Вы находитесь на странице: 1из 19

International Journal of Engineering Research & Technology (IJERT)

ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

Improving Guaranteed Minimum Billing Demand for the Reduction


of Energy Cost at Rizal Technological University
Arturo Tadeos C. Cabugayan 1 Ruben J. Dichoso 2 Roland M. Valencia 3
EE-Faculty, CEIT-RTU RTU, GBF-Technical Lecturer EE-Faculty, CEIT-RTU

Abstract 1. Introduction

The electrical system design has been Conservation of energy is good but
installed with greater flexibility to match does not mean effective when the electricity
the connected loads for long period bill is concerned. At present, in seven (7)
of time. This condition requires greater components of unbundled electric bill, the
contracted capacity from electric utility large percentage of energy cost are part of
company. The difference between contracted generation, transmission and distribution cost
capacity and the actual consumption of power (RA 9136 known as EPIRA Law). Unless,
establishes the main source of high electricity utilization of energy decreases, the customer
RT
bill under distribution cost, and makes the has nothing to do in reducing monetary
traditional energy conservation techniques obligation every month for generation
ineffective. The high difference between the and transmission cost. However, in the
IJE

actual power and the contracted capacity distribution charge, monetary savings will be
results to a higher cost of Guaranteed realized through improved Guaranteed
Minimum Billing Demand (GMBD), and Minimum Billing Demand (GMBD).
develop the standby loss in energy bill every Stakeholders of RTU are becoming
month. By using the difference between more aware in efficient use of electric energy.
the actual load and the existing value Normally, operating more loads in lightings,
of GMBD determine the amount of idle small appliances, motors, air-conditioning
power. Distribution charge of monthly units and other power equipment increase
electricity bill reduces significantly through the supply requirement of electric energy,
recontracted capacity. The improved GMBDs which results to high electric bills. The
shows an optimum cost of electricity and administration has developed a program to
saves for more than half a million pesos each control and conserve the use of electric
year in Rizal Technological University. energy. Effort has been made to cut and limit
the utilization of electricity, which eventually
Keywords - GMBD, improving GMBD, caused a considerable amount of saving.
effects of GMBD, distribution cost, energy However, despite of the determination by
bill, electricity bill, energy conservation, school authority to reduce the amount of
unbundled cost, EPIRA Law, RA 9136, electricity bills, still the bill amount each
monetary savings, standby loss, potential month is relatively the same high. In this
monetary loss, potential monetary gain, study, the analysis for the effects of improving
RTU energy bill, MERALCO bill, utility bill. GMBD in the reduction of electricity bill
is presented as experience in RTU.

IJERTV2IS110518 www.ijert.org 1496


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

1.1. Energy Conservation Background distribution charge. Despite of the actual


consumption of power is lower than the
About 20% of electric energy is GMBD, but still the amount of minimum
intended to lighting purposes for the school demand at the fixed cost is the basis of
setting like RTU. This percentage attracts the charging energy.
school administration to enhance lighting The predefined value of GMBD
efficiency to reduce the power consumption was subjected for the computation of
and thus, energy bills. And so, the approach distribution cost. Regardless of the amount
will be done through replacing types of lights, saved below the minimum demand (GMBD),
which consider the location, condition and the prevailing charge is based on the
appropriateness of the lamp. contracted value of GMBD. The disadvantage
In the study conducted by Santos, et al was found in the increase of net difference
[10] had showed of about 45% consumption between the actual load and the GMBD due to
of electricity in RTU was applied for Air energy conservation program applied by the
Conditioning Units (ACUs). They suggest that institution.
by selecting high efficient ratio with periodic The solution for the holistic approach
maintenance of equipment would save utility has presented through improved GMBD.
cost and increase the performance of the The value of GMBD will calculate to
machine. Further, it was observed that a high match the actual consumed power based
efficiency motor reduces the required amount on the 12-month recent electric bills.
of energy to run. This effective machine has This computation will optimize the energy
RT
showed significant cost of return that prolongs conservation methods and realize the
life and increases the productivity due to monetary savings for electricity bill. The
maximum tardiness [9]. Also, the significance standby monetary loss was eliminated each
IJE

in the creation of Energy Management is month. Also, the idle power will utilize by
highly recommended for the overall impact in operating the actual connected loads relatively
saving electric energy [11]. the same or greater than the value of GMBD.

1.2. Problem in Energy Reduction in RTU and 2. Review of Related Literature


Its Solution
The increase of electric energy bill
Current techniques and methodology is due to different factors. From generation to
mentioned above in reducing the monthly distribution system, the unbundled cost are
electricity bills were considered part and collectively added and made significant
parcel in the totality of solution. Since, these impact for the monthly energy cost. Details of
energy saving practices would only affect the parameters are available in the statement
directly the generation and transmission cost of account given by the utility company
of the consumed power. However, in the to their customers. The complex parameters
distribution charge, the approach use by RTU imposed by utility company lead most of the
is relatively ineffective to earn monetary clients from residential to industrial sector to
saving. The actual consumed power decreases develop a methodology in reducing energy
due to traditional energy saving techniques. consumption. And so, an optimization in
In effect, the difference between the actual energy usage of RTU renewed continuously to
connected load and the value of GMBD decrease energy demand and derive the
increases. In such condition, the idle power potential monetary savings.
magnifies monetary losses in the part of

IJERTV2IS110518 www.ijert.org 1497


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

2.1. Current Practices to Mitigate the Increase sacrificing the illumination level required
of Electric Energy Bill in the area. Basically for the typical school
like RTU, energy consumption for lightings
In general, the unbundled bill has has about 20% maximum. Study conducted by
seven (7) parts that shows in statement EE faculty group in RTU [10] reported that
of the account. These are the generation, the estimated 18% of energy in lightings
transmission, and distribution cost. Also alone would be drastically reduced through
includes system loss, subsidies, government retrofitting.
taxes, and universal charges. Based on EPIRA The retrofit technique described by E.
law, the first three (3) of these elements Franconi and F. Rubinstein [6] was related to
are the dominant factors that affects the the effects of room temperature. According to
percentage cost of energy, which practically this study, the lightings with the decreased of
taken the total charge of electricity. power rating without losing the luminance
Generation charge was referred to the level had found less contribution of heat and
cost of power, which generated and sold to the thereby saved the energy exerted by the ACUs
distribution utility by the National Power in the area. The combination of lighting and
Corporation (NPC) as well as the Independent heat energy consumption were converted into
Power Producers (IPPs). The transmission monetary savings.
charge was the regulated cost for the use of a Study in lighting controls [7] revealed
transmission system that may include the the significant potential energy savings in
availment of ancillary service. While the commercial buildings. Like the lighting layout
RT
distribution charge was dedicated to regulated of RTU, when the switches and controls are
cost of building, operating and maintaining properly specified, installed, and maintained;
the distribution system, which brings power lightings will be utilized according to its need.
IJE

from high-voltage transmission grids, to Also, the results of the study [1] implied
commercial, industrial establishments, and to the possibility of identifying general patterns
residential end-users. of user control behavior as a function of
Loads of the RTU are classified indoor and outdoor environmental parameters.
in lightings, small appliances, electrical Currently, an LED shows aggressive
equipment and machineries, which includes in the market with a decreased in power rating
air conditioning units and pumps. Currently, and free from energy loss consumed by the
the methods of the institution to save ballast. An LED described the superiority in
the consumption of energy were described terms of electrical ballast, lamp operational,
into four (4) approaches. These techniques system efficiency, and light output. The
imposed by the administration are (a) technology is used an AC/DC converter to
retrofitting for lightings with lamp type emulate the required input impedance for the
replacement, (b) acquisition of motors with ballast output, which convert the high-
high efficiency, (c) periodic maintenance, and frequency AC power from the ballast into DC
(d) force conservation for the utilization of power as an LED input [4]. Further, 30% of
electric energy. energy consumption in the building can save
Improved lighting efficiency was in lighting system by using the LED. Study
treated as the simple ways to lower energy suggested the replacement of the LEDS or
bills. The decreased of energy consumption O-LEDs (organic-LED) for the existing old
has derived easily by retrofitting and replacing lamps. Substantial savings incurred due to
an appropriate types of lamp without good performance of the new develop in

IJERTV2IS110518 www.ijert.org 1498


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

lighting application [12]. Grgrgrgrgrg hrtgrgr implementation of periodic maintenance [5].


rg5rrgr.Acquisition of motor with high Hgrh. The force conservation for utilization
efficiency equates to significant cost of of electric energy by RTU has been
savings over the life span of the machine. contributed in saving of power. Elevators that
The increase of more than 20% due to high consumed much power were used in special
efficiency has an impact in the performance occasions, and those people who have
of the machine in terms of productivity difficulty in using stairs. These relatively
and reliability. Motors found in industrial and large machines are capable to save more
commercial establishments were consumed energy, and subsequently converted into
high energy of about 70% maximum in total monetary gains. The ACU’s for selected
electricity bill. In the experimental study classrooms and administrative offices were
conducted by R. Saidur [13] that the highest run at definite time and fully shutdown
amount of loss takes place at the rotor and in break time. Further, these approaches
stator parts of a motor. It explained that this had considered useful in the conservation of
area can be treated as potential spot for energy for lightings and small appliance
savings by reducing its loss. Also, the study loads.
was found that about 75% of motors are
operated below 60% and some are 40% of the 2.2. Problems of the Existing Practices in
load. It was further reported that motors Dealing with Energy Bill
perform better when operated of not less than
75% of the load. The methodologies used by RTU are
RT
Through electronic converter to create only part and parcel in the holistic approach
variable-speed, the motor efficiency increase in the reduction of electrical consumption.
remarkably. Study conducted by B.C. Mecrow The above four (4) approaches described were
IJE

and A.G. Jack [3] reported the increase only affected directly the generation and
in the efficiency of systems driven by transmission charges. But these techniques are
electrical machines with 7% reduced electrical independent in part of distribution charge.
consumption. Based on the analysis, despite Despite of effort to conserve electric
the high initial cost in investing variable energy through different forms, still the
speed drive (VSD), the payback period found distribution cost was explicitly increased.
relatively short. Since, the current practice in energy
The same results confirmed in a conservation focuses only to decrease the
comparative study conducted by Slobodan generation and transmission charges.
Mirchevski [14], which the cost of electric Subsequently, the net difference in power
energy using the standard motor has doubled increase between the actual load consumed
as compared to high efficient motor. and the value of Guaranteed Minimum Billing
Study was significantly found that under Demand (GMBD).
some reasonable condition of the motor, The GMBD is a predefined amount of
the production affected with respect power based on the total power of the
to the status of the machine [15]. electrical plan, which submitted by RTU to
Machine is highly recommended to the utility company (MERALCO). In
develop an optimal preventive maintenance compliance under Section 36 of RA 9136
policy due to effects of deteriorating system. (EPIRA Law), MERALCO proposed the
The prediction in this study explained in a minimum billing demand to 70% of the
minimal repair for each failure under the contracted capacity or not less than 40 kW for

IJERTV2IS110518 www.ijert.org 1499


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

General Power (GP) and 5 kW for General converts monetary savings. Efger efe efef fe
Service-B customers. In this provision, the ewfe. Study conducted by Cabugayan [2] in
utility company approved by the Energy energy management and savings ascertained
Regulatory Commission (ERC) to recover the that the equivalent cost of electric supply
reasonable investment made in distribution was not fully utilized. Further, the actual
assets to provide a contracted capacity to a consumption of power represented as the total
consumer. cost of energy bill with the inclusion of
In effect as ordered by Energy some empirical calculations. These complex
Regulatory Commission (ERC) that even if calculations ensure the utility company for
the actual demand falls below the contracted the return on their investment. However,
level of GMBD, the distribution charge must this non-related energy cost in distribution
be based on the kW of GMBD (ERC Case part has affected considerably the monthly
Nos. 2008-004 RC and 2008-018 RC). This electricity bill.
rule made the traditional energy conservation Importantly, stationary loss was
ineffective without the adjustment in GMBD. detected on the effects of the high contracted
Ultimately, the net difference between the demand. This perpetual loss that converted
actual load and GMBD translated in a monetary loss has seized through revision of
considerable amount of monetary loss in part the recontracted capacity.
of distribution charge. This value reflected to Standby losses were eliminated
the total bill amount each month with large without any investment, which created by
standby losses each year. common methodologies in the conservation of
RT
energy. The monthly electricity bill was
2.3. Holistic Approach in Conservation of estimated low in part of distribution cost
Energy to Reduce Electricity Bill through recontracted capacity and the new
IJE

value of GMBD.
The value of GMBD depends on
the amount of power treated as contracted 3. Methods and Procedures
capacity. An improved GMBD has optimized
the contracted capacity based on the actual In recent energy record, the energy
utilization of energy that affects the meter for ITC and Old Building has operated
distribution part significantly. significantly below GMBD. Subsequently,
At present, studies about the GMBD the institution’s conservation of energy has
have found critically unavailable. However, increased the difference between the GMBD
utility company was cooperated with their and the actual consumption of power. In
clients to improve further the utilization of effect, the amount charge of power by RTU
energy in any methods legally. Almost all of each month has remained relatively the same.
the customers of MERALCO were preferred
to common techniques in saving electric 3.1. Profile of the Location Buildings
power. Most of these common methods for
power saving have treated only the generation Three electric utility service meters are
and transmission charges in the electricity bill. installed in RTU and classified as General
Significantly, the combination of four Power applied in educational institution.
(4) approaches discussed above and the The combined ITC and Old Building has a
improvement of the GMBD were considered Service Id Number (SIN) 800878201, for the
holistic approach in reduction of power that Administration Building given with SIN

IJERTV2IS110518 www.ijert.org 1500


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

800878001, and two collective buildings of for the maximum and minimum values of load
MAB and GSRC, which registered as SIN factor (L.F.). These values were used in the
986305201. empirical formula for the new GMBD to
Loads are composed of lightings, prevent the overshoot value of recontracted
power, motors, and other auxiliary equipment. capacity.
These are typically operated from 7:30 in the The improved GMBD simulates the
morning to 9:30 in the evening. The school monthly bills from January to December with
has consumed more electric energy from demand charge for the year 2012, and thereby
Monday to Friday as compared to Saturday derive the estimated monetary savings.
and Sunday. This behavior is due to the
presence of combined loads of the 3.3. Statistical and Empirical Treatment
administrative offices and classes related
activities. The data was tabulated by month from
January to December of 2012. The maximum
3.2. Research Design and minimum values are evaluated using the
spreadsheet program for energy consumed,
The study involved applied research actual load, load factor, and the amount of
to solve the high electricity bill in part electricity bill. While the technique applied to
of distribution cost and thereby define measure the central tendency is given by the
the potential monetary savings in Rizal following expression,
Technological University (RTU).
RT
The data derived from utility company X
X  ............................... (1)
for the year 2012 from January to December N
electric bills. From this information, the
IJE

existing contracted capacity for the two where the X is the arithmetic mean (or
service meters and their GMBDs determined. average),  X for the sum of all elements of
The service meter 800878001 has no record the variables and N is referred to the total
for the demand capacity due to update issue in number of cases.
the account for SIN.
The amount of GMBD determined for  LF 
the comparison on the actual consumption of New GMBD  kWmax  ave  ................... (2)
power used by RTU. Each of the two service  LFmax 
meters installed within the premises are
evaluated their electric bill. The differences The equation 2 for new GMBD refers
are computed in terms of kilowatts (kW), to the recomputed Guaranteed Minimum
which refers to demand capacity and actual Billing Demand (GMBD), and the kWmax is
power consumed. The net values are analysed the maximum actual consumed power by
to estimate the idle power caused by GMBD. RTU. The LFave and LFmax are referred to the
This excess power was used in the load factors in average and maximum,
computation of recontracted capacity after the respectively. The ratio between the average
new GMBD determined. Since the variation and maximum load factor has predicted to
of loads depends on utilization of electric capture the swing of actual loads in deviating
energy with respect to time, consumption of further in the new GMBD value. While the
load requires under the proposed recontracted maximum consumed power (kWmax) estimate
capacity. In this case, the calculation develops the probability spike of actual loads to avoid

IJERTV2IS110518 www.ijert.org 1501


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

overshoot in the value of recontracted By using equations 5 and 6, the two service
capacity. meters of RTU developed their monetary loss
The recontracted capacity (RC) in (ML) and savings (MS). These meters are
equation 3 expressed as the product of GMBD referred to SIN 800878201 for ITC and Old
with an increase factor of 1.43. This Building, and SIN 986305201 for MAB and
expression in kW determined the proposed GSRC Building.
contracted demand required by the utility
company. Further, the calculated value ML  Existing GMBD x DC per month ...... (5)
compensates the outright rule by the
MERALCO in the application of 70% from MS  New GMBD x DC per month ........ (6)
the contracted capacity.
The projected monetary savings due to
RC  1.43 x New GMBD .................... (3) recontracted capacity determined through
implementation of the improved GMBD that
The load factor (L.F) defined as the simulated into 12-month of the year 2012. The
ratio of average and the peak load for the total generated savings of RTU derived from
specified period of time. This fraction the difference between equations (5) and (6).
explains that a system with high load factor
consumed relatively constant in power. In 4. Results and Discussion
contrast, the low value in load factor shows an
The financial loss in two (2) of three
RT
instantaneous high demand of power. To
serve such amount under short period of time, (3) service meters of RTU each month existed
capacity is set in idle for long periods. As a because of idle power. The amount of power
loss reflected significantly in part of the
IJE

result, the system imposed higher cost of


electric energy in RTU. distribution charge. Moreover, the amount of
electricity bill increased as seen in load profile
caused by utilization of electric power below
Average Load
L.F  ... (4) the GMBD value.
MaxLoad in a given time period
4.1. Characteristics of Electrical Loads in ITC
In Equation 4, the load factor (LF) is and OB Building
significant in the variation of loads from
average to a peak value. This change that In 12-month of 2012, the ITC and Old
relative in time of consumption has used in Building found an average consumed energy
equation 2 to set the boundary of variation of of about 90,000 kWhr (Table 1). The amount
the actual load. The estimated boundary of energy brought about 34% in load factor
without monetary loss remained in between when the peak power occurs with respect to
the value of new GMBD and the recontracted average power. The changed about 9% in load
capacity. factor from average to maximum showed
The monetary loss existed due to considerably high, and thereby increased the
relationship of the existing GMBD to the idle power of the system. An average of 366
demand charge per month. These values of kW of the actual consumed power pronounced
GMBD are constants based on the 70% a high mean power factor of 91%. These
contracted capacity. While the demand charge values explained relatively well in terms of
(DM) per month vary from time-to-time balanced loads for the inductive equipment.
caused by the parameterization of electric bill. This condition earned an incentive from utility

IJERTV2IS110518 www.ijert.org 1502


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

company for the operation of the system because of double reading rule by the utility
above 85% in power factor. Average monthly company.
electricity bill soared to about 944,000 pesos. Normally, the amount due for
The maximum recorded energy cost of about electricity bills takes place twice either by
1.3 million pesos announced noticeably in December or January. This default system
July for the ITC and Old Building alone. This of MERALCO conformed to the audit matters
month belongs to first semester of the for closing of book at the end of the year.
academic year of 2012. However, the In this condition, the demand charge
minimum amount of 120,000 pesos in energy significantly increased in part of the
bill occurred in second semester for the half distribution cost even the total bill amount
month of January. decreased.
Significantly, the actual consumed
power in ITC and Old Building observed a 4.3. Characteristics of Electrical Loads in
considerably lower value than the 515 kW of Administrative Building
Guaranteed Minimum Billing Demand
(GMBD). Further, the average value of 366 In three service meters of the RTU,
kW and even the maximum of 422 kW only the Administrative building has no
of the actual consumed power showed record on their minimum demand (GMBD)
comparatively less than the existing GMBD of (Table 3). However, energy profile explicitly
515 kW. Considerably, the 30% difference showed the good performance of the load
described relatively large between the GMBD with an average of 94% power factor and 96%
RT
and the actual consumed power. This net under maximum value. The value explained
value implied for the opportunity in reducing that the system in terms of inductive
electrical consumption. loads revealed considerably small. Even at
IJE

the condition of minimum value, this


4.2. Characteristics of Electrical Loads in Administrative Building received an incentive
MAB and GSRC Building as a discount for taking the high ratio of true
power to apparent power. The maximum
The maximum energy was consumed energy cost of 668,000 pesos existed in July,
of about 80,000 kWhr and 288 kW for the which found the same in Table 4.1 and 4.2 as
actual power (Table 2). The expense for the highest recorded electricity bill. While in
electricity bill reached around 873,000 pesos, January, this account reflected the minimum
which occurred in July. In terms of variation charge of energy with 40,000 pesos. The
of peak with respect to average value, average values recorded are 43000 kWhr, 189
this service meter found relatively the same as kW and 31 percent for energy consumed,
the load factor with 43% in Table 1. actual power and load factor, respectively.
The maximum power factor of the system
slightly decreased of about 88% but 4.4. Load Profile with High Potential
significantly low in its average value with Monetary Savings
87%.
Total charged of electricity for MAB The load profile of ITC and Old Building
and GSRC Building reached to 623,000 pesos showed its high possibility for potential
in average with less than 30% difference of monetary savings. With 366 kW average and
energy expenditure in ITC and Old building. 422 kW peak power for the actual utilization
Minimum energy cost recorded in January described significantly far to the 515 kW of
the

IJERTV2IS110518 www.ijert.org 1503


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

GMBD. The prospective value of about 149 showed relatively constant in terms of
kW as the difference between the actual percentage in energy cost, which varied from
consumed power and the GMBD indicated the minimum of about 10% to maximum of 20%.
possibility of conversion into monetary While the average of the transmission cost for
savings. However, the discrepancy of average ITC and Old Building recorded of about 13%.
power of 253 kW with 264 kW GMBD The generation sector with an average of 54%
of MAB and GSRC Building treated as and closed to the maximum value of about
practically low. This difference of about 11 60% with 32% minimum shared. These
kW showed comparatively small to the fractions reciprocated in distribution charge,
ITC and OB Building for saving electrical which the average of 14% near to 11%
consumption. It means that the consumption minimum value at 33% maximum were
of power in MAB and GSRC Building resulted twice as the average percentage. This
utilized nearly the same at the fixed value of erratic changed of about 33% in maximum
its GMBD. showed under distribution part (Figure 1.a).
The service meter for ITC and Old The amount increased in distribution
Building recorded as the largest idle power. spiked the energy cost of December and
This standby power affected directly January due to double reading done by the
the distribution cost. Because of over utility company. The energy demand in kW
calculation of electrical design submitted, the considered substantially low during vacation
utility company (MERALCO) received a in December. Despite of the decreased in
considerable amount of contracted capacity. demand, the distribution charge remained high
RT
Subsequently, the value of 515 kW GMBD due to explicitly dependent to the GMBD
derived in seventy percent (70%) of of 515 kW. The characteristic curves of the
the contracted capacity. Consequently, the breakdown of electric energy charges in
IJE

registered demand cost and thereby Figure 1.b showed relatively the same as
contributed to high electricity bill. While the depicted in Figure 1.a. The abrupt changed
electrical system designs of MAB and GSRC in percentage for the distribution cost
building obtained nearly the same on observed of about 33%, which also
their actual power consumption. Also, the experienced in MAB & GSRC Building.
contracted capacity of about 377 kW resulted The projected curves of 264 kW GMBD
to 264 kW GMBD, in which the value showed described comparatively identical with 515
considerably the same on the existed 253 kW kW GMBD in terms of percentage breakdown
average power consumption. The actual for electricity charges. Other parts like
consumed power of Administrative Building system loss, subsidies, government taxes and
with an average of 189 kW was excluded for universal charges are practically constants.
evaluation because of availability of GMBD
record. 4.6. Losses in Distribution Charge for Two
Service Meters Based on GMBD
4.5. Percentage of Energy Cost Allocated in
the Unbundled Electricity Bill The account of ITC and Old Building
showed significantly their losses for the year
In seven components of the unbundled 2012. For the whole year, the idle power loss
electricity bill, the generation, transmission each month indicated relatively high. These
and distribution sectors revealed the majority losses in the buildings affected the consumed
of percentage shares. The transmission part power, which operated at less than the

IJERTV2IS110518 www.ijert.org 1504


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

prescribed GMBD. Fguuf buiyfu8rbrf8irb standby power loss, in which there is no


ryfh8rThe month of November registered the monetary loss incurred. While, the month of
highest monetary loss of nearly 50,000 pesos November consumed the actual load for about
in Figure 2. This amount worth noticeable in 263 kW. This amount of power considered
Table 1 for the month of January with lowest practically the same as compared to the
actual load of 159 kW, and this supposedly in existing 264 kW of GMBD. These buildings
principle the largest monetary loss in part of in terms of utilization of electricity consumed
distribution cost. However, the demand in almost the same amount of present GMBD.
charge for January for only about 103 pesos This advantage revealed in the distribution
described more than twice as compare with charge for paying only the actual consumed
278 pesos in November. This condition power of the loads.
explained the month of November emerged as The overall monetary losses for
the largest monetary loss than the month of the two service meters escalated to half a
January. Further, about 188 kW difference on million pesos for the year 2012. This total
their actual consumption of load showed loss projected to increase further due to
between the months of November and traditional energy conservation approached,
January. which widened the gap between GMBD
Aside from January, the lowest and actual loads. The demand charge
monetary loss for demand power traced in in part of distribution cost increased with
April of about 25,000 pesos. In this month, a considerable amount every year. Any
the actual load of about 422 kW with changes in the increase of this variable affect
RT
net difference of 93 kW developed from significantly the monthly electricity bill.
515 kW of GMBD. The discrepancy in power
utilization of 93 kW with 263 pesos demand 4.7. Monetary Savings with the Improved
IJE

charge showed relatively the same for the GMBD in Part of Distribution Cost
month of January. In this month, the 356 kW
at 103 pesos demand charge translated in The combined amount of monetary
terms of monetary loss under the distribution losses for about half a million pesos in two
part. service meters acquired due to existing values
Collectively, the two service meters of of GMBD. These collective losses in year
the ITC and OB, and the MAB and GSRC 2012 considered as wasted power for about
Buildings are subjected to standby monetary 1942 kW and 201 kW for SIN 800878201 and
losses of about 450,000 pesos. The monetary SIN 986305201, respectively (Table 1 and 2).
loss established of not less than a half million These values are translated into monetary loss
pesos each year due to the presence of idle of more than 450,000 pesos, which found in
power caused by GMBD. the distribution part. Through the improved
In MAB and GSRC Building, the 337 kW GMBD for the ITC and Old Building,
monetary losses occurred only in the months the losses significantly terminated for about
of January, February, April, and May with a 450,000 pesos. Except the first half of January
total of about 29,000 pesos. The month of with 18,000 pesos monetary loss remained
January showed the highest losses of about (Figure 4.a). The existing value of 515 kW
19,000 pesos in part of distribution charge as GMBD reduced to an improved 337 kW
shown in Figure 3. The remaining seven (7) GMBD, which calculated using an empirical
months are operated above the value of 264 formula. This new GMBD observed their
kW GMBD. These months are free from the importance for the suppressed losses annually

IJERTV2IS110518 www.ijert.org 1505


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

of not less than 450,000 pesos. Aside from dedicated to Administrative Building, the
this optimized loss in part of distribution cost, contracted capacity existed under an update
a considerable saving of not less than 127,000 of SIN issue. In such case, the actual
pesos realized each year. Essentially, the consumption of power treated as the GMBD
monetary savings by way of the improved value. The quantification of monetary loss
GMBD generated of not less than a half experienced the difficulty in distribution
million pesos annually. charge under this service meter. However, the
However, the MAB and GSRC two remaining service meters collectively
Building performed better than the ITC earned a projected monetary loss more than
and Old Building in terms of GMBD and half a million pesos each year in part of
the actual consumed power. The 264 kW distribution cost.
existing GMBD of MAB and GSRC Building Through application of the improved
relatively realized the actual load in kW. The 225 kW GMBD, it revealed significantly
sum of the net difference between the GMBD the removal of loss about 29,000 pesos.
and the actual utilization of power reached Moreover, this adjustment saved of more
for about 201 kW in four (4) months of than 20,000 pesos each year for SIN
the year 2012. These values converted into 986305201. The total monetary savings
29,000 pesos monetary loss for the months incurred comparatively low of about 49,000
of January, February, April and May. pesos. But the greater impact in computation
Consequently, the potential monetary of the new GMBD pronounced in ITC and
savings as simulated the improved 225 kW Old Building. The improved 337 kW for
RT
GMBD resulted for about 49,000 pesos SIN 800878201 eliminated the monetary
each year (Figure 4.b). Significantly, the loss each year of about half a million
distribution charge drastically reduced by pesos. Aside from this significant reduction
IJE

improved values of contracted capacity and in part of distribution cost, it saved further
GMBD, in which the monetary savings in the additional amount of 127,000 pesos
electricity showed relatively high (Table 4). annually. Improvement in the existing GMBD
Based on electrical design submitted, the ITC generated a monetary savings of about half a
and OB reached the contracted capacity of million pesos for the ITC and Old Building
about 736 kW. From this value, the 515 kW alone. The combined savings for two service
GMBD derived at seventy (70%) percent meters of the RTU asserted the amount
contracted capacity. This constant value for greater than a half million pesos each year.
the minimum demand developed the idle This explained the optimization of energy
power, which translated to monetary loss of usage that consumed above the GMBD value,
about half a million under the distribution and thereby the system removed the idle
charge yearly. power that caused monetary losses.
While the MAB and GSRC, the
contracted capacity resulted to 377 kW with 5. Conclusions
264 kW GMBD. This value produced a
monetary loss of about 29,000 pesos in part The method described the difference
of distribution cost. The amount observed that between the GMBD and the actual energy
SIN 986305201 performed better than SIN consumption. The net values had extracted for
800878201 in terms of efficient used of two service meters in ITC and OB and the
electric energy with respect to GMBD value. MAB and GSRC with 216.78 kW as standby
For the account of SIN 800878001 losses. Source of monetary loss discovered

IJERTV2IS110518 www.ijert.org 1506


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

from distribution charge due to unused power validated if the net difference between GMBD
about half a million pesos annually. and the actual loads has promoted.
Calculation developed in this study to In the prospective of holistic approach
derive the improved contracted capacity and for energy management [8], the study strongly
thereby the new GMBD. More than half a suggest in the administration to develop the
million pesos a year saved without any initial so called, RTU – Energy Group Management
investment through eradication of idled power (RTU-EGM). The group has recommended as
and from the residues in recontracted values. the overall in-charge for evaluation, planning,
The optimization values ascertained in and implementation for the optimization in
two accounts with 482.51 kW for ITC and OB energy use (Figure 5).
and 321.66 kW for MAB and GSRC, and The customer of MERALCO with
collectively have residues gained of 147,000 energy demand of more than 40 kW should be
pesos annually. periodically evaluated their discrepancy
The implementation in conservation of between GMBD and the actual consumed
energy found within the premises of the power. Most particularly, if the energy
school has established their significant impact conservation has been campaigned, and the
in generation and transmission charges. consequence has found sufficiently high
However, this strategy has widened the gap difference, this research recommends the
between GMBD and the actual load, and computation of new contracted capacity, and
subsequently increased the unused power that this should be presented to utility company.
transmutes high monetary loss in distribution
RT
part. 7. References
The adverse implication established
due to excessive electrical design as referred [1] A. Mohammadi, E. Kabir, A. Mahdavi,
IJE

to contracted capacity. The finding suggests and C. Pröglhöf, “Modeling User Control
that the tendency of high difference between of Lighting and Shading Devices in Office
GMBD and the actual load capacity of the Buildings: An Empirical Case Study”,
ITC and OB has found significantly under Proceedings: Building Simulation 2007,
extremely over power design that leads to Vienna University of Technology, Vienna,
high kW contract of RTU to utility company. Austria, 2007.
However, the MAB and GSRC electrical
design has showed effectively in terms of [2] A. T. C. Cabugayan, “Electrical Energy
electricity bill, and the result has revealed that Analysis for Energy Management and
the standby power loss was essentially small. Savings: The New Era University
Experience”, Knowledge, vol., 2, pp., 6 and
6. Recommendations 14, New Era University, Milton Hills, Quezon
City, 2003.
To terminate the significant monetary
loss in energy bill each month of RTU, the [3] B. C. Mecrow, and A. G. Jack, “Efficiency
administration should be given the priority in Trends in Electric Machines and Drives”,
ITC and OB account to reapply the existing Foresight Sustainable Energy Management
contracted capacity to MERALCO. However, and the Built Environment Project, Energy
this study was conducted in year 2012, and so Policy, Volume 36, Iss.12, pp. 4336–4341,
it is important that the current bills should be December 2008.

IJERTV2IS110518 www.ijert.org 1507


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

[4] C. Nan and W. Jianjing, “A Driving [11] P. Thollander and M. Ottosson, “Energy
Technology for Retrofit LED Lamp management practices in Swedish Energy-
for Flourescent Lighting Fixtures with Intensive Industries”, Journal of Cleaner
Electronic Ballasts”, Department of Electronic Production, (18), 12, 1125-1133, 2010,
Engineering, Final Report, OEPA 2009-2010,
Hong Kong, 2010. [12] R. Faranda, Ş. Guzzetti, C. Lazaroiu, and
S. Leva, “LEDs Lighting: Two Case Studies”,
[5] C. Y. Cheng and M. C. Chen, “The U.P.B. Sci. Bull., Series C, Vol. 73, Iss.1,
Periodic Preventive Maintenance Policy for 2011.
Deteriorating Systems by Using Improvement
Factor Model”, International Journal of [13] R. Saidur, “A Review on Electrical
Applied Science and Engineering, 1, 2: 114- Motors Energy Use and Energy Savings”,
122, 2003. Elsevier Ltd., Renewable and Sustainable
Energy Reviews 14 (2010) 877–898, 2009.
[6] E. Franconi and F. Rubinstein,
“Considering Lighting System Performance [14] S. Mirchevski, “Energy Efficiency in
and HVAC Interactions in Lighting Retrofit Electric Drives”, Electronics, vol.16, No.1,
Analysis”, IEEE-IAS Annual Conference, June 2012.
Houston, TX, October 4-9, 1992.
[15] T. W. Sloan, “A Periodic Review
[7] F. Rubinstein, D. Avery, and J. Jennings, Production and Maintenance Model with
RT
“On the Calibration and Commissioning of Random Demand, Deteriorating Equipment,
Lighting Controls”, Proceedings of the Right and Binomial Yield”, USA Journal of the
Light 4 Conference, Copenhagen, Denmark, Operational Research Society, 55, 647–656,
IJE

November 19-21, 1997. 2004.

[8] M. Krati, “Energy Audit of Building


Systems – An Engineering Approach”, 2nd
ed., Taylor & Francis Group, LLC, Boca
Raton, FL 33487-2742, 2011.

[9] M. Sbihi and C. Varnier, “Single-machine


Scheduling with Periodic and Flexible
Periodic Maintenance to Minimize Maximum
Tardiness”, Computer & Industrial
Engineering 55, pp. 830-840, 2008.

[10] P. S. Advincula, L. E. Bascao, R. C.


Cruz, Jr., R. J. Dichoso, R. M. Santos,
“Energy Audit Of Rizal Technological
University – Boni Campus: Building A
System For Energy Conservation”, Research
Paper in Executive Master Program (thesis),
GS RTU, April 2012.

IJERTV2IS110518 www.ijert.org 1508


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

Table 1. Load Profile of Service Id Number 800878201 for


the 12-month of the year 2012 in ITC and Old Building.

Energy Actual Load Total


P.F.
MONTHS Consumed Load Factor Amount Due
(%)
(kWhr) (kW) (%) (Pesos)
Jan 5200 158.80 11.37 90.80 119984.18
Jan 70400 362.80 42.55 90.25 695308.34
Feb 107200 393.60 36.61 90.37 1080362.55
Mar 110400 405.20 39.15 91.22 1066524.23
Apr 84800 422.40 26.98 91.42 930129.15
May 85600 358.80 33.14 92.33 906744.67
Jun 76000 358.40 28.50 91.64 896440.87
Jul 118000 401.60 40.81 91.16 1302690.58
Aug 99200 364.00 36.63 89.87 1160362.44
Sep 109200 384.80 38.14 89.77 1063628.82
Oct 116000 400.80 40.20 90.42 1129132.80
Nov 72800 346.80 28.21 90.61 820881.89
RT
Dec 112400 394.80 39.54 90.76 1091457.56
MAX 118000 422.40 42.55 92.33 1302690.58
AVE 89785 365.60 33.99 90.82 943357.54
IJE

MIN 5200 158.80 11.37 89.77 119984.18

Table 2. Load Profile of Service Id Number 986305201 for the


12-month of the year 2012 in MAB and GSRC Building.
Energy Actual Load Total
P.F.
MONTHS Consumed Load Factor Amount Due
(%)
(kWhr) (kW) (%) (Pesos)
Jan 5280 135.20 13.56 86.66 92021.30
Jan 44320 228.00 42.63 85.78 432573.85
Feb 63680 251.36 34.05 86.20 644716.61
Mar 68000 266.56 36.65 87.25 656992.50
Apr 58080 254.24 30.71 86.25 609336.89
May 63840 251.04 35.32 88.22 645410.86
Jun 62240 288.48 29.00 86.95 703405.57
Jul 79680 281.76 39.28 88.28 872460.01

IJERTV2IS110518 www.ijert.org 1509


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

Aug 67200 268.00 33.70 85.39 778674.68


Sep 70880 270.88 35.17 85.39 687199.69
Oct 71200 265.28 37.28 86.09 693433.82
Nov 50240 262.72 25.70 84.95 557124.67
Dec 76000 270.40 39.04 87.49 724768.34
MAX 79680 288.48 42.63 88.28 872460.01
AVE 60049 253.38 33.24 86.53 622932.21
MIN 5280 135.20 13.56 84.95 92021.30

Table 3. Load Profile of the Unknown GMBD with SIN 800878001


for the 12-month of the year 2012 in Administrative Building.
RT
Energy Actual Load Total
P.F.
MONTHS Consumed Load Factor Amount Due
(%)
(kWhr) (kW) (%) (Pesos)
IJE

Jan 2800 72.80 13.35 96.15 39483.58


Jan 21600 122.40 38.70 92.61 209217.90
Feb 31200 128.40 32.66 92.93 312056.01
Mar 49200 210.00 33.66 94.63 482522.14
Apr 43600 196.00 29.90 94.15 448813.46
May 47600 210.80 31.36 95.03 489728.11
Jun 42000 203.20 27.78 94.59 477355.57
Jul 60400 229.60 36.54 94.55 667546.02
Aug 50800 214.40 31.85 93.30 591771.15
Sep 54400 220.40 33.18 93.17 530111.87
Oct 56400 214.80 36.47 93.16 547613.36
Nov 40800 203.20 27.00 93.10 440903.48
Dec 58400 234.40 34.60 93.79 568406.51
MAX 60400 234.40 38.70 96.15 667546.02
AVE 43015 189.26 31.31 93.94 446579.17
MIN 2800 72.80 13.35 92.61 39483.58

IJERTV2IS110518 www.ijert.org 1510


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

(a)
RT
IJE

(b)

Figure 1. The seven components of the unbundled electricity bill and breakdown the
allotted charges into percentage for (a) 515 kW and (b) 263.62 kW GMBD.

IJERTV2IS110518 www.ijert.org 1511


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

Figure 2. Losses of ITC & Old Building in distribution


charge due to 515 kW GMBD.
RT
IJE

Figure 3. Losses of MAB & GSRC Building in distribution


charge due to 264 kW GMBD.

263.62kW Demand

IJERTV2IS110518 www.ijert.org 1512


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

(a)
RT
IJE

(b)
Figure 4. The amount loss and monetary saving for the two service
meters under the Guaranteed Minimum Billing Demand
(GMBD) of (a) 515 kW and (b) 263.62 kW.

IJERTV2IS110518 www.ijert.org 1513


International Journal of Engineering Research & Technology (IJERT)
ISSN: 2278-0181
Vol. 2 Issue 11, November - 2013

Table 4. The Contracted Capacity and GMBD from existing to improved values
with an impact for the Distribution Charge annually.

RT
IJE

Figure 5. The life cycle of RTU – Energy Group Management (RTU-EGM).


The life cycle of RTU-EGM begins with the observation in energy bill. From this observed data, the
group will generate the recommendation on how to improve or maintain the optimum energy utilization. The
recommendation divides into two, the Efficient Electrical Equipment and Maintenance (E3M) and
recontracted capacity (RECONCAP). These two approaches will be applied to the loads to control the
generation, transmission and distribution charges, and thereby induce the effective monetary savings of the
institution.

IJERTV2IS110518 www.ijert.org 1514

Вам также может понравиться