Академический Документы
Профессиональный Документы
Культура Документы
ISSUE
For issue to all Ausgrid and Accredited Service Providers’ staff involved with the design and
construction of underground sub-transmission lines forming part of Ausgrid’s network, and
for general reference by field, technical and engineering staff.
Ausgrid maintains a copy of this and other Network Standards together with updates and
amendments on www.ausgrid.com.au.
Where this standard is issued as a controlled document replacing an earlier edition, remove
and destroy the superseded document.
DISCLAIMER
As Ausgrid’s standards are subject to ongoing review, the information contained in this
document may be amended by Ausgrid at any time.
It is possible that conflict may exist between standard documents. In this event, the most
recent standard shall prevail.
This document has been developed using information available from field and other sources
and is suitable for most situations encountered in Ausgrid. Particular conditions, projects or
localities may require special or different practices. It is the responsibility of the local
manager, supervisor, assured quality contractor and the individuals involved to ensure that a
safe system of work is employed and that statutory requirements are met.
Ausgrid disclaims any and all liability to any person or persons for any procedure, process or
any other thing done or not done, as a result of this Standard.
Note that compliance with this Network Standard does not automatically satisfy the
requirements of a Designer Safety Report. The designer must comply with the provisions of
the WHS Regulation 2011 (NSW - Part 6.2 Duties of designer of structure and person who
commissions construction work) which requires the designer to provide a written safety
report to the person who commissioned the design. This report must be provided to Ausgrid
in all instances, including where the design was commissioned by or on behalf of a person
who proposes to connect premises to Ausgrid’s network, and will form part of the Designer
Safety Report which must also be presented to Ausgrid. Further information is provided in
Network Standard (NS) 212 Integrated Support Requirements for Ausgrid Network Assets.
INTERPRETATION
In the event that any user of this Standard considers that any of its provisions is uncertain,
ambiguous or otherwise in need of interpretation, the user should request Ausgrid to clarify
the provision. Ausgrid’s interpretation shall then apply as though it was included in the
Standard, and is final and binding. No correspondence will be entered into with any person
disputing the meaning of the provision published in the Standard or the accuracy of
Ausgrid’s interpretation.
Network Standard
NS201
All Dielectric Self Supporting Fibre Optic Cabling for Installation
on Distribution Assets
February 2008
CONTENTS
1 INTRODUCTION ......................................................................................................... 1
1.1 Purpose ............................................................................................................ 1
1.2 Scope ............................................................................................................... 1
1.3 References and other relevant standards........................................................ 1
8 MINIMUM CLEARANCES............................................................................................ 7
8.1 ADSS Minimum Clearances from Aerial Fixed Attachments ........................... 7
8.2 ADSS Minimum Clearances from Ground ....................................................... 8
1 INTRODUCTION
1.1 Purpose
This document provides an overview of the minimum requirements that are to be
used when constructing an All Dielectric Self Supporting (ADSS) circular fibre optic
cabling system attached to Ausgrid assets.
An optical cable network must provide a very high service level for continuity of both
internal control networks and other services. Installation must be carried out by
experienced personnel in a professional manner in order to minimize the risk of
subsequent failure.
1.2 Scope
The intent of this document is to provide a general guide to the technical issues that
must be addressed in the design and construction of an ADSS communications
network on Ausgrid assets. It is neither practical nor possible to cover every issue
that may arise during a network rollout. In the event that clarification is required the
reader must contact the Manager, Engineering Standards and Research.
NEG TC01 All Dielectric Self Supporting (ADSS) Cable on Poles - Design Guidelines
Planning and Design Standards for Electrical Network Telecommunications
NS203
Assets
NS204.2.1 Communications Pits – Specifications and Installation Guidelines
NS201
February 2008 2
2 COMPLIANCE REQUIREMENTS
Design and construction shall:
comply with all relevant provisions of applicable legislation, regulations and
industry codes of practice including any relevant Codes;
comply with any other Australian Standards at the time relevant to the
telecommunications industry and the electricity industry;
comply with such other codes, procedures or standards as agreed between the
Parties from time to time; and
comply with Ausgrid documents including but not limited to Network Standards,
Network Management Plan and Electrical Safety Rules as relevant and
appropriate.
be aware of and reference NEG-TC01, All Dielectric Self Supporting Cable on
Poles – Design Guidelines
3.1 Abbreviations
ABC Aerial Bundled Cable
ADSS All Dielectric Self Supporting cable
AS Australian Standards
CMEN Common Multiple Earth Neutral
EPR Earth Potential Rise
ES Electrical Standard
GIS Geographic Information System
HFC Hybrid Fibre Coaxial cable network
HV High Voltage
IM Integral Messenger
kN kilo Newton
kV kilo Volt
LFI Low Frequency Induction
LV Low Voltage
NS Network Standard
WH&S Work Health and Safety
PE Photo Electric (Cell)
PSTN Public Switched Telephone Network
UGOH Underground to Overhead transition structure
XLPE Cross-linked polyethylene
NS201
3 February 2008
3.2 Definitions
ADSS All Dielectric Self Supporting fibre optic cable which is
nonconductive, self supporting and is capable of being
erected under tension between supports. It does not
require a separate catenary.
Catenary A separately constructed strength member attached to a
pole to which communications equipment and cable may
be attached. This also includes that part of an integral
bearer cable which is used to support wires and cables
which are enclosed in a cover or sheath.
Down Traffic Side The side of the pole on the far side of the on-coming traffic
(of a pole) (with pole and on-coming traffic on same side of road).
Earth Potential Rise The potential with respect to remote earth potential to
which a location rises due to the flow of current in the
earth.
High Voltage High voltage is normally more than 1,000 volts AC or 1500
volts DC
Hybrid Fibre Copper Telco network cable consisting of copper co-axial and
fibre optics.
Low Voltage Low voltage is normally more than 50 volts AC or 120
volts ripple free DC but is not more than 1,000 volts AC or
1500 volts DC.
Low Frequency Induction The generation of induced voltages in conductors
inductively coupled to a power line due to 50 Hz currents
flowing in the power line and using the earth as a return
path.
Make Ready Work The work which is required to be carried out prior to or at
the time when equipment is being attached to a pole in
order to ensure compliance with the requirements of this
document or the requirements of other relevant
authorities.
Normal Shared Use Shared use of a pole under conditions which comply with
this document and do not unduly stress the pole. This
does not include poles which are specifically listed as
Special Shared Use poles.
Pole Pole owned by Ausgrid.
Project Manager The person managing the design and construction of the
relevant ADSS project.
Special Shared Use Shared use of poles of a type specified by Ausgrid and as
defined in this document.
NS201
February 2008 4
4 REGULATORY ISSUES
All work carried out on Ausgrid’s network and/or its poles must be in accordance
with Ausgrid’s Electrical Safety Rules.
Design and construction must comply with all relevant provisions of applicable
legislation, regulations and industry codes of practice as well as any relevant
Australian and International Standards, as detailed in Standards Clause and Work
Health and Safety Clause of the Design and Deployment Agreement.
4.1 Asbestos
All materials and equipment used for construction of Ausgrid’s assets are to be free
from asbestos and / or asbestos related products. Suppliers are expected to comply
with the Work Health and Safety Act 2011 (NSW) together with the Work Health and
Safety Regulation 2011 (NSW) and confirm in writing that all products supplied to
Ausgrid contain no asbestos related materials.
4.2 Environment
ADSS project plans shall consider the environmental impacts of the proposed
installation and satisfy the requirements of the Environmental Planning and
Assessment Act 1979. An Environmental Impact Assessment may be required
before works can commence. Refer to NUS174 – Environmental Procedures, for
further information regarding environmental issues. Alternatively, contact Ausgrid.
4.3 Council
Relevant local councils must be informed, in writing, with a minimum of 40 days
notice, of any Ausgrid plans to construct aerial communications infrastructure.
Councils must be asked to advise if special zoning or consent requirements apply to
the proposed works in the relevant area.
NS201
5 February 2008
The majority of the Ausgrid poles are desapped or treated hardwood poles with
some poles being of a spun concrete construction with internal metal strength
members.
In addition to the power network assets, the poles are also used for supporting a
number of other types of equipment such as public street lighting, special lighting,
supporting road and street signs and traffic signal equipment. There may also be
other private and public communications networks which can utilise both copper and
optic fibre based cables. In addition there are a number of HFC networks which
involve stranded cable, fibre optic cable, co-axial cable and network components.
Some poles support mobile phone transmitter units, which emit high frequency
electromagnetic radiation and may require disconnection prior to working on the
pole1. Refer to the owner of the installation using the 24-hour number attached to
the equipment.
6 EXCLUSIONS
This Network Standard describes the requirement for the aerial communications
systems deployed with cable that is circular in cross-section and entirely non-
conductive (all-dielectric). Excluded are cabling systems that contain conductive
cable components such as metallic armouring, integral bearer wires or metallic
catenary supports.
This Network Standard does not describe the requirements for ADSS to be installed
in areas of extreme pollution. ADSS must not be installed without prior consultation
with Ausgrid in areas where there is a perceived risk that extreme pollution may
cause the outer sheath of the cable to become conductive and be subject to
electrical tracking or other electric field effects.
Some specific pole types will require modifications to the normal attachment to the
pole to facilitate safe access and operation of the power system equipment such as
air break switches, pole mounted transformers.
Service poles should not be used for main communications lines.
1
Refer to NS102, Working on Poles with Mobile Phone Transmitter Installations
NS201
February 2008 6
7 POLE CLASSIFICATIONS
Not all poles within the area serviced by Ausgrid are owned by Ausgrid2. The Project
Manager is responsible for confirming the ownership of any pole. Plans from
Ausgrid’s GIS may provide an indication of those poles owned by Ausgrid.
Poles proposed to be used for the construction of the communication network can
be classified as being one of three types, i.e.
Normal Shared Use
Special Shared Use
Defective and Condemned poles.
During the route planning and design process the classification for each pole along
the desired route (i.e. Normal, Special or Condemned) shall be determined.
2
Common-Use Pole. Refer to NS145. A pole belonging to another public utility or authority,
on which Ausgrid’s wires are attached. The pole is mainly used to carry conductors belonging
to the owner of the pole.
NS201
7 February 2008
The installation of ADSS fittings on Special Shared use poles may require the
relocation of existing plant, or the construction of additional overhead infrastructure,
such as a cross arm or stand-off bracket.
It is recommended to avoid locating ADSS terminations on Special Shared Use
poles.
8 MINIMUM CLEARANCES
Notes:
1. For voltages 66kV and above, the cable manufacturer shall be asked to advise
as to the cable placement, which minimises electric field effects, based upon the
NS201
February 2008 8
overhead electricity construction. The cable manufacturer may suggest the use
of an anti-tracking cable sheath and/or corona coils.
In considering the point of attachment for ADSS cables, the designer, Project
Manager and installer shall consider:
Electrical Safety Rules
The minimum clearances 8.1 and 8.2 of this Network Standard.
Aim to maximize above ground clearance
The visual amenity of the installation.
Risk of damage to the ADSS cable during tree trimming.
Access requirements for future repairs and maintenance of the ADSS cable
and other aerial plant.
The mid-span clearance of the cable considering the sag of ADSS and
overhead conductors
Please also refer to NEG TC 01, ADSS Cables on Poles – Design Guidelines.
Notes:
1. Some local councils and private land-holders impose minimum clearances
different from those in the above table. The Project Manager shall confirm with
the relevant authorities whether different clearances are required.
2. Over land in industrial areas, in particular driveways where LV cables exist, the
ADSS can be installed below 6500mm PROVIDED the ADSS cables are
located a minimum of 125mm higher than the LV cable.
3. *The NSW Maritime Crossing Guide must be referred to for ADSS installations
with water crossings. The installer must adhere to any clearance implied or
NS201
9 February 2008
NS201
February 2008 10
all the Ausgrid requirements, at the time of writing this document is the Fibreguard
600 enclosure supplied by Preformed Line Products Australia.
NS201
11 February 2008
NS201
February 2008 12
NS201
13 February 2008
ADSS Hanger Fitting – Line Deviation Max 30 Degrees, 350m < Span < 600m
NS201
February 2008 14
ADSS Double Yoke Hanger Fitting – Line Deviation Max 60 Degrees, 350m < Span < 600m
ADSS Double Termination Fitting – Line Deviation greater than 60 Degrees, 350m
< Span < 600m
The shackles, chain and other fittings used for the long-span terminations must be
rated at 70kiloNewton. Long-span terminations must use tongue bolts, rather than
hook-bolts. Structural rods used for long-span fittings are longer than those used for
shorter spans.
3
Extract from Network Standard NS122, Pole Mounted Substation Construction
NS201
15 February 2008
The preferred location for pole-mounted ADSS Splice Enclosures is the down-traffic
side of the pole. However, the location shall be selected with consideration given to
the visual amenity of the installation, future access by means of a ladder or
otherwise and current or planned additions to the pole.
NS201
February 2008 16
The minimum distance above ground for the bottom of the coil is 4000 mm.
The maximum height is to suit retrieval by unqualified4 staff and to suit the
available ladders
Coil brackets for ADSS loop storage shall conform to the minimum no-load
bend radius of the cable. The bracket manufacturer should be informed of the
specification of the selected cable.
The coil bracket shall be mounted below the splice enclosure, with
approximately 90 degrees rotation between the two fixtures.
The coil must be suitably secured to the bracket with cable ties and the bottom
of the coil must be secured to avoid swinging in the wind.
4
As defined in the Ausgrid Electrical Safety Rules (table 5.1).
NS201
17 February 2008
NS201
February 2008 18
Confirm the current status of this investigation prior to undertaking any work on steel
poles5.
5 One solution that would be satisfactory is to fabricate a gasket of 1 or 2mm thick, black
“Neoprene” (polychloroprene ) for fitting between the stainless steel band and the pole.
NS201
19 February 2008
NS201
February 2008 20
NS201
21 February 2008
NS201
February 2008 22
NS201
23 February 2008
NS201
Ausgrid.
Revision History
Initial issue: 24/11/2006
This edition 15/02/08
Document Control
UNCONTROLLED COPY