EPC -1 Level 1 Schedule

Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
Dept Decription Start Finish
Remarks 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Phase 1
Equip Foundation 20-Aug-17 15-Sep-17
Pits, Manhole,valve chamber 20-Aug-17 30-Sep-17
Concrete Pavement 20-Aug-17 30-Nov-17
Pipe Sleeper (Around CPI) 1-Sep-17 30-Sep-17
Misc Foundation 20-Aug-17 21-Oct-17
Civil
Phase 2
Equip Foundation 25-Aug-17 21-Oct-17
Pits, Manhole,valve chamber 25-Aug-17 11-Oct-17
Concrete Pavement 25-Aug-17 30-Jan-18
Misc Foundation 25-Aug-17 15-Jan-18

Pipe Sleeper main utility (Goal Post) 20-Aug-17 15-Sep-17


Steel Pipe Sleeper Around CPI (Goal Post) 1-Oct-17 10-Oct-17
Structure
Pipe Rack 1-Sep-17 30-Oct-17

Phase 1
Building
Building GEG 21-Sep-17
Substation Done
MCR Done
Shelter
EDG 20-Aug-17 10-Sep-17
AIR compressor 11-Sep 21-Sep-17
Water Treatment 22-Sep-17 2-Oct-17
Fire Water Pump 3-Oct 13-Oct-17
CPI 14-Oct-17 24-Oct-17
Closed drain 25-Oct-17 4-Nov-17
Building & Shelter
Condensate Loading 5-Nov-17 15-Nov-17
Flare Ignition Skid 16-Nov-17 26-Nov-17

Phase 2
Building
Workshop & Warehouse 20-Sep 20-Nov-17
Chemical Storage 20-Aug-17 20-Sep-17
Waste Storage 21-Nov-17 20-Jan-18
Shelter
Amine storage 1-Dec-17 11-Dec-17

Phase 1
EDG & Diesel Tank Balance: Day Tank 30-Sep-17

Balance: filter. Civil has to complete backfilling


IA, UA, Nitrogen 7-Sep-17
before 30 August 2017

87 Unit , received 60, balance 27, 3 Unit ETA by


Water Treatment 11 sept and 24 Unit ETA by 23 Sept, Civil has to 7-Oct-17
complete the backfilling before 30 August
Outstanding jockey pump & Tank (Tank
Fire Water completion including hydrotest is highly critical 15-Oct-17
task force to monitor)

2 Unit, 2 Received, Balance 0, Civil & Mechnical


CPI to verify and complete foundation before 21 Sept 30-Sep-17
2017

Boiler Balance: Stack for boiler, 2160 Din for piping 30-Nov-17

Structural to complete before 15 Sept 2017 for


Deaerator 21-Sep-17
installation of equipment

access for erection by civil by 7 Sept 2017 and


Condensate & Water Separation (Inc
waiting for custom clearance to install platform 15-Sep-17
Production Separator and Slug catcher) and vessel trim to release for piping

Condensate stabilization Done

Balance: foundation for corosion inhibitor,


Condensate and Produced water storage hydrotest to be done for 2 tank at the time and 30-Nov-17
transfer to the remaining tank

Fuel Gas Done

main GEG erected accessories equipment is


GEG 1-Oct-17 11-Oct-17 `
waiting for foundation
Mechanical

Area around flare stack 45 Mtr area to be clear


before end of sept 2017
Flare System 1-Oct-17 10-Oct-17
3 Dead man to be installed by civil before end
sept

Closed drain 4 Unit, 4 Received, Balance 0 30-Sep-17


Civil has to complete the footing foundation and
Dehydration (GDPC,EGR) backfill to have access for erection before 7 Sept 21-Sep-17
2017

Phase 2
L/R for JR by 1st Oct 2017 , remaining L/R by end
Launcher and Reciver 1-Oct-17 31-Oct-17
of Oct 2017

33 Unit , received 30 , balance 3. 5 unit will be


received at site by august and 1 by 21 sept and 1
by 2 Oct 2017
AGR 5-Oct-17
- 35 equipment to be installed before august and
2 equip to be installed based on ETA at site (Sept
- Oct)

AGE 22 Unit , received all 15-Sep-17

27 Unit, Received 18, balance 9 , 8 will be


SRU received before august and 1 will be received by 15-Sep-17
20 Oct (Burner)

Hydrotest will be conducted before end Sept


Amine System 30-Sep-17
2017
9 Unit, Received 1, balance 8, main package and
Incenerator other accessories ETA by 15 Sept (Bridge to be 20-Sep-17
ready) and burner ETA by 20 Sept 2017

17 Unit, Received 0, balance 17, main package


Sulfur granulation 30-Sep-17
and other accessories ETA by 8 Sept

Phase 1
Fire Water & Raw water 15-Sep-17
Sewer Line 15-Sep-17
Oil & Chemical 20-Sep-17
Closed drain 30-Sep-17
U/G Piping Amine Line 7-Oct-17
Phase 2
Fire Water & Raw water 15-Sep-17
Sewer Line 15-Sep-17
Oil & Chemical 20-Sep-17
Closed drain 30-Sep-17
Amine Line 7-Oct-17

Phase 1
Utility Phase 1

Piping to complete all lines except day tank which


EDG & Diesel Tank 1-Sep-17 7-Oct-17
include hydrotest and reinstatement

IA, UA, Nintrogent 1-Sep-17 30-Oct-17


Water Treatment 20-Sep-17 30-Oct-17

Boiler Included in the mechanical package

Deaerator 22-Sep-17 3-Nov-17

OW, UA, IA and Nitrogen, PW , WS , DW etc can


Fire Water & CPI 15-Sep-17 7-Dec-17
start early prior to tank hand over to piping

Hydrocarbon Phase 1
Condensate & Water Separation (Inc
Production Separator and Slug 10-Sep-17 30-Oct-17
catcher)
A/G Piping
Condensate stabilization Fabricated spool status to be closely monitored 1-Sep-17 30-Oct-17

Condensate and Produced water Hydrotest condensate tank is critical, expedite for 1-Dec-17 23-Jan-18
storage early completion
Fuel Gas 15-Sep-17 25-Oct-17
Flare System 11-Oct-17 15-Dec-17
GEG 12-Oct-17 11-Dec-17
Utility pipes on Pipe sleeper 1-Sep-17 30-Oct-17
Utility pipes on Pipe rack 15-Sep-17 30-Nov-17
Phase 2

Launcher and Reciver L/R to be received before end oct 15-Nov-17 15-Jan-18

AGR 16 Weeks for piping 1-Oct-17 30-Jan-18


AGE 14 weeks for piping 1-Oct-17 9-Jan-18
SRU & Amine 24 weeks for piping 15-Sep-17 16-Feb-18

Incenerator & Sulfur granulation Incenerator to be installed before end sept 15-Oct-17 3-Dec-17
Control Room
Sulfur Recovery Panel Supply by package vendor 20-Oct-17 30-Oct-17
Install SRU Panel Include Package system 1-Oct-17 22-Oct-17
Power Cable to Energize control room unit By electrical contractor 1-Oct-17 16-Oct-17
through UPS
FALCP for control room building By building contractor 1-Oct-17 31-Oct-17

HVAC HVAC under building contractor On going 30-Oct-17

Master List Issue (VESDA panel to be received


VESDA (Smoke Detection) 15-Nov-17 30-Nov-17
before 7 Nov )
Primary cable (Process Area)
Tray 24-Aug-17 7-Nov-17
Trenching from MCR to pipe rack 8-Nov-17 6-Dec-17

Remaining pipe rack from flare up to the main


process piperack to complete before end of Sept
Cable Main process piperack conecting to produce 7-Dec-17 4-Jan-18
water and condensate tank firm to complete
before end of Nov 2017

Primary cable (Utility Area)


Tray 1-Oct-17 16-Oct-17
Trenching from MCR to pipe sleeper 10-Oct-17 15-Oct-17
Cable 16-Oct-17 6-Nov-17
Secondary Cable
Phase 1 8-Nov-17 23-Dec-17
Utility
EDG & Diesel Tank 27-Sep-17 18-Oct-17
IA, UA, Nintrogent 20-Oct-17 17-Nov-17
Water Treatment 20-Oct-17 17-Nov-17
Boiler 20-Nov-17 25-Dec-17
Deaerator 24-Oct-17 28-Nov-17
Fire Water & CPI 27-Nov-17 8-Jan-18
Closed drain 20-Sep-17 1-Nov-17
Hydrocarbon
Condensate & Water Separation (Inc
Production Separator and Slug 20-Oct-17 17-Nov-17
catcher)
Condensate stabilization 20-Oct-17 24-Nov-17
Condensate and Produce water 13-Jan-18 10-Feb-18
storage
Fuel Gas 15-Oct-17 12-Nov-17
Flare System 5-Dec-17 26-Dec-17
GEG 1-Dec-17 12-Jan-18
Phase 2
Launcher and Reciver 5-Jan-18 2-Feb-18
AGR 20-Jan-18 24-Feb-18
AGE 30-Dec-17 10-Feb-18
SRU & Amine 6-Feb-18 3-Apr-18
Incenerator & Sulfur granul 23-Nov-17 4-Jan-18

Loop test and Function Test


Phase 1
Utility
EDG & Diesel Tank 18-Oct-17 25-Oct-17
IA, UA, Nitrogen 17-Nov-17 1-Dec-17
Water Treatment 17-Nov-17 1-Dec-17
Instrument
Instrument
Boiler 25-Dec-17 8-Jan-18
Deaerator 28-Nov-17 5-Dec-17
Fire Water & CPI 8-Jan-18 15-Jan-18
Closed drain 1-Nov-17 8-Nov-17
Hydrocarbon
Condensate & Water Separation (Inc
Production Separator and Slug 17-Nov-17 24-Nov-17
catcher)
Condensate stabilization 24-Nov-17 1-Dec-17

This sch for 1 Produced water + 3 condensate


tank however 1st sales gas can be with 1
condensate tank, which will save 4 weeks. 1
Condensate and Produced water Produced water + 2 Condensate is adequate for 10-Feb-18 17-Feb-18
storage JR gas in which can be achieve by 24 Jan ,
remaining 1 tank shall be made ready before end
of feb 2018

Fuel Gas 12-Nov-17 19-Nov-17


Flare System 26-Dec-17 2-Jan-18
GEG 12-Jan-18 26-Jan-18
Phase 2
Launcher and Receiver 2-Feb-18 16-Feb-18
AGR 24-Feb-18 10-Mar-18
AGE 10-Feb-18 24-Feb-18
SRU & Amine 3-Apr-18 18-Apr-18
Incenerator & Sulfur granulation 4-Jan-18 18-Jan-18

Tubing Master List Issue


Phase 1
Utility
EDG & Diesel Tank 7-Oct-17 21-Oct-17
IA, UA, Nintrogent 30-Oct-17 13-Nov-17
Water Treatment 30-Oct-17 13-Nov-17
Boiler 30-Nov-17 14-Dec-17
Deaerator 3-Nov-17 17-Nov-17
Fire Water & CPI 7-Dec-17 21-Dec-17
Closed drain 30-Sep-17 14-Oct-17
Hydrocarbon
Condensate & Water Separation (Inc
Production Separator and Slug 30-Oct-17 13-Nov-17
catcher)
Condensate stabilization 30-Oct-17 13-Nov-17

This sch for 1 Produced water + 3 condensate


tank however 1st sales gas can be with 1
condensate tank, which will save 4 weeks. 1
Condensate and Produce water Produced water + 2 Condensate is adequate for 23-Jan-18 6-Feb-18
storage JR gas in which can be achieve by 24 Jan ,
remaining 1 tank shall be made ready before end
of feb 2018

Fuel Gas 25-Oct-17 8-Nov-17


Flare System 15-Dec-17 29-Dec-17
GEG 11-Dec-17 25-Dec-17
Phase 2
Launcher and Reciver 15-Jan-18 29-Jan-18
AGR 30-Jan-18 13-Mar-18
AGE 9-Jan-18 20-Feb-18
SRU & Amine 16-Feb-18 13-Apr-18
Incenerator & Sulfur granulation 3-Dec-17 7-Jan-18
all panel installed, internal wiring on going.
Substation Vendor ETA at site by mid sept for SAT 30-Sep-17

SAT completed with temp power supply ,


UPS and Battery Done
permanent power supply to line up

Transformers 8 / 12 done, 4 number to be install 30-Sep-17

Cable
Primary
EDG to Substation 30-Sep-17
Utility 30-Sep-17
Building 14-Oct-17
Process 30-Oct-17
Secondary
Plant cable for Lighting
Phase 1 1-Oct-17 30-Jan-18
Phase 2 30-Jan-18 30-Apr-18
Lightning
Main Grid 1-Dec-17 30-Dec-17
Secondary Grid
Phase 1 1-Oct-17 30-Dec-17
Phase 2 20-Oct-17 30 Feb 2018
Earthing
Electrical Phase 1 1-Sep-17 31-Oct-17
Phase 2 1-Nov-17 31-Dec-17
Lightning Protection
Building 1-Jan-18 31-Jan-18

Process Equipment (Phase 1 & 2) 1-Jan-18 31-Mar-18

Cathodic Protection
Phase 1
Piping 1-Dec-17 30-Dec-17
Tank 1-Dec-17 30-Jan-18
Phase 2
Piping 1-Jan-18 15-Feb-18
Tank 1-Mar-18 28-Mar-18
Motor Solo Run
Phase 1 1-Nov-17 1-Jan-18
Phase 2 1-Feb-18 15-Mar-18
Lighting Com
Phase 1 1-Jan-18 15-Feb-18
Phase 2 1-Mar-18 15 Aprl 2018
Cathodic Protection Mechanical
Completion
Under ground Piping
Phase 1 & 2 1-Jan-18 20-Feb-18
Earthing Mechanical Completion

Phase 1 1-Nov-17 16-Dec-17


Phase 2 1-Jan-18 15-Feb-18

Phase 1
Utility
EDG & Diesel Tank 26-Oct-17 2-Nov-17
IA, UA, Nitrogen 2-Dec-17 16-Dec-17
Water Treatment 2-Dec-17 23-Dec-17
Boiler Need fuel Gas 14-Feb-18 28-Feb-18
Deaerator Need fuel Gas 21-Feb-18 28-Feb-18
Fire Water & CPI 16-Jan-18 30-Jan-18
Closed drain 9-Nov-17 16-Nov-17
Hydrocarbon

Condensate & Water Separation (Inc


Production Separator and Slug to make ready for hydrocarbon introduction 25-Nov-17 9-Dec-17
catcher)

Condensate stabilization to make ready for hydrocarbon introduction 2-Dec-17 16-Dec-17

Commissioning
This sch for 1 Produced water + 3 condensate
tank however 1st sales gas can be with 1
condensate tank, which will save 4 weeks. 1
Condensate and Produced water
Produced water + 2 Condensate is adequate for 20-Jan-18 27-Jan-18
storage JR gas in which can be achieve by 24 Jan ,
remaining 1 tank shall be made ready before end
of feb 2018

Fuel Gas 28-Jan-18 7-Feb-18


Flare System 3-Jan-18 13-Jan-18
GEG 7-Feb-18 17-Feb-18
Phase 2
Launcher and Receiver 1-Apr-18 8-Apr-18
AGR 9-Apr-18 7-May-18
AGE 12-Apr-18 10-May-18
SRU & Amine 18-Apr-18 23-May-18
Incenerator & Sulfur granul 16-May-18 30-May-18
Jun-18 Jul-18