BILL OF MATERIALS/ESTIMATE SHEET

PROJECT : STEEL CHAIRS FABRICATION (50 UNITS) STEEL TUBE SHEET NO.:
LOCATION : SAN FRANCISCO, AGUSAN DEL SUR 1 OF 1

MATERIAL EQUIPT.
ITEM NO.: ITEM DESCRIPTION UNIT QTY. UNIT COST LABOR COST TOTAL
COST COST

A FRAMING MATERIALS 37,950.00


1" X 1.5mm SQUARE TUBE LNGTH 50.00 700.00 35,000.00
10mm SQUARE BAR LNGTH 7.00 150.00 1,050.00
WELDING ROD BOX 1.00 1,900.00 1,900.00

B FINISHING MATERIALS 20,125.00


3/4 MARINE PLYWOOD SHT 9.00 900.00 8,100.00
1" FLATHEAD SCREW (METAL) PC 850.00 0.50 425.00
RUBBER STOPPER (25mm SQ. TUBE) PC 300.00 25.00 7,500.00
METAL PRIMER GAL 2.00 400.00 800.00
EPOXY ENAMEL GAL 2.00 1,100.00 2,200.00
EPOXY REDUCER GAL 1.00 500.00 500.00
TIMBERCOAT (GLOSS) GAL 1.00 600.00 600.00

C CONTINGENCIES 6,969.00
CONTINGENCIES LOT 1.00 6,969.00

D LABOR 23,230.00
LABOR COST LOT 1.00 23,230.00

TOTAL COST 88,274.00

Prepared by: Recommended by:

ALDRENE ROBERT S. BADILLA JENNY C. ABUCEJO


Project Base Architect Executive Vice-President

Approved:

ROSELYN P. CARLOS
President