In this paper I will be putting together information relevant to the discussion why someone should look
forward to use MRP on Hana & how this can be done to achieve the full potential.
The performance optimization for the classic MRP transactions is available as of SAP enhancement package 6
for SAP ERP 6.0, version for SAP HANA.
MRP Live & MRP Fiori Apps are available as of SAP enhancement package 7 for SAP ERP 6.0.
Improved performance and execute the planning run in much shorter cycles (10+ times) – several planning
runs daily can be executed providing the MRP controller with the following benefits, for example:
S4/HANA offers prioritized view on material flow issues with clear visibility. It also gives system-generated
solution proposals & automated creation of procurement proposals. It’s flexible in tailoring of available
capacities and receipts to meet required quantities.
The old MRP transactions, (such as MD01, MD02, etc…) were optimized to improve the performance when
reading planning elements from the database, when running on a HANA database.
The internal logic to read the planning elements from the database to the internal table MDPSX has been
completely redesigned for better performance with HANA.
The classic MRP run (MD01) also runs on HANA (parallel to MD01N) with exactly the same functionality as
on any other database.
There is no substantial change on the transaction design but you can find a flag pointing that the optimization
was active during the MRP execution:
What is MRP LIVE
MRP Live on HANA (MD01N) was implemented to improve MRP performance on HANA. This is a new
MRP mode, where MRP has been fully redesigned to run an in-memory planning run. Can be run in
background or foreground as well.
Materials which might be unable to be planned via MRP live, will be automatically planned on Classic MRP
(internally) – No extra user effort. (Restriction)
The already existing MRP functionalities are still supported, but with a few exceptions.
In addition to the planning scopes covered by the classic MRP transactions, MRP Live also supports the
following planning scopes, for example:
The planning of a selected material in a selected location (such as a distribution center) and its
supplying locations (such as a production plant).
The planning of the distribution of a selected material across several locations.
The planning of a selected material in a selected location and its supplying locations and the
components in the production location or locations, multilevel across the complete supply chain.
The planning of all the materials for which one MRP controller is responsible.
Using the settings and control parameters in the initial screen of the MRP Live planning run, you can
determine how the planning run is to be carried out.
Once the MRP Run finished, Performance log appears: If MRP Levels button is clicked then detail log can be
seen.
Stock/Requirement list is used to see the summary of the MRP Run. And the detail list shows the requirements
and created PurReqs.
When to use? Classic vs MRP Live
For each low level code, which planning run is used depends on the MRP parameters defined for the materials
in the material master record and in Customizing. Below is the sequence of planning when using MRP Hana.
Report PPH_CHECK_MRP_ON_HANA is run to estimate how many materials can be planned by MRP
Live and exactly which restrictions do you have on your system. This can be run even Non Hana systems with
support package.
If you are considering to use MRP on HANA, you can use this report to improve your master data and reduce
the number of restrictions, focusing a better performance on MRP Live.
Total number of materials that can be planned by MRP Live by low-level code, and also specifying the number
of materials that cannot be planned by MRP Live for a specific restriction.
All the materials are displayed. Here, the report will tell you if the material will be planned in HANA or in ABAP
and it will also tell you if there is any specific restriction for this material.
Factors that Impact Performance of MRP on HANA
MRP live (transaction MD01N) is designed to perform MRP for a large set of materials in one or even multiple
locations with fast runtime. The improvement in performance in MRP live on HANA compared to classic MRP
depends on the following:
References-
SAP Notes-
1863808 MD01N: When to plan in MRP Live, when to plan in classic MRP
Links-
http://help.sap.com/erp2005_ehp_07/helpdata/EN/81/9F1A74147F4A9089132288E7C6AB3C/frameset.htm
https://wiki.scn.sap.com/wiki/display/ERPMan/MRP+on+HANA+FAQ
http://help.sap.com/erp2005_ehp_07/helpdata/en/1d/4ee5514ec5c90ae10000000a44176d/frameset.htm