MIS-001-PL-1610 Install Dewatering system 4 0% 15-Feb-18 19-Feb-18 15-Feb-18 19-Feb-18 -53 Install Dewatering system
NAD-MIS-001-PL-1620 Excavation to Formation Level 4 0% 20-Feb-18 24-Feb-18 20-Feb-18 24-Feb-18 -53 Excavation to Formation Level
NAD-MIS-001-PL-1640 Pipe Surround 3 0% 27-Feb-18 01-Mar-18 27-Feb-18 01-Mar-18 -50 Pipe Surround
NAD-MIS-001-PL-1680 Install Dewatering system 4 0% 20-Feb-18 24-Feb-18 20-Feb-18 24-Feb-18 -55 Install Dewatering system
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 30 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-1690 Excavation to Formation Level 4 0% 25-Feb-18 28-Feb-18 25-Feb-18 28-Feb-18 -55 Excavation to Formation Level
NAD-MIS-001-PL-1710 Pipe Surround 3 0% 03-Mar-18 05-Mar-18 03-Mar-18 05-Mar-18 -51 Pipe Surround
NAD-MIS-001-MH-2110 Casting/Placing of Base Slab 2 0% 01-Mar-18 03-Mar-18 01-Mar-18 03-Mar-18 -55 Casting/Placing of Base Slab
NAD-MIS-001-MH-2120 Casting/Placing of Walls 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 -55 Casting/Placing of Walls
NAD-MIS-001-MH-2130 Casting/Placing of Reducer Slab 2 0% 06-Mar-18 07-Mar-18 06-Mar-18 07-Mar-18 -55 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2140 Cating/Placing of Shafts 2 0% 08-Mar-18 10-Mar-18 08-Mar-18 10-Mar-18 -55 Cating/Placing of Shafts
NAD-MIS-001-MH-2150 Construction of Backdrop 2 0% 11-Mar-18 12-Mar-18 11-Mar-18 12-Mar-18 -55 Construction of Backdrop
NAD-MIS-001-MH-2160 External Water Proofing 2 0% 11-Mar-18 12-Mar-18 11-Mar-18 12-Mar-18 -55 External Water Proofing
NAD-MIS-001-MH-2180 Cating/Placing of Cover Slab 2 0% 13-Mar-18 14-Mar-18 13-Mar-18 14-Mar-18 -55 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2190 Internal Finishing 2 0% 15-Mar-18 17-Mar-18 15-Mar-18 17-Mar-18 -55 Internal Finishing
NAD-MIS-001-MH-2200 Cover and Frames 2 0% 18-Mar-18 19-Mar-18 18-Mar-18 19-Mar-18 -55 Cover and Frames
NAD-MIS-001-PL-3710 Excavation for Receiving Pit 5 0% 20-Mar-18 25-Mar-18 20-Mar-18 25-Mar-18 -17 Excavation for Receiving Pit
NAD-MIS-001-PL-3740 Pipe Surround 2 0% 04-Apr-18 05-Apr-18 04-Apr-18 05-Apr-18 -17 Pipe Surround
NAD-MIS-001-PL-1750 Install Dewatering system 3 0% 25-Feb-18 27-Feb-18 25-Feb-18 27-Feb-18 -54 Install Dewatering system
NAD-MIS-001-PL-1760 Excavation to Formation Level 2 0% 28-Feb-18 01-Mar-18 28-Feb-18 01-Mar-18 -54 Excavation to Formation Level
NAD-MIS-001-PL-1780 Pipe Surround 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 -49 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 31 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-1790 Backfilling 2 0% 06-Mar-18 07-Mar-18 06-Mar-18 07-Mar-18 -49 Backfilling
NAD-MIS-001-MH-2220 Casting/Placing of Base Slab 2 0% 03-Mar-18 04-Mar-18 03-Mar-18 04-Mar-18 -54 Casting/Placing of Base Slab
NAD-MIS-001-MH-2230 Casting/Placing of Walls 2 0% 05-Mar-18 06-Mar-18 05-Mar-18 06-Mar-18 -54 Casting/Placing of Walls
NAD-MIS-001-MH-2240 Casting/Placing of Reducer Slab 2 0% 07-Mar-18 08-Mar-18 07-Mar-18 08-Mar-18 -54 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2250 Cating/Placing of Shafts 2 0% 10-Mar-18 11-Mar-18 10-Mar-18 11-Mar-18 -54 Cating/Placing of Shafts
NAD-MIS-001-MH-2260 Construction of Backdrop 2 0% 12-Mar-18 13-Mar-18 12-Mar-18 13-Mar-18 -54 Construction of Backdrop
NAD-MIS-001-MH-2270 External Water Proofing 2 0% 12-Mar-18 13-Mar-18 12-Mar-18 13-Mar-18 -54 External Water Proofing
NAD-MIS-001-MH-2290 Cating/Placing of Cover Slab 2 0% 15-Mar-18 17-Mar-18 15-Mar-18 17-Mar-18 -55 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2300 Internal Finishing 2 0% 18-Mar-18 19-Mar-18 18-Mar-18 19-Mar-18 -55 Internal Finishing
NAD-MIS-001-MH-2310 Cover and Frames 2 0% 20-Mar-18 21-Mar-18 20-Mar-18 21-Mar-18 -55 Cover and Frames
NAD-MIS-001-PL-1820 Install Dewatering system 4 0% 28-Feb-18 04-Mar-18 28-Feb-18 04-Mar-18 -58 Install Dewatering system
NAD-MIS-001-PL-1830 Excavation to Formation Level 4 0% 05-Mar-18 08-Mar-18 05-Mar-18 08-Mar-18 -58 Excavation to Formation Level
NAD-MIS-001-PL-1850 Pipe Surround 2 0% 12-Mar-18 13-Mar-18 12-Mar-18 13-Mar-18 -54 Pipe Surround
NAD-MIS-001-MH-2330 Casting/Placing of Base Slab 2 0% 10-Mar-18 11-Mar-18 10-Mar-18 11-Mar-18 -58 Casting/Placing of Base Slab
NAD-MIS-001-MH-2340 Casting/Placing of Walls 2 0% 12-Mar-18 13-Mar-18 12-Mar-18 13-Mar-18 -58 Casting/Placing of Walls
NAD-MIS-001-MH-2350 Casting/Placing of Reducer Slab 2 0% 14-Mar-18 15-Mar-18 14-Mar-18 15-Mar-18 -58 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2360 Cating/Placing of Shafts 2 0% 17-Mar-18 18-Mar-18 17-Mar-18 18-Mar-18 -58 Cating/Placing of Shafts
NAD-MIS-001-MH-2370 Construction of Backdrop 2 0% 19-Mar-18 20-Mar-18 19-Mar-18 20-Mar-18 -58 Construction of Backdrop
NAD-MIS-001-MH-2380 External Water Proofing 2 0% 19-Mar-18 20-Mar-18 19-Mar-18 20-Mar-18 -58 External Water Proofing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 32 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-2400 Cating/Placing of Cover Slab 2 0% 21-Mar-18 22-Mar-18 21-Mar-18 22-Mar-18 -58 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2410 Internal Finishing 2 0% 24-Mar-18 25-Mar-18 24-Mar-18 25-Mar-18 -58 Internal Finishing
NAD-MIS-001-MH-2420 Cover and Frames 2 0% 26-Mar-18 27-Mar-18 26-Mar-18 27-Mar-18 -58 Cover and Frames
NAD-MIS-001-PL-1890 Install Dewatering system 4 0% 05-Mar-18 08-Mar-18 05-Mar-18 08-Mar-18 -59 Install Dewatering system
NAD-MIS-001-PL-1900 Excavation to Formation Level 3 0% 10-Mar-18 12-Mar-18 10-Mar-18 12-Mar-18 -59 Excavation to Formation Level
NAD-MIS-001-PL-1920 Pipe Surround 3 0% 15-Mar-18 18-Mar-18 15-Mar-18 18-Mar-18 -56 Pipe Surround
NAD-MIS-001-MH-2440 Casting/Placing of Base Slab 2 0% 13-Mar-18 14-Mar-18 13-Mar-18 14-Mar-18 -59 Casting/Placing of Base Slab
NAD-MIS-001-MH-2450 Casting/Placing of Walls 2 0% 15-Mar-18 17-Mar-18 15-Mar-18 17-Mar-18 -59 Casting/Placing of Walls
NAD-MIS-001-MH-2460 Casting/Placing of Reducer Slab 2 0% 18-Mar-18 19-Mar-18 18-Mar-18 19-Mar-18 -59 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2470 Cating/Placing of Shafts 2 0% 20-Mar-18 21-Mar-18 20-Mar-18 21-Mar-18 -59 Cating/Placing of Shafts
NAD-MIS-001-MH-2480 Construction of Backdrop 2 0% 22-Mar-18 24-Mar-18 22-Mar-18 24-Mar-18 -59 Construction of Backdrop
NAD-MIS-001-MH-2490 External Water Proofing 2 0% 22-Mar-18 24-Mar-18 22-Mar-18 24-Mar-18 -59 External Water Proofing
NAD-MIS-001-MH-2510 Cating/Placing of Cover Slab 2 0% 25-Mar-18 26-Mar-18 25-Mar-18 26-Mar-18 -59 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2520 Internal Finishing 2 0% 27-Mar-18 28-Mar-18 27-Mar-18 28-Mar-18 -59 Internal Finishing
NAD-MIS-001-MH-2530 Cover and Frames 2 0% 29-Mar-18 31-Mar-18 29-Mar-18 31-Mar-18 -59 Cover and Frames
NAD-MIS-001-PL-1960 Install Dewatering system 3 0% 10-Mar-18 12-Mar-18 10-Mar-18 12-Mar-18 -62 Install Dewatering system
NAD-MIS-001-PL-1970 Excavation to Formation Level 3 0% 13-Mar-18 15-Mar-18 13-Mar-18 15-Mar-18 -62 Excavation to Formation Level
NAD-MIS-001-PL-1990 Pipe Surround 3 0% 19-Mar-18 21-Mar-18 19-Mar-18 21-Mar-18 -57 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 33 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MANHOLE CONSTRUCTION 20 14-Mar-18 05-Apr-18 14-Mar-18 05-Apr-18 -62
NAD-MIS-001-MH-2540 Excavation and Blinding 2 0% 14-Mar-18 15-Mar-18 14-Mar-18 15-Mar-18 -62 Excavation and Blinding
NAD-MIS-001-MH-2550 Casting/Placing of Base Slab 2 0% 17-Mar-18 18-Mar-18 17-Mar-18 18-Mar-18 -62 Casting/Placing of Base Slab
NAD-MIS-001-MH-2560 Casting/Placing of Walls 2 0% 19-Mar-18 20-Mar-18 19-Mar-18 20-Mar-18 -62 Casting/Placing of Walls
NAD-MIS-001-MH-2570 Casting/Placing of Reducer Slab 2 0% 21-Mar-18 22-Mar-18 21-Mar-18 22-Mar-18 -62 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2580 Cating/Placing of Shafts 2 0% 24-Mar-18 25-Mar-18 24-Mar-18 25-Mar-18 -62 Cating/Placing of Shafts
NAD-MIS-001-MH-2590 Construction of Backdrop 2 0% 26-Mar-18 27-Mar-18 26-Mar-18 27-Mar-18 -62 Construction of Backdrop
NAD-MIS-001-MH-2600 External Water Proofing 2 0% 28-Mar-18 29-Mar-18 28-Mar-18 29-Mar-18 -62 External Water Proofing
NAD-MIS-001-MH-2620 Cating/Placing of Cover Slab 2 0% 31-Mar-18 01-Apr-18 31-Mar-18 01-Apr-18 -62 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2630 Internal Finishing 2 0% 02-Apr-18 03-Apr-18 02-Apr-18 03-Apr-18 -62 Internal Finishing
NAD-MIS-001-MH-2640 Cover and Frames 2 0% 04-Apr-18 05-Apr-18 04-Apr-18 05-Apr-18 -62 Cover and Frames
NAD-MIS-001-PL-3780 Excavation for Receiving Pit 5 0% 07-Apr-18 11-Apr-18 07-Apr-18 11-Apr-18 -34 Excavation for Receiving Pit
NAD-MIS-001-PL-3810 Pipe Surround 2 0% 24-Apr-18 25-Apr-18 24-Apr-18 25-Apr-18 -34 Pipe Surround
NAD-MIS-001-PL-2030 Install Dewatering system 4 0% 13-Mar-18 17-Mar-18 13-Mar-18 17-Mar-18 -63 Install Dewatering system
NAD-MIS-001-PL-2040 Excavation to Formation Level 4 0% 18-Mar-18 21-Mar-18 18-Mar-18 21-Mar-18 -63 Excavation to Formation Level
NAD-MIS-001-PL-2060 Pipe Surround 3 0% 25-Mar-18 27-Mar-18 25-Mar-18 27-Mar-18 -60 Pipe Surround
NAD-MIS-001-MH-2660 Casting/Placing of Base Slab 2 0% 22-Mar-18 24-Mar-18 22-Mar-18 24-Mar-18 -63 Casting/Placing of Base Slab
NAD-MIS-001-MH-2670 Casting/Placing of Walls 2 0% 25-Mar-18 26-Mar-18 25-Mar-18 26-Mar-18 -63 Casting/Placing of Walls
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 34 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-2680 Casting/Placing of Reducer Slab 2 0% 27-Mar-18 28-Mar-18 27-Mar-18 28-Mar-18 -63 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2690 Cating/Placing of Shafts 2 0% 29-Mar-18 31-Mar-18 29-Mar-18 31-Mar-18 -63 Cating/Placing of Shafts
NAD-MIS-001-MH-2700 Construction of Backdrop 2 0% 01-Apr-18 02-Apr-18 01-Apr-18 02-Apr-18 -63 Construction of Backdrop
NAD-MIS-001-MH-2710 External Water Proofing 2 0% 01-Apr-18 02-Apr-18 01-Apr-18 02-Apr-18 -63 External Water Proofing
NAD-MIS-001-MH-2730 Cating/Placing of Cover Slab 2 0% 03-Apr-18 04-Apr-18 03-Apr-18 04-Apr-18 -63 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2740 Internal Finishing 2 0% 05-Apr-18 07-Apr-18 05-Apr-18 07-Apr-18 -63 Internal Finishing
NAD-MIS-001-MH-2750 Cover and Frames 2 0% 08-Apr-18 09-Apr-18 08-Apr-18 09-Apr-18 -63 Cover and Frames
NAD-MIS-001-PL-2100 Install Dewatering system 4 0% 18-Mar-18 21-Mar-18 18-Mar-18 21-Mar-18 -65 Install Dewatering system
NAD-MIS-001-PL-2110 Excavation to Formation Level 4 0% 22-Mar-18 26-Mar-18 22-Mar-18 26-Mar-18 -65 Excavation to Formation Level
NAD-MIS-001-PL-2130 Pipe Surround 2 0% 29-Mar-18 31-Mar-18 29-Mar-18 31-Mar-18 -61 Pipe Surround
NAD-MIS-001-MH-2770 Casting/Placing of Base Slab 2 0% 27-Mar-18 28-Mar-18 27-Mar-18 28-Mar-18 -65 Casting/Placing of Base Slab
NAD-MIS-001-MH-2780 Casting/Placing of Walls 2 0% 29-Mar-18 31-Mar-18 29-Mar-18 31-Mar-18 -65 Casting/Placing of Walls
NAD-MIS-001-MH-2790 Casting/Placing of Reducer Slab 2 0% 01-Apr-18 02-Apr-18 01-Apr-18 02-Apr-18 -65 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2800 Cating/Placing of Shafts 2 0% 03-Apr-18 04-Apr-18 03-Apr-18 04-Apr-18 -65 Cating/Placing of Shafts
NAD-MIS-001-MH-2810 Construction of Backdrop 2 0% 05-Apr-18 07-Apr-18 05-Apr-18 07-Apr-18 -65 Construction of Backdrop
NAD-MIS-001-MH-2820 External Water Proofing 2 0% 05-Apr-18 07-Apr-18 05-Apr-18 07-Apr-18 -65 External Water Proofing
NAD-MIS-001-MH-2840 Cating/Placing of Cover Slab 2 0% 08-Apr-18 09-Apr-18 08-Apr-18 09-Apr-18 -65 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2850 Internal Finishing 2 0% 10-Apr-18 11-Apr-18 10-Apr-18 11-Apr-18 -65 Internal Finishing
NAD-MIS-001-MH-2860 Cover and Frames 2 0% 12-Apr-18 14-Apr-18 12-Apr-18 14-Apr-18 -65 Cover and Frames
NAD-MIS-001-PL-2170 Install Dewatering system 2 0% 22-Mar-18 24-Mar-18 22-Mar-18 24-Mar-18 -63 Install Dewatering system
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 35 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-2180 Excavation to Formation Level 2 0% 25-Mar-18 26-Mar-18 25-Mar-18 26-Mar-18 -63 Excavation to Formation Level
NAD-MIS-001-PL-2200 Pipe Surround 2 0% 29-Mar-18 31-Mar-18 29-Mar-18 31-Mar-18 -59 Pipe Surround
NAD-MIS-001-MH-2880 Casting/Placing of Base Slab 2 0% 27-Mar-18 28-Mar-18 27-Mar-18 28-Mar-18 -63 Casting/Placing of Base Slab
NAD-MIS-001-MH-2890 Casting/Placing of Walls 2 0% 29-Mar-18 31-Mar-18 29-Mar-18 31-Mar-18 -63 Casting/Placing of Walls
NAD-MIS-001-MH-2900 Casting/Placing of Reducer Slab 2 0% 01-Apr-18 02-Apr-18 01-Apr-18 02-Apr-18 -63 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-2910 Cating/Placing of Shafts 2 0% 03-Apr-18 04-Apr-18 03-Apr-18 04-Apr-18 -63 Cating/Placing of Shafts
NAD-MIS-001-MH-2930 External Water Proofing 2 0% 05-Apr-18 07-Apr-18 05-Apr-18 07-Apr-18 -63 External Water Proofing
NAD-MIS-001-MH-2920 Construction of Backdrop 2 0% 05-Apr-18 07-Apr-18 05-Apr-18 07-Apr-18 -63 Construction of Backdrop
NAD-MIS-001-MH-2950 Cating/Placing of Cover Slab 2 0% 10-Apr-18 11-Apr-18 10-Apr-18 11-Apr-18 -65 Cating/Placing of Cover Slab
NAD-MIS-001-MH-2960 Internal Finishing 2 0% 12-Apr-18 14-Apr-18 12-Apr-18 14-Apr-18 -65 Internal Finishing
NAD-MIS-001-MH-2970 Cover and Frames 2 0% 15-Apr-18 16-Apr-18 15-Apr-18 16-Apr-18 -65 Cover and Frames
NAD-MIS-001-PL-3850 Excavation for Receiving Pit 5 0% 17-Apr-18 22-Apr-18 17-Apr-18 22-Apr-18 -44 Excavation for Receiving Pit
NAD-MIS-001-PL-3880 Pipe Surround 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -44 Pipe Surround
NAD-MIS-001-PL-2240 Install Dewatering system 3 0% 25-Mar-18 27-Mar-18 25-Mar-18 27-Mar-18 -65 Install Dewatering system
NAD-MIS-001-PL-2250 Excavation to Formation Level 3 0% 28-Mar-18 31-Mar-18 28-Mar-18 31-Mar-18 -65 Excavation to Formation Level
NAD-MIS-001-PL-2270 Pipe Surround 2 0% 03-Apr-18 04-Apr-18 03-Apr-18 04-Apr-18 -61 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 36 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-2280 Backfilling 2 0% 05-Apr-18 07-Apr-18 05-Apr-18 07-Apr-18 -61 Backfilling
NAD-MIS-001-MH-2990 Casting/Placing of Base Slab 2 0% 01-Apr-18 02-Apr-18 01-Apr-18 02-Apr-18 -65 Casting/Placing of Base Slab
NAD-MIS-001-MH-3000 Casting/Placing of Walls 2 0% 03-Apr-18 04-Apr-18 03-Apr-18 04-Apr-18 -65 Casting/Placing of Walls
NAD-MIS-001-MH-3010 Casting/Placing of Reducer Slab 2 0% 05-Apr-18 07-Apr-18 05-Apr-18 07-Apr-18 -65 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3020 Cating/Placing of Shafts 2 0% 08-Apr-18 09-Apr-18 08-Apr-18 09-Apr-18 -65 Cating/Placing of Shafts
NAD-MIS-001-MH-3030 Construction of Backdrop 2 0% 10-Apr-18 11-Apr-18 10-Apr-18 11-Apr-18 -65 Construction of Backdrop
NAD-MIS-001-MH-3040 External Water Proofing 2 0% 10-Apr-18 11-Apr-18 10-Apr-18 11-Apr-18 -65 External Water Proofing
NAD-MIS-001-MH-3060 Cating/Placing of Cover Slab 2 0% 12-Apr-18 14-Apr-18 12-Apr-18 14-Apr-18 -65 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3070 Internal Finishing 2 0% 15-Apr-18 16-Apr-18 15-Apr-18 16-Apr-18 -65 Internal Finishing
NAD-MIS-001-MH-3080 Cover and Frames 2 0% 17-Apr-18 18-Apr-18 17-Apr-18 18-Apr-18 -65 Cover and Frames
NAD-MIS-001-PL-2310 Install Dewatering system 3 0% 28-Mar-18 31-Mar-18 28-Mar-18 31-Mar-18 -66 Install Dewatering system
NAD-MIS-001-PL-2320 Excavation to Formation Level 3 0% 01-Apr-18 03-Apr-18 01-Apr-18 03-Apr-18 -66 Excavation to Formation Level
NAD-MIS-001-PL-2340 Pipe Surround 2 0% 07-Apr-18 08-Apr-18 07-Apr-18 08-Apr-18 -62 Pipe Surround
NAD-MIS-001-MH-3100 Casting/Placing of Base Slab 2 0% 04-Apr-18 05-Apr-18 04-Apr-18 05-Apr-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-3110 Casting/Placing of Walls 2 0% 07-Apr-18 08-Apr-18 07-Apr-18 08-Apr-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-3120 Casting/Placing of Reducer Slab 2 0% 09-Apr-18 10-Apr-18 09-Apr-18 10-Apr-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3130 Cating/Placing of Shafts 2 0% 11-Apr-18 12-Apr-18 11-Apr-18 12-Apr-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-3140 Construction of Backdrop 2 0% 14-Apr-18 15-Apr-18 14-Apr-18 15-Apr-18 -66 Construction of Backdrop
NAD-MIS-001-MH-3150 External Water Proofing 2 0% 14-Apr-18 15-Apr-18 14-Apr-18 15-Apr-18 -66 External Water Proofing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 37 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-3170 Cating/Placing of Cover Slab 2 0% 16-Apr-18 17-Apr-18 16-Apr-18 17-Apr-18 -66 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3180 Internal Finishing 2 0% 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18 -66 Internal Finishing
NAD-MIS-001-MH-3190 Cover and Frames 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -66 Cover and Frames
NAD-MIS-001-PL-2380 Install Dewatering system 3 0% 01-Apr-18 03-Apr-18 01-Apr-18 03-Apr-18 -67 Install Dewatering system
NAD-MIS-001-PL-2390 Excavation to Formation Level 3 0% 04-Apr-18 07-Apr-18 04-Apr-18 07-Apr-18 -67 Excavation to Formation Level
NAD-MIS-001-PL-2410 Pipe Surround 2 0% 10-Apr-18 11-Apr-18 10-Apr-18 11-Apr-18 -63 Pipe Surround
NAD-MIS-001-MH-3210 Casting/Placing of Base Slab 2 0% 08-Apr-18 09-Apr-18 08-Apr-18 09-Apr-18 -67 Casting/Placing of Base Slab
NAD-MIS-001-MH-3220 Casting/Placing of Walls 2 0% 10-Apr-18 11-Apr-18 10-Apr-18 11-Apr-18 -67 Casting/Placing of Walls
NAD-MIS-001-MH-3230 Casting/Placing of Reducer Slab 2 0% 12-Apr-18 14-Apr-18 12-Apr-18 14-Apr-18 -67 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3240 Cating/Placing of Shafts 2 0% 15-Apr-18 16-Apr-18 15-Apr-18 16-Apr-18 -67 Cating/Placing of Shafts
NAD-MIS-001-MH-3250 Construction of Backdrop 2 0% 17-Apr-18 18-Apr-18 17-Apr-18 18-Apr-18 -67 Construction of Backdrop
NAD-MIS-001-MH-3260 External Water Proofing 2 0% 17-Apr-18 18-Apr-18 17-Apr-18 18-Apr-18 -67 External Water Proofing
NAD-MIS-001-MH-3280 Cating/Placing of Cover Slab 2 0% 19-Apr-18 21-Apr-18 19-Apr-18 21-Apr-18 -67 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3290 Internal Finishing 2 0% 22-Apr-18 23-Apr-18 22-Apr-18 23-Apr-18 -67 Internal Finishing
NAD-MIS-001-MH-3300 Cover and Frames 2 0% 24-Apr-18 25-Apr-18 24-Apr-18 25-Apr-18 -67 Cover and Frames
NAD-MIS-001-PL-2450 Install Dewatering system 4 0% 04-Apr-18 08-Apr-18 04-Apr-18 08-Apr-18 -70 Install Dewatering system
NAD-MIS-001-PL-2460 Excavation to Formation Level 4 0% 09-Apr-18 12-Apr-18 09-Apr-18 12-Apr-18 -70 Excavation to Formation Level
NAD-MIS-001-PL-2480 Pipe Surround 3 0% 16-Apr-18 18-Apr-18 16-Apr-18 18-Apr-18 -67 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 38 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MANHOLE CONSTRUCTION 18 11-Apr-18 01-May-18 11-Apr-18 01-May-18 -70
NAD-MIS-001-MH-3310 Excavation and Blinding 2 0% 11-Apr-18 12-Apr-18 11-Apr-18 12-Apr-18 -70 Excavation and Blinding
NAD-MIS-001-MH-3320 Casting/Placing of Base Slab 2 0% 14-Apr-18 15-Apr-18 14-Apr-18 15-Apr-18 -70 Casting/Placing of Base Slab
NAD-MIS-001-MH-3330 Casting/Placing of Walls 2 0% 16-Apr-18 17-Apr-18 16-Apr-18 17-Apr-18 -70 Casting/Placing of Walls
NAD-MIS-001-MH-3340 Casting/Placing of Reducer Slab 2 0% 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18 -70 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3350 Cating/Placing of Shafts 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -70 Cating/Placing of Shafts
NAD-MIS-001-MH-3360 Construction of Backdrop 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -70 Construction of Backdrop
NAD-MIS-001-MH-3370 External Water Proofing 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -70 External Water Proofing
NAD-MIS-001-MH-3390 Cating/Placing of Cover Slab 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3400 Internal Finishing 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -70 Internal Finishing
NAD-MIS-001-MH-3410 Cover and Frames 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -70 Cover and Frames
NAD-MIS-001-PL-3920 Excavation for Receiving Pit 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -49 Excavation for Receiving Pit
NAD-MIS-001-PL-3950 Pipe Surround 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -49 Pipe Surround
NAD-MIS-001-PL-2520 Install Dewatering system 2 0% 09-Apr-18 10-Apr-18 09-Apr-18 10-Apr-18 -68 Install Dewatering system
NAD-MIS-001-PL-2530 Excavation to Formation Level 2 0% 11-Apr-18 12-Apr-18 11-Apr-18 12-Apr-18 -68 Excavation to Formation Level
NAD-MIS-001-PL-2550 Pipe Surround 2 0% 16-Apr-18 17-Apr-18 16-Apr-18 17-Apr-18 -64 Pipe Surround
NAD-MIS-001-MH-3430 Casting/Placing of Base Slab 2 0% 14-Apr-18 15-Apr-18 14-Apr-18 15-Apr-18 -68 Casting/Placing of Base Slab
NAD-MIS-001-MH-3440 Casting/Placing of Walls 2 0% 16-Apr-18 17-Apr-18 16-Apr-18 17-Apr-18 -68 Casting/Placing of Walls
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 39 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-3450 Casting/Placing of Reducer Slab 2 0% 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18 -68 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3460 Cating/Placing of Shafts 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -68 Cating/Placing of Shafts
NAD-MIS-001-MH-3470 Construction of Backdrop 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -68 Construction of Backdrop
NAD-MIS-001-MH-3480 External Water Proofing 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -68 External Water Proofing
NAD-MIS-001-MH-3500 Cating/Placing of Cover Slab 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3510 Internal Finishing 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -70 Internal Finishing
NAD-MIS-001-MH-3520 Cover and Frames 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -70 Cover and Frames
NAD-MIS-001-PL-3990 Excavation for Receiving Pit 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -50 Excavation for Receiving Pit
NAD-MIS-001-PL-4020 Pipe Surround 2 0% 13-May-18 14-May-18 13-May-18 14-May-18 -50 Pipe Surround
NAD-MIS-001-PL-2590 Install Dewatering system 2 0% 11-Apr-18 12-Apr-18 11-Apr-18 12-Apr-18 -68 Install Dewatering system
NAD-MIS-001-PL-2600 Excavation to Formation Level 2 0% 14-Apr-18 15-Apr-18 14-Apr-18 15-Apr-18 -68 Excavation to Formation Level
NAD-MIS-001-PL-2620 Pipe Surround 2 0% 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18 -64 Pipe Surround
NAD-MIS-001-MH-3540 Casting/Placing of Base Slab 2 0% 16-Apr-18 17-Apr-18 16-Apr-18 17-Apr-18 -68 Casting/Placing of Base Slab
NAD-MIS-001-MH-3550 Casting/Placing of Walls 2 0% 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18 -68 Casting/Placing of Walls
NAD-MIS-001-MH-3560 Casting/Placing of Reducer Slab 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -68 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3570 Cating/Placing of Shafts 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -68 Cating/Placing of Shafts
NAD-MIS-001-MH-3580 Construction of Backdrop 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -68 Construction of Backdrop
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 40 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-3590 External Water Proofing 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -68 External Water Proofing
NAD-MIS-001-MH-3610 Cating/Placing of Cover Slab 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3620 Internal Finishing 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -70 Internal Finishing
NAD-MIS-001-MH-3630 Cover and Frames 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -70 Cover and Frames
NAD-MIS-001-PL-2660 Install Dewatering system 2 0% 14-Apr-18 15-Apr-18 14-Apr-18 15-Apr-18 -68 Install Dewatering system
NAD-MIS-001-PL-2670 Excavation to Formation Level 2 0% 16-Apr-18 17-Apr-18 16-Apr-18 17-Apr-18 -68 Excavation to Formation Level
NAD-MIS-001-PL-2690 Pipe Surround 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -64 Pipe Surround
NAD-MIS-001-MH-3650 Casting/Placing of Base Slab 2 0% 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18 -68 Casting/Placing of Base Slab
NAD-MIS-001-MH-3660 Casting/Placing of Walls 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -68 Casting/Placing of Walls
NAD-MIS-001-MH-3670 Casting/Placing of Reducer Slab 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -68 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3680 Cating/Placing of Shafts 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -68 Cating/Placing of Shafts
NAD-MIS-001-MH-3690 Construction of Backdrop 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -68 Construction of Backdrop
NAD-MIS-001-MH-3700 External Water Proofing 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -68 External Water Proofing
NAD-MIS-001-MH-3720 Cating/Placing of Cover Slab 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3730 Internal Finishing 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -70 Internal Finishing
NAD-MIS-001-MH-3740 Cover and Frames 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -70 Cover and Frames
NAD-MIS-001-PL-2730 Install Dewatering system 2 0% 16-Apr-18 17-Apr-18 16-Apr-18 17-Apr-18 -68 Install Dewatering system
NAD-MIS-001-PL-2740 Excavation to Formation Level 2 0% 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18 -68 Excavation to Formation Level
NAD-MIS-001-PL-2760 Pipe Surround 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -64 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 41 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-2770 Backfilling 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -64 Backfilling
NAD-MIS-001-MH-3760 Casting/Placing of Base Slab 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -68 Casting/Placing of Base Slab
NAD-MIS-001-MH-3770 Casting/Placing of Walls 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -68 Casting/Placing of Walls
NAD-MIS-001-MH-3780 Casting/Placing of Reducer Slab 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -68 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3790 Cating/Placing of Shafts 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -68 Cating/Placing of Shafts
NAD-MIS-001-MH-3800 Construction of Backdrop 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -68 Construction of Backdrop
NAD-MIS-001-MH-3810 External Water Proofing 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -68 External Water Proofing
NAD-MIS-001-MH-3830 Cating/Placing of Cover Slab 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3840 Internal Finishing 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -70 Internal Finishing
NAD-MIS-001-MH-3850 Cover and Frames 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -70 Cover and Frames
NAD-MIS-001-PL-2800 Install Dewatering system 1 0% 18-Apr-18 18-Apr-18 18-Apr-18 18-Apr-18 -66 Install Dewatering system
NAD-MIS-001-PL-2810 Excavation to Formation Level 1 0% 19-Apr-18 19-Apr-18 19-Apr-18 19-Apr-18 -66 Excavation to Formation Level
NAD-MIS-001-PL-2830 Pipe Surround 1 0% 23-Apr-18 23-Apr-18 23-Apr-18 23-Apr-18 -60 Pipe Surround
NAD-MIS-001-MH-3870 Casting/Placing of Base Slab 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-3880 Casting/Placing of Walls 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-3890 Casting/Placing of Reducer Slab 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-3900 Cating/Placing of Shafts 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-3910 Construction of Backdrop 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-3920 External Water Proofing 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -66 External Water Proofing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 42 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-3940 Cating/Placing of Cover Slab 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-3950 Internal Finishing 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -70 Internal Finishing
NAD-MIS-001-MH-3960 Cover and Frames 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -70 Cover and Frames
NAD-MIS-001-PL-2870 Install Dewatering system 1 0% 19-Apr-18 19-Apr-18 19-Apr-18 19-Apr-18 -65 Install Dewatering system
NAD-MIS-001-PL-2880 Excavation to Formation Level 1 0% 21-Apr-18 21-Apr-18 21-Apr-18 21-Apr-18 -65 Excavation to Formation Level
NAD-MIS-001-PL-2900 Pipe Surround 1 0% 24-Apr-18 24-Apr-18 24-Apr-18 24-Apr-18 -59 Pipe Surround
NAD-MIS-001-MH-3980 Casting/Placing of Base Slab 2 0% 22-Apr-18 23-Apr-18 22-Apr-18 23-Apr-18 -65 Casting/Placing of Base Slab
NAD-MIS-001-MH-3990 Casting/Placing of Walls 2 0% 24-Apr-18 25-Apr-18 24-Apr-18 25-Apr-18 -65 Casting/Placing of Walls
NAD-MIS-001-MH-4000 Casting/Placing of Reducer Slab 2 0% 26-Apr-18 28-Apr-18 26-Apr-18 28-Apr-18 -65 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4010 Cating/Placing of Shafts 2 0% 29-Apr-18 30-Apr-18 29-Apr-18 30-Apr-18 -65 Cating/Placing of Shafts
NAD-MIS-001-MH-4020 Construction of Backdrop 2 0% 01-May-18 02-May-18 01-May-18 02-May-18 -65 Construction of Backdrop
NAD-MIS-001-MH-4030 External Water Proofing 2 0% 01-May-18 02-May-18 01-May-18 02-May-18 -65 External Water Proofing
NAD-MIS-001-MH-4050 Cating/Placing of Cover Slab 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4060 Internal Finishing 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4070 Cover and Frames 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -70 Cover and Frames
NAD-MIS-001-PL-2940 Install Dewatering system 2 0% 21-Apr-18 22-Apr-18 21-Apr-18 22-Apr-18 -66 Install Dewatering system
NAD-MIS-001-PL-2950 Excavation to Formation Level 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -66 Excavation to Formation Level
NAD-MIS-001-PL-2970 Pipe Surround 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -62 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 43 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MANHOLE CONSTRUCTION 22 23-Apr-18 17-May-18 23-Apr-18 17-May-18 -70
NAD-MIS-001-MH-4080 Excavation and Blinding 2 0% 23-Apr-18 24-Apr-18 23-Apr-18 24-Apr-18 -66 Excavation and Blinding
NAD-MIS-001-MH-4090 Casting/Placing of Base Slab 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4100 Casting/Placing of Walls 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4110 Casting/Placing of Reducer Slab 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4120 Cating/Placing of Shafts 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4130 Construction of Backdrop 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-4140 External Water Proofing 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4160 Cating/Placing of Cover Slab 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4170 Internal Finishing 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4180 Cover and Frames 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -70 Cover and Frames
NAD-MIS-001-MH-4200 Casting/Placing of Base Slab 2 0% 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4210 Casting/Placing of Walls 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4220 Casting/Placing of Reducer Slab 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4230 Cating/Placing of Shafts 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4240 Construction of Backdrop 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-4250 External Water Proofing 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4270 Cating/Placing of Cover Slab 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -66 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4280 Internal Finishing 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -66 Internal Finishing
NAD-MIS-001-MH-4290 Cover and Frames 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -66 Cover and Frames
NAD-MIS-001-MH-4310 Casting/Placing of Base Slab 2 0% 28-Apr-18 29-Apr-18 28-Apr-18 29-Apr-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4320 Casting/Placing of Walls 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4330 Casting/Placing of Reducer Slab 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4340 Cating/Placing of Shafts 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4350 Construction of Backdrop 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -66 Construction of Backdrop
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 44 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-4360 External Water Proofing 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4380 Cating/Placing of Cover Slab 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4390 Internal Finishing 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4400 Cover and Frames 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -70 Cover and Frames
NAD-MIS-001-MH-4420 Casting/Placing of Base Slab 2 0% 30-Apr-18 01-May-18 30-Apr-18 01-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4430 Casting/Placing of Walls 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4440 Casting/Placing of Reducer Slab 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4450 Cating/Placing of Shafts 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4470 External Water Proofing 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4460 Construction of Backdrop 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-4490 Cating/Placing of Cover Slab 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4500 Internal Finishing 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4510 Cover and Frames 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -70 Cover and Frames
NAD-MIS-001-MH-4530 Casting/Placing of Base Slab 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4540 Casting/Placing of Walls 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4550 Casting/Placing of Reducer Slab 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4560 Cating/Placing of Shafts 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4570 Construction of Backdrop 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-4580 External Water Proofing 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4600 Cating/Placing of Cover Slab 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4610 Internal Finishing 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4620 Cover and Frames 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -70 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 45 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-4630 Excavation and Blinding 2 0% 02-May-18 03-May-18 02-May-18 03-May-18 -66 Excavation and Blinding
NAD-MIS-001-MH-4640 Casting/Placing of Base Slab 2 0% 05-May-18 06-May-18 05-May-18 06-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4650 Casting/Placing of Walls 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4660 Casting/Placing of Reducer Slab 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4670 Cating/Placing of Shafts 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4680 Construction of Backdrop 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-4690 External Water Proofing 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4710 Cating/Placing of Cover Slab 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4720 Internal Finishing 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4730 Cover and Frames 2 0% 26-May-18 27-May-18 26-May-18 27-May-18 -70 Cover and Frames
NAD-MIS-001-MH-4750 Casting/Placing of Base Slab 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4760 Casting/Placing of Walls 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4770 Casting/Placing of Reducer Slab 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4780 Cating/Placing of Shafts 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4790 Construction of Backdrop 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-4800 External Water Proofing 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4820 Cating/Placing of Cover Slab 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4830 Internal Finishing 2 0% 26-May-18 27-May-18 26-May-18 27-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4840 Cover and Frames 2 0% 28-May-18 29-May-18 28-May-18 29-May-18 -70 Cover and Frames
NAD-MIS-001-MH-4860 Casting/Placing of Base Slab 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4870 Casting/Placing of Walls 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4880 Casting/Placing of Reducer Slab 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-4890 Cating/Placing of Shafts 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-4900 Construction of Backdrop 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -66 Construction of Backdrop
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 46 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-4910 External Water Proofing 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -66 External Water Proofing
NAD-MIS-001-MH-4930 Cating/Placing of Cover Slab 2 0% 26-May-18 27-May-18 26-May-18 27-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-4940 Internal Finishing 2 0% 28-May-18 29-May-18 28-May-18 29-May-18 -70 Internal Finishing
NAD-MIS-001-MH-4950 Cover and Frames 2 0% 30-May-18 31-May-18 30-May-18 31-May-18 -70 Cover and Frames
NAD-MIS-001-MH-4970 Casting/Placing of Base Slab 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-4980 Casting/Placing of Walls 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-4990 Casting/Placing of Reducer Slab 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5000 Cating/Placing of Shafts 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-5010 Construction of Backdrop 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-5020 External Water Proofing 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -66 External Water Proofing
NAD-MIS-001-MH-5040 Cating/Placing of Cover Slab 2 0% 28-May-18 29-May-18 28-May-18 29-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5050 Internal Finishing 2 0% 30-May-18 31-May-18 30-May-18 31-May-18 -70 Internal Finishing
NAD-MIS-001-MH-5060 Cover and Frames 2 0% 02-Jun-18 03-Jun-18 02-Jun-18 03-Jun-18 -70 Cover and Frames
NAD-MIS-001-MH-5080 Casting/Placing of Base Slab 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-5090 Casting/Placing of Walls 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-5100 Casting/Placing of Reducer Slab 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5110 Casting/Placing of Shafts 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -66 Casting/Placing of Shafts
NAD-MIS-001-MH-5120 Construction of Backdrop 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-5130 External Water Proofing 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -66 External Water Proofing
NAD-MIS-001-MH-5150 Cating/Placing of Cover Slab 2 0% 30-May-18 31-May-18 30-May-18 31-May-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5160 Internal Finishing 2 0% 02-Jun-18 03-Jun-18 02-Jun-18 03-Jun-18 -70 Internal Finishing
NAD-MIS-001-MH-5170 Cover and Frames 2 0% 04-Jun-18 05-Jun-18 04-Jun-18 05-Jun-18 -70 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 47 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-5180 Excavation and Blinding 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -66 Excavation and Blinding
NAD-MIS-001-MH-5190 Casting/Placing of Base Slab 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-5200 Casting/Placing of Walls 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-5210 Casting/Placing of Reducer Slab 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5220 Casting/Placing of Shafts 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -66 Casting/Placing of Shafts
NAD-MIS-001-MH-5230 Construction of Backdrop 2 0% 26-May-18 27-May-18 26-May-18 27-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-5240 External Water Proofing 2 0% 26-May-18 27-May-18 26-May-18 27-May-18 -66 External Water Proofing
NAD-MIS-001-MH-5260 Cating/Placing of Cover Slab 2 0% 02-Jun-18 03-Jun-18 02-Jun-18 03-Jun-18 -70 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5270 Internal Finishing 2 0% 04-Jun-18 05-Jun-18 04-Jun-18 05-Jun-18 -70 Internal Finishing
NAD-MIS-001-MH-5280 Cover and Frames 2 0% 06-Jun-18 07-Jun-18 06-Jun-18 07-Jun-18 -70 Cover and Frames
NAD-MIS-001-MH-5300 Casting/Placing of Base Slab 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -66 Casting/Placing of Base Slab
NAD-MIS-001-MH-5310 Casting/Placing of Walls 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -66 Casting/Placing of Walls
NAD-MIS-001-MH-5320 Casting/Placing of Reducer Slab 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -66 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5330 Cating/Placing of Shafts 2 0% 26-May-18 27-May-18 26-May-18 27-May-18 -66 Cating/Placing of Shafts
NAD-MIS-001-MH-5340 Construction of Backdrop 2 0% 28-May-18 29-May-18 28-May-18 29-May-18 -66 Construction of Backdrop
NAD-MIS-001-MH-5350 External Water Proofing 2 0% 28-May-18 29-May-18 28-May-18 29-May-18 -66 External Water Proofing
NAD-MIS-001-MH-5370 Casting/Placing of Cover Slab 2 0% 04-Jun-18 05-Jun-18 04-Jun-18 05-Jun-18 -70 Casting/Placing of Cover Slab
NAD-MIS-001-MH-5380 Internal Finishing 2 0% 06-Jun-18 07-Jun-18 06-Jun-18 07-Jun-18 -70 Internal Finishing
NAD-MIS-001-MH-5390 Cover and Frames 2 0% 09-Jun-18 10-Jun-18 09-Jun-18 10-Jun-18 -70 Cover and Frames
JUM-MIS-002-PL-1010 Excavation for Receiving Pit 6 100% 04-Sep-17 10-Sep-17 04-Sep-17 A 10-Sep-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 48 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
JUM-MIS-002-PL-1060 Testing 4 100% 17-Oct-17 21-Oct-17 17-Oct-17 A 21-Oct-17 A
NAD-MIS-002-MH-1010 Casting/Placing of Base Slab 4 0% 05-Feb-18 08-Feb-18 05-Feb-18 08-Feb-18 15 Casting/Placing of Base Slab
NAD-MIS-002-MH-1030 Casting/Placing of Reducer Slab 2 0% 14-Feb-18 15-Feb-18 14-Feb-18 15-Feb-18 15 Casting/Placing of Reducer Slab
NAD-MIS-002-MH-1060 External Water Proofing 2 0% 20-Feb-18 21-Feb-18 20-Feb-18 21-Feb-18 15 External Water Proofing
NAD-MIS-002-MH-1080 Cating/Placing of Cover Slab 2 0% 22-Feb-18 24-Feb-18 22-Feb-18 24-Feb-18 15 Cating/Placing of Cover Slab
NAD-MIS-002-MH-1100 Cover and Frames 2 0% 27-Feb-18 28-Feb-18 27-Feb-18 28-Feb-18 15 Cover and Frames
JUM-MIS-002-MH-1120 Casting/Placing of Base Slab 3 0% 11-Feb-18 14-Feb-18 11-Feb-18 14-Feb-18 13 Casting/Placing of Base Slab
JUM-MIS-002-MH-1140 Casting/Placing of Reducer Slab 3 0% 18-Feb-18 21-Feb-18 18-Feb-18 21-Feb-18 13 Casting/Placing of Reducer Slab
JUM-MIS-002-MH-1170 External Water Proofing 2 0% 24-Feb-18 26-Feb-18 24-Feb-18 26-Feb-18 13 External Water Proofing
JUM-MIS-002-MH-1190 Cating/Placing of Cover Slab 2 0% 26-Feb-18 28-Feb-18 26-Feb-18 28-Feb-18 13 Cating/Placing of Cover Slab
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 49 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-002-MH-1210 Cover and Frames 2 0% 03-Mar-18 05-Mar-18 03-Mar-18 05-Mar-18 13 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 50 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
AM-MIS-213/2-PL-1230 Testing 2 100% 06-Mar-17 08-Mar-17 06-Mar-17 A 08-Mar-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 51 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
CH-3+752-3+846 12 18-Mar-17 01-Apr-17 18-Mar-17 A 01-Apr-17 A
PIPELINE 12 18-Mar-17 01-Apr-17 18-Mar-17 A 01-Apr-17 A
AM-MIS-213/2-PL-1480 Excavation and Formation 3 100% 18-Mar-17 21-Mar-17 18-Mar-17 A 21-Mar-17 A
AM-MIS-213/2-MH-1030 Installation of DI Valves and Fittings 2 100% 09-Apr-17 11-Apr-17 09-Apr-17 A 11-Apr-17 A
AM-MIS-213/2-MH-1040 Casting / Placing of Cover Slab 2 100% 11-Apr-17 13-Apr-17 11-Apr-17 A 13-Apr-17 A
AM-MIS-213/2-MH-1050 External Waterproofing and Backfilling 2 100% 11-Apr-17 13-Apr-17 11-Apr-17 A 13-Apr-17 A
AM-MIS-213/2-MH-1070 Installation of Cover & Frame 2 100% 11-Apr-17 13-Apr-17 11-Apr-17 A 13-Apr-17 A
AM-MIS-213/2-MH-1110 Installation of DI Valves and Fittings 2 100% 11-Apr-17 13-Apr-17 11-Apr-17 A 13-Apr-17 A
AM-MIS-213/2-MH-1120 Casting / Placing of Cover Slab 2 100% 13-Apr-17 16-Apr-17 13-Apr-17 A 16-Apr-17 A
AM-MIS-213/2-MH-1130 External Waterproofing and Backfilling 2 100% 13-Apr-17 16-Apr-17 13-Apr-17 A 16-Apr-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 52 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
AM-MIS-213/2-MH-1140 Internal Finishing 2 100% 13-Apr-17 16-Apr-17 13-Apr-17 A 16-Apr-17 A
AM-MIS-213/2-MH-1150 Installation of Cover & Frame 2 100% 13-Apr-17 16-Apr-17 13-Apr-17 A 16-Apr-17 A
AM-MIS-213/2-MH-1190 Installation of DI Valves and Fittings 2 100% 13-Apr-17 16-Apr-17 13-Apr-17 A 16-Apr-17 A
AM-MIS-213/2-MH-1200 Casting / Placing of Cover Slab 2 100% 16-Apr-17 18-Apr-17 16-Apr-17 A 18-Apr-17 A
AM-MIS-213/2-MH-1210 External Waterproofing and Backfilling 2 100% 16-Apr-17 18-Apr-17 16-Apr-17 A 18-Apr-17 A
AM-MIS-213/2-MH-1230 Installation of Cover & Frame 2 100% 16-Apr-17 18-Apr-17 16-Apr-17 A 18-Apr-17 A
AM-MIS-213/2-MH-1270 Installation of DI Valves and Fittings 2 100% 16-Apr-17 18-Apr-17 16-Apr-17 A 18-Apr-17 A
AM-MIS-213/2-MH-1280 Casting / Placing of Cover Slab 2 100% 18-Apr-17 20-Apr-17 18-Apr-17 A 20-Apr-17 A
AM-MIS-213/2-MH-1290 External Waterproofing and Backfilling 2 100% 18-Apr-17 20-Apr-17 18-Apr-17 A 20-Apr-17 A
AM-MIS-213/2-MH-1310 Installation of Cover & Frame 2 100% 18-Apr-17 20-Apr-17 18-Apr-17 A 20-Apr-17 A
AM-MIS-213/2-MH-1350 Installation of DI Valves and Fittings 2 100% 18-Apr-17 20-Apr-17 18-Apr-17 A 20-Apr-17 A
AM-MIS-213/2-MH-1360 Casting / Placing of Cover Slab 2 100% 20-Apr-17 23-Apr-17 20-Apr-17 A 23-Apr-17 A
AM-MIS-213/2-MH-1370 External Waterproofing and Backfilling 2 100% 20-Apr-17 23-Apr-17 20-Apr-17 A 23-Apr-17 A
AM-MIS-213/2-MH-1390 Installation of Cover & Frame 2 100% 20-Apr-17 23-Apr-17 20-Apr-17 A 23-Apr-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 53 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
AM-MIS-213/2-MH-1410 Casting/Placing of Base Slab 2 100% 15-Apr-17 17-Apr-17 15-Apr-17 A 17-Apr-17 A
AM-MIS-213/2-MH-1430 Installation of DI Valves and Fittings 2 100% 20-Apr-17 23-Apr-17 20-Apr-17 A 23-Apr-17 A
AM-MIS-213/2-MH-1440 Casting / Placing of Cover Slab 2 100% 23-Apr-17 25-Apr-17 23-Apr-17 A 25-Apr-17 A
AM-MIS-213/2-MH-1450 External Waterproofing and Backfilling 2 100% 23-Apr-17 25-Apr-17 23-Apr-17 A 25-Apr-17 A
AM-MIS-213/2-MH-1470 Installation of Cover & Frame 2 100% 23-Apr-17 25-Apr-17 23-Apr-17 A 25-Apr-17 A
AM-MIS-213/2-MH-1510 Installation of DI Valves and Fittings 2 100% 10-Sep-17 11-Sep-17 10-Sep-17 A 11-Sep-17 A
AM-MIS-213/2-MH-1520 Casting / Placing of Cover Slab 2 100% 12-Sep-17 13-Sep-17 12-Sep-17 A 13-Sep-17 A
AM-MIS-213/2-MH-1530 External Waterproofing and Backfilling 2 100% 14-Sep-17 16-Sep-17 14-Sep-17 A 16-Sep-17 A
AM-MIS-213/2-MH-1550 Installation of Cover & Frame 2 100% 19-Sep-17 20-Sep-17 19-Sep-17 A 20-Sep-17 A
AM-MIS-213/2-MH-1590 Installation of DI Valves and Fittings 2 100% 28-Sep-17 30-Sep-17 28-Sep-17 A 30-Sep-17 A
AM-MIS-213/2-MH-1600 Casting / Placing of Cover Slab 2 100% 01-Oct-17 02-Oct-17 01-Oct-17 A 02-Oct-17 A
AM-MIS-213/2-MH-1610 External Waterproofing and Backfilling 2 100% 03-Oct-17 04-Oct-17 03-Oct-17 A 04-Oct-17 A
AM-MIS-213/2-MH-1630 Installation of Cover & Frame 2 100% 09-Oct-17 10-Oct-17 09-Oct-17 A 10-Oct-17 A
AM-MIS-213/2-MH-1670 Installation of DI Valves and Fittings 2 100% 18-Nov-17 19-Nov-17 18-Nov-17 A 19-Nov-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 54 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
AM-MIS-213/2-MH-1680 Casting / Placing of Cover Slab 2 100% 19-Nov-17 20-Nov-17 19-Nov-17 A 20-Nov-17 A
AM-MIS-213/2-MH-1690 External Waterproofing and Backfilling 2 100% 21-Nov-17 22-Nov-17 21-Nov-17 A 22-Nov-17 A
AM-MIS-213/2-MH-1710 Installation of Cover & Frame 2 100% 26-Nov-17 27-Nov-17 26-Nov-17 A 27-Nov-17 A
AM-MIS-213/2-MH-1750 Installation of DI Valves and Fittings 2 100% 11-Dec-17 12-Dec-17 11-Dec-17 A 12-Dec-17 A
AM-MIS-213/2-MH-1760 Casting / Placing of Cover Slab 2 100% 13-Dec-17 14-Dec-17 13-Dec-17 A 14-Dec-17 A
AM-MIS-213/2-MH-1770 External Waterproofing and Backfilling 2 100% 16-Dec-17 17-Dec-17 16-Dec-17 A 17-Dec-17 A
AM-MIS-213/2-MH-1790 Installation of Cover & Frame 2 100% 20-Dec-17 21-Dec-17 20-Dec-17 A 21-Dec-17 A
AM-MIS-213/2-MH-1830 Installation of DI Valves and Fittings 2 100% 28-Dec-17 30-Dec-17 28-Dec-17 A 30-Dec-17 A
AM-MIS-213/2-MH-1840 Casting / Placing of Cover Slab 2 0% 31-Jan-18 01-Feb-18 31-Jan-18 01-Feb-18 -54 Casting / Placing of Cover Slab
AM-MIS-213/2-MH-1850 External Waterproofing and Backfilling 2 0% 31-Jan-18 01-Feb-18 31-Jan-18 01-Feb-18 -54 External Waterproofing and Backfilling
AM-MIS-213/2-MH-1860 Internal Finishing 2 0% 31-Jan-18 01-Feb-18 31-Jan-18 01-Feb-18 -54 Internal Finishing
AM-MIS-213/2-MH-1870 Installation of Cover & Frame 2 0% 31-Jan-18 01-Feb-18 31-Jan-18 01-Feb-18 -54 Installation of Cover & Frame
AM-MIS-213/2-MH-1890 Casting/Placing of Base Slab 2 0% 03-Feb-18 04-Feb-18 03-Feb-18 04-Feb-18 -61 Casting/Placing of Base Slab
AM-MIS-213/2-MH-1900 Casting/Placing of Walls 2 0% 05-Feb-18 06-Feb-18 05-Feb-18 06-Feb-18 -61 Casting/Placing of Walls
AM-MIS-213/2-MH-1910 Installation of DI Valves and Fittings 2 0% 08-Feb-18 10-Feb-18 08-Feb-18 10-Feb-18 -61 Installation of DI Valves and Fittings
AM-MIS-213/2-MH-1920 Casting / Placing of Cover Slab 2 0% 11-Feb-18 12-Feb-18 11-Feb-18 12-Feb-18 -61 Casting / Placing of Cover Slab
AM-MIS-213/2-MH-1930 External Waterproofing and Backfilling 2 0% 11-Feb-18 12-Feb-18 11-Feb-18 12-Feb-18 -61 External Waterproofing and Backfilling
AM-MIS-213/2-MH-1940 Internal Finishing 2 0% 11-Feb-18 12-Feb-18 11-Feb-18 12-Feb-18 -61 Internal Finishing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 55 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
AM-MIS-213/2-MH-1950 Installation of Cover & Frame 2 0% 11-Feb-18 12-Feb-18 11-Feb-18 12-Feb-18 -61 Installation of Cover & Frame
AM-MIS-213/2-MH-1970 Casting/Placing of Base Slab 2 0% 05-Feb-18 06-Feb-18 05-Feb-18 06-Feb-18 -61 Casting/Placing of Base Slab
AM-MIS-213/2-MH-1980 Casting/Placing of Walls 2 0% 07-Feb-18 08-Feb-18 07-Feb-18 08-Feb-18 -61 Casting/Placing of Walls
AM-MIS-213/2-MH-1990 Installation of DI Valves and Fittings 2 0% 11-Feb-18 12-Feb-18 11-Feb-18 12-Feb-18 -61 Installation of DI Valves and Fittings
AM-MIS-213/2-MH-2000 Casting / Placing of Cover Slab 2 0% 13-Feb-18 14-Feb-18 13-Feb-18 14-Feb-18 -61 Casting / Placing of Cover Slab
AM-MIS-213/2-MH-2010 External Waterproofing and Backfilling 2 0% 13-Feb-18 14-Feb-18 13-Feb-18 14-Feb-18 -61 External Waterproofing and Backfilling
AM-MIS-213/2-MH-2020 Internal Finishing 2 0% 13-Feb-18 14-Feb-18 13-Feb-18 14-Feb-18 -61 Internal Finishing
AM-MIS-213/2-MH-2030 Installation of Cover & Frame 2 0% 13-Feb-18 14-Feb-18 13-Feb-18 14-Feb-18 -61 Installation of Cover & Frame
INV-MIS-273-PL-1010 Install Dewatering system 15 0% 18-Feb-18 06-Mar-18 18-Feb-18 06-Mar-18 -10 Install Dewatering system
INV-MIS-273-PL-1020 Excavation to Formation Level 12 0% 22-Feb-18 07-Mar-18 22-Feb-18 07-Mar-18 -10 Excavation to Formation Level
INV-MIS-273-PL-1040 Pipe Surround 8 0% 12-Mar-18 20-Mar-18 12-Mar-18 20-Mar-18 -10 Pipe Surround
JUM-MIS-493-MH-1110 Casting/Placing of Base Slab 3 0% 04-Feb-18 06-Feb-18 04-Feb-18 06-Feb-18 21 Casting/Placing of Base Slab
JUM-MIS-493-MH-1130 Casting/Placing of Reducer Slab 2 0% 11-Feb-18 12-Feb-18 11-Feb-18 12-Feb-18 21 Casting/Placing of Reducer Slab
JUM-MIS-493-MH-1160 External Water Proofing 2 0% 15-Feb-18 17-Feb-18 15-Feb-18 17-Feb-18 21 External Water Proofing
JUM-MIS-493-MH-1180 Cating/Placing of Cover Slab 2 0% 18-Feb-18 19-Feb-18 18-Feb-18 19-Feb-18 21 Cating/Placing of Cover Slab
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 56 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
JUM-MIS-493-MH-1190 Internal Finishing 2 0% 20-Feb-18 21-Feb-18 20-Feb-18 21-Feb-18 21 Internal Finishing
JUM-MIS-493-MH-1200 Cover and Frames 2 0% 22-Feb-18 24-Feb-18 22-Feb-18 24-Feb-18 21 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 57 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
JUM-MIS-493-MH-1730 Casting/Placing of Reducer Slab 2 100% 01-Mar-17 04-Mar-17 01-Mar-17 A 04-Mar-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 58 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
JUM-MIS-493-MH-2190 Internal Finishing 2 100% 16-Mar-17 19-Mar-17 16-Mar-17 A 19-Mar-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 59 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
LEH-MIS-584-PL-1010 Pipelaying 10 60% 18-Nov-17 28-Nov-17 18-Nov-17 A 30-Apr-18 -42 Pipelaying
LEH-MIS-584-MH-1010 Casting/Placing of Base Slab 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -53 Casting/Placing of Base Slab
LEH-MIS-584-MH-1020 Casting/Placing of Walls 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -53 Casting/Placing of Walls
LEH-MIS-584-MH-1030 Installation of DI Valves and Fittings 2 0% 13-May-18 14-May-18 13-May-18 14-May-18 -53 Installation of DI Valves and Fitting
LEH-MIS-584-MH-1040 Casting / Placing of Cover Slab 2 0% 15-May-18 16-May-18 15-May-18 16-May-18 -53 Casting / Placing of Cover Slab
LEH-MIS-584-MH-1050 External Waterproofing and Backfilling 2 0% 15-May-18 16-May-18 15-May-18 16-May-18 -53 External Waterproofing and Backf
LEH-MIS-584-MH-1060 Internal Finishing 2 0% 15-May-18 16-May-18 15-May-18 16-May-18 -53 Internal Finishing
LEH-MIS-584-MH-1070 Installation of Cover & Frame 2 0% 15-May-18 16-May-18 15-May-18 16-May-18 -53 Installation of Cover & Frame
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 60 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
AV-1 11 07-May-18 19-May-18 07-May-18 19-May-18 -53
CHAMBER CONSTRUCTION 11 07-May-18 19-May-18 07-May-18 19-May-18 -53
LEH-MIS-584-MH-1080 Blinding and Water proofing 2 0% 07-May-18 08-May-18 07-May-18 08-May-18 -61 Blinding and Water proofing
LEH-MIS-584-MH-1090 Casting/Placing of Base Slab 2 0% 09-May-18 10-May-18 09-May-18 10-May-18 -53 Casting/Placing of Base Slab
LEH-MIS-584-MH-1100 Casting/Placing of Walls 2 0% 12-May-18 13-May-18 12-May-18 13-May-18 -53 Casting/Placing of Walls
LEH-MIS-584-MH-1110 Installation of DI Valves and Fittings 2 0% 15-May-18 16-May-18 15-May-18 16-May-18 -53 Installation of DI Valves and Fitting
LEH-MIS-584-MH-1120 Casting / Placing of Cover Slab 2 0% 17-May-18 19-May-18 17-May-18 19-May-18 -53 Casting / Placing of Cover Slab
LEH-MIS-584-MH-1130 External Waterproofing and Backfilling 2 0% 17-May-18 19-May-18 17-May-18 19-May-18 -53 External Waterproofing and Back
LEH-MIS-584-MH-1140 Internal Finishing 2 0% 17-May-18 19-May-18 17-May-18 19-May-18 -53 Internal Finishing
LEH-MIS-584-MH-1150 Installation of Cover & Frame 2 0% 17-May-18 19-May-18 17-May-18 19-May-18 -53 Installation of Cover & Frame
LEH-MIS-584-MH-1170 Casting/Placing of Base Slab 2 0% 14-May-18 15-May-18 14-May-18 15-May-18 -55 Casting/Placing of Base Slab
LEH-MIS-584-MH-1180 Casting/Placing of Walls 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -55 Casting/Placing of Walls
LEH-MIS-584-MH-1190 Installation of DI Valves and Fittings 2 0% 20-May-18 21-May-18 20-May-18 21-May-18 -55 Installation of DI Valves and Fittin
LEH-MIS-584-MH-1200 Casting / Placing of Cover Slab 2 0% 22-May-18 23-May-18 22-May-18 23-May-18 -55 Casting / Placing of Cover Slab
LEH-MIS-584-MH-1210 External Waterproofing and Backfilling 2 0% 22-May-18 23-May-18 22-May-18 23-May-18 -55 External Waterproofing and Back
LEH-MIS-584-MH-1220 Internal Finishing 2 0% 22-May-18 23-May-18 22-May-18 23-May-18 -55 Internal Finishing
LEH-MIS-584-MH-1230 Installation of Cover & Frame 2 0% 22-May-18 23-May-18 22-May-18 23-May-18 -55 Installation of Cover & Frame
LEH-MIS-584-MH-1250 Casting/Placing of Base Slab 2 0% 16-May-18 17-May-18 16-May-18 17-May-18 -57 Casting/Placing of Base Slab
LEH-MIS-584-MH-1260 Casting/Placing of Walls 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -57 Casting/Placing of Walls
LEH-MIS-584-MH-1270 Installation of DI Valves and Fittings 2 0% 22-May-18 23-May-18 22-May-18 23-May-18 -57 Installation of DI Valves and Fittin
LEH-MIS-584-MH-1280 Casting / Placing of Cover Slab 2 0% 24-May-18 26-May-18 24-May-18 26-May-18 -57 Casting / Placing of Cover Slab
LEH-MIS-584-MH-1290 External Waterproofing and Backfilling 2 0% 24-May-18 26-May-18 24-May-18 26-May-18 -57 External Waterproofing and Back
LEH-MIS-584-MH-1300 Internal Finishing 2 0% 24-May-18 26-May-18 24-May-18 26-May-18 -57 Internal Finishing
LEH-MIS-584-MH-1310 Installation of Cover & Frame 2 0% 24-May-18 26-May-18 24-May-18 26-May-18 -57 Installation of Cover & Frame
LEH-MIS-584-MH-1330 Casting/Placing of Base Slab 2 0% 19-May-18 20-May-18 19-May-18 20-May-18 -61 Casting/Placing of Base Slab
LEH-MIS-584-MH-1340 Casting/Placing of Walls 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -61 Casting/Placing of Walls
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 61 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
LEH-MIS-584-MH-1350 Installation of DI Valves and Fittings 2 0% 24-May-18 26-May-18 24-May-18 26-May-18 -61 Installation of DI Valves and Fittin
LEH-MIS-584-MH-1360 Casting / Placing of Cover Slab 2 0% 27-May-18 28-May-18 27-May-18 28-May-18 -61 Casting / Placing of Cover Slab
LEH-MIS-584-MH-1370 External Waterproofing and Backfilling 2 0% 27-May-18 28-May-18 27-May-18 28-May-18 -61 External Waterproofing and Back
LEH-MIS-584-MH-1380 Internal Finishing 2 0% 27-May-18 28-May-18 27-May-18 28-May-18 -61 Internal Finishing
LEH-MIS-584-MH-1390 Installation of Cover & Frame 2 0% 27-May-18 28-May-18 27-May-18 28-May-18 -61 Installation of Cover & Frame
LEH-MIS-584-MH-1410 Casting/Placing of Base Slab 2 0% 21-May-18 22-May-18 21-May-18 22-May-18 -61 Casting/Placing of Base Slab
LEH-MIS-584-MH-1420 Casting/Placing of Walls 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -61 Casting/Placing of Walls
LEH-MIS-584-MH-1430 Installation of DI Valves and Fittings 2 0% 27-May-18 28-May-18 27-May-18 28-May-18 -61 Installation of DI Valves and Fittin
LEH-MIS-584-MH-1450 External Waterproofing and Backfilling 2 0% 29-May-18 30-May-18 29-May-18 30-May-18 -61 External Waterproofing and Back
LEH-MIS-584-MH-1460 Internal Finishing 2 0% 29-May-18 30-May-18 29-May-18 30-May-18 -61 Internal Finishing
LEH-MIS-584-MH-1470 Installation of Cover & Frame 2 0% 29-May-18 30-May-18 29-May-18 30-May-18 -61 Installation of Cover & Frame
LEH-MIS-584-MH-1440 Casting / Placing of Cover Slab 2 0% 29-May-18 30-May-18 29-May-18 30-May-18 -61 Casting / Placing of Cover Slab
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 62 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
BAR-MIS-965-MH-1070 Backfilling 2 100% 25-Jan-18 27-Jan-18 25-Jan-18 A 27-Jan-18 A
BAR-MIS-965-PL-1080 Install Dewatering system 2 0% 31-Jan-18 01-Feb-18 31-Jan-18 01-Feb-18 18 Install Dewatering system
BAR-MIS-965-PL-1090 Excavation to Formation Level 2 0% 03-Feb-18 04-Feb-18 03-Feb-18 04-Feb-18 18 Excavation to Formation Level
BAR-MIS-965-MH-1120 Casting/Placing of Base Slab 2 0% 05-Feb-18 06-Feb-18 05-Feb-18 06-Feb-18 18 Casting/Placing of Base Slab
BAR-MIS-965-MH-1140 Casting/Placing of Reducer Slab 2 0% 10-Feb-18 11-Feb-18 10-Feb-18 11-Feb-18 18 Casting/Placing of Reducer Slab
BAR-MIS-965-MH-1170 External Water Proofing 2 0% 14-Feb-18 15-Feb-18 14-Feb-18 15-Feb-18 18 External Water Proofing
BAR-MIS-965-MH-1190 Cating/Placing of Cover Slab 2 0% 17-Feb-18 18-Feb-18 17-Feb-18 18-Feb-18 18 Cating/Placing of Cover Slab
BAR-MIS-965-MH-1210 Cover and Frames 2 0% 21-Feb-18 22-Feb-18 21-Feb-18 22-Feb-18 18 Cover and Frames
BAR-MIS-965-PL-1160 Install Dewatering system 2 0% 03-Feb-18 04-Feb-18 03-Feb-18 04-Feb-18 18 Install Dewatering system
BAR-MIS-965-PL-1170 Excavation to Formation Level 2 0% 05-Feb-18 06-Feb-18 05-Feb-18 06-Feb-18 18 Excavation to Formation Level
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 63 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
BAR-MIS-965-PL-1210 Testing 2 0% 14-Feb-18 15-Feb-18 14-Feb-18 15-Feb-18 23 Testing
BAR-MIS-965-MH-1230 Casting/Placing of Base Slab 2 0% 07-Feb-18 08-Feb-18 07-Feb-18 08-Feb-18 18 Casting/Placing of Base Slab
BAR-MIS-965-MH-1250 Casting/Placing of Reducer Slab 2 0% 12-Feb-18 13-Feb-18 12-Feb-18 13-Feb-18 18 Casting/Placing of Reducer Slab
BAR-MIS-965-MH-1280 External Water Proofing 2 0% 17-Feb-18 18-Feb-18 17-Feb-18 18-Feb-18 18 External Water Proofing
BAR-MIS-965-MH-1300 Cating/Placing of Cover Slab 2 0% 19-Feb-18 20-Feb-18 19-Feb-18 20-Feb-18 18 Cating/Placing of Cover Slab
BAR-MIS-965-MH-1320 Cover and Frames 2 0% 24-Feb-18 25-Feb-18 24-Feb-18 25-Feb-18 18 Cover and Frames
BAR-MIS-965-PL-1230 Install Dewatering system 3 0% 05-Feb-18 07-Feb-18 05-Feb-18 07-Feb-18 2 Install Dewatering system
BAR-MIS-965-PL-1240 Excavation to Formation Level 12 0% 08-Feb-18 21-Feb-18 08-Feb-18 21-Feb-18 2 Excavation to Formation Level
BAR-MIS-965-MH-1340 Casting/Placing of Base Slab 2 0% 22-Feb-18 24-Feb-18 22-Feb-18 24-Feb-18 7 Casting/Placing of Base Slab
BAR-MIS-965-MH-1360 Casting/Placing of Reducer Slab 2 0% 27-Feb-18 28-Feb-18 27-Feb-18 28-Feb-18 7 Casting/Placing of Reducer Slab
BAR-MIS-965-MH-1390 External Water Proofing 2 0% 04-Mar-18 05-Mar-18 04-Mar-18 05-Mar-18 7 External Water Proofing
BAR-MIS-965-MH-1410 Cating/Placing of Cover Slab 2 0% 12-Mar-18 13-Mar-18 12-Mar-18 13-Mar-18 2 Cating/Placing of Cover Slab
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 64 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
BAR-MIS-965-MH-1420 Internal Finishing 2 0% 14-Mar-18 15-Mar-18 14-Mar-18 15-Mar-18 2 Internal Finishing
BAR-MIS-965-MH-1430 Cover and Frames 2 0% 17-Mar-18 18-Mar-18 17-Mar-18 18-Mar-18 2 Cover and Frames
BAR-MIS-965-PL-1300 Excavation for Receiving pit 2 100% 28-Oct-17 29-Oct-17 28-Oct-17 A 29-Oct-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 65 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
BAR-MIS-965-MH-1560 Excavation and Blinding 2 100% 12-Sep-17 14-Sep-17 12-Sep-17 A 14-Sep-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 66 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
BAR-MIS-965-MH-1840 External Water Proofing 2 100% 28-Sep-17 01-Oct-17 28-Sep-17 A 01-Oct-17 A
BAR-MIS-965-MH-1990 Cover and Frames 2 0% 08-Feb-18 10-Feb-18 08-Feb-18 10-Feb-18 33 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 67 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
BAR-MIS-965-MH-2120 Excavation and Blinding 2 100% 24-Sep-17 26-Sep-17 24-Sep-17 A 26-Sep-17 A
NAD-MIS-001-MH-5410 Casting/Placing of Base Slab 3 0% 04-Feb-18 06-Feb-18 04-Feb-18 06-Feb-18 -11 Casting/Placing of Base Slab
NAD-MIS-001-MH-5420 Casting/Placing of Walls 3 0% 07-Feb-18 10-Feb-18 07-Feb-18 10-Feb-18 -11 Casting/Placing of Walls
NAD-MIS-001-MH-5430 Casting/Placing of Reducer Slab 3 0% 11-Feb-18 13-Feb-18 11-Feb-18 13-Feb-18 -11 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5440 Cating/Placing of Shafts 3 0% 14-Feb-18 17-Feb-18 14-Feb-18 17-Feb-18 -11 Cating/Placing of Shafts
NAD-MIS-001-MH-5450 Construction of Backdrop 3 0% 18-Feb-18 20-Feb-18 18-Feb-18 20-Feb-18 -11 Construction of Backdrop
NAD-MIS-001-MH-5460 External Water Proofing 3 0% 18-Feb-18 20-Feb-18 18-Feb-18 20-Feb-18 -11 External Water Proofing
NAD-MIS-001-MH-5480 Cating/Placing of Cover Slab 3 0% 21-Feb-18 24-Feb-18 21-Feb-18 24-Feb-18 -11 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5490 Internal Finishing 3 0% 25-Feb-18 27-Feb-18 25-Feb-18 27-Feb-18 -11 Internal Finishing
NAD-MIS-001-MH-5500 Cover and Frames 3 0% 28-Feb-18 03-Mar-18 28-Feb-18 03-Mar-18 -11 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 68 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-3060 Testing 2 100% 23-Sep-17 24-Sep-17 23-Sep-17 A 24-Sep-17 A
NAD-MIS-001-MH-5520 Casting/Placing of Base Slab 3 0% 04-Feb-18 06-Feb-18 04-Feb-18 06-Feb-18 -8 Casting/Placing of Base Slab
NAD-MIS-001-MH-5540 Casting/Placing of Reducer Slab 3 0% 11-Feb-18 13-Feb-18 11-Feb-18 13-Feb-18 -8 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5570 External Water Proofing 3 0% 18-Feb-18 20-Feb-18 18-Feb-18 20-Feb-18 -8 External Water Proofing
NAD-MIS-001-MH-5590 Cating/Placing of Cover Slab 3 0% 25-Feb-18 27-Feb-18 25-Feb-18 27-Feb-18 -11 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5600 Internal Finishing 3 0% 28-Feb-18 03-Mar-18 28-Feb-18 03-Mar-18 -11 Internal Finishing
NAD-MIS-001-MH-5610 Cover and Frames 3 0% 04-Mar-18 06-Mar-18 04-Mar-18 06-Mar-18 -11 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 69 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-5630 Casting/Placing of Base Slab 3 0% 04-Feb-18 06-Feb-18 04-Feb-18 06-Feb-18 -5 Casting/Placing of Base Slab
NAD-MIS-001-MH-5650 Casting/Placing of Reducer Slab 3 0% 11-Feb-18 13-Feb-18 11-Feb-18 13-Feb-18 -5 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5680 External Water Proofing 3 0% 18-Feb-18 20-Feb-18 18-Feb-18 20-Feb-18 -5 External Water Proofing
NAD-MIS-001-MH-5700 Cating/Placing of Cover Slab 3 0% 28-Feb-18 03-Mar-18 28-Feb-18 03-Mar-18 -11 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5710 Internal Finishing 3 0% 04-Mar-18 06-Mar-18 04-Mar-18 06-Mar-18 -11 Internal Finishing
NAD-MIS-001-MH-5720 Cover and Frames 3 0% 07-Mar-18 10-Mar-18 07-Mar-18 10-Mar-18 -11 Cover and Frames
NAD-MIS-001-PL-3220 Install Dewatering system 12 0% 31-Jan-18 13-Feb-18 31-Jan-18 13-Feb-18 -189 Install Dewatering system
NAD-MIS-001-PL-3230 Excavation to Formation Level 12 0% 14-Feb-18 27-Feb-18 14-Feb-18 27-Feb-18 -189 Excavation to Formation Level
NAD-MIS-001-PL-3250 Pipe Surround 5 0% 05-Mar-18 10-Mar-18 05-Mar-18 10-Mar-18 -189 Pipe Surround
NAD-MIS-001-MH-5740 Casting/Placing of Base Slab 3 0% 28-Feb-18 03-Mar-18 28-Feb-18 03-Mar-18 -23 Casting/Placing of Base Slab
NAD-MIS-001-MH-5750 Casting/Placing of Walls 3 0% 04-Mar-18 06-Mar-18 04-Mar-18 06-Mar-18 -23 Casting/Placing of Walls
NAD-MIS-001-MH-5760 Casting/Placing of Reducer Slab 3 0% 07-Mar-18 10-Mar-18 07-Mar-18 10-Mar-18 -23 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5770 Cating/Placing of Shafts 3 0% 11-Mar-18 13-Mar-18 11-Mar-18 13-Mar-18 -23 Cating/Placing of Shafts
NAD-MIS-001-MH-5780 Construction of Backdrop 3 0% 14-Mar-18 17-Mar-18 14-Mar-18 17-Mar-18 -23 Construction of Backdrop
NAD-MIS-001-MH-5790 External Water Proofing 3 0% 14-Mar-18 17-Mar-18 14-Mar-18 17-Mar-18 -23 External Water Proofing
NAD-MIS-001-MH-5810 Cating/Placing of Cover Slab 3 0% 18-Mar-18 20-Mar-18 18-Mar-18 20-Mar-18 -23 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5820 Internal Finishing 3 0% 21-Mar-18 24-Mar-18 21-Mar-18 24-Mar-18 -23 Internal Finishing
NAD-MIS-001-MH-5830 Cover and Frames 3 0% 25-Mar-18 27-Mar-18 25-Mar-18 27-Mar-18 -23 Cover and Frames
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 70 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-3280 Lowering 12 0% 14-Feb-18 27-Feb-18 14-Feb-18 27-Feb-18 -200 Lowering
NAD-MIS-001-PL-3290 Install Dewatering system 12 0% 14-Feb-18 27-Feb-18 14-Feb-18 27-Feb-18 -200 Install Dewatering system
NAD-MIS-001-PL-3300 Excavation to Formation Level 12 0% 28-Feb-18 13-Mar-18 28-Feb-18 13-Mar-18 -200 Excavation to Formation Level
NAD-MIS-001-PL-3320 Pipe Surround 6 0% 18-Mar-18 24-Mar-18 18-Mar-18 24-Mar-18 -200 Pipe Surround
NAD-MIS-001-MH-5850 Casting/Placing of Base Slab 2 0% 14-Mar-18 15-Mar-18 14-Mar-18 15-Mar-18 -28 Casting/Placing of Base Slab
NAD-MIS-001-MH-5860 Casting/Placing of Walls 2 0% 17-Mar-18 18-Mar-18 17-Mar-18 18-Mar-18 -28 Casting/Placing of Walls
NAD-MIS-001-MH-5870 Casting/Placing of Reducer Slab 2 0% 19-Mar-18 20-Mar-18 19-Mar-18 20-Mar-18 -28 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5880 Cating/Placing of Shafts 2 0% 21-Mar-18 22-Mar-18 21-Mar-18 22-Mar-18 -28 Cating/Placing of Shafts
NAD-MIS-001-MH-5890 Construction of Backdrop 2 0% 24-Mar-18 25-Mar-18 24-Mar-18 25-Mar-18 -28 Construction of Backdrop
NAD-MIS-001-MH-5900 External Water Proofing 2 0% 24-Mar-18 25-Mar-18 24-Mar-18 25-Mar-18 -28 External Water Proofing
NAD-MIS-001-MH-5920 Cating/Placing of Cover Slab 2 0% 31-Mar-18 01-Apr-18 31-Mar-18 01-Apr-18 -31 Cating/Placing of Cover Slab
NAD-MIS-001-MH-5930 Internal Finishing 2 0% 02-Apr-18 03-Apr-18 02-Apr-18 03-Apr-18 -29 Internal Finishing
NAD-MIS-001-MH-5940 Cover and Frames 2 0% 04-Apr-18 05-Apr-18 04-Apr-18 05-Apr-18 -29 Cover and Frames
NEW MH-1-NEW EX FLOW SPLITTING CH. 38 28-Feb-18 12-Apr-18 28-Feb-18 12-Apr-18 -32
PIPE LINE 30 28-Feb-18 03-Apr-18 28-Feb-18 03-Apr-18 -200
NAD-MIS-001-PL-3360 Install Dewatering system 7 0% 28-Feb-18 07-Mar-18 28-Feb-18 07-Mar-18 -196 Install Dewatering system
NAD-MIS-001-PL-3370 Excavation to Formation Level 7 0% 08-Mar-18 15-Mar-18 08-Mar-18 15-Mar-18 -196 Excavation to Formation Level
NAD-MIS-001-PL-3390 Pipe Surround 4 0% 19-Mar-18 22-Mar-18 19-Mar-18 22-Mar-18 -196 Pipe Surround
NAD-MIS-001-MH-5960 Casting/Placing of Base Slab 3 0% 17-Mar-18 19-Mar-18 17-Mar-18 19-Mar-18 -32 Casting/Placing of Base Slab
NAD-MIS-001-MH-5970 Casting/Placing of Walls 3 0% 20-Mar-18 22-Mar-18 20-Mar-18 22-Mar-18 -32 Casting/Placing of Walls
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 71 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-5980 Casting/Placing of Reducer Slab 3 0% 24-Mar-18 26-Mar-18 24-Mar-18 26-Mar-18 -32 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-5990 Cating/Placing of Shafts 3 0% 27-Mar-18 29-Mar-18 27-Mar-18 29-Mar-18 -32 Cating/Placing of Shafts
NAD-MIS-001-MH-6000 Construction of Backdrop 3 0% 31-Mar-18 02-Apr-18 31-Mar-18 02-Apr-18 -32 Construction of Backdrop
NAD-MIS-001-MH-6010 External Water Proofing 3 0% 31-Mar-18 02-Apr-18 31-Mar-18 02-Apr-18 -32 External Water Proofing
NAD-MIS-001-MH-6030 Cating/Placing of Cover Slab 3 0% 03-Apr-18 05-Apr-18 03-Apr-18 05-Apr-18 -32 Cating/Placing of Cover Slab
NAD-MIS-001-MH-6040 Internal Finishing 3 0% 07-Apr-18 09-Apr-18 07-Apr-18 09-Apr-18 -32 Internal Finishing
NAD-MIS-001-MH-6050 Cover and Frames 3 0% 10-Apr-18 12-Apr-18 10-Apr-18 12-Apr-18 -32 Cover and Frames
NAD-MIS-001-PL-3430 Receiving Pit 10 0% 31-Jan-18 11-Feb-18 31-Jan-18 11-Feb-18 -186 Receiving Pit
NAD-MIS-001-MH-6070 Casting/Placing of Base Slab 3 0% 07-Mar-18 10-Mar-18 07-Mar-18 10-Mar-18 -21 Casting/Placing of Base Slab
NAD-MIS-001-MH-6080 Casting/Placing of Walls 3 0% 11-Mar-18 13-Mar-18 11-Mar-18 13-Mar-18 -21 Casting/Placing of Walls
NAD-MIS-001-MH-6090 Casting/Placing of Reducer Slab 3 0% 14-Mar-18 17-Mar-18 14-Mar-18 17-Mar-18 -21 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-6100 Cating/Placing of Shafts 3 0% 18-Mar-18 20-Mar-18 18-Mar-18 20-Mar-18 -21 Cating/Placing of Shafts
NAD-MIS-001-MH-6110 Construction of Backdrop 3 0% 21-Mar-18 24-Mar-18 21-Mar-18 24-Mar-18 -21 Construction of Backdrop
NAD-MIS-001-MH-6120 External Water Proofing 3 0% 21-Mar-18 24-Mar-18 21-Mar-18 24-Mar-18 -21 External Water Proofing
NAD-MIS-001-MH-6140 Cating/Placing of Cover Slab 3 0% 07-Apr-18 09-Apr-18 07-Apr-18 09-Apr-18 -32 Cating/Placing of Cover Slab
NAD-MIS-001-MH-6150 Internal Finishing 3 0% 10-Apr-18 12-Apr-18 10-Apr-18 12-Apr-18 -32 Internal Finishing
NAD-MIS-001-MH-6160 Cover and Frames 3 0% 14-Apr-18 16-Apr-18 14-Apr-18 16-Apr-18 -32 Cover and Frames
NAD-MIS-001-PL-3500 Receiving Pit 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -196 Receiving Pit
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 72 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-PL-3520 Pipelaying 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -196 Pipelaying
NAD-MIS-001-MH-6180 Casting/Placing of Base Slab 3 0% 19-Mar-18 21-Mar-18 19-Mar-18 21-Mar-18 -28 Casting/Placing of Base Slab
NAD-MIS-001-MH-6190 Casting/Placing of Walls 3 0% 22-Mar-18 25-Mar-18 22-Mar-18 25-Mar-18 -28 Casting/Placing of Walls
NAD-MIS-001-MH-6200 Casting/Placing of Reducer Slab 3 0% 26-Mar-18 28-Mar-18 26-Mar-18 28-Mar-18 -28 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-6210 Cating/Placing of Shafts 3 0% 29-Mar-18 01-Apr-18 29-Mar-18 01-Apr-18 -28 Cating/Placing of Shafts
NAD-MIS-001-MH-6220 Construction of Backdrop 3 0% 02-Apr-18 04-Apr-18 02-Apr-18 04-Apr-18 -28 Construction of Backdrop
NAD-MIS-001-MH-6230 External Water Proofing 3 0% 02-Apr-18 04-Apr-18 02-Apr-18 04-Apr-18 -28 External Water Proofing
NAD-MIS-001-MH-6250 Cating/Placing of Cover Slab 3 0% 10-Apr-18 12-Apr-18 10-Apr-18 12-Apr-18 -32 Cating/Placing of Cover Slab
NAD-MIS-001-MH-6260 Internal Finishing 3 0% 14-Apr-18 16-Apr-18 14-Apr-18 16-Apr-18 -32 Internal Finishing
NAD-MIS-001-MH-6270 Cover and Frames 3 0% 17-Apr-18 19-Apr-18 17-Apr-18 19-Apr-18 -32 Cover and Frames
NAD-MIS-001-PL-3570 Receiving Pit 7 0% 04-Mar-18 11-Mar-18 04-Mar-18 11-Mar-18 -191 Receiving Pit
NAD-MIS-001-MH-6290 Casting/Placing of Base Slab 3 0% 24-Mar-18 26-Mar-18 24-Mar-18 26-Mar-18 -29 Casting/Placing of Base Slab
NAD-MIS-001-MH-6300 Casting/Placing of Walls 3 0% 27-Mar-18 29-Mar-18 27-Mar-18 29-Mar-18 -29 Casting/Placing of Walls
NAD-MIS-001-MH-6310 Casting/Placing of Reducer Slab 3 0% 31-Mar-18 02-Apr-18 31-Mar-18 02-Apr-18 -29 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-6320 Cating/Placing of Shafts 3 0% 03-Apr-18 05-Apr-18 03-Apr-18 05-Apr-18 -29 Cating/Placing of Shafts
NAD-MIS-001-MH-6330 Construction of Backdrop 3 0% 07-Apr-18 09-Apr-18 07-Apr-18 09-Apr-18 -29 Construction of Backdrop
NAD-MIS-001-MH-6340 External Water Proofing 3 0% 07-Apr-18 09-Apr-18 07-Apr-18 09-Apr-18 -29 External Water Proofing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 73 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
NAD-MIS-001-MH-6360 Cating/Placing of Cover Slab 3 0% 14-Apr-18 16-Apr-18 14-Apr-18 16-Apr-18 -32 Cating/Placing of Cover Slab
NAD-MIS-001-MH-6370 Internal Finishing 3 0% 17-Apr-18 19-Apr-18 17-Apr-18 19-Apr-18 -32 Internal Finishing
NAD-MIS-001-MH-6380 Cover and Frames 3 0% 21-Apr-18 23-Apr-18 21-Apr-18 23-Apr-18 -32 Cover and Frames
NEW MH-7- NEW MH-6 112 04-Mar-18 11-Jul-18 04-Mar-18 11-Jul-18 -97
NDRC WORKS=124m 67 04-Mar-18 20-May-18 04-Mar-18 20-May-18 -229
NAD-MIS-001-PL-3630 Driving Pit 10 0% 04-Mar-18 14-Mar-18 04-Mar-18 14-Mar-18 -229 Driving Pit
NAD-MIS-001-PL-3640 Receivng Pit 10 0% 15-Mar-18 26-Mar-18 15-Mar-18 26-Mar-18 -229 Receivng Pit
NAD-MIS-001-MH-6400 Casting/Placing of Base Slab 3 0% 22-Apr-18 24-Apr-18 22-Apr-18 24-Apr-18 -51 Casting/Placing of Base Slab
NAD-MIS-001-MH-6410 Casting/Placing of Walls 3 0% 25-Apr-18 28-Apr-18 25-Apr-18 28-Apr-18 -51 Casting/Placing of Walls
NAD-MIS-001-MH-6420 Casting/Placing of Reducer Slab 3 0% 29-Apr-18 01-May-18 29-Apr-18 01-May-18 -51 Casting/Placing of Reducer Slab
NAD-MIS-001-MH-6430 Cating/Placing of Shafts 3 0% 02-May-18 05-May-18 02-May-18 05-May-18 -51 Cating/Placing of Shafts
NAD-MIS-001-MH-6440 Construction of Backdrop 3 0% 06-May-18 08-May-18 06-May-18 08-May-18 -51 Construction of Backdrop
NAD-MIS-001-MH-6450 External Water Proofing 3 0% 06-May-18 08-May-18 06-May-18 08-May-18 -51 External Water Proofing
NAD-MIS-001-MH-6470 Cating/Placing of Cover Slab 3 0% 17-May-18 20-May-18 17-May-18 20-May-18 -58 Cating/Placing of Cover Slab
NAD-MIS-001-MH-6480 Internal Finishing 3 0% 21-May-18 23-May-18 21-May-18 23-May-18 -58 Internal Finishing
NAD-MIS-001-MH-6490 Cover and Frames 3 0% 24-May-18 27-May-18 24-May-18 27-May-18 -58 Cover and Frames
NAD-MIS-001-PL-4550 Excavation for Receiving Pit 7 0% 29-May-18 05-Jun-18 29-May-18 05-Jun-18 -229 Excavation for Receiving Pit
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 74 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-003-PL-1000 Lowering 2 0% 12-Jul-18 14-Jul-18 12-Jul-18 14-Jul-18 -229 Lowering
WSL-MIS-003-PL-1010 Install Dewatering System / Dewatering 2 0% 16-Jul-18 17-Jul-18 16-Jul-18 17-Jul-18 -123 Install Dewatering System / D
WSL-MIS-003-PL-1020 Excavation to Formation Level 2 0% 19-Jul-18 21-Jul-18 19-Jul-18 21-Jul-18 -123 Excavation to Formation Lev
WSL-MIS-003-PL-1030 Pipe Laying 2 0% 22-Jul-18 23-Jul-18 22-Jul-18 23-Jul-18 -123 Pipe Laying
WSL-MIS-003-PL-1040 Pipe Surround 2 0% 23-Jul-18 24-Jul-18 23-Jul-18 24-Jul-18 -123 Pipe Surround
WSL-MIS-003-MH-1010 Casting / Placing of Base Slab 2 0% 22-Jul-18 23-Jul-18 22-Jul-18 23-Jul-18 -120 Casting / Placing of Base Sl
WSL-MIS-003-MH-1020 Casting / Placing of Walls 1 0% 24-Jul-18 24-Jul-18 24-Jul-18 24-Jul-18 -120 Casting / Placing of Walls
WSL-MIS-003-MH-1030 Casting / Placing of Reducer Slab 1 0% 25-Jul-18 25-Jul-18 25-Jul-18 25-Jul-18 -120 Casting / Placing of Reduce
WSL-MIS-003-MH-1040 Casting / Placing of Shafts 1 0% 26-Jul-18 26-Jul-18 26-Jul-18 26-Jul-18 -120 Casting / Placing of Shafts
WSL-MIS-003-MH-1050 Construction of Backdrops 1 0% 28-Jul-18 28-Jul-18 28-Jul-18 28-Jul-18 -120 Construction of Backdrops
WSL-MIS-003-MH-1060 External Waterproofing 1 0% 29-Jul-18 29-Jul-18 29-Jul-18 29-Jul-18 -120 External Waterproofing
WSL-MIS-003-MH-1080 Casting / Placing of Cover Slab 1 0% 30-Jul-18 30-Jul-18 30-Jul-18 30-Jul-18 -120 Casting / Placing of Cover S
WSL-MIS-003-MH-1090 Internal Finishing 1 0% 31-Jul-18 31-Jul-18 31-Jul-18 31-Jul-18 -120 Internal Finishing
WSL-MIS-003-MH-1100 DI Frame and Cover 1 0% 01-Aug-18 01-Aug-18 01-Aug-18 01-Aug-18 -120 DI Frame and Cover
WSL-MIS-003-PL-1080 Install Dewatering System / Dewatering 2 0% 18-Jul-18 19-Jul-18 18-Jul-18 19-Jul-18 -123 Install Dewatering System / D
WSL-MIS-003-PL-1090 Excavation to Formation Level 2 0% 22-Jul-18 23-Jul-18 22-Jul-18 23-Jul-18 -123 Excavation to Formation Lev
WSL-MIS-003-PL-1100 Pipe Laying 2 0% 24-Jul-18 25-Jul-18 24-Jul-18 25-Jul-18 -123 Pipe Laying
WSL-MIS-003-PL-1110 Pipe Surround 2 0% 25-Jul-18 26-Jul-18 25-Jul-18 26-Jul-18 -123 Pipe Surround
WSL-MIS-003-MH-1120 Casting / Placing of Base Slab 2 0% 24-Jul-18 25-Jul-18 24-Jul-18 25-Jul-18 -121 Casting / Placing of Base Sl
WSL-MIS-003-MH-1130 Casting / Placing of Walls 1 0% 26-Jul-18 26-Jul-18 26-Jul-18 26-Jul-18 -121 Casting / Placing of Walls
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 75 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-003-MH-1140 Casting / Placing of Reducer Slab 1 0% 28-Jul-18 28-Jul-18 28-Jul-18 28-Jul-18 -121 Casting / Placing of Reduce
WSL-MIS-003-MH-1150 Casting / Placing of Shafts 1 0% 29-Jul-18 29-Jul-18 29-Jul-18 29-Jul-18 -121 Casting / Placing of Shafts
WSL-MIS-003-MH-1160 Construction of Backdrops 1 0% 30-Jul-18 30-Jul-18 30-Jul-18 30-Jul-18 -121 Construction of Backdrops
WSL-MIS-003-MH-1170 External Waterproofing 1 0% 31-Jul-18 31-Jul-18 31-Jul-18 31-Jul-18 -121 External Waterproofing
WSL-MIS-003-MH-1190 Casting / Placing of Cover Slab 1 0% 01-Aug-18 01-Aug-18 01-Aug-18 01-Aug-18 -121 Casting / Placing of Cover S
WSL-MIS-003-MH-1200 Internal Finishing 1 0% 02-Aug-18 02-Aug-18 02-Aug-18 02-Aug-18 -121 Internal Finishing
WSL-MIS-003-MH-1210 DI Frame and Cover 1 0% 04-Aug-18 04-Aug-18 04-Aug-18 04-Aug-18 -121 DI Frame and Cover
WSL-MIS-003-PL-1150 Install Dewatering System / Dewatering 2 0% 21-Jul-18 22-Jul-18 21-Jul-18 22-Jul-18 -124 Install Dewatering System /
WSL-MIS-003-PL-1160 Excavation to Formation Level 3 0% 24-Jul-18 26-Jul-18 24-Jul-18 26-Jul-18 -124 Excavation to Formation Lev
WSL-MIS-003-PL-1170 Pipe Laying 2 0% 28-Jul-18 29-Jul-18 28-Jul-18 29-Jul-18 -124 Pipe Laying
WSL-MIS-003-PL-1180 Pipe Surround 2 0% 29-Jul-18 30-Jul-18 29-Jul-18 30-Jul-18 -124 Pipe Surround
WSL-MIS-003-MH-1230 Casting / Placing of Base Slab 2 0% 28-Jul-18 29-Jul-18 28-Jul-18 29-Jul-18 -123 Casting / Placing of Base S
WSL-MIS-003-MH-1240 Casting / Placing of Walls 1 0% 30-Jul-18 30-Jul-18 30-Jul-18 30-Jul-18 -123 Casting / Placing of Walls
WSL-MIS-003-MH-1250 Casting / Placing of Reducer Slab 1 0% 31-Jul-18 31-Jul-18 31-Jul-18 31-Jul-18 -123 Casting / Placing of Reduce
WSL-MIS-003-MH-1260 Casting / Placing of Shafts 1 0% 01-Aug-18 01-Aug-18 01-Aug-18 01-Aug-18 -123 Casting / Placing of Shafts
WSL-MIS-003-MH-1270 Construction of Backdrops 1 0% 02-Aug-18 02-Aug-18 02-Aug-18 02-Aug-18 -123 Construction of Backdrops
WSL-MIS-003-MH-1280 External Waterproofing 1 0% 04-Aug-18 04-Aug-18 04-Aug-18 04-Aug-18 -123 External Waterproofing
WSL-MIS-003-MH-1300 Casting / Placing of Cover Slab 1 0% 05-Aug-18 05-Aug-18 05-Aug-18 05-Aug-18 -123 Casting / Placing of Cover S
WSL-MIS-003-MH-1410 Internal Finishing 1 0% 06-Aug-18 06-Aug-18 06-Aug-18 06-Aug-18 -123 Internal Finishing
WSL-MIS-003-MH-1420 DI Frame and Cover 1 0% 07-Aug-18 07-Aug-18 07-Aug-18 07-Aug-18 -123 DI Frame and Cover
WSL-MIS-003-PL-1220 Install Dewatering System / Dewatering 2 0% 23-Jul-18 24-Jul-18 23-Jul-18 24-Jul-18 -124 Install Dewatering System /
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 76 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-003-PL-1230 Excavation to Formation Level 3 0% 26-Jul-18 29-Jul-18 26-Jul-18 29-Jul-18 -124 Excavation to Formation Lev
WSL-MIS-003-PL-1240 Pipe Laying 2 0% 30-Jul-18 31-Jul-18 30-Jul-18 31-Jul-18 -124 Pipe Laying
WSL-MIS-003-PL-1250 Pipe Surround 2 0% 31-Jul-18 01-Aug-18 31-Jul-18 01-Aug-18 -124 Pipe Surround
WSL-MIS-003-MH-1440 Casting / Placing of Base Slab 2 0% 30-Jul-18 31-Jul-18 30-Jul-18 31-Jul-18 -124 Casting / Placing of Base S
WSL-MIS-003-MH-1450 Casting / Placing of Walls 1 0% 01-Aug-18 01-Aug-18 01-Aug-18 01-Aug-18 -124 Casting / Placing of Walls
WSL-MIS-003-MH-1460 Casting / Placing of Reducer Slab 1 0% 02-Aug-18 02-Aug-18 02-Aug-18 02-Aug-18 -124 Casting / Placing of Reduce
WSL-MIS-003-MH-1470 Casting / Placing of Shafts 1 0% 04-Aug-18 04-Aug-18 04-Aug-18 04-Aug-18 -124 Casting / Placing of Shafts
WSL-MIS-003-MH-1480 Construction of Backdrops 1 0% 05-Aug-18 05-Aug-18 05-Aug-18 05-Aug-18 -124 Construction of Backdrops
WSL-MIS-003-MH-1490 External Waterproofing 1 0% 06-Aug-18 06-Aug-18 06-Aug-18 06-Aug-18 -124 External Waterproofing
WSL-MIS-003-MH-1510 Casting / Placing of Cover Slab 1 0% 07-Aug-18 07-Aug-18 07-Aug-18 07-Aug-18 -124 Casting / Placing of Cover
WSL-MIS-003-MH-1520 Internal Finishing 1 0% 08-Aug-18 08-Aug-18 08-Aug-18 08-Aug-18 -124 Internal Finishing
WSL-MIS-003-MH-1530 DI Frame and Cover 1 0% 09-Aug-18 09-Aug-18 09-Aug-18 09-Aug-18 -124 DI Frame and Cover
WSL-MIS-003-ND-1290 Receving Pit 2 0% 24-Jul-18 25-Jul-18 24-Jul-18 25-Jul-18 -124 Receving Pit
WSL-MIS-003-MH-1550 Casting / Placing of Base Slab 2 0% 31-Jul-18 01-Aug-18 31-Jul-18 01-Aug-18 -124 Casting / Placing of Base S
WSL-MIS-003-MH-1560 Casting / Placing of Walls 1 0% 02-Aug-18 02-Aug-18 02-Aug-18 02-Aug-18 -124 Casting / Placing of Walls
WSL-MIS-003-MH-1570 Casting / Placing of Reducer Slab 1 0% 04-Aug-18 04-Aug-18 04-Aug-18 04-Aug-18 -124 Casting / Placing of Reduce
WSL-MIS-003-MH-1580 Casting / Placing of Shafts 1 0% 05-Aug-18 05-Aug-18 05-Aug-18 05-Aug-18 -124 Casting / Placing of Shafts
WSL-MIS-003-MH-1590 Construction of Backdrops 1 0% 06-Aug-18 06-Aug-18 06-Aug-18 06-Aug-18 -124 Construction of Backdrops
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 77 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-003-MH-1600 External Waterproofing 1 0% 07-Aug-18 07-Aug-18 07-Aug-18 07-Aug-18 -124 External Waterproofing
WSL-MIS-003-MH-1620 Casting / Placing of Cover Slab 1 0% 08-Aug-18 08-Aug-18 08-Aug-18 08-Aug-18 -124 Casting / Placing of Cover
WSL-MIS-003-MH-1630 Internal Finishing 1 0% 09-Aug-18 09-Aug-18 09-Aug-18 09-Aug-18 -124 Internal Finishing
WSL-MIS-003-MH-1640 DI Frame and Cover 1 0% 11-Aug-18 11-Aug-18 11-Aug-18 11-Aug-18 -124 DI Frame and Cover
WSL-MIS-003-PL-1350 Install Dewatering System / Dewatering 3 0% 28-Jul-18 30-Jul-18 28-Jul-18 30-Jul-18 -126 Install Dewatering System /
WSL-MIS-003-PL-1360 Excavation to Formation Level 3 0% 31-Jul-18 02-Aug-18 31-Jul-18 02-Aug-18 -126 Excavation to Formation Le
WSL-MIS-003-PL-1370 Pipe Laying 2 0% 04-Aug-18 05-Aug-18 04-Aug-18 05-Aug-18 -125 Pipe Laying
WSL-MIS-003-PL-1380 Pipe Surround 2 0% 05-Aug-18 06-Aug-18 05-Aug-18 06-Aug-18 -125 Pipe Surround
WSL-MIS-003-MH-1660 Casting / Placing of Base Slab 2 0% 04-Aug-18 05-Aug-18 04-Aug-18 05-Aug-18 -126 Casting / Placing of Base S
WSL-MIS-003-MH-1670 Casting / Placing of Walls 1 0% 06-Aug-18 06-Aug-18 06-Aug-18 06-Aug-18 -126 Casting / Placing of Walls
WSL-MIS-003-MH-1680 Casting / Placing of Reducer Slab 1 0% 07-Aug-18 07-Aug-18 07-Aug-18 07-Aug-18 -126 Casting / Placing of Reduc
WSL-MIS-003-MH-1690 Casting / Placing of Shafts 1 0% 08-Aug-18 08-Aug-18 08-Aug-18 08-Aug-18 -126 Casting / Placing of Shafts
WSL-MIS-003-MH-1700 Construction of Backdrops 1 0% 09-Aug-18 09-Aug-18 09-Aug-18 09-Aug-18 -126 Construction of Backdrops
WSL-MIS-003-MH-1710 External Waterproofing 1 0% 11-Aug-18 11-Aug-18 11-Aug-18 11-Aug-18 -126 External Waterproofing
WSL-MIS-003-MH-1730 Casting / Placing of Cover Slab 1 0% 12-Aug-18 12-Aug-18 12-Aug-18 12-Aug-18 -126 Casting / Placing of Cover
WSL-MIS-003-MH-1740 Internal Finishing 1 0% 13-Aug-18 13-Aug-18 13-Aug-18 13-Aug-18 -126 Internal Finishing
WSL-MIS-003-MH-1750 DI Frame and Cover 1 0% 14-Aug-18 14-Aug-18 14-Aug-18 14-Aug-18 -126 DI Frame and Cover
WSL-MIS-003-PL-1420 Install Dewatering System / Dewatering 3 0% 31-Jul-18 02-Aug-18 31-Jul-18 02-Aug-18 -129 Install Dewatering System /
WSL-MIS-003-PL-1430 Excavation to Formation Level 3 0% 04-Aug-18 06-Aug-18 04-Aug-18 06-Aug-18 -129 Excavation to Formation Le
WSL-MIS-003-PL-1440 Pipe Laying 2 0% 07-Aug-18 08-Aug-18 07-Aug-18 08-Aug-18 -128 Pipe Laying
WSL-MIS-003-PL-1450 Pipe Surround 2 0% 08-Aug-18 09-Aug-18 08-Aug-18 09-Aug-18 -128 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 78 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-003-PL-1460 Backfilling 2 0% 11-Aug-18 12-Aug-18 11-Aug-18 12-Aug-18 -128 Backfilling
WSL-MIS-003-MH-1770 Casting / Placing of Base Slab 2 0% 07-Aug-18 08-Aug-18 07-Aug-18 08-Aug-18 -129 Casting / Placing of Base S
WSL-MIS-003-MH-1780 Casting / Placing of Walls 1 0% 09-Aug-18 09-Aug-18 09-Aug-18 09-Aug-18 -129 Casting / Placing of Walls
WSL-MIS-003-MH-1790 Casting / Placing of Reducer Slab 1 0% 11-Aug-18 11-Aug-18 11-Aug-18 11-Aug-18 -129 Casting / Placing of Reduc
WSL-MIS-003-MH-1800 Casting / Placing of Shafts 1 0% 12-Aug-18 12-Aug-18 12-Aug-18 12-Aug-18 -129 Casting / Placing of Shafts
WSL-MIS-003-MH-1810 Construction of Backdrops 1 0% 13-Aug-18 13-Aug-18 13-Aug-18 13-Aug-18 -129 Construction of Backdrops
WSL-MIS-003-MH-1820 External Waterproofing 1 0% 14-Aug-18 14-Aug-18 14-Aug-18 14-Aug-18 -129 External Waterproofing
WSL-MIS-003-MH-1840 Casting / Placing of Cover Slab 1 0% 15-Aug-18 15-Aug-18 15-Aug-18 15-Aug-18 -129 Casting / Placing of Cover
WSL-MIS-003-MH-1850 Internal Finishing 1 0% 16-Aug-18 16-Aug-18 16-Aug-18 16-Aug-18 -129 Internal Finishing
WSL-MIS-003-MH-1860 DI Frame and Cover 1 0% 18-Aug-18 18-Aug-18 18-Aug-18 18-Aug-18 -129 DI Frame and Cover
WSL-MIS-003-PL-1490 Install Dewatering System / Dewatering 1 0% 04-Aug-18 04-Aug-18 04-Aug-18 04-Aug-18 -229 Install Dewatering System /
WSL-MIS-003-PL-1500 Excavation to Formation Level 2 0% 07-Aug-18 08-Aug-18 07-Aug-18 08-Aug-18 -229 Excavation to Formation Le
WSL-MIS-003-PL-1510 Pipe Laying 2 0% 09-Aug-18 11-Aug-18 09-Aug-18 11-Aug-18 -228 Pipe Laying
WSL-MIS-003-PL-1520 Pipe Surround 2 0% 11-Aug-18 12-Aug-18 11-Aug-18 12-Aug-18 -228 Pipe Surround
WSL-MIS-003-MH-1880 Casting / Placing of Base Slab 2 0% 09-Aug-18 11-Aug-18 09-Aug-18 11-Aug-18 -229 Casting / Placing of Base S
WSL-MIS-003-MH-1890 Casting / Placing of Walls 1 0% 12-Aug-18 12-Aug-18 12-Aug-18 12-Aug-18 -229 Casting / Placing of Walls
WSL-MIS-003-MH-1900 Casting / Placing of Reducer Slab 1 0% 13-Aug-18 13-Aug-18 13-Aug-18 13-Aug-18 -229 Casting / Placing of Reduc
WSL-MIS-003-MH-1910 Casting / Placing of Shafts 1 0% 14-Aug-18 14-Aug-18 14-Aug-18 14-Aug-18 -229 Casting / Placing of Shafts
WSL-MIS-003-MH-1920 Construction of Backdrops 1 0% 15-Aug-18 15-Aug-18 15-Aug-18 15-Aug-18 -229 Construction of Backdrops
WSL-MIS-003-MH-1930 External Waterproofing 1 0% 16-Aug-18 16-Aug-18 16-Aug-18 16-Aug-18 -229 External Waterproofing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 79 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-003-MH-1950 Casting / Placing of Cover Slab 1 0% 18-Aug-18 18-Aug-18 18-Aug-18 18-Aug-18 -229 Casting / Placing of Cover
WSL-MIS-003-MH-1960 Internal Finishing 1 0% 19-Aug-18 19-Aug-18 19-Aug-18 19-Aug-18 -229 Internal Finishing
WSL-MIS-003-MH-1970 DI Frame and Cover 1 0% 20-Aug-18 20-Aug-18 20-Aug-18 20-Aug-18 -229 DI Frame and Cover
WSL-MIS-006-PL-1010 Install Dewatering System / Dewatering 2 0% 25-Aug-18 26-Aug-18 25-Aug-18 26-Aug-18 -222 Install Dewatering System
WSL-MIS-006-PL-1020 Excavation to Formation Level 2 0% 28-Aug-18 29-Aug-18 28-Aug-18 29-Aug-18 -222 Excavation to Formation L
WSL-MIS-006-PL-1030 Pipe Laying 2 0% 30-Aug-18 01-Sep-18 30-Aug-18 01-Sep-18 -222 Pipe Laying
WSL-MIS-006-PL-1040 Pipe Surround 2 0% 01-Sep-18 02-Sep-18 01-Sep-18 02-Sep-18 -222 Pipe Surround
WSL-MIS-006-MH-4580 Casting / Placing of Base Slab 2 0% 30-Aug-18 01-Sep-18 30-Aug-18 01-Sep-18 -214 Casting / Placing of Base
WSL-MIS-006-MH-4585 Casting / Placing of Walls 1 0% 02-Sep-18 02-Sep-18 02-Sep-18 02-Sep-18 -214 Casting / Placing of Walls
WSL-MIS-006-MH-4590 Casting / Placing of Reducer Slab 1 0% 03-Sep-18 03-Sep-18 03-Sep-18 03-Sep-18 -214 Casting / Placing of Redu
WSL-MIS-006-MH-4595 Casting / Placing of Shafts 1 0% 04-Sep-18 04-Sep-18 04-Sep-18 04-Sep-18 -214 Casting / Placing of Shaf
WSL-MIS-006-MH-4600 Construction of Backdrops 1 0% 05-Sep-18 05-Sep-18 05-Sep-18 05-Sep-18 -214 Construction of Backdrop
WSL-MIS-006-MH-4605 External Waterproofing 1 0% 06-Sep-18 06-Sep-18 06-Sep-18 06-Sep-18 -214 External Waterproofing
WSL-MIS-006-MH-4615 Casting / Placing of Cover Slab 1 0% 08-Sep-18 08-Sep-18 08-Sep-18 08-Sep-18 -213 Casting / Placing of Cove
WSL-MIS-006-MH-4620 Internal Finishing 1 0% 09-Sep-18 09-Sep-18 09-Sep-18 09-Sep-18 -211 Internal Finishing
WSL-MIS-006-MH-4625 DI Frame and Cover 1 0% 10-Sep-18 10-Sep-18 10-Sep-18 10-Sep-18 -211 DI Frame and Cover
WSL-MIS-006-PL-1080 Install Dewatering System / Dewatering 2 0% 27-Aug-18 28-Aug-18 27-Aug-18 28-Aug-18 -222 Install Dewatering System
WSL-MIS-006-PL-1090 Excavation to Formation Level 2 0% 30-Aug-18 01-Sep-18 30-Aug-18 01-Sep-18 -222 Excavation to Formation
WSL-MIS-006-PL-1100 Pipe Laying 2 0% 02-Sep-18 03-Sep-18 02-Sep-18 03-Sep-18 -222 Pipe Laying
WSL-MIS-006-PL-1110 Pipe Surround 2 0% 03-Sep-18 04-Sep-18 03-Sep-18 04-Sep-18 -222 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 80 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-006-PL-1120 Backfilling 2 0% 05-Sep-18 06-Sep-18 05-Sep-18 06-Sep-18 -222 Backfilling
WSL-MIS-006-MH-4635 Casting / Placing of Base Slab 2 0% 02-Sep-18 03-Sep-18 02-Sep-18 03-Sep-18 -215 Casting / Placing of Base
WSL-MIS-006-MH-4640 Casting / Placing of Walls 1 0% 04-Sep-18 04-Sep-18 04-Sep-18 04-Sep-18 -215 Casting / Placing of Walls
WSL-MIS-006-MH-4645 Casting / Placing of Reducer Slab 1 0% 05-Sep-18 05-Sep-18 05-Sep-18 05-Sep-18 -215 Casting / Placing of Redu
WSL-MIS-006-MH-4650 Casting / Placing of Shafts 1 0% 06-Sep-18 06-Sep-18 06-Sep-18 06-Sep-18 -215 Casting / Placing of Shaf
WSL-MIS-006-MH-4655 Construction of Backdrops 1 0% 08-Sep-18 08-Sep-18 08-Sep-18 08-Sep-18 -215 Construction of Backdro
WSL-MIS-006-MH-4660 External Waterproofing 1 0% 09-Sep-18 09-Sep-18 09-Sep-18 09-Sep-18 -215 External Waterproofing
WSL-MIS-006-MH-4670 Casting / Placing of Cover Slab 1 0% 10-Sep-18 10-Sep-18 10-Sep-18 10-Sep-18 -214 Casting / Placing of Cov
WSL-MIS-006-MH-4675 Internal Finishing 1 0% 11-Sep-18 11-Sep-18 11-Sep-18 11-Sep-18 -212 Internal Finishing
WSL-MIS-006-MH-4680 DI Frame and Cover 1 0% 12-Sep-18 12-Sep-18 12-Sep-18 12-Sep-18 -212 DI Frame and Cover
WSL-MIS-006-PL-1160 Install Dewatering System / Dewatering 2 0% 29-Aug-18 30-Aug-18 29-Aug-18 30-Aug-18 -223 Install Dewatering System
WSL-MIS-006-PL-1170 Excavation to Formation Level 3 0% 02-Sep-18 04-Sep-18 02-Sep-18 04-Sep-18 -223 Excavation to Formation
WSL-MIS-006-PL-1180 Pipe Laying 2 0% 05-Sep-18 06-Sep-18 05-Sep-18 06-Sep-18 -223 Pipe Laying
WSL-MIS-006-PL-1190 Pipe Surround 2 0% 06-Sep-18 08-Sep-18 06-Sep-18 08-Sep-18 -223 Pipe Surround
WSL-MIS-006-MH-4690 Casting / Placing of Base Slab 2 0% 05-Sep-18 06-Sep-18 05-Sep-18 06-Sep-18 -217 Casting / Placing of Base
WSL-MIS-006-MH-4695 Casting / Placing of Walls 1 0% 08-Sep-18 08-Sep-18 08-Sep-18 08-Sep-18 -217 Casting / Placing of Wall
WSL-MIS-006-MH-4700 Casting / Placing of Reducer Slab 1 0% 09-Sep-18 09-Sep-18 09-Sep-18 09-Sep-18 -217 Casting / Placing of Red
WSL-MIS-006-MH-4705 Casting / Placing of Shafts 1 0% 10-Sep-18 10-Sep-18 10-Sep-18 10-Sep-18 -217 Casting / Placing of Sha
WSL-MIS-006-MH-4710 Construction of Backdrops 1 0% 11-Sep-18 11-Sep-18 11-Sep-18 11-Sep-18 -217 Construction of Backdro
WSL-MIS-006-MH-4715 External Waterproofing 1 0% 12-Sep-18 12-Sep-18 12-Sep-18 12-Sep-18 -217 External Waterproofing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 81 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-006-MH-4725 Casting / Placing of Cover Slab 1 0% 13-Sep-18 13-Sep-18 13-Sep-18 13-Sep-18 -216 Casting / Placing of Cov
WSL-MIS-006-MH-4730 Internal Finishing 1 0% 15-Sep-18 15-Sep-18 15-Sep-18 15-Sep-18 -214 Internal Finishing
WSL-MIS-006-MH-4735 DI Frame and Cover 1 0% 16-Sep-18 16-Sep-18 16-Sep-18 16-Sep-18 -214 DI Frame and Cover
WSL-MIS-006-PL-1230 Install Dewatering System / Dewatering 2 0% 01-Sep-18 02-Sep-18 01-Sep-18 02-Sep-18 -223 Install Dewatering System
WSL-MIS-006-PL-1240 Excavation to Formation Level 3 0% 04-Sep-18 06-Sep-18 04-Sep-18 06-Sep-18 -223 Excavation to Formation
WSL-MIS-006-PL-1250 Pipe Laying 2 0% 08-Sep-18 09-Sep-18 08-Sep-18 09-Sep-18 -223 Pipe Laying
WSL-MIS-006-PL-1260 Pipe Surround 2 0% 09-Sep-18 10-Sep-18 09-Sep-18 10-Sep-18 -223 Pipe Surround
WSL-MIS-006-MH-4745 Casting / Placing of Base Slab 2 0% 08-Sep-18 09-Sep-18 08-Sep-18 09-Sep-18 -218 Casting / Placing of Base
WSL-MIS-006-MH-4750 Casting / Placing of Walls 1 0% 10-Sep-18 10-Sep-18 10-Sep-18 10-Sep-18 -218 Casting / Placing of Wall
WSL-MIS-006-MH-4755 Casting / Placing of Reducer Slab 1 0% 11-Sep-18 11-Sep-18 11-Sep-18 11-Sep-18 -218 Casting / Placing of Red
WSL-MIS-006-MH-4760 Casting / Placing of Shafts 1 0% 12-Sep-18 12-Sep-18 12-Sep-18 12-Sep-18 -218 Casting / Placing of Sha
WSL-MIS-006-MH-4765 Construction of Backdrops 1 0% 13-Sep-18 13-Sep-18 13-Sep-18 13-Sep-18 -218 Construction of Backdro
WSL-MIS-006-MH-4770 External Waterproofing 1 0% 15-Sep-18 15-Sep-18 15-Sep-18 15-Sep-18 -218 External Waterproofing
WSL-MIS-006-MH-4780 Casting / Placing of Cover Slab 1 0% 16-Sep-18 16-Sep-18 16-Sep-18 16-Sep-18 -217 Casting / Placing of Cov
WSL-MIS-006-MH-4785 Internal Finishing 1 0% 17-Sep-18 17-Sep-18 17-Sep-18 17-Sep-18 -215 Internal Finishing
WSL-MIS-006-MH-4790 DI Frame and Cover 1 0% 18-Sep-18 18-Sep-18 18-Sep-18 18-Sep-18 -215 DI Frame and Cover
WSL-MIS-006-ND-1300 Receving Pit 2 0% 02-Sep-18 03-Sep-18 02-Sep-18 03-Sep-18 -221 Receving Pit
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 82 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-006-MH-5400 Excavation and Blinding 2 0% 06-Sep-18 08-Sep-18 06-Sep-18 08-Sep-18 -218 Excavation and Blinding
WSL-MIS-006-MH-5405 Casting / Placing of Base Slab 2 0% 09-Sep-18 10-Sep-18 09-Sep-18 10-Sep-18 -218 Casting / Placing of Bas
WSL-MIS-006-MH-5410 Casting / Placing of Walls 1 0% 11-Sep-18 11-Sep-18 11-Sep-18 11-Sep-18 -218 Casting / Placing of Wall
WSL-MIS-006-MH-5415 Casting / Placing of Reducer Slab 1 0% 12-Sep-18 12-Sep-18 12-Sep-18 12-Sep-18 -218 Casting / Placing of Red
WSL-MIS-006-MH-5420 Casting / Placing of Shafts 1 0% 13-Sep-18 13-Sep-18 13-Sep-18 13-Sep-18 -218 Casting / Placing of Sha
WSL-MIS-006-MH-5425 Construction of Backdrops 1 0% 15-Sep-18 15-Sep-18 15-Sep-18 15-Sep-18 -218 Construction of Backdro
WSL-MIS-006-MH-5430 External Waterproofing 1 0% 16-Sep-18 16-Sep-18 16-Sep-18 16-Sep-18 -218 External Waterproofing
WSL-MIS-006-MH-5440 Casting / Placing of Cover Slab 1 0% 17-Sep-18 17-Sep-18 17-Sep-18 17-Sep-18 -217 Casting / Placing of Cov
WSL-MIS-006-MH-5445 Internal Finishing 1 0% 18-Sep-18 18-Sep-18 18-Sep-18 18-Sep-18 -215 Internal Finishing
WSL-MIS-006-MH-5450 DI Frame and Cover 1 0% 19-Sep-18 19-Sep-18 19-Sep-18 19-Sep-18 -215 DI Frame and Cover
WSL-MIS-006-PL-1360 Install Dewatering System / Dewatering 1 0% 05-Sep-18 05-Sep-18 05-Sep-18 05-Sep-18 -222 Install Dewatering System
WSL-MIS-006-PL-1370 Excavation to Formation Level 2 0% 09-Sep-18 10-Sep-18 09-Sep-18 10-Sep-18 -222 Excavation to Formation
WSL-MIS-006-PL-1380 Pipe Laying 2 0% 11-Sep-18 12-Sep-18 11-Sep-18 12-Sep-18 -222 Pipe Laying
WSL-MIS-006-PL-1390 Pipe Surround 2 0% 12-Sep-18 13-Sep-18 12-Sep-18 13-Sep-18 -222 Pipe Surround
WSL-MIS-006-MH-4800 Casting / Placing of Base Slab 2 0% 11-Sep-18 12-Sep-18 11-Sep-18 12-Sep-18 -219 Casting / Placing of Bas
WSL-MIS-006-MH-4805 Casting / Placing of Walls 1 0% 13-Sep-18 13-Sep-18 13-Sep-18 13-Sep-18 -219 Casting / Placing of Wal
WSL-MIS-006-MH-4810 Casting / Placing of Reducer Slab 1 0% 15-Sep-18 15-Sep-18 15-Sep-18 15-Sep-18 -219 Casting / Placing of Red
WSL-MIS-006-MH-4815 Casting / Placing of Shafts 1 0% 16-Sep-18 16-Sep-18 16-Sep-18 16-Sep-18 -219 Casting / Placing of Sha
WSL-MIS-006-MH-4820 Construction of Backdrops 1 0% 17-Sep-18 17-Sep-18 17-Sep-18 17-Sep-18 -219 Construction of Backdro
WSL-MIS-006-MH-4825 External Waterproofing 1 0% 18-Sep-18 18-Sep-18 18-Sep-18 18-Sep-18 -219 External Waterproofing
WSL-MIS-006-MH-4835 Casting / Placing of Cover Slab 1 0% 19-Sep-18 19-Sep-18 19-Sep-18 19-Sep-18 -218 Casting / Placing of Cov
WSL-MIS-006-MH-4840 Internal Finishing 1 0% 20-Sep-18 20-Sep-18 20-Sep-18 20-Sep-18 -216 Internal Finishing
WSL-MIS-006-MH-4845 DI Frame and Cover 1 0% 22-Sep-18 22-Sep-18 22-Sep-18 22-Sep-18 -216 DI Frame and Cover
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 83 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MH206-513-MH206-514 18 04-Sep-18 24-Sep-18 04-Sep-18 24-Sep-18 -217
PIPELINE 16 04-Sep-18 22-Sep-18 04-Sep-18 22-Sep-18 -223
WSL-MIS-006-PL-1420 Lowering 2 0% 04-Sep-18 05-Sep-18 04-Sep-18 05-Sep-18 -229 Lowering
WSL-MIS-006-PL-1430 Install Dewatering System / Dewatering 1 0% 08-Sep-18 08-Sep-18 08-Sep-18 08-Sep-18 -222 Install Dewatering Syste
WSL-MIS-006-PL-1440 Excavation to Formation Level 2 0% 11-Sep-18 12-Sep-18 11-Sep-18 12-Sep-18 -222 Excavation to Formation
WSL-MIS-006-PL-1450 Pipe Laying 2 0% 13-Sep-18 15-Sep-18 13-Sep-18 15-Sep-18 -222 Pipe Laying
WSL-MIS-006-PL-1460 Pipe Surround 2 0% 15-Sep-18 16-Sep-18 15-Sep-18 16-Sep-18 -222 Pipe Surround
WSL-MIS-006-MH-4855 Casting / Placing of Base Slab 2 0% 13-Sep-18 15-Sep-18 13-Sep-18 15-Sep-18 -220 Casting / Placing of Bas
WSL-MIS-006-MH-4860 Casting / Placing of Walls 1 0% 16-Sep-18 16-Sep-18 16-Sep-18 16-Sep-18 -220 Casting / Placing of Wal
WSL-MIS-006-MH-4865 Casting / Placing of Reducer Slab 1 0% 17-Sep-18 17-Sep-18 17-Sep-18 17-Sep-18 -220 Casting / Placing of Red
WSL-MIS-006-MH-4870 Casting / Placing of Shafts 1 0% 18-Sep-18 18-Sep-18 18-Sep-18 18-Sep-18 -220 Casting / Placing of Sha
WSL-MIS-006-MH-4875 Construction of Backdrops 1 0% 19-Sep-18 19-Sep-18 19-Sep-18 19-Sep-18 -220 Construction of Backdro
WSL-MIS-006-MH-4880 External Waterproofing 1 0% 20-Sep-18 20-Sep-18 20-Sep-18 20-Sep-18 -220 External Waterproofing
WSL-MIS-006-MH-4890 Casting / Placing of Cover Slab 1 0% 22-Sep-18 22-Sep-18 22-Sep-18 22-Sep-18 -219 Casting / Placing of Cov
WSL-MIS-006-MH-4895 Internal Finishing 1 0% 23-Sep-18 23-Sep-18 23-Sep-18 23-Sep-18 -217 Internal Finishing
WSL-MIS-006-MH-4900 DI Frame and Cover 1 0% 24-Sep-18 24-Sep-18 24-Sep-18 24-Sep-18 -217 DI Frame and Cover
WSL-MIS-006-PL-1500 Install Dewatering System / Dewatering 1 0% 10-Sep-18 10-Sep-18 10-Sep-18 10-Sep-18 -222 Install Dewatering Syste
WSL-MIS-006-PL-1510 Excavation to Formation Level 2 0% 13-Sep-18 15-Sep-18 13-Sep-18 15-Sep-18 -222 Excavation to Formation
WSL-MIS-006-PL-1520 Pipe Laying 2 0% 16-Sep-18 17-Sep-18 16-Sep-18 17-Sep-18 -222 Pipe Laying
WSL-MIS-006-PL-1530 Pipe Surround 2 0% 17-Sep-18 18-Sep-18 17-Sep-18 18-Sep-18 -222 Pipe Surround
WSL-MIS-006-MH-4910 Casting / Placing of Base Slab 2 0% 16-Sep-18 17-Sep-18 16-Sep-18 17-Sep-18 -221 Casting / Placing of Bas
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 84 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-006-MH-4915 Casting / Placing of Walls 1 0% 18-Sep-18 18-Sep-18 18-Sep-18 18-Sep-18 -221 Casting / Placing of Wa
WSL-MIS-006-MH-4920 Casting / Placing of Reducer Slab 1 0% 19-Sep-18 19-Sep-18 19-Sep-18 19-Sep-18 -221 Casting / Placing of Red
WSL-MIS-006-MH-4925 Casting / Placing of Shafts 1 0% 20-Sep-18 20-Sep-18 20-Sep-18 20-Sep-18 -221 Casting / Placing of Sha
WSL-MIS-006-MH-4930 Construction of Backdrops 1 0% 22-Sep-18 22-Sep-18 22-Sep-18 22-Sep-18 -221 Construction of Backdr
WSL-MIS-006-MH-4935 External Waterproofing 1 0% 23-Sep-18 23-Sep-18 23-Sep-18 23-Sep-18 -221 External Waterproofing
WSL-MIS-006-MH-4945 Casting / Placing of Cover Slab 1 0% 24-Sep-18 24-Sep-18 24-Sep-18 24-Sep-18 -220 Casting / Placing of Co
WSL-MIS-006-MH-4950 Internal Finishing 1 0% 25-Sep-18 25-Sep-18 25-Sep-18 25-Sep-18 -218 Internal Finishing
WSL-MIS-006-MH-4955 DI Frame and Cover 1 0% 26-Sep-18 26-Sep-18 26-Sep-18 26-Sep-18 -218 DI Frame and Cover
WSL-MIS-006-ND-1545 Receving Pit 2 0% 11-Sep-18 12-Sep-18 11-Sep-18 12-Sep-18 -222 Receving Pit
WSL-MIS-006-MH-5460 Casting / Placing of Base Slab 2 0% 18-Sep-18 19-Sep-18 18-Sep-18 19-Sep-18 -222 Casting / Placing of Bas
WSL-MIS-006-MH-5465 Casting / Placing of Walls 1 0% 20-Sep-18 20-Sep-18 20-Sep-18 20-Sep-18 -222 Casting / Placing of Wa
WSL-MIS-006-MH-5470 Casting / Placing of Reducer Slab 1 0% 22-Sep-18 22-Sep-18 22-Sep-18 22-Sep-18 -222 Casting / Placing of Red
WSL-MIS-006-MH-5475 Casting / Placing of Shafts 1 0% 23-Sep-18 23-Sep-18 23-Sep-18 23-Sep-18 -222 Casting / Placing of Sha
WSL-MIS-006-MH-5480 Construction of Backdrops 1 0% 24-Sep-18 24-Sep-18 24-Sep-18 24-Sep-18 -222 Construction of Backdr
WSL-MIS-006-MH-5485 External Waterproofing 1 0% 25-Sep-18 25-Sep-18 25-Sep-18 25-Sep-18 -222 External Waterproofing
WSL-MIS-006-MH-5495 Casting / Placing of Cover Slab 1 0% 26-Sep-18 26-Sep-18 26-Sep-18 26-Sep-18 -221 Casting / Placing of Co
WSL-MIS-006-MH-5500 Internal Finishing 1 0% 27-Sep-18 27-Sep-18 27-Sep-18 27-Sep-18 -219 Internal Finishing
WSL-MIS-006-MH-5505 DI Frame and Cover 1 0% 29-Sep-18 29-Sep-18 29-Sep-18 29-Sep-18 -219 DI Frame and Cover
WSL-MIS-006-PL-2370 Install Dewatering System / Dewatering 1 0% 15-Sep-18 15-Sep-18 15-Sep-18 15-Sep-18 -223 Install Dewatering Syste
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 85 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-006-PL-2375 Excavation to Formation Level 2 0% 18-Sep-18 19-Sep-18 18-Sep-18 19-Sep-18 -223 Excavation to Formation
WSL-MIS-006-PL-2380 Pipe Laying 2 0% 20-Sep-18 22-Sep-18 20-Sep-18 22-Sep-18 -222 Pipe Laying
WSL-MIS-006-PL-2385 Pipe Surround 2 0% 22-Sep-18 23-Sep-18 22-Sep-18 23-Sep-18 -222 Pipe Surround
WSL-MIS-006-MH-4965 Casting / Placing of Base Slab 2 0% 20-Sep-18 22-Sep-18 20-Sep-18 22-Sep-18 -223 Casting / Placing of Bas
WSL-MIS-006-MH-4970 Casting / Placing of Walls 1 0% 23-Sep-18 23-Sep-18 23-Sep-18 23-Sep-18 -223 Casting / Placing of Wa
WSL-MIS-006-MH-4975 Casting / Placing of Reducer Slab 1 0% 24-Sep-18 24-Sep-18 24-Sep-18 24-Sep-18 -223 Casting / Placing of Re
WSL-MIS-006-MH-4980 Casting / Placing of Shafts 1 0% 25-Sep-18 25-Sep-18 25-Sep-18 25-Sep-18 -223 Casting / Placing of Sha
WSL-MIS-006-MH-4985 Construction of Backdrops 1 0% 26-Sep-18 26-Sep-18 26-Sep-18 26-Sep-18 -223 Construction of Backdr
WSL-MIS-006-MH-4990 External Waterproofing 1 0% 27-Sep-18 27-Sep-18 27-Sep-18 27-Sep-18 -223 External Waterproofing
WSL-MIS-006-MH-5000 Casting / Placing of Cover Slab 1 0% 29-Sep-18 29-Sep-18 29-Sep-18 29-Sep-18 -222 Casting / Placing of Co
WSL-MIS-006-MH-5005 Internal Finishing 1 0% 30-Sep-18 30-Sep-18 30-Sep-18 30-Sep-18 -220 Internal Finishing
WSL-MIS-006-MH-5010 DI Frame and Cover 1 0% 01-Oct-18 01-Oct-18 01-Oct-18 01-Oct-18 -220 DI Frame and Cover
WSL-MIS-006-PL-2405 Install Dewatering System / Dewatering 1 0% 17-Sep-18 17-Sep-18 17-Sep-18 17-Sep-18 -224 Install Dewatering Syste
WSL-MIS-006-PL-2410 Excavation to Formation Level 2 0% 20-Sep-18 22-Sep-18 20-Sep-18 22-Sep-18 -224 Excavation to Formation
WSL-MIS-006-PL-2415 Pipe Laying 2 0% 23-Sep-18 24-Sep-18 23-Sep-18 24-Sep-18 -223 Pipe Laying
WSL-MIS-006-PL-2420 Pipe Surround 2 0% 24-Sep-18 25-Sep-18 24-Sep-18 25-Sep-18 -223 Pipe Surround
WSL-MIS-006-MH-5020 Casting / Placing of Base Slab 2 0% 23-Sep-18 24-Sep-18 23-Sep-18 24-Sep-18 -224 Casting / Placing of Bas
WSL-MIS-006-MH-5025 Casting / Placing of Walls 1 0% 25-Sep-18 25-Sep-18 25-Sep-18 25-Sep-18 -224 Casting / Placing of Wa
WSL-MIS-006-MH-5030 Casting / Placing of Reducer Slab 1 0% 26-Sep-18 26-Sep-18 26-Sep-18 26-Sep-18 -224 Casting / Placing of Re
WSL-MIS-006-MH-5035 Casting / Placing of Shafts 1 0% 27-Sep-18 27-Sep-18 27-Sep-18 27-Sep-18 -224 Casting / Placing of Sh
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 86 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
WSL-MIS-006-MH-5040 Construction of Backdrops 1 0% 29-Sep-18 29-Sep-18 29-Sep-18 29-Sep-18 -224 Construction of Backdr
WSL-MIS-006-MH-5045 External Waterproofing 1 0% 30-Sep-18 30-Sep-18 30-Sep-18 30-Sep-18 -224 External Waterproofing
WSL-MIS-006-MH-5055 Casting / Placing of Cover Slab 1 0% 01-Oct-18 01-Oct-18 01-Oct-18 01-Oct-18 -223 Casting / Placing of Co
WSL-MIS-006-MH-5060 Internal Finishing 1 0% 02-Oct-18 02-Oct-18 02-Oct-18 02-Oct-18 -221 Internal Finishing
WSL-MIS-006-MH-5065 DI Frame and Cover 1 0% 03-Oct-18 03-Oct-18 03-Oct-18 03-Oct-18 -221 DI Frame and Cover
WSL-MIS-006-PL-2440 Install Dewatering System / Dewatering 1 0% 19-Sep-18 19-Sep-18 19-Sep-18 19-Sep-18 -229 Install Dewatering Syste
WSL-MIS-006-PL-2445 Excavation to Formation Level 2 0% 23-Sep-18 24-Sep-18 23-Sep-18 24-Sep-18 -229 Excavation to Formatio
WSL-MIS-006-PL-2450 Pipe Laying 2 0% 25-Sep-18 26-Sep-18 25-Sep-18 26-Sep-18 -224 Pipe Laying
WSL-MIS-006-PL-2455 Pipe Surround 2 0% 26-Sep-18 27-Sep-18 26-Sep-18 27-Sep-18 -224 Pipe Surround
WSL-MIS-006-MH-5075 Casting / Placing of Base Slab 2 0% 25-Sep-18 26-Sep-18 25-Sep-18 26-Sep-18 -229 Casting / Placing of Ba
WSL-MIS-006-MH-5080 Casting / Placing of Walls 2 0% 27-Sep-18 29-Sep-18 27-Sep-18 29-Sep-18 -229 Casting / Placing of Wa
WSL-MIS-006-MH-5085 Casting / Placing of Reducer Slab 2 0% 30-Sep-18 01-Oct-18 30-Sep-18 01-Oct-18 -229 Casting / Placing of Re
WSL-MIS-006-MH-5090 Casting / Placing of Shafts 2 0% 02-Oct-18 03-Oct-18 02-Oct-18 03-Oct-18 -229 Casting / Placing of Sh
WSL-MIS-006-MH-5095 Construction of Backdrops 2 0% 04-Oct-18 06-Oct-18 04-Oct-18 06-Oct-18 -229 Construction of Backd
WSL-MIS-006-MH-5100 External Waterproofing 2 0% 07-Oct-18 08-Oct-18 07-Oct-18 08-Oct-18 -229 External Waterproofing
WSL-MIS-006-MH-5110 Casting / Placing of Cover Slab 2 0% 09-Oct-18 10-Oct-18 09-Oct-18 10-Oct-18 -229 Casting / Placing of C
WSL-MIS-006-MH-5115 Internal Finishing 2 0% 11-Oct-18 13-Oct-18 11-Oct-18 13-Oct-18 -229 Internal Finishing
WSL-MIS-006-MH-5120 DI Frame and Cover 2 0% 14-Oct-18 15-Oct-18 14-Oct-18 15-Oct-18 -229 DI Frame and Cover
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 87 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
UM-MIS-213/1-PL-1070 Testing 4 100% 22-Nov-17 26-Nov-17 22-Nov-17 A 26-Nov-17 A
NAD-MIS-001-PL-4270 Excavation for Receiving Pit 4 100% 03-Jan-18 07-Jan-18 03-Jan-18 A 07-Jan-18 A
NAD-MIS-001-PL-4340 Excavation for Receiving Pit 2 100% 02-Jan-18 03-Jan-18 02-Jan-18 A 03-Jan-18 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 88 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
CH-1+770-2+550 24 25-Apr-18 22-May-18 25-Apr-18 22-May-18 -77
PIPELINE 24 25-Apr-18 22-May-18 25-Apr-18 22-May-18 -77
UM-MIS-213/1-PL-1120 Excavation and Formation 15 0% 25-Apr-18 12-May-18 25-Apr-18 12-May-18 -224 Excavation and Formation
NAD-MIS-001-PL-4410 Excavation for Receiving Pit 2 0% 23-May-18 24-May-18 23-May-18 24-May-18 -69 Excavation for Receiving Pit
NAD-MIS-001-PL-4440 Pipe Surround 3 0% 31-May-18 03-Jun-18 31-May-18 03-Jun-18 -69 Pipe Surround
NAD-MIS-001-PL-4480 Excavation for Receiving Pit 2 0% 04-Jun-18 05-Jun-18 04-Jun-18 05-Jun-18 -81 Excavation for Receiving Pit
NAD-MIS-001-PL-4510 Pipe Surround 3 0% 14-Jun-18 17-Jun-18 14-Jun-18 17-Jun-18 -81 Pipe Surround
UM-MIS-213/1-MH-1010 Casting/Placing of Base Slab 2 0% 29-May-18 30-May-18 29-May-18 30-May-18 -72 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1020 Casting/Placing of Walls 2 0% 31-May-18 02-Jun-18 31-May-18 02-Jun-18 -72 Casting/Placing of Walls
UM-MIS-213/1-MH-1030 Installation of DI Valves and Fittings 2 0% 04-Jun-18 05-Jun-18 04-Jun-18 05-Jun-18 -72 Installation of DI Valves and Fitti
UM-MIS-213/1-MH-1040 Casting / Placing of Cover Slab 2 0% 06-Jun-18 07-Jun-18 06-Jun-18 07-Jun-18 -72 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1050 External Waterproofing and Backfilling 2 0% 06-Jun-18 07-Jun-18 06-Jun-18 07-Jun-18 -72 External Waterproofing and Bac
UM-MIS-213/1-MH-1060 Internal Finishing 2 0% 06-Jun-18 07-Jun-18 06-Jun-18 07-Jun-18 -72 Internal Finishing
UM-MIS-213/1-MH-1070 Installation of Cover & Frame 2 0% 06-Jun-18 07-Jun-18 06-Jun-18 07-Jun-18 -72 Installation of Cover & Frame
UM-MIS-213/1-MH-1090 Casting/Placing of Base Slab 2 0% 31-May-18 02-Jun-18 31-May-18 02-Jun-18 -72 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1100 Casting/Placing of Walls 2 0% 03-Jun-18 04-Jun-18 03-Jun-18 04-Jun-18 -72 Casting/Placing of Walls
UM-MIS-213/1-MH-1110 Installation of DI Valves and Fittings 2 0% 06-Jun-18 07-Jun-18 06-Jun-18 07-Jun-18 -72 Installation of DI Valves and Fitti
UM-MIS-213/1-MH-1140 Internal Finishing 2 0% 09-Jun-18 10-Jun-18 09-Jun-18 10-Jun-18 -72 Internal Finishing
UM-MIS-213/1-MH-1150 Installation of Cover & Frame 2 0% 09-Jun-18 10-Jun-18 09-Jun-18 10-Jun-18 -72 Installation of Cover & Frame
UM-MIS-213/1-MH-1120 Casting / Placing of Cover Slab 2 0% 09-Jun-18 10-Jun-18 09-Jun-18 10-Jun-18 -72 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1130 External Waterproofing and Backfilling 2 0% 09-Jun-18 10-Jun-18 09-Jun-18 10-Jun-18 -72 External Waterproofing and Bac
UM-MIS-213/1-MH-1170 Casting/Placing of Base Slab 2 0% 03-Jun-18 04-Jun-18 03-Jun-18 04-Jun-18 -72 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1180 Casting/Placing of Walls 2 0% 05-Jun-18 06-Jun-18 05-Jun-18 06-Jun-18 -72 Casting/Placing of Walls
UM-MIS-213/1-MH-1190 Installation of DI Valves and Fittings 2 0% 09-Jun-18 10-Jun-18 09-Jun-18 10-Jun-18 -72 Installation of DI Valves and Fitt
UM-MIS-213/1-MH-1210 External Waterproofing and Backfilling 2 0% 11-Jun-18 12-Jun-18 11-Jun-18 12-Jun-18 -72 External Waterproofing and Bac
UM-MIS-213/1-MH-1220 Internal Finishing 2 0% 11-Jun-18 12-Jun-18 11-Jun-18 12-Jun-18 -72 Internal Finishing
UM-MIS-213/1-MH-1230 Installation of Cover & Frame 2 0% 11-Jun-18 12-Jun-18 11-Jun-18 12-Jun-18 -72 Installation of Cover & Frame
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 90 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
UM-MIS-213/1-MH-1200 Casting / Placing of Cover Slab 2 0% 11-Jun-18 12-Jun-18 11-Jun-18 12-Jun-18 -72 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1250 Casting/Placing of Base Slab 2 0% 05-Jun-18 06-Jun-18 05-Jun-18 06-Jun-18 -74 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1260 Casting/Placing of Walls 2 0% 07-Jun-18 09-Jun-18 07-Jun-18 09-Jun-18 -74 Casting/Placing of Walls
UM-MIS-213/1-MH-1270 Installation of DI Valves and Fittings 2 0% 11-Jun-18 12-Jun-18 11-Jun-18 12-Jun-18 -74 Installation of DI Valves and Fitt
UM-MIS-213/1-MH-1280 Casting / Placing of Cover Slab 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -74 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1290 External Waterproofing and Backfilling 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -74 External Waterproofing and Bac
UM-MIS-213/1-MH-1300 Internal Finishing 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -74 Internal Finishing
UM-MIS-213/1-MH-1310 Installation of Cover & Frame 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -74 Installation of Cover & Frame
UM-MIS-213/1-MH-1330 Casting/Placing of Base Slab 2 0% 05-Jun-18 06-Jun-18 05-Jun-18 06-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1340 Casting/Placing of Walls 2 0% 07-Jun-18 09-Jun-18 07-Jun-18 09-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1350 Installation of DI Valves and Fittings 2 0% 11-Jun-18 12-Jun-18 11-Jun-18 12-Jun-18 -224 Installation of DI Valves and Fitt
UM-MIS-213/1-MH-1360 Casting / Placing of Cover Slab 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -224 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1370 External Waterproofing and Backfilling 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -224 External Waterproofing and Bac
UM-MIS-213/1-MH-1380 Internal Finishing 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -224 Internal Finishing
UM-MIS-213/1-MH-1390 Installation of Cover & Frame 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1410 Casting/Placing of Base Slab 2 0% 07-Jun-18 09-Jun-18 07-Jun-18 09-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1420 Casting/Placing of Walls 2 0% 10-Jun-18 11-Jun-18 10-Jun-18 11-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1430 Installation of DI Valves and Fittings 2 0% 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18 -224 Installation of DI Valves and Fitt
UM-MIS-213/1-MH-1440 Casting / Placing of Cover Slab 2 0% 16-Jun-18 17-Jun-18 16-Jun-18 17-Jun-18 -224 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1450 External Waterproofing and Backfilling 2 0% 16-Jun-18 17-Jun-18 16-Jun-18 17-Jun-18 -224 External Waterproofing and Bac
UM-MIS-213/1-MH-1460 Internal Finishing 2 0% 16-Jun-18 17-Jun-18 16-Jun-18 17-Jun-18 -224 Internal Finishing
UM-MIS-213/1-MH-1470 Installation of Cover & Frame 2 0% 16-Jun-18 17-Jun-18 16-Jun-18 17-Jun-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1490 Casting/Placing of Base Slab 2 0% 10-Jun-18 11-Jun-18 10-Jun-18 11-Jun-18 -224 Casting/Placing of Base Slab
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 91 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
UM-MIS-213/1-MH-1500 Casting/Placing of Walls 2 0% 12-Jun-18 13-Jun-18 12-Jun-18 13-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1510 Installation of DI Valves and Fittings 2 0% 16-Jun-18 17-Jun-18 16-Jun-18 17-Jun-18 -224 Installation of DI Valves and Fit
UM-MIS-213/1-MH-1520 Casting / Placing of Cover Slab 2 0% 18-Jun-18 19-Jun-18 18-Jun-18 19-Jun-18 -224 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1530 External Waterproofing and Backfilling 2 0% 18-Jun-18 19-Jun-18 18-Jun-18 19-Jun-18 -224 External Waterproofing and Ba
UM-MIS-213/1-MH-1540 Internal Finishing 2 0% 18-Jun-18 19-Jun-18 18-Jun-18 19-Jun-18 -224 Internal Finishing
UM-MIS-213/1-MH-1550 Installation of Cover & Frame 2 0% 18-Jun-18 19-Jun-18 18-Jun-18 19-Jun-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1570 Casting/Placing of Base Slab 2 0% 12-Jun-18 13-Jun-18 12-Jun-18 13-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1580 Casting/Placing of Walls 2 0% 14-Jun-18 16-Jun-18 14-Jun-18 16-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1590 Installation of DI Valves and Fittings 2 0% 18-Jun-18 19-Jun-18 18-Jun-18 19-Jun-18 -224 Installation of DI Valves and Fit
UM-MIS-213/1-MH-1600 Casting / Placing of Cover Slab 2 0% 20-Jun-18 21-Jun-18 20-Jun-18 21-Jun-18 -224 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1610 External Waterproofing and Backfilling 2 0% 20-Jun-18 21-Jun-18 20-Jun-18 21-Jun-18 -224 External Waterproofing and Ba
UM-MIS-213/1-MH-1620 Internal Finishing 2 0% 20-Jun-18 21-Jun-18 20-Jun-18 21-Jun-18 -224 Internal Finishing
UM-MIS-213/1-MH-1630 Installation of Cover & Frame 2 0% 20-Jun-18 21-Jun-18 20-Jun-18 21-Jun-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1650 Casting/Placing of Base Slab 2 0% 14-Jun-18 16-Jun-18 14-Jun-18 16-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1660 Casting/Placing of Walls 2 0% 17-Jun-18 18-Jun-18 17-Jun-18 18-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1670 Installation of DI Valves and Fittings 2 0% 20-Jun-18 21-Jun-18 20-Jun-18 21-Jun-18 -224 Installation of DI Valves and Fit
UM-MIS-213/1-MH-1680 Casting / Placing of Cover Slab 2 0% 23-Jun-18 24-Jun-18 23-Jun-18 24-Jun-18 -224 Casting / Placing of Cover Slab
UM-MIS-213/1-MH-1690 External Waterproofing and Backfilling 2 0% 23-Jun-18 24-Jun-18 23-Jun-18 24-Jun-18 -224 External Waterproofing and Ba
UM-MIS-213/1-MH-1700 Internal Finishing 2 0% 23-Jun-18 24-Jun-18 23-Jun-18 24-Jun-18 -224 Internal Finishing
UM-MIS-213/1-MH-1710 Installation of Cover & Frame 2 0% 23-Jun-18 24-Jun-18 23-Jun-18 24-Jun-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1730 Casting/Placing of Base Slab 2 0% 17-Jun-18 18-Jun-18 17-Jun-18 18-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1740 Casting/Placing of Walls 2 0% 19-Jun-18 20-Jun-18 19-Jun-18 20-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1750 Installation of DI Valves and Fittings 2 0% 23-Jun-18 24-Jun-18 23-Jun-18 24-Jun-18 -224 Installation of DI Valves and Fi
UM-MIS-213/1-MH-1760 Casting / Placing of Cover Slab 2 0% 25-Jun-18 26-Jun-18 25-Jun-18 26-Jun-18 -224 Casting / Placing of Cover Sla
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 92 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
UM-MIS-213/1-MH-1770 External Waterproofing and Backfilling 2 0% 25-Jun-18 26-Jun-18 25-Jun-18 26-Jun-18 -224 External Waterproofing and Ba
UM-MIS-213/1-MH-1780 Internal Finishing 2 0% 25-Jun-18 26-Jun-18 25-Jun-18 26-Jun-18 -224 Internal Finishing
UM-MIS-213/1-MH-1790 Installation of Cover & Frame 2 0% 25-Jun-18 26-Jun-18 25-Jun-18 26-Jun-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1810 Casting/Placing of Base Slab 2 0% 19-Jun-18 20-Jun-18 19-Jun-18 20-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1820 Casting/Placing of Walls 2 0% 21-Jun-18 23-Jun-18 21-Jun-18 23-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1830 Installation of DI Valves and Fittings 2 0% 25-Jun-18 26-Jun-18 25-Jun-18 26-Jun-18 -224 Installation of DI Valves and Fi
UM-MIS-213/1-MH-1840 Casting / Placing of Cover Slab 2 0% 27-Jun-18 28-Jun-18 27-Jun-18 28-Jun-18 -224 Casting / Placing of Cover Sla
UM-MIS-213/1-MH-1850 External Waterproofing and Backfilling 2 0% 27-Jun-18 28-Jun-18 27-Jun-18 28-Jun-18 -224 External Waterproofing and Ba
UM-MIS-213/1-MH-1860 Internal Finishing 2 0% 27-Jun-18 28-Jun-18 27-Jun-18 28-Jun-18 -224 Internal Finishing
UM-MIS-213/1-MH-1870 Installation of Cover & Frame 2 0% 27-Jun-18 28-Jun-18 27-Jun-18 28-Jun-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1890 Casting/Placing of Base Slab 2 0% 21-Jun-18 23-Jun-18 21-Jun-18 23-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1900 Casting/Placing of Walls 2 0% 24-Jun-18 25-Jun-18 24-Jun-18 25-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1910 Installation of DI Valves and Fittings 2 0% 27-Jun-18 28-Jun-18 27-Jun-18 28-Jun-18 -224 Installation of DI Valves and Fi
UM-MIS-213/1-MH-1920 Casting / Placing of Cover Slab 2 0% 30-Jun-18 01-Jul-18 30-Jun-18 01-Jul-18 -224 Casting / Placing of Cover Sla
UM-MIS-213/1-MH-1930 External Waterproofing and Backfilling 2 0% 30-Jun-18 01-Jul-18 30-Jun-18 01-Jul-18 -224 External Waterproofing and Ba
UM-MIS-213/1-MH-1940 Internal Finishing 2 0% 30-Jun-18 01-Jul-18 30-Jun-18 01-Jul-18 -224 Internal Finishing
UM-MIS-213/1-MH-1950 Installation of Cover & Frame 2 0% 30-Jun-18 01-Jul-18 30-Jun-18 01-Jul-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-1970 Casting/Placing of Base Slab 2 0% 24-Jun-18 25-Jun-18 24-Jun-18 25-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-1980 Casting/Placing of Walls 2 0% 26-Jun-18 27-Jun-18 26-Jun-18 27-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-1990 Installation of DI Valves and Fittings 2 0% 30-Jun-18 01-Jul-18 30-Jun-18 01-Jul-18 -224 Installation of DI Valves and F
UM-MIS-213/1-MH-2000 Casting / Placing of Cover Slab 2 0% 02-Jul-18 03-Jul-18 02-Jul-18 03-Jul-18 -224 Casting / Placing of Cover Sla
UM-MIS-213/1-MH-2010 External Waterproofing and Backfilling 2 0% 02-Jul-18 03-Jul-18 02-Jul-18 03-Jul-18 -224 External Waterproofing and Ba
UM-MIS-213/1-MH-2020 Internal Finishing 2 0% 02-Jul-18 03-Jul-18 02-Jul-18 03-Jul-18 -224 Internal Finishing
UM-MIS-213/1-MH-2030 Installation of Cover & Frame 2 0% 02-Jul-18 03-Jul-18 02-Jul-18 03-Jul-18 -224 Installation of Cover & Frame
UM-MIS-213/1-MH-2050 Casting/Placing of Base Slab 2 0% 26-Jun-18 27-Jun-18 26-Jun-18 27-Jun-18 -224 Casting/Placing of Base Slab
UM-MIS-213/1-MH-2060 Casting/Placing of Walls 2 0% 28-Jun-18 30-Jun-18 28-Jun-18 30-Jun-18 -224 Casting/Placing of Walls
UM-MIS-213/1-MH-2070 Installation of DI Valves and Fittings 2 0% 02-Jul-18 03-Jul-18 02-Jul-18 03-Jul-18 -224 Installation of DI Valves and F
UM-MIS-213/1-MH-2080 Casting / Placing of Cover Slab 2 0% 04-Jul-18 05-Jul-18 04-Jul-18 05-Jul-18 -224 Casting / Placing of Cover Sla
UM-MIS-213/1-MH-2090 External Waterproofing and Backfilling 2 0% 04-Jul-18 05-Jul-18 04-Jul-18 05-Jul-18 -224 External Waterproofing and B
UM-MIS-213/1-MH-2300 Internal Finishing 2 0% 04-Jul-18 05-Jul-18 04-Jul-18 05-Jul-18 -224 Internal Finishing
UM-MIS-213/1-MH-2310 Installation of Cover & Frame 2 0% 04-Jul-18 05-Jul-18 04-Jul-18 05-Jul-18 -224 Installation of Cover & Frame
TRA-MIS-178-PL-2475 Install Dewatering System / Dewatering 4 0% 20-Oct-18 23-Oct-18 20-Oct-18 23-Oct-18 -210 Install Dewatering Sy
TRA-MIS-178-PL-2480 Excavation to Formation Level 4 0% 23-Oct-18 27-Oct-18 23-Oct-18 27-Oct-18 -210 Excavation to Forma
TRA-MIS-178-PL-2490 Pipe Surround 2 0% 29-Oct-18 30-Oct-18 29-Oct-18 30-Oct-18 -210 Pipe Surround
TRA-MIS-178-PL-2485 Pipe Laying 4 0% 28-Oct-18 31-Oct-18 28-Oct-18 31-Oct-18 -210 Pipe Laying
TRA-MIS-178-MH-5515 Casting / Placing of Base Slab 2 0% 28-Oct-18 29-Oct-18 28-Oct-18 29-Oct-18 -209 Casting / Placing of B
TRA-MIS-178-MH-5520 Casting / Placing of Walls 1 0% 30-Oct-18 30-Oct-18 30-Oct-18 30-Oct-18 -209 Casting / Placing of W
TRA-MIS-178-MH-5525 Casting / Placing of Reducer Slab 1 0% 31-Oct-18 31-Oct-18 31-Oct-18 31-Oct-18 -209 Casting / Placing of R
TRA-MIS-178-MH-5530 Casting / Placing of Shafts 1 0% 01-Nov-18 01-Nov-18 01-Nov-18 01-Nov-18 -209 Casting / Placing of
TRA-MIS-178-MH-5535 Construction of Backdrops 1 0% 03-Nov-18 03-Nov-18 03-Nov-18 03-Nov-18 -209 Construction of Bac
TRA-MIS-178-MH-5540 External Waterproofing 1 0% 04-Nov-18 04-Nov-18 04-Nov-18 04-Nov-18 -209 External Waterproof
TRA-MIS-178-MH-5550 Casting / Placing of Cover Slab 1 0% 05-Nov-18 05-Nov-18 05-Nov-18 05-Nov-18 -209 Casting / Placing of
TRA-MIS-178-MH-5555 Internal Finishing 1 0% 06-Nov-18 06-Nov-18 06-Nov-18 06-Nov-18 -209 Internal Finishing
TRA-MIS-178-MH-5560 DI Frame and Cover 1 0% 07-Nov-18 07-Nov-18 07-Nov-18 07-Nov-18 -209 DI Frame and Cove
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 94 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
TRA-MIS-178-PL-2510 Install Dewatering System / Dewatering 3 0% 24-Oct-18 27-Oct-18 24-Oct-18 27-Oct-18 -211 Install Dewatering Sy
TRA-MIS-178-PL-2515 Excavation to Formation Level 3 0% 28-Oct-18 30-Oct-18 28-Oct-18 30-Oct-18 -211 Excavation to Forma
TRA-MIS-178-PL-2520 Pipe Laying 2 0% 31-Oct-18 01-Nov-18 31-Oct-18 01-Nov-18 -211 Pipe Laying
TRA-MIS-178-PL-2525 Pipe Surround 2 0% 01-Nov-18 03-Nov-18 01-Nov-18 03-Nov-18 -211 Pipe Surround
TRA-MIS-178-MH-5570 Casting / Placing of Base Slab 2 0% 31-Oct-18 01-Nov-18 31-Oct-18 01-Nov-18 -211 Casting / Placing of
TRA-MIS-178-MH-5575 Casting / Placing of Walls 1 0% 03-Nov-18 03-Nov-18 03-Nov-18 03-Nov-18 -211 Casting / Placing of
TRA-MIS-178-MH-5580 Casting / Placing of Reducer Slab 1 0% 04-Nov-18 04-Nov-18 04-Nov-18 04-Nov-18 -211 Casting / Placing of
TRA-MIS-178-MH-5585 Casting / Placing of Shafts 1 0% 05-Nov-18 05-Nov-18 05-Nov-18 05-Nov-18 -211 Casting / Placing of
TRA-MIS-178-MH-5590 Construction of Backdrops 1 0% 06-Nov-18 06-Nov-18 06-Nov-18 06-Nov-18 -211 Construction of Bac
TRA-MIS-178-MH-5595 External Waterproofing 1 0% 07-Nov-18 07-Nov-18 07-Nov-18 07-Nov-18 -211 External Waterproof
TRA-MIS-178-MH-5605 Casting / Placing of Cover Slab 1 0% 08-Nov-18 08-Nov-18 08-Nov-18 08-Nov-18 -211 Casting / Placing of
TRA-MIS-178-MH-5610 Internal Finishing 1 0% 10-Nov-18 10-Nov-18 10-Nov-18 10-Nov-18 -211 Internal Finishing
TRA-MIS-178-MH-5615 DI Frame and Cover 1 0% 11-Nov-18 11-Nov-18 11-Nov-18 11-Nov-18 -211 DI Frame and Cove
TRA-MIS-178-PL-2545 Install Dewatering System / Dewatering 2 0% 28-Oct-18 29-Oct-18 28-Oct-18 29-Oct-18 -214 Install Dewatering Sy
TRA-MIS-178-PL-2550 Excavation to Formation Level 3 0% 31-Oct-18 03-Nov-18 31-Oct-18 03-Nov-18 -214 Excavation to Forma
TRA-MIS-178-PL-2555 Pipe Laying 2 0% 04-Nov-18 05-Nov-18 04-Nov-18 05-Nov-18 -212 Pipe Laying
TRA-MIS-178-PL-2560 Pipe Surround 2 0% 05-Nov-18 06-Nov-18 05-Nov-18 06-Nov-18 -212 Pipe Surround
TRA-MIS-178-MH-5625 Casting / Placing of Base Slab 3 0% 04-Nov-18 06-Nov-18 04-Nov-18 06-Nov-18 -214 Casting / Placing of
TRA-MIS-178-MH-5630 Casting / Placing of Walls 1 0% 07-Nov-18 07-Nov-18 07-Nov-18 07-Nov-18 -214 Casting / Placing of
TRA-MIS-178-MH-5635 Casting / Placing of Reducer Slab 1 0% 08-Nov-18 08-Nov-18 08-Nov-18 08-Nov-18 -214 Casting / Placing of
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 95 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
TRA-MIS-178-MH-5640 Casting / Placing of Shafts 1 0% 10-Nov-18 10-Nov-18 10-Nov-18 10-Nov-18 -214 Casting / Placing of
TRA-MIS-178-MH-5645 Construction of Backdrops 1 0% 11-Nov-18 11-Nov-18 11-Nov-18 11-Nov-18 -214 Construction of Bac
TRA-MIS-178-MH-5650 External Waterproofing 1 0% 12-Nov-18 12-Nov-18 12-Nov-18 12-Nov-18 -214 External Waterproo
TRA-MIS-178-MH-5660 Casting / Placing of Cover Slab 1 0% 13-Nov-18 13-Nov-18 13-Nov-18 13-Nov-18 -214 Casting / Placing of
TRA-MIS-178-MH-5665 Internal Finishing 1 0% 14-Nov-18 14-Nov-18 14-Nov-18 14-Nov-18 -214 Internal Finishing
TRA-MIS-178-MH-5670 DI Frame and Cover 1 0% 15-Nov-18 15-Nov-18 15-Nov-18 15-Nov-18 -214 DI Frame and Cove
TRA-MIS-178-PL-2580 Install Dewatering System / Dewatering 4 0% 31-Oct-18 04-Nov-18 31-Oct-18 04-Nov-18 -215 Install Dewatering S
TRA-MIS-178-PL-2585 Excavation to Formation Level 3 0% 04-Nov-18 06-Nov-18 04-Nov-18 06-Nov-18 -215 Excavation to Forma
TRA-MIS-178-PL-2595 Pipe Surround 2 0% 08-Nov-18 10-Nov-18 08-Nov-18 10-Nov-18 -214 Pipe Surround
TRA-MIS-178-PL-2590 Pipe Laying 4 0% 07-Nov-18 11-Nov-18 07-Nov-18 11-Nov-18 -214 Pipe Laying
TRA-MIS-178-MH-5680 Casting / Placing of Base Slab 2 0% 07-Nov-18 08-Nov-18 07-Nov-18 08-Nov-18 -215 Casting / Placing of
TRA-MIS-178-MH-5685 Casting / Placing of Walls 1 0% 10-Nov-18 10-Nov-18 10-Nov-18 10-Nov-18 -215 Casting / Placing of
TRA-MIS-178-MH-5690 Casting / Placing of Reducer Slab 1 0% 11-Nov-18 11-Nov-18 11-Nov-18 11-Nov-18 -215 Casting / Placing of
TRA-MIS-178-MH-5695 Casting / Placing of Shafts 1 0% 12-Nov-18 12-Nov-18 12-Nov-18 12-Nov-18 -215 Casting / Placing of
TRA-MIS-178-MH-5700 Construction of Backdrops 1 0% 13-Nov-18 13-Nov-18 13-Nov-18 13-Nov-18 -215 Construction of Bac
TRA-MIS-178-MH-5705 External Waterproofing 1 0% 14-Nov-18 14-Nov-18 14-Nov-18 14-Nov-18 -215 External Waterproo
TRA-MIS-178-MH-5715 Casting / Placing of Cover Slab 1 0% 15-Nov-18 15-Nov-18 15-Nov-18 15-Nov-18 -215 Casting / Placing of
TRA-MIS-178-MH-5720 Internal Finishing 1 0% 17-Nov-18 17-Nov-18 17-Nov-18 17-Nov-18 -215 Internal Finishing
TRA-MIS-178-MH-5725 DI Frame and Cover 1 0% 18-Nov-18 18-Nov-18 18-Nov-18 18-Nov-18 -215 DI Frame and Cove
TRA-MIS-178-ND-1575 Receving Pit 4 0% 06-Nov-18 10-Nov-18 06-Nov-18 10-Nov-18 -224 Receving Pit
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 96 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
TRA-MIS-178-ND-1585 Pipelaying 2 0% 15-Nov-18 17-Nov-18 15-Nov-18 17-Nov-18 -219 Pipelaying
TRA-MIS-178-MH-6065 Casting / Placing of Base Slab 3 0% 15-Nov-18 18-Nov-18 15-Nov-18 18-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-6070 Casting / Placing of Walls 3 0% 19-Nov-18 21-Nov-18 19-Nov-18 21-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-6075 Casting / Placing of Reducer Slab 1 0% 22-Nov-18 22-Nov-18 22-Nov-18 22-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-6080 Casting / Placing of Shafts 1 0% 24-Nov-18 24-Nov-18 24-Nov-18 24-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-6090 External Waterproofing 1 0% 26-Nov-18 26-Nov-18 26-Nov-18 26-Nov-18 -224 External Waterproo
TRA-MIS-178-MH-6100 Casting / Placing of Cover Slab 1 0% 27-Nov-18 27-Nov-18 27-Nov-18 27-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-6105 Internal Finishing 1 0% 28-Nov-18 28-Nov-18 28-Nov-18 28-Nov-18 -224 Internal Finishing
TRA-MIS-178-MH-6110 DI Frame and Cover 1 0% 29-Nov-18 29-Nov-18 29-Nov-18 29-Nov-18 -224 DI Frame and Cov
TRA-MIS-178-PL-2615 Install Dewatering System / Dewatering 3 0% 10-Nov-18 12-Nov-18 10-Nov-18 12-Nov-18 -221 Install Dewatering S
TRA-MIS-178-PL-2620 Excavation to Formation Level 3 0% 13-Nov-18 15-Nov-18 13-Nov-18 15-Nov-18 -221 Excavation to Form
TRA-MIS-178-PL-2625 Pipe Laying 2 0% 17-Nov-18 18-Nov-18 17-Nov-18 18-Nov-18 -220 Pipe Laying
TRA-MIS-178-PL-2630 Pipe Surround 2 0% 18-Nov-18 19-Nov-18 18-Nov-18 19-Nov-18 -220 Pipe Surround
TRA-MIS-178-MH-5735 Casting / Placing of Base Slab 2 0% 17-Nov-18 18-Nov-18 17-Nov-18 18-Nov-18 -221 Casting / Placing o
TRA-MIS-178-MH-5740 Casting / Placing of Walls 1 0% 19-Nov-18 19-Nov-18 19-Nov-18 19-Nov-18 -221 Casting / Placing o
TRA-MIS-178-MH-5745 Casting / Placing of Reducer Slab 1 0% 20-Nov-18 20-Nov-18 20-Nov-18 20-Nov-18 -221 Casting / Placing o
TRA-MIS-178-MH-5750 Casting / Placing of Shafts 1 0% 21-Nov-18 21-Nov-18 21-Nov-18 21-Nov-18 -221 Casting / Placing o
TRA-MIS-178-MH-5760 External Waterproofing 1 0% 24-Nov-18 24-Nov-18 24-Nov-18 24-Nov-18 -221 External Waterproo
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 97 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
TRA-MIS-178-MH-5765 Backfilling 1 0% 27-Nov-18 27-Nov-18 27-Nov-18 27-Nov-18 -224 Backfilling
TRA-MIS-178-MH-5770 Casting / Placing of Cover Slab 1 0% 28-Nov-18 28-Nov-18 28-Nov-18 28-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-5775 Internal Finishing 1 0% 29-Nov-18 29-Nov-18 29-Nov-18 29-Nov-18 -224 Internal Finishing
TRA-MIS-178-MH-5780 DI Frame and Cover 1 0% 01-Dec-18 01-Dec-18 01-Dec-18 01-Dec-18 -224 DI Frame and Cov
TRA-MIS-178-PL-2650 Install Dewatering System / Dewatering 3 0% 13-Nov-18 15-Nov-18 13-Nov-18 15-Nov-18 -222 Install Dewatering S
TRA-MIS-178-PL-2655 Excavation to Formation Level 2 0% 17-Nov-18 18-Nov-18 17-Nov-18 18-Nov-18 -222 Excavation to Form
TRA-MIS-178-PL-2660 Pipe Laying 2 0% 19-Nov-18 20-Nov-18 19-Nov-18 20-Nov-18 -221 Pipe Laying
TRA-MIS-178-PL-2665 Pipe Surround 2 0% 20-Nov-18 21-Nov-18 20-Nov-18 21-Nov-18 -221 Pipe Surround
TRA-MIS-178-MH-5790 Casting / Placing of Base Slab 2 0% 19-Nov-18 20-Nov-18 19-Nov-18 20-Nov-18 -222 Casting / Placing o
TRA-MIS-178-MH-5795 Casting / Placing of Walls 1 0% 21-Nov-18 21-Nov-18 21-Nov-18 21-Nov-18 -222 Casting / Placing o
TRA-MIS-178-MH-5800 Casting / Placing of Reducer Slab 1 0% 22-Nov-18 22-Nov-18 22-Nov-18 22-Nov-18 -222 Casting / Placing o
TRA-MIS-178-MH-5805 Casting / Placing of Shafts 1 0% 24-Nov-18 24-Nov-18 24-Nov-18 24-Nov-18 -222 Casting / Placing o
TRA-MIS-178-MH-5815 External Waterproofing 1 0% 26-Nov-18 26-Nov-18 26-Nov-18 26-Nov-18 -222 External Waterproo
TRA-MIS-178-MH-5825 Casting / Placing of Cover Slab 1 0% 29-Nov-18 29-Nov-18 29-Nov-18 29-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-5830 Internal Finishing 1 0% 01-Dec-18 01-Dec-18 01-Dec-18 01-Dec-18 -224 Internal Finishing
TRA-MIS-178-MH-5835 DI Frame and Cover 1 0% 02-Dec-18 02-Dec-18 02-Dec-18 02-Dec-18 -224 DI Frame and Cov
TRA-MIS-178-PL-2685 Install Dewatering System / Dewatering 4 0% 17-Nov-18 20-Nov-18 17-Nov-18 20-Nov-18 -224 Install Dewatering S
TRA-MIS-178-PL-2690 Excavation to Formation Level 2 0% 20-Nov-18 21-Nov-18 20-Nov-18 21-Nov-18 -224 Excavation to Form
TRA-MIS-178-PL-2695 Pipe Laying 2 0% 22-Nov-18 24-Nov-18 22-Nov-18 24-Nov-18 -223 Pipe Laying
TRA-MIS-178-PL-2700 Pipe Surround 2 0% 24-Nov-18 25-Nov-18 24-Nov-18 25-Nov-18 -223 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 98 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
TRA-MIS-178-PL-2710 Testing 2 0% 28-Nov-18 29-Nov-18 28-Nov-18 29-Nov-18 -218 Testing
TRA-MIS-178-MH-5845 Casting / Placing of Base Slab 2 0% 22-Nov-18 24-Nov-18 22-Nov-18 24-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-5850 Casting / Placing of Walls 1 0% 25-Nov-18 25-Nov-18 25-Nov-18 25-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-5855 Casting / Placing of Reducer Slab 1 0% 26-Nov-18 26-Nov-18 26-Nov-18 26-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-5860 Casting / Placing of Shafts 1 0% 27-Nov-18 27-Nov-18 27-Nov-18 27-Nov-18 -224 Casting / Placing o
TRA-MIS-178-MH-5870 External Waterproofing 1 0% 29-Nov-18 29-Nov-18 29-Nov-18 29-Nov-18 -224 External Waterpro
TRA-MIS-178-MH-5880 Casting / Placing of Cover Slab 1 0% 01-Dec-18 01-Dec-18 01-Dec-18 01-Dec-18 -224 Casting / Placing o
TRA-MIS-178-MH-5885 Internal Finishing 1 0% 02-Dec-18 02-Dec-18 02-Dec-18 02-Dec-18 -224 Internal Finishing
TRA-MIS-178-MH-5890 DI Frame and Cover 1 0% 03-Dec-18 03-Dec-18 03-Dec-18 03-Dec-18 -224 DI Frame and Cov
TRA-MIS-178-ND-1605 Receving Pit 2 0% 20-Nov-18 21-Nov-18 20-Nov-18 21-Nov-18 -227 Receving Pit
TRA-MIS-178-MH-6120 Casting / Placing of Base Slab 2 0% 27-Nov-18 28-Nov-18 27-Nov-18 28-Nov-18 -227 Casting / Placing o
TRA-MIS-178-MH-6125 Casting / Placing of Walls 1 0% 29-Nov-18 29-Nov-18 29-Nov-18 29-Nov-18 -227 Casting / Placing o
TRA-MIS-178-MH-6130 Casting / Placing of Reducer Slab 1 0% 01-Dec-18 01-Dec-18 01-Dec-18 01-Dec-18 -227 Casting / Placing o
TRA-MIS-178-MH-6135 Casting / Placing of Shafts 1 0% 02-Dec-18 02-Dec-18 02-Dec-18 02-Dec-18 -227 Casting / Placing o
TRA-MIS-178-MH-6145 External Waterproofing 1 0% 04-Dec-18 04-Dec-18 04-Dec-18 04-Dec-18 -227 External Waterpro
TRA-MIS-178-MH-6155 Casting / Placing of Cover Slab 1 0% 05-Dec-18 05-Dec-18 05-Dec-18 05-Dec-18 -227 Casting / Placing
TRA-MIS-178-MH-6160 Internal Finishing 1 0% 06-Dec-18 06-Dec-18 06-Dec-18 06-Dec-18 -227 Internal Finishing
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 99 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
TRA-MIS-178-MH-6165 DI Frame and Cover 1 0% 08-Dec-18 08-Dec-18 08-Dec-18 08-Dec-18 -227 DI Frame and Co
TRA-MIS-178-PL-2720 Install Dewatering System / Dewatering 1 0% 24-Nov-18 24-Nov-18 24-Nov-18 24-Nov-18 -228 Install Dewatering
TRA-MIS-178-PL-2725 Excavation to Formation Level 2 0% 27-Nov-18 28-Nov-18 27-Nov-18 28-Nov-18 -228 Excavation to Form
TRA-MIS-178-PL-2730 Pipe Laying 2 0% 29-Nov-18 01-Dec-18 29-Nov-18 01-Dec-18 -227 Pipe Laying
TRA-MIS-178-PL-2735 Pipe Surround 2 0% 01-Dec-18 02-Dec-18 01-Dec-18 02-Dec-18 -227 Pipe Surround
TRA-MIS-178-MH-5900 Casting / Placing of Base Slab 2 0% 29-Nov-18 01-Dec-18 29-Nov-18 01-Dec-18 -228 Casting / Placing o
TRA-MIS-178-MH-5905 Casting / Placing of Walls 1 0% 02-Dec-18 02-Dec-18 02-Dec-18 02-Dec-18 -228 Casting / Placing o
TRA-MIS-178-MH-5910 Casting / Placing of Reducer Slab 1 0% 03-Dec-18 03-Dec-18 03-Dec-18 03-Dec-18 -228 Casting / Placing
TRA-MIS-178-MH-5915 Casting / Placing of Shafts 1 0% 04-Dec-18 04-Dec-18 04-Dec-18 04-Dec-18 -228 Casting / Placing
TRA-MIS-178-MH-5925 External Waterproofing 1 0% 06-Dec-18 06-Dec-18 06-Dec-18 06-Dec-18 -228 External Waterpro
TRA-MIS-178-MH-5935 Casting / Placing of Cover Slab 1 0% 08-Dec-18 08-Dec-18 08-Dec-18 08-Dec-18 -228 Casting / Placing
TRA-MIS-178-MH-5940 Internal Finishing 1 0% 09-Dec-18 09-Dec-18 09-Dec-18 09-Dec-18 -228 Internal Finishing
TRA-MIS-178-MH-5945 DI Frame and Cover 1 0% 10-Dec-18 10-Dec-18 10-Dec-18 10-Dec-18 -228 DI Frame and Co
TRA-MIS-178-PL-2755 Install Dewatering System / Dewatering 1 0% 26-Nov-18 26-Nov-18 26-Nov-18 26-Nov-18 -229 Install Dewatering
TRA-MIS-178-PL-2760 Excavation to Formation Level 2 0% 29-Nov-18 01-Dec-18 29-Nov-18 01-Dec-18 -229 Excavation to Form
TRA-MIS-178-PL-2765 Pipe Laying 2 0% 02-Dec-18 03-Dec-18 02-Dec-18 03-Dec-18 -228 Pipe Laying
TRA-MIS-178-PL-2770 Pipe Surround 2 0% 03-Dec-18 04-Dec-18 03-Dec-18 04-Dec-18 -228 Pipe Surround
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 100 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
TRA-MIS-178-MH-5955 Casting / Placing of Base Slab 2 0% 02-Dec-18 03-Dec-18 02-Dec-18 03-Dec-18 -229 Casting / Placing
TRA-MIS-178-MH-5960 Casting / Placing of Walls 1 0% 04-Dec-18 04-Dec-18 04-Dec-18 04-Dec-18 -229 Casting / Placing
TRA-MIS-178-MH-5965 Casting / Placing of Reducer Slab 1 0% 05-Dec-18 05-Dec-18 05-Dec-18 05-Dec-18 -229 Casting / Placing
TRA-MIS-178-MH-5970 Casting / Placing of Shafts 1 0% 06-Dec-18 06-Dec-18 06-Dec-18 06-Dec-18 -229 Casting / Placing
TRA-MIS-178-MH-5980 External Waterproofing 1 0% 09-Dec-18 09-Dec-18 09-Dec-18 09-Dec-18 -229 External Waterpro
TRA-MIS-178-MH-5990 Casting / Placing of Cover Slab 1 0% 10-Dec-18 10-Dec-18 10-Dec-18 10-Dec-18 -229 Casting / Placing
TRA-MIS-178-MH-5995 Internal Finishing 1 0% 11-Dec-18 11-Dec-18 11-Dec-18 11-Dec-18 -229 Internal Finishing
TRA-MIS-178-MH-6000 DI Frame and Cover 1 0% 12-Dec-18 12-Dec-18 12-Dec-18 12-Dec-18 -229 DI Frame and Co
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 101 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-1090 Micellaneous Work MISC-71 10 100% 14-Sep-17 25-Sep-17 14-Sep-17 A 25-Sep-17 A
MIN-MISC-WR-1175 Micellaneous Work MISC-140 10 0% 31-Jan-18 11-Feb-18 31-Jan-18 11-Feb-18 -54 Micellaneous Work MISC-140
MIN-MISC-WR-1185 Micellaneous Work MISC-148 10 0% 31-Jan-18 11-Feb-18 31-Jan-18 11-Feb-18 -54 Micellaneous Work MISC-148
MIN-MISC-WR-1245 Micellaneous Work MISC-209 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-209
MIN-MISC-WR-1250 Micellaneous Work MISC-212 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-212
MIN-MISC-WR-1255 Micellaneous Work MISC-216 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-216
MIN-MISC-WR-1260 Micellaneous Work MISC-229 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-229
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 102 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-1265 Micellaneous Work MISC-232 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-232
MIN-MISC-WR-1270 Micellaneous Work MISC-234 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-234
MIN-MISC-WR-1275 Micellaneous Work MISC-241 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-241
MIN-MISC-WR-1280 Micellaneous Work MISC-255 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-255
MIN-MISC-WR-1285 Micellaneous Work MISC-258 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-258
MIN-MISC-WR-1290 Micellaneous Work MISC-269 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-269
MIN-MISC-WR-1295 Micellaneous Work MISC-276 (2 of 2) 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-276 (2 of 2)
MIN-MISC-WR-1300 Micellaneous Work MISC-282 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-282
MIN-MISC-WR-1220 Micellaneous Work MISC-192 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-192
MIN-MISC-WR-1225 Micellaneous Work MISC-198 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-198
MIN-MISC-WR-1230 Micellaneous Work MISC-204 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-204
MIN-MISC-WR-1235 Micellaneous Work MISC-205 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-205
MIN-MISC-WR-1240 Micellaneous Work MISC-206 10 0% 12-Feb-18 22-Feb-18 12-Feb-18 22-Feb-18 -54 Micellaneous Work MISC-206
MIN-MISC-WR-1305 Micellaneous Work MISC-283 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 -54 Micellaneous Work MISC-283
MIN-MISC-WR-1310 Micellaneous Work MISC-291 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-291
MIN-MISC-WR-1315 Micellaneous Work MISC-296 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-296
MIN-MISC-WR-1320 Micellaneous Work MISC-297 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-297
MIN-MISC-WR-1325 Micellaneous Work MISC-313 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-313
MIN-MISC-WR-1330 Micellaneous Work MISC-315 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-315
MIN-MISC-WR-1335 Micellaneous Work MISC-325 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-325
MIN-MISC-WR-1340 Micellaneous Work MISC-334 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-334
MIN-MISC-WR-1345 Micellaneous Work MISC-342 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-342
MIN-MISC-WR-1350 Micellaneous Work MISC-343 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-343
MIN-MISC-WR-1355 Micellaneous Work MISC-348 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-348
MIN-MISC-WR-1360 Micellaneous Work MISC-359 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-359
MIN-MISC-WR-1365 Micellaneous Work MISC-360 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 12 Micellaneous Work MISC-360
MIN-MISC-WR-1370 Micellaneous Work MISC-364 10 0% 24-Feb-18 06-Mar-18 24-Feb-18 06-Mar-18 -54 Micellaneous Work MISC-364
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 103 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-1385 Micellaneous Work MISC-376 10 100% 01-Oct-17 11-Oct-17 01-Oct-17 A 11-Oct-17 A
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 104 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-1550 Micellaneous Work MISC-548 10 100% 10-Jan-18 21-Jan-18 10-Jan-18 A 21-Jan-18 A
MIN-MISC-WR-1430 Micellaneous Work MISC-435 10 100% 01-Oct-17 11-Oct-17 01-Oct-17 A 07-Mar-18 -44 Micellaneous Work MISC-435
MIN-MISC-WR-1445 Micellaneous Work MISC-447 10 0% 07-Mar-18 18-Mar-18 07-Mar-18 18-Mar-18 -54 Micellaneous Work MISC-447
MIN-MISC-WR-1470 Micellaneous Work MISC-473 (1 of 4) 10 0% 14-Oct-17 24-Oct-17 14-Oct-17 A 18-Mar-18 -54 Micellaneous Work MISC-473 (1 of 4)
MIN-MISC-WR-1555 Micellaneous Work MISC-575 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-575
MIN-MISC-WR-1560 Micellaneous Work MISC-587 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-587
MIN-MISC-WR-1565 Micellaneous Work MISC-590 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-590
MIN-MISC-WR-1570 Micellaneous Work MISC-596 (1 of 2) 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-596 (1 of 2
MIN-MISC-WR-1575 Micellaneous Work MISC-596 (2 of 2) 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-596 (2 of 2
MIN-MISC-WR-1580 Micellaneous Work MISC-604 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-604
MIN-MISC-WR-1585 Micellaneous Work MISC-606 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-606
MIN-MISC-WR-1590 Micellaneous Work MISC-636 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-636
MIN-MISC-WR-1595 Micellaneous Work MISC-641 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-641
MIN-MISC-WR-1600 Micellaneous Work MISC-642 10 0% 19-Mar-18 29-Mar-18 19-Mar-18 29-Mar-18 -54 Micellaneous Work MISC-642
MIN-MISC-WR-1745 Micellaneous Work MISC-752 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -54 Micellaneous Work MISC-752
MIN-MISC-WR-1605 Micellaneous Work MISC-643 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -54 Micellaneous Work MISC-643
MIN-MISC-WR-1610 Micellaneous Work MISC-645 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-645
MIN-MISC-WR-1615 Micellaneous Work MISC-652 (1 of 2) 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-652 (1 of
MIN-MISC-WR-1620 Micellaneous Work MISC-652 (2 of 2) 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-652 (2 of
MIN-MISC-WR-1625 Micellaneous Work MISC-660 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-660
MIN-MISC-WR-1630 Micellaneous Work MISC-662 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-662
MIN-MISC-WR-1635 Micellaneous Work MISC-665 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-665
MIN-MISC-WR-1640 Micellaneous Work MISC-667 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-667
MIN-MISC-WR-1645 Micellaneous Work MISC-670 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-670
MIN-MISC-WR-1650 Micellaneous Work MISC-672 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-672
MIN-MISC-WR-1655 Micellaneous Work MISC-680 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-680
MIN-MISC-WR-1660 Micellaneous Work MISC-685 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-685
MIN-MISC-WR-1665 Micellaneous Work MISC-689 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-689
MIN-MISC-WR-1670 Micellaneous Work MISC-697-A & B) 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-697-A & B
MIN-MISC-WR-1675 Micellaneous Work MISC-706 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-706
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 105 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-1680 Micellaneous Work MISC-713 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-713
MIN-MISC-WR-1685 Micellaneous Work MISC-715 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-715
MIN-MISC-WR-1690 Micellaneous Work MISC-716 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-716
MIN-MISC-WR-1695 Micellaneous Work MISC-717 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-717
MIN-MISC-WR-1700 Micellaneous Work MISC-725 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-725
MIN-MISC-WR-1705 Micellaneous Work MISC-737 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-737
MIN-MISC-WR-1710 Micellaneous Work MISC-738 (1 of 2) 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-738 (1 of
MIN-MISC-WR-1715 Micellaneous Work MISC-740 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-740
MIN-MISC-WR-1720 Micellaneous Work MISC-743 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-743
MIN-MISC-WR-1725 Micellaneous Work MISC-745 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-745
MIN-MISC-WR-1730 Micellaneous Work MISC-746 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-746
MIN-MISC-WR-1735 Micellaneous Work MISC-750 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-750
MIN-MISC-WR-1740 Micellaneous Work MISC-751 10 0% 31-Mar-18 10-Apr-18 31-Mar-18 10-Apr-18 -18 Micellaneous Work MISC-751
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 106 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-1840 Micellaneous Work MISC-840 10 100% 17-Dec-17 27-Dec-17 17-Dec-17 A 27-Dec-17 A
MIN-MISC-WR-1945 Micellaneous Work MISC-925 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-925
MIN-MISC-WR-1950 Micellaneous Work MISC-931 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-931
MIN-MISC-WR-1880 Micellaneous Work MISC-872 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-872
MIN-MISC-WR-1885 Micellaneous Work MISC-526 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-526
MIN-MISC-WR-1890 Micellaneous Work MISC-877 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-877
MIN-MISC-WR-1895 Micellaneous Work MISC-884 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-884
MIN-MISC-WR-1900 Micellaneous Work MISC-888 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-888
MIN-MISC-WR-1905 Micellaneous Work MISC-892 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-892
MIN-MISC-WR-1910 Micellaneous Work MISC-893 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-893
MIN-MISC-WR-1915 Micellaneous Work MISC-902 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-902
MIN-MISC-WR-1920 Micellaneous Work MISC-903 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-903
MIN-MISC-WR-1925 Micellaneous Work MISC-904 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-904
MIN-MISC-WR-1930 Micellaneous Work MISC-916 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-916
MIN-MISC-WR-1935 Micellaneous Work MISC-919 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-919
MIN-MISC-WR-1940 Micellaneous Work MISC-924 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-924
MIN-MISC-WR-1750 Micellaneous Work MISC-760 10 0% 11-Apr-18 22-Apr-18 11-Apr-18 22-Apr-18 -54 Micellaneous Work MISC-760
MIN-MISC-WR-1955 Micellaneous Work MISC-936 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -54 Micellaneous Work MISC-936
MIN-MISC-WR-1960 Micellaneous Work MISC-937 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-937
MIN-MISC-WR-1965 Micellaneous Work MISC-940 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-940
MIN-MISC-WR-1970 Micellaneous Work MISC-946 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-946
MIN-MISC-WR-1975 Micellaneous Work MISC-950 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-950
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 107 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-1980 Micellaneous Work MISC-956 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-956
MIN-MISC-WR-1985 Micellaneous Work MISC-960 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-960
MIN-MISC-WR-1990 Micellaneous Work MISC-962 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-962
MIN-MISC-WR-1995 Micellaneous Work MISC-963 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-963
MIN-MISC-WR-2000 Micellaneous Work MISC-966 (1 of 2) 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-966 (1 o
MIN-MISC-WR-2005 Micellaneous Work MISC-968 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-968
MIN-MISC-WR-2010 Micellaneous Work MISC-971 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-971
MIN-MISC-WR-2015 Micellaneous Work MISC-972 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-972
MIN-MISC-WR-2020 Micellaneous Work MISC-976 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-976
MIN-MISC-WR-2025 Micellaneous Work MISC-977 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-977
MIN-MISC-WR-2030 Micellaneous Work MISC-979 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-979
MIN-MISC-WR-2035 Micellaneous Work MISC-980 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-980
MIN-MISC-WR-2040 Micellaneous Work MISC-983 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-983
MIN-MISC-WR-2045 Micellaneous Work MISC-986 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-986
MIN-MISC-WR-2050 Micellaneous Work MISC-994 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-994
MIN-MISC-WR-2055 Micellaneous Work MISC-995 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-995
MIN-MISC-WR-2060 Micellaneous Work MISC-998 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-998
MIN-MISC-WR-2065 Micellaneous Work MISC-1000 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1000
MIN-MISC-WR-2070 Micellaneous Work MISC-1010 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1010
MIN-MISC-WR-2075 Micellaneous Work MISC-1012 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1012
MIN-MISC-WR-2080 Micellaneous Work MISC-1014 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1014
MIN-MISC-WR-2085 Micellaneous Work MISC-1016 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1016
MIN-MISC-WR-2090 Micellaneous Work MISC-1023 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1023
MIN-MISC-WR-2095 Micellaneous Work MISC-1026 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1026
MIN-MISC-WR-2100 Micellaneous Work MISC-1028 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1028
MIN-MISC-WR-2105 Micellaneous Work MISC-1029 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1029
MIN-MISC-WR-2110 Micellaneous Work MISC-1031 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1031
MIN-MISC-WR-2115 Micellaneous Work MISC-1034 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -38 Micellaneous Work MISC-1034
MIN-MISC-WR-2120 Micellaneous Work MISC-1041 10 0% 23-Apr-18 03-May-18 23-Apr-18 03-May-18 -54 Micellaneous Work MISC-1041
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 108 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-2125 Micellaneous Work MISC-1043 5 100% 01-Oct-17 05-Oct-17 01-Oct-17 A 05-Oct-17 A
MIN-MISC-WR-2240 Micellaneous Work MISC-1108 (1 & 2) 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1108 (1
MIN-MISC-WR-2245 Micellaneous Work MISC-1110 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1110
MIN-MISC-WR-2250 Micellaneous Work MISC-1114 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1114
MIN-MISC-WR-2255 Micellaneous Work MISC-1117 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1117
MIN-MISC-WR-2260 Micellaneous Work MISC-1123 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1123
MIN-MISC-WR-2265 Micellaneous Work MISC-1125 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1125
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 109 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-2270 Micellaneous Work MISC-1133 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1133
MIN-MISC-WR-2275 Micellaneous Work MISC-1134 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1134
MIN-MISC-WR-2280 Micellaneous Work MISC-1135 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1135
MIN-MISC-WR-2285 Micellaneous Work MISC-1136 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1136
MIN-MISC-WR-2290 Micellaneous Work MISC-1137 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1137
MIN-MISC-WR-2295 Micellaneous Work MISC-1140 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1140
MIN-MISC-WR-2300 Micellaneous Work MISC-1143 5 0% 05-May-18 09-May-18 05-May-18 09-May-18 -54 Micellaneous Work MISC-1143
MIN-MISC-WR-2305 Micellaneous Work MISC-1145 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -54 Micellaneous Work MISC-1145
MIN-MISC-WR-2315 Micellaneous Work MISC-1149 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1149
MIN-MISC-WR-2390 Micellaneous Work MISC-1217 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1217
MIN-MISC-WR-2395 Micellaneous Work MISC-1220 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1220
MIN-MISC-WR-2400 Micellaneous Work MISC-1221 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1221
MIN-MISC-WR-2320 Micellaneous Work MISC-1151 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1151
MIN-MISC-WR-2325 Micellaneous Work MISC-1153 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1153
MIN-MISC-WR-2330 Micellaneous Work MISC-1156 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1156
MIN-MISC-WR-2335 Micellaneous Work MISC-1157 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1157
MIN-MISC-WR-2340 Micellaneous Work MISC-1164 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1164
MIN-MISC-WR-2345 Micellaneous Work MISC-1166 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1166
MIN-MISC-WR-2350 Micellaneous Work MISC-1180 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1180
MIN-MISC-WR-2355 Micellaneous Work MISC-1183 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1183
MIN-MISC-WR-2360 Micellaneous Work MISC-1184 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1184
MIN-MISC-WR-2365 Micellaneous Work MISC-1187 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1187
MIN-MISC-WR-2370 Micellaneous Work MISC-1203 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1203
MIN-MISC-WR-2375 Micellaneous Work MISC-1205 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1205
MIN-MISC-WR-2380 Micellaneous Work MISC-1211 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1211
MIN-MISC-WR-2385 Micellaneous Work MISC-1213 5 0% 10-May-18 15-May-18 10-May-18 15-May-18 -49 Micellaneous Work MISC-1213
MIN-MISC-WR-2310 Micellaneous Work MISC-1147 (1 & 2) 5 0% 16-May-18 21-May-18 16-May-18 21-May-18 -54 Micellaneous Work MISC-1147 (1
MIN-MISC-WR-2445 Micellaneous Work MISC-1263 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1263
MIN-MISC-WR-2450 Micellaneous Work MISC-1280 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1280
MIN-MISC-WR-2455 Micellaneous Work MISC-1280 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1280
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 110 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone
DS 210 HOUSE CONNECTIONS AND MISCELLANEOUS WORK
INTERIM CLAIM FOR EXTENSION OF TIME
Consolidated Program
Activity ID Activity Name Original Activity % BL1 Start BL1 Finish Start Finish Total Float 2016 2017 2018 2019
Duration Complete M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
MIN-MISC-WR-2460 Micellaneous Work MISC-1284 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1284
MIN-MISC-WR-2465 Micellaneous Work MISC-1285 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1285
MIN-MISC-WR-2470 Micellaneous Work MISC-1286 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1286
MIN-MISC-WR-2510 Micellaneous Work MISC-1330 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1330
MIN-MISC-WR-2515 Micellaneous Work MISC-1341 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1341
MIN-MISC-WR-2475 Micellaneous Work MISC-1289 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1289
MIN-MISC-WR-2480 Micellaneous Work MISC-1290 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1290
MIN-MISC-WR-2485 Micellaneous Work MISC-1299 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1299
MIN-MISC-WR-2490 Micellaneous Work MISC-1300 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1300
MIN-MISC-WR-2495 Micellaneous Work MISC-1310 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1310
MIN-MISC-WR-2500 Micellaneous Work MISC-1316 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1316
MIN-MISC-WR-2505 Micellaneous Work MISC-1326 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1326
MIN-MISC-WR-2405 Micellaneous Work MISC-1226 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1226
MIN-MISC-WR-2410 Micellaneous Work MISC-1236 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1236
MIN-MISC-WR-2415 Micellaneous Work MISC-1237 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1237
MIN-MISC-WR-2420 Micellaneous Work MISC-1246 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1246
MIN-MISC-WR-2425 Micellaneous Work MISC-1253 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1253
MIN-MISC-WR-2430 Micellaneous Work MISC-1254 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1254
MIN-MISC-WR-2435 Micellaneous Work MISC-1255 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1255
MIN-MISC-WR-2440 Micellaneous Work MISC-1258 5 0% 17-May-18 22-May-18 17-May-18 22-May-18 -54 Micellaneous Work MISC-1258
Level of Effort Remaining Work Summary CONTRACT DS-210 Date Revision Chec... Approved 111 of 111
Primary Baseline Critical Remaining Work
31-Jan-18 EOT MG
Actual Work Milestone