Вы находитесь на странице: 1из 1

DATE 2 28 2018

BILL OF MATERIALS/ESTIMATE SHEET

PROJECT : STEEL CHAIRS FABRICATION (50 UNITS) G.I. PIPE SHEET NO.:
LOCATION : SAN FRANCISCO, AGUSAN DEL SUR 1 OF 1

MATERIAL EQUIPT.
ITEM NO.: ITEM DESCRIPTION UNIT QTY. UNIT COST LABOR COST TOTAL
COST COST

A FRAMING MATERIALS 32,640.00


1" X 2.0mm G.I. PIPE LNGTH 37.00 700.00 25,900.00
2mm X 3/4" X 3/4" ANGLE BAR LNGTH 22.00 220.00 4,840.00
WELDING ROD BOX 1.00 1,900.00 1,900.00

B FINISHING MATERIALS 71,485.00


3/4 MARINE PLYWOOD SHT 9.00 900.00 8,100.00
1" FLATHEAD SCREW (METAL) PC 750.00 0.50 375.00
COLORED FORMICA SHT 9.00 990.00 8,910.00
RUBBER EDGING MTR 260.00 195.00 50,700.00
RUBBER STOPPER (FOR 25mm PIPE) PC 300.00 10.00 3,000.00
METAL PRIMER GAL 1.00 400.00 400.00

C CONTINGENCIES 12,495.00
CONTINGENCIES LOT 1.00 12,495.00

D LABOR 41,650.00
LABOR COST LOT 1.00 41,650.00

TOTAL COST 158,270.00

Prepared by: Recommended by:

ALDRENE ROBERT S. BADILLA JENNY C. ABUCEJO


Project Base Architect Executive Vice-President

Approved:

ROSELYN P. CARLOS
President