Академический Документы
Профессиональный Документы
Культура Документы
Annexure Particulars
VI) Contingencies
40
ANNEXURE - I
Promoters To be Total
Contribuction Financed
As per estimate Enclosed- submitted by Civil Engineer, based on
present Schedule of Rate excluding contractor margin norms and
standards.
CIVIL COST
As per estimate Enclosed- submitted by Civil Engineer, based on
present Schedule of Rate excluding contractor margin norms and - 18.00 18.00
standards.
Total Cost - 18.00 18.00
ANNEXURE - II
Promoters To be Total
Contribuction Financed
- - 42.65
- - 42.65
41
ANNEXURE - III
Existing To be Total
Financed
As per quotation enclosed
Electrical Transmission works (2.1 KVA - 625 KVA)
(Electrical Transformer, Insttalation & D.G.Set)
with all Standard Accessories with instalations
1) Transformer - - 7.35
ANNEXURE - VI
ANNEXURE - IV
- - 0.75
42
ANNEXURE - V
Contingencies
- - 0.70
43
1. SYNOPSIS OF PROJECT COST
Rs. in Lakhs
1. Project Cost Being
Total
Incurred Incurred
Working Capital requirement towards trading- activities (Bank Finance) 0.00 50.25 50.25
2. MEANS OF FINANCING
The estimated cost of proposed unit to be met out of the following sources :-
Source of Finance
1) Promoter Contribution
a. In the mode of Share Capital including Promoters Capital Account 0.00 24.37 24.37
44
DISBURSEMENT (MPBF) /MARGIN STIPULATION OF THE PROJECT
Bank Finance
SL. TOTAL COST MARGIN Promoter Bank Finance
ITEM Contribution
required Bank Finance
further required
NO. ENVISAGED %
I Factory Building and Civil Construction 18.00 41.00% 7.38 59.00% 0.00 10.62
III Electrical Transformer & D.G. Set 7.35 33.00% 2.43 67.00% 0.00 4.92
IV Details of Misc Fixed Assets 0.00 33.00% 0.00 67.00% 0.00 0.00
V Errection, Commissioning & Testing 0.75 33.00% 0.25 67.00% 0.00 0.50
40.935 95.52
Term loan (A) र 45.08
Working Capital
1 -to be infused on operation of the plant, as margin 67.00 25% 16.75 75% 50.25
45
6. SCHEDULE OF POWER COST
The Efective electric load has been estimated at ...... KVA which is expected to be obtained from the state Electricity Board as the application in this regard is
being made. For smooth operation of the unit, electric power consumption is estimated at around ............. H.P., P.A. unit. Besides, it has been considered
that power remains often non co-operating and during the period , additional stand by arrangement is urgently required for maintaining the continuous power
supply.
Details Power Consumption as follows: -
2 Total Cost of Running the Plant per Season on Power Rs. 6/- 36.72 Lakhs
( On Full Load)
46
7. INTEREST SCHEDULE :
COMPUTATION OF INTEREST ON TERM LOAN :
Proposed Term Loan shall bear interest @ 12.50% ( Subject to change, as per Bank's norm, time to time) on Rs. ........... Lakhs , considering the moratorium period of one year on
Interest & Tweleve months ( minimum) on repayment of principal instalments as specified for this sector.
Amt. of Loan
Opening add during Interest Bearing Intt. Bearing Closing
Year
44
Opening Amt. of Loan Interest Bearing Intt. Bearing Closing
Year
45
DEPRECIATION AS PER COMPANIES ACT
Electrical
Utilities & Misc. Fixed
Year Land Building P&M Transformer & Total
D.G. Set
Auxiliaries Assets
9.5% 18.1% 18.1% 18.1% 18.1%
Total 20 1.70
Add: Other benefit @ 15% 0.26
1.96
Administration
Manager- Cum-Accountant 1 0.200 0.20
Office Staff/Cashier/Clerk 1 0.120 0.12
Peon / Darwan 1 0.070 0.07
Total 3 0.39
Add: Other benefit @ 15% 0.06
0.45
46
Project at Glance for Atta Chakki (Plant)
Processing of Wheat (MT) per annum 2880 3600 3720 3840 3960 4080 4200
Cost of Wheat Consumption during year (lacs) 483.36 604.20 624.34 644.47 664.61 684.75 704.89
Product
Atta 62%
Maida 15%
Sooji 20%
Bye-product
Bran 3%
100%
At Full capacity
Particulars 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2024-25
100%
Capacity (MT) 4800
Capacity Utilisation 100% 60.0% 75.0% 77.5% 80.0% 82.5% 85.0% 87.5% 90.0%
Overall Production (MT) 2880.00 3600.00 3720.00 3840.00 3960.00 4080.00 4200.00 4320.00
Production of Atta (MT) 1785.60 2232.00 2306.40 2380.80 2455.20 2529.60 2604.00 2678.40
Production of Maida (MT) 432.00 540.00 558.00 576.00 594.00 612.00 630.00 648.00
Production of Sooji (MT) 576.00 720.00 744.00 768.00 792.00 816.00 840.00 864.00
Production of Bran (MT) 86.40 108.00 111.60 115.20 118.80 122.40 126.00 129.60
WORK-IN-PROCESS
Opening stock of WIP (MT) 0.00 8.00 10.00 10.33 10.67 11.00 11.33 11.67
Closing stock of WIP (MT) 1 8.00 10.00 10.33 10.67 11.00 11.33 11.67 12.00
FINISHED GOODS
Opening stock of FG (MT) 0.00 56.00 70.00 72.33 74.67 77.00 79.33 81.67
Closing stock of FG (MT) 7 56.00 70.00 72.33 74.67 77.00 79.33 81.67 84.00
Sales (Quantity) 2824.00 3586.00 3717.67 3837.67 3957.67 4077.67 4197.67 4317.67
Atta (MT) 62% 1750.88 2223.32 2304.95 2379.35 2453.75 2528.15 2602.55 2676.95
Bran (MT) 3% 84.72 107.58 111.53 115.13 118.73 122.33 125.93 129.53
Sales in Value
[Amt in Rs.] [Rs in lacs]
Atta 19900.00 348.43 442.44 458.69 473.49 488.30 503.10 517.91 532.71
Maida 21000.00 88.96 112.96 117.11 120.89 124.67 128.45 132.23 136.01
Suji 22500.00 127.08 161.37 167.30 172.70 178.10 183.50 188.90 194.30
Bran 12000.00 10.17 12.91 13.38 13.82 14.25 14.68 15.11 15.54
574.63 729.68 756.47 780.89 805.31 829.72 854.14 878.56
Consumable Item 1.5% of Sales 8.62 10.95 11.35 11.71 12.08 12.45 12.81 13.18
Value
Projections of Performance, Profitability and Repayment
A% utilisation of installed capacity 60% 75.0% 77.5% 80.0% 83% 85.0% 88%
Net Sales (Revenue) 576.06 731.50 758.36 782.84 807.72 831.80 856.28
CCost of Production
1 Cost of Purchases 483.36 604.20 624.34 644.47 664.61 684.75 704.89
2 Consumable Stores 8.62 10.95 11.35 11.71 12.08 12.45 12.81
3 Power & Fuel 28.14 35.18 36.35 37.52 38.70 39.87 41.04
4 Direct Labour and Wages 14.08 17.60 18.18 18.77 19.35 19.94 20.53
5 Other Manufacturing Expenses 1.44 1.83 1.90 1.96 2.02 2.08 2.14
6 Depreciation 11.02 9.17 6.38 5.34 4.47 3.75 3.15
Total Cost of Sales 546.66 678.92 698.49 719.77 741.23 762.84 784.57
7 Add: Op. Stock of stock-in-process 0.00 1.52 1.89 0.00 2.00 2.06 2.12
8 Deduct: Cl. Stock of stock-in-process 1 1.52 1.89 1.94 2.00 2.06 2.12 2.18
Cost of Production 545.14 678.55 698.44 717.77 741.17 762.78 784.51
9 Add: Op. Stock of finished item 0.00 10.60 13.19 13.58 13.96 14.41 14.83
10 Deduct: Cl. Stock of finished item 7 10.60 13.19 13.58 13.96 14.41 14.83 15.25
DTotal Cost of Sales 534.54 675.96 698.05 717.39 740.72 762.36 784.09
E General and Administrative Exp. 3.75% of Sale 21.55 27.36 28.37 29.28 30.20 31.11 32.03
F Interest on
1 Term Loans 5.50 4.66 3.72 2.78 1.84 0.90 0.10
2 Working Capital 6.28 6.28 6.28 6.28 6.28 6.28 6.28
3 Other Loans, if any 0.00 0.00 0.00 0.00 0.00 0.00 0.00
GPremilinary & Pre-operative Expenses 0.84 0.84 0.84 0.84 0.84 0.00 0.00
HProfit before Taxation {E-(F + G)} 8.19 17.24 21.94 27.10 28.68 31.14 33.78
I. Provision for Taxes 2.53 5.33 6.78 8.37 8.86 9.62 10.44
J. Net Profit (H - I) 5.66 11.91 15.16 18.73 19.82 21.52 23.34
KDepreciation added back 11.02 9.17 6.38 5.34 4.47 3.75 3.15
L Net Cash Accruals 16.68 21.08 21.54 24.06 24.29 25.27 26.50
MRepayment obligations
1 Towards Term Loans 3.76 7.51 7.51 7.51 7.51 7.51 3.76
2 Other Loans, if any 0.00 0.00 0.00 0.00 0.00 0.00 0.00
NDebt Service Coverage Ratio 2.40 2.11 2.25 2.61 2.79 3.11 6.90
OAverage DSCR 3.17
56
Projected Balance Sheet
3 Deferred Tax Liabilities 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Loan Liability
4 Term Loans - Proposed 41.32 33.81 26.30 18.78 11.27 3.76 0.00
5 Bank Borrowings for W.C. 50.25 50.25 50.25 50.25 50.25 50.25 50.25
6 Unsecured Loan from Director 5.00 5.00 5.00 5.00 5.00 5.00 5.00
Current Liabilities
7 Sundry Creditors 9.40 11.75 12.14 12.53 12.92 13.31 13.71
8 TL Installment Payable 3.76 7.51 7.51 7.51 7.51 7.51 3.76
9 Provision for tax 2.53 5.33 6.78 8.37 8.86 9.62 10.44
10 Expenses Payable 2.50 2.75 3.03 3.33 3.66 4.03 4.43
B. Assets
4 Long Term Investment/Advances 0.00 0.00 5.00 27.00 40.00 55.00 70.00
5 Non Current - Security Deposit 7.23 7.23 7.23 7.23 7.23 7.23 7.23
6 Current Assets, Loans & Advances
a. Stock-in-hand 73.26 91.52 94.51 97.49 100.55 103.58 106.61
b. Sundry Debtors 11.17 14.19 14.71 15.18 15.66 16.13 16.61
c. Other Advance 0.00 0.00 0.00 0.00 0.00 0.00 0.00
d. Cash and Bank Balances 5.56 5.05 13.34 7.01 9.68 10.41 12.28
e. Advance Tax 2.53 5.33 6.78 8.37 8.86 9.62 10.44
58
ASP Flour Bhog Mill
PROFITABILITY STATEMENT
Rs. In lacs
Year of Operation 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25
A. Cost of Operation :
B. Total Cost of operation 535.63 669.74 692.11 714.44 736.76 759.09 781.42
RECEIPTS
D. Gross Receipts from Sale 574.63 729.68 756.47 780.89 805.31 829.72 854.14
Other Income 1.44 1.82 1.89 1.95 2.42 2.07 2.14
Gross Receipts 576.06 731.50 758.36 782.84 807.72 831.80 856.28
F. General & Administrative Exps. 21.55 27.36 28.37 29.28 30.20 31.11 32.03
H. Net Profit before Int. 19.98 28.18 31.94 36.16 36.80 38.32 40.16
Interest on Term Loan 5.50 4.66 3.72 2.78 1.84 0.90 0.10
Interest on Cash Credit 6.28 6.28 6.28 6.28 6.28 6.28 6.28
Other Finance Costs - - - - - - -
K. Net Profit before Tax 8.20 17.24 21.94 27.10 28.68 31.14 33.78
C. Secured Loan
Term Loan (New) 41.32 33.81 26.30 18.78 11.27 3.76 0.00
Cash Credit - Bank of India CC A/c 50.25 50.25 50.25 50.25 50.25 50.25 50.25
E. Current Liabilities
Provision for Tax 2.53 5.33 6.78 8.37 8.86 9.62 10.44
Instalments on Term Loan 3.76 7.51 7.51 7.51 7.51 7.51 3.76
Sundry Creditors 9.40 11.75 12.14 12.53 12.92 13.31 13.71
Liability for Expenses 2.50 2.75 3.03 3.33 3.66 4.03 4.43
TOTAL : 161.54 175.09 184.85 198.35 211.87 227.40 244.84
F. Assets
Gross Value 69.45 69.45 69.45 69.45 69.45 69.45 69.45
Less:Depreciation 11.02 20.20 27.84 34.23 39.57 44.04 47.79
Net Block 58.43 49.25 41.61 35.22 29.89 25.42 21.67
G Work in Progress - - - - - - -
I Non-Current Assests - Security Deposit 7.23 7.23 7.23 7.23 7.23 7.23 7.23
J Priliminary & Pre-operative Exp not W/off 3.36 2.52 1.68 0.84 - - -
K Current Assets
Sundry Debtors 11.17 14.19 14.71 15.18 15.66 16.13 16.61
Stock in hand 73.26 91.52 94.51 97.49 100.55 103.58 106.61
Other Advance - - - - - - -
Advance to Tax 2.53 5.33 6.78 8.37 8.86 9.62 10.44
86.96 111.03 116.00 121.05 125.08 129.34 133.66
L Cash & Bank Balances 5.56 5.05 13.34 7.01 9.68 10.41 12.28
1 Cash Accruals 19.97 28.18 31.94 36.16 36.81 38.32 40.16 41.90
( Net Profit before Taxation )
2 Increase in share capital 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Equity / Preference
4 Increase in long term loans / #VALUE! 0.00 0.00 0.00 0.00 0.00 0.00 0.00
debentures
5 Decrease in Advance to 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Suppliers
6 Decrease in Preliminary & 0.84 0.84 0.84 0.84 0.84 0.00 0.00 0.00
Pre-operative exp
7 Increase In Current Liabilities
7.1 Sundry Creditors 9.40 2.35 0.39 0.39 0.39 0.39 0.39 0.39
7.2 Installment Payable 3.76 3.76 0.00 0.00 0.00 0.00 -3.75 -3.76
7.3 Provision for Tax 2.53 2.79 1.45 1.60 0.49 0.76 0.82 0.57
7.4 Expenses Payable 1.76 0.25 0.28 0.30 0.33 0.37 0.40 0.44
8 Increase in Unsecured loans -44.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
and deposit
9 Increase in bank borrowings 50.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
for working capital
10 Sales of Fixed assets / 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
investments
11 Margin Money for W.C. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 Subsidy 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 Decrease stock-in-hand 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Sources (A) #VALUE! 47.34 41.28 44.63 43.33 43.59 41.17 42.20
Disposition of Funds
1 Increase in Non Current 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Assets
2 Increase in Capital 69.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Expenditure
3 Increase in current assets
3.1 Sundry Debtors 11.17 3.01 0.52 0.47 0.47 0.47 0.47 0.47
3.2 Increase in Stock-in-hand 73.26 18.26 2.99 2.98 3.06 3.03 3.03 3.03
3.3 Other Advance -20.61 0.00 -6.11 -17.29 0.00 0.00 0.00 0.00
3.4 Advance Tax 2.53 2.79 1.45 1.60 0.49 0.76 0.82 0.57
4 Decrease in long term loans / 0.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
debentures
5 Decrease in Current 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liabilities
6 Decrease in Deferredpayment 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Tax
7 Increase in Investments 0.00 0.00 5.00 22.00 13.00 15.00 15.00 55.00
8 Interest on Term Loan 5.50 4.66 3.72 2.78 1.84 0.90 0.10 0.00
9 Interest on W / C 6.28 6.28 6.28 6.28 6.28 6.28 6.28 6.28
10 Interest on Other Loan 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 Taxation 2.53 5.33 6.78 8.37 8.86 9.62 10.44 11.01
12 Decrease in Cash Credit 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Disposition (B) 150.11 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Opening Balance 59.65 #VALUE! #VALUE! 1.77 #VALUE! #VALUE! #VALUE! #VALUE!
Net Surplus (A-B) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Closing Balance #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
5.56 5.05 13.34 7.01 9.68 10.41 12.28 -21.39
58
1. Computation of Break Even Po
Mar-19 Mar-20 Mar-21 Mar-22 Mar-23 Mar-24 Mar-25
I. Realisation 576.06 731.50 758.36 782.84 807.72 831.80 856.28
60
Computation of Debt Service Coverage Ratio:
S.N. Particulars Mar-19 Mar-20 Mar-21 Mar-22 Mar-23 Mar-24 Mar-25
A. Net Profit after Tax 5.66 11.91 15.16 18.73 19.82 21.52 23.34
Add. Depreciation 11.02 9.17 6.38 5.34 4.47 3.75 3.15
Add.
Add. Interest on Term Loan
Pre-operative 5.50 4.66 3.72 2.78 1.84 0.90 0.10
expenses
Add. Other writtenitem
non-cash off
written off
TOTAL (A) 22.18 25.74 25.26 26.84 26.13 26.17 26.59
B. Intelment on Term Loan 3.76 7.51 7.51 7.51 7.51 7.51 3.76
Interest on Term Loan 5.50 4.66 3.72 2.78 1.84 0.90 0.10
TOTAL (B) 9.25 12.17 11.23 10.29 9.35 8.41 3.85
C. DSCR (A/B) 2.40 2.11 2.25 2.61 2.79 3.11 6.90
D. Average DSCR 3.17
61
bi
D
vl
ie
rt
V
ye
ASSESSMENT OF WORKING CAPITAL REQUIREMENTS saN
ctre
FORM II - OPERATING STATEMENT A
tito
### n
C
O
raaF
obS
Name: ASP Flour Bhog Mill [Rs. In 00000's omitted] lp einn
O
al
Years' Mar-19 Mar-20 Mar-21 Mar-22 Mar-23 Mar-24 Mar-25 sex tlpbel
re y
No. of months 12 12 12 12 12 12 12 eoras
&
rudiC
s
t i o
1. Gross Sales
abris
574.63 729.68 756.47 780.89 805.31 829.72 854.14 C
sus
i. Domestic Sales ,tnp
ott
ii. Other Direct Income 1.44 1.82 1.89 1.95 2.42 2.07 2.14 i g a*si
nD
Total 576.06 731.50 758.36 782.84 807.72 831.80 856.28 rg toe
P
esn
2. Less Excise Duty rp
*sP
3. Net Sales (1 - 2) 576.06 731.50 758.36 782.84 807.72 831.80 856.28 ro ,*
ref
4. % age rise (+) or fall (-) in net sales N/A 26.98% 3.67% 3.23% 3.18% 2.98% 2.94% o Break Even Sales
ics
as compared to previous year (annualised) tfiCash Break Even
ia/
o
5. Cost of Sales tS
c
i. Raw materials (including stores and aik
other items used in the process of
lo
nea
manufacture) 483.36 604.20 624.34 644.47 664.61 684.75 704.89 ,sd
j
a. Imported
S
b. Indigenous 483.36 604.20 624.34 644.47 664.61 684.75 704.89 G
a
ii. Other Spares A
n
d
a. Imported
a
b. Indigenous 8.62 10.95 11.35 11.71 12.08 12.45 12.81 n
o
iii. Power and Fuel 28.14 35.18 36.35 37.52 38.70 39.87 41.04 d t
iv. Direct Labour 14.08 17.60 18.18 18.77 19.35 19.94 20.53 h Ie
(Factory wages & salaries) nr
t
v. Other manufacturing expenses 1.44 1.83 1.90 1.96 2.02 2.08 2.14
em
vi. Depreciation 11.02 9.17 6.38 5.34 4.47 3.75 3.15 r
f
vii. Sub-total (i to vi) 546.66 678.92 698.49 719.77 741.23 762.84 784.57 eg
s
viii. Add: Opening Stock-in-process 0.00 1.52 1.89 0.00 2.00 2.06 2.12 t
e
Sub-total (vii + viii) 546.66 680.44 700.38 719.77 743.23 764.90 786.69 x
ix. Deduct: Closing Stock-in-process 1.52 1.89 1.94 2.00 2.06 2.12 2.18 p
e
x. Cost of Production 545.14 678.55 698.44 717.77 741.17 762.78 784.51
n
s
e
s
64
xi. Add: Opening Stock of finished goods 0.00 10.60 13.19 13.58 13.96 14.41 14.83
Sub-total (x + xi) 545.14 689.15 711.63 731.35 755.13 777.19 799.34
xii. Deduct: Closing Stock of finished
goods 10.60 13.19 13.58 13.96 14.41 14.83 15.25
xiii. Sub-total (Total Cost of Sales) 534.54 675.96 698.05 717.39 740.72 762.36 784.09
a.
b.
c.
d.
Sub-total (Income) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ii.
Deduct: Other non-operating expenses.
a.
b.
c.
d.
expenses [net of 11(i) & 11(ii)] 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12. Profit/Loss Before Tax [10 + 11(iii)] 8.19 17.24 21.94 27.11 28.68 31.15 33.78
13. Provision for taxes 2.53 5.33 6.78 8.37 8.86 9.62 10.44
14. Net Profit / Loss (12 -13) 5.66 11.91 15.16 18.74 19.82 21.53 23.34
15. a. Equity dividend paid-amount
65
FORM III - ANALYSIS OF BALANCE SHEET
LIABILITIES
i. From applicant bank 50.25 50.25 50.25 50.25 50.25 50.25 50.25
ii. From other banks
Sub-total [i + ii] (A) 50.25 50.25 50.25 50.25 50.25 50.25 50.25
2. Short term borrowings from others
3. Sundry Creditors (Trade) 9.40 11.75 12.14 12.53 12.92 13.31 13.71
4. Advance payments from customers / 0.00 0.00 0.00 0.00 0.00 0.00 0.00
deposits from dealers
5. Provision for taxation 2.53 5.33 6.78 8.37 8.86 9.62 10.44
6. Dividend payable
Other statutory liabilities (due within 1
7. year) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8. Deposits / instalments of term loans / 3.76 7.51 7.51 7.51 7.51 7.51 3.76
DPGs / debentures etc. (due within 1 year)
(due within 1 year) - specify major items 2.50 2.75 3.03 3.33 3.66 4.03 4.43
a. Net Current Liabilities 2.50 2.75 3.03 3.33 3.66 4.03 4.43
b.
c.
d.
Sub total [2 to 9] (B) 18.19 27.34 29.46 31.75 32.96 34.48 32.33
10. Total current liabilities [A + B] 68.44 77.59 79.71 82.00 83.21 84.73 82.58
66
TERM LIABILITIES
payable within 1 year) 41.32 33.81 26.30 18.78 11.27 3.76 0.00
14. Deferred Payment Credits (excluding
16. Other term liabilities( unsecured ) 5.00 5.00 5.00 5.00 5.00 5.00 5.00
17. Total Term Liabilities [11 to 16] 46.32 38.81 31.30 23.78 16.27 8.76 5.00
18. Total Outside Liabilities [10 + 17] 114.76 116.40 111.01 105.78 99.48 93.49 87.58
NET WORTH
19. Ordinary Share Capital 41.12 41.12 41.12 41.12 41.12 41.12 41.12
20. General Reserve 0.00 0.00 0.00 0.00 0.00 0.00 0.00
21. Revaluation Reserve
b. Share Premium
24. Net Worth 46.78 58.69 73.85 92.57 112.39 133.91 157.26
25. TOTAL LIABILITIES [18 + 24] 161.54 175.09 184.86 198.35 211.87 227.40 244.84
67
FORM III - ANALYSIS OF BALANCE SHEET (continued)
ASSETS
68
FIXED ASSETS
35 Gross Block (land, building, machinery,
work-in-progress) 69.45 69.45 69.45 69.45 69.45 69.45 69.45
36 Depreciation to date 11.02 20.20 27.84 34.23 39.57 44.04 47.79
37 Net Block (35 - 36) 58.43 49.25 41.61 35.22 29.89 25.42 21.67
69
FORM IV
COMPARATIVE STATEMENT OF CURRENT ASSETS AND CURRENT LIABILITIES
70
FORM IV
COMPARATIVE STATEMENT OF CURRENT ASSETS AND CURRENT LIABILITIES
stores & consumable spares 9.40 11.75 12.14 12.53 12.92 13.31 13.71
Month's purchases (0.21) (0.23) (0.23) (0.23) (0.23) (0.23) (0.23)
11. Advances from customers 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12. Statutory liabilities 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 Other current liabilities: 8.79 15.59 17.32 19.21 20.03 21.16 18.63
Short term borrowings from others 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Provision for taxation 2.53 5.33 6.78 8.37 8.86 9.62 10.44
Dividend payable 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Deposits/instalments of term loans/DPGs
/ debentures etc. (due within 1 year) 3.76 7.51 7.51 7.51 7.51 7.51 3.76
Other current liabilities & provisions
(due within 1 year) 2.50 2.75 3.03 3.33 3.66 4.03 4.43
14. Total (To agree with total B of Form-III) 18.19 27.34 29.46 31.74 32.95 34.47 32.34
71
FORM V
Computation of Maximum Permissible Bank Finance For Working Capital
(25% of WCG excluding export 18.58 22.19 24.97 24.08 25.45 26.32 28.40
receivables)
5 Actual / Projected net working capital
(item-6 or 7, whichever is lower) 50.25 50.25 50.25 50.27 50.26 50.26 50.24
9 Excess borrowings representing
shortfall in NWC (4 - 5)
(other than bank borrowings (Form-IV-14) 18.19 27.34 29.46 31.74 32.95 34.47 32.34
3 Working Capital Gap (WCG) (1-2) 74.33 88.74 99.88 96.32 101.80 105.28 113.60
4 Min. stipulated net working capital:
(25% of total CA excluding export
receivables) 23.13 29.02 32.34 32.02 33.69 34.94 36.49
5 Actual / Projected net working capital
(Form-III-45) 24.08 38.49 49.63 46.05 51.54 55.02 63.36
6 Item-3 minus Item-4 51.20 59.72 67.54 64.30 68.11 70.34 77.11
7 Item-3 minus Item-5 50.25 50.25 50.25 50.27 50.26 50.26 50.24
8 Max. permissible bank finance
(item-6 or 7, whichever is lower) 50.25 50.25 50.25 50.27 50.26 50.26 50.24
9 Excess borrowings representing
shortfall in NWC (4 - 5)
72
FORM VI
FUNDS FLOW STATEMENT
Name: ASP Flour Bhog Mill
Year Mar-19 Mar-20 Mar-21 Mar-22 Mar-23 Mar-24 Mar-25
1. SOURCES
a. Net Profit 5.66 11.91 15.16 18.74 19.82 21.53 23.34
b. Depreciation 0.00 9.17 7.65 6.38 5.34 4.47 3.75
c. Increase in Capital 0.00 0.00 0.00 0.00 0.00 0.00 0.00
d. Increase in Term Liabilities 0.00
(including Public Deposits)
e. Decrease in
i. Fixed Assets
ii. Other non-current Assets 0.00 0.84
f. Others 0.00 0.00 0.00 0.00 0.01
g. TOTAL 5.66 21.92 22.81 25.12 25.16 26.00 27.10
2. USES
a. Net loss
b. Decrease in Term Liabilities
(including Public Deposits) 7.51 7.51 7.52 7.51 7.51 3.76
c. Increase in
i. Fixed Assets 11.16 0.00 0.00 0.00 0.00 0.00 0.00
ii. Other non-current Assets 4.16 21.16 12.16 15.00 15.00
d. Dividend Payments 0.00 0.00 0.00 0.00 0.00 0.00 0.00
e. Others 0.00 0.02 0.01
f. TOTAL 11.16 7.51 11.67 28.70 19.67 22.52 18.76
3. Long Term Surplus (+) / Deficit (-) [1-2] -5.50 14.41 11.14 -3.58 5.49 3.48 8.34
4. Increase/decrease in current assets
* (as per details given below) 92.52 23.56 13.25 -1.28 6.70 5.00 6.19
5. Increase/decrease in current liabilities
other than bank borrowings 18.19 9.15 2.12 2.28 1.21 1.52 -2.15
6. Increase/decrease in working capital gap 74.34 14.41 11.13 -3.56 5.48 3.47 8.34
7. Net Surplus / Deficit (-) [3-6] -79.84 0.00 0.01 -0.01 0.00 0.01 0.00
8. Increase/decrease in bank borrowings 50.25 0.00 0.00 0.00 0.00 0.00 0.00
9. Increase/decrease in NET SALES 576.06 155.44 26.86 24.48 24.88 24.08 24.48
* Break up of item-4
i. Increase/decrease in Raw Materials 60.42 15.10 2.52 2.52 2.52 2.51 2.52
ii. Increase/decrease in Stocks-in-Process 0.00 0.37 0.05 0.06 0.06 0.06 0.06
iii. Increase/decrease in Finished Goods 10.60 2.59 0.39 0.38 0.46 0.42 0.42
iv. Increase/decrease in Receivables
a) Domestic 0.00 0.00 0.00 0.00 0.00 0.00 0.00
b) Export 0.00 0.00 0.00 0.00 0.00 0.00 0.00
v. Increase/decrease in Stores & Spares 0.72 0.19 0.04 0.03 0.03 0.03 0.03
vi. Increase/decrease in other current assets 92.52 5.31 10.25 -4.27 3.63 1.98 3.16
TOTAL 164.26 23.56 13.25 -1.28 6.70 5.00 6.19
73
Key Indicators
S. Mar-19 Mar-20 Mar-21 Mar-22 Mar-23 Mar-24 Mar-25
No For year ended / ending March 31,
Other Indicators
22 R O C E (%) 14.26% 19.40% 20.78% 21.82% 20.57% 19.87% 18.90%
23 Interest Coverage Ratio 2.63 3.41 3.83 4.58 5.08 5.86 6.79
24 DSCR 2.40 2.11 2.25 2.61 2.79 3.11 6.90
Fund Flow Analysis
For year ended / ending March 31,
Long Term Sources 5.66 21.92 22.81 25.12 25.16 26.00 27.10
Long Term uses 11.16 7.51 11.67 28.70 19.67 22.52 18.76
Surplus/Deficit -5.50 14.41 11.14 -3.58 5.49 3.48 8.34
Surplus / Incremental build up of current assets
(%) 15% 25% 11% -1% 5% 4% 4%
74
Form - IV
SPECIMEN `D'
(FIGURES IN LAKHS)
1.2 Constitution [please strike out which are not applicable] Proprietary / Partnership Firm / Private Limited / Public
Limited Company / Co-operative Society
(Please Strike out whichever is not applicable)
1.3 Name of the business house/group to which the unit - DO -
belongs
3 Business Address with Telephone/Talex /Fax No. AT- KODARIYA MANGO, P.S. -PAROO
5.1 Existing
(*) Indicate sources of funds with name & address, e.g., banks/financial institutions/others (specify)
8 Past Performance (To be filled up by the existing unit only) NEW PROPOSED
(Figures in 000s Rs.)
Last but One Year
Particulars Last Year Last but Two Years
Turn Over
Net Profit
Retained Profit
9.1 Management The Main Promoter behind the project is Mr. Saniw Kumar
(Please furnish background of the main Singh, he remained associated for long with several
promoter other than those furnished in Business organisations of such sector, earning long
Appendix I , write-up on other companies, if ,remarkable goodwill & success -details enclosed.
any, promoted by him or with which he is
associated together with a copy of the latest
balance sheet)
9.2 In case the promoter is a limited company, The Company started with its first venture as proposed
please furnish a write-up on the activities and multipurspose cold storage.
past performance of the company and any
other expansion programmes(s) /
diversification contemplated.
9.3 SHAREHOLDING
Executives 0 1
Surpervisory 0 2
Administrative/Office Staff 0 5
Skilled Labour 0 -
Unskilled Labour 0 -
Other (specify) 0 5
9.5 Particulars of existing key techincal and executive staff : Please Refer Project Report
(Please furnish data for existing as well as proposed staff)
Any special
achievement Functional Duties at
Name Designation Qualification Experience
(Inventions / the Unit
Research etc.)
10 If the unit is an ancillary unit, the undertaking to which it is -
catering and its address Enclosed
Name of the associate concern(s), if any , and its address Protech Biosystems Pvt. Ltd & Protech
11 Biosciences Pvt Limited
11.4 Turnover and profit during preceding three years As enclosed- herewith
12.1 Name of the product(s) including bye- Cold Storage service industry with Hort. Trading capacity.
products & its (their) use
12.2 Manufacturing Process, in brief (indicate to Refrigeration in specified temperature & humidity as
the extent possible,stage-wise capacity data, for required different commodities.
yield/ conversion data, material flow, etc.)
12.3 Capacity
Please enclose -
b) Fees payable and the manner in which payable As required for the Job
d) Brief particulars of consultants including organisational set-up , bio-data, As per project Report
of senior personnel, names of directors/partners, particulars of work done
in the past and work on head.
Please enclose a copy of the agreement with the consultant, and in case N.A.
of foreign consultant(s) approval of the Government.
d. transport
The site is very near to NH & road links in develop area.
12.6 LAND & BUILDING Value
Area/Plinth Area
(in 000s of
(in Sq. metres)
Rs.)
Existing Proposed Existing Proposed
Factory Land
Ancillary Building
Open Storage
Space
12.7 Type of soil and load bearing capacity (enclose test report) Sampling has been done and soil have been
found very much suitable for the project,
Enclosure : reports attached.
12.8.1.3 Rates quoted and detailed estimed of expenses As per works & requirement / scope
12.8.1.6 Penalties -
12.9.2 Arrangements made for erection and commissioning of Erection & Commissioning will be done by
the plant. Er. Sushil Kumar Refrigeration, Mach.
Enginers
12.10 Necessity & purpose for the proposed investment /
addition to factory premises/ machinery (in case where As per project Report
such investment is intended) for achievement of the
anticipated turnover.
Sources of Supply
Lead/Procurement Time
13.1 Power
- own generation
- stand-by arrangements
Please enclose
13.2.1 Indicate the requirements and suitability of water Water in suitable & available for this industry
13.3 Steam
14. Effluent
Please furnish full details of the value of atmosphere, In the indstry of cold stroage
soil, and water pollution likely to be created by the ammonia refrigerant no pollution
project and the measures propsed for control of warranted.
pollution.
15 QUALITY CONTROL
15.1 Details of arrangement made for quality control. The Plant to be set-up will be of Fin Coil system
If BIS/FPO/ISO specifications are followed, no. and ISO specification as sponsored approved
of BIS/FPO/ISO standards and the particulars by NHB
thereof should be provide
16 ECONOMIC FEASIBILITY
16.3 Region/Area where the product is/will be sold LOCAL & OTHER FAR MARKET TERMINALS.
16.4 Extent of competition & No. of units engaged in NO UNIT EXISTS WITHIN THE MINIMUM RADIUS OF
similar line in the area 25 KMs
16.5 How does the unti meets/proposes to meet the FOR THIS CAPACITY -SPECIFIED COLD STORAGE-
competition (comment on the competitive NO COMPETITION IS THERE.
advantages enjoyed by the unit)
16.5.1 In price and quality, how does the unit’s product This facility is being controlled of Temp. & Humidity
compare with those of its competitors for different Hort. Produces.
N.A.
Code No.
Name of he Product Exported Name of the Country where Exported F.O.B. Value in US $
17 Cost of Project
(Please furnish estimates of cost of project under the following heads. Indicate the basis for arriving at the cost of
project)
(In 00000s of Rs.)
E. Testing Equipment/Charges
H. Preliminary Expenses
I. Pre-Operative Expenses
Provision for Contingencies
1 Building
J.
2 Plant & Machinery
3 Other Fixed Assets
L. Total -
18 Means of Finance
(Please furnish details of sources of finance
for meeting the cost under the following heads)
B. Reserves
J. Total - - -
18.2 Indicate sources from which expenditure Share Capital & Intt. Free Unsecured Loan from
already incurred has been finances Friends & Relations
19.3 Underwriting
19.3.3 Debentures -
20 Schedule of Implementation
AS PER PROJECT REPORT
Please indicate the progress made so far in
the implementation of the project and furnish
the schedule of implementation as follows :
Date of Expected Date of
Commencement Completion
a. Acquisition of Land
b. Development of Land
Factory Building
Machinery Foundation
Administrative Building
Imported
Indigenous
g. Erecition of equipment
h. Commissioning
j. Trial Runs
k. Commercial Production
21 Future Projections (to be given for the next five years)
Please furnish data on
26.31 Name
I/We certify that all information furnished by me/us is true ; that I/We have no borrwing arrangemetns for
the unit with any bank except as indicted in the application ; that there is no overdues/statutory dues against
me/us/promoters except a
Date :
Signature of the Borrower
Place : (Name & Designation)
Encl. :
Certified Xerox Copied of ENCLOSED
a. Audited Balance Sheets with Trading And Profit & Loss Account for the last threee years.
c. Income TAx, Wealth TAx Returns and assessment orders for the last three years, for the unit
as well as proprietor/partners/promoters/directors.
3 Age
4 Sex MALE
8 Passport No.
Office
Permanent Residence
11 Experience
Year Employer Designation Last Salary Drawn
15.8 Working results of the units for the past three years
Place :
Date : Signature
Particulars of Building Proposed to be Constructed
ENCLOSED
Note : 1. In case constract is awarde for construction of building, furnish details thereof such as name of
contractor, amount of contract, etc.
2. Other approvals from inspector of fectories ; drug controllers, etc., if any, should be enclosed.
Particulars of machinery
1. Existing Machinery
1.2 Imported -
2. Proposed to be acquired
2.2 Imported -
1. Quotation / Catalogues / Invoice and other details in respect of each machine to be furnished.
2. If sound hand machinery, valuation report regarding age, performance and value from competent valuer to be
submitted. Also please indicate reasons for going in for second hand machinery and its depreciated value.
3. In case of importeed machinery,please indicate mode of payment and price of the machinery in foreign currency
4. In case the assets have been revalued or written up at any time during the existence of unit, furnish full details of such
revaluation together with the reason therefor.
Appendix - II
A. Land
1. Location
2. Area
6. Terms of Lease -
B. Building
1 Location
Type of Structure
Actual Cost Date of
Structure (indicate "P" if Dimensions Area (in Sq. m.)
(in Lakhs) Erection
Permanent)
1. Workship
2. Godown
3. Administrative
4. Other Buildings
In case the assets have been revalued or written up at any time during the existence of unit, furnish full details of
such revaluation together with the reason therefor.
Appendix - III
Break-even point
% of Installed
Capacity
Break-even Quantity
Break-even Value
2nd
1st Year 3rd Year 4th Year 5th Year 6th Year 7th Year 8th Year
Year
B. Sales ENCLOSED
2 Less Excise
3 Net Sales
C. Cost of Production
4. Consumable Stores
7. Depreciation / Development
Rebate Reserve
D. Cost of Sales
E. Gross Profit (B - D)
[Figures in 000s of Rs.]
2nd
1st Year 3rd Year 4th Year 5th Year 6th Year 7th Year 8th Year
Year
F. Interest on
1. Term Loans
2. Working Capital
J. Net Profit (H - I)
M. Repayment obligations
Total Repayment
Constru
2nd
ction 1st Year 3rd Year 4th Year 5th Year
Year
Priod
A. Source of Funds
3. Depreciation
B. Disposition of Funds
Opeing Balance
Closing Balance
[Figures in 000s of Rs.]
2nd
1st Year 3rd Year 4th Year 5th Year
Year
(Month Purchases)
Statutory Liabilities
V. Bank Borrowings
Appendix - V
Projected Balance Sheet
[Figures in 000s of Rs.]
2nd
1st Year 3rd Year 4th Year 5th Year 6th Year 7th Year 8th Year
Year
A. Liabilities
3. Term Loans
5. Other Liabilities
Total Liabilities
B. Assets
1. Gross Block
2. Depreciation
3. Net Block
4. Investment
5. Current Assets
I. Current Assets
3. Stock-in-process (Month's
Cost of Production)
6. Export Receivables
(including Bills purchases /
Discount by banks)
7. Advance to Suppliers of
Raw Materials and Stores /
Spares / Consumables