Академический Документы
Профессиональный Документы
Культура Документы
NO:
PLL/PSPL/QC/P17
MAINLINE VALVE / INSULATION JOINT
INSTALLATION REV. NO.: 0
PUNJ LLOYD LTD.
PROJECT: PUNE SOLAPUR PIPELINE PROJECT
ISSUED TO
NAME:
CONTROLLED COPY NO.: DESIGNATION:
ISSUED BY
SIGNATURE/DATE:
NEW DELHI
______________________________________________________________________
WORK INSTRUCTION
FOR
TABLE OF CONTENTS
1.0 PURPOSE............................................................................................................................................3
2.0 SCOPE.................................................................................................................................................3
3.0 REFERENCES....................................................................................................................................3
5.0 RESPONSIBILITIES..........................................................................................................................4
6.0 METHODOLOGY..............................................................................................................................5
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
For the Purpose of this document, the term “shall” indicates a mandatory
requirement and “should,” indicates a recommended practice.
b) EIL’s Specification
6.0 METHODOLOGY
Valves shall be installed in line with the AFC drawings. The civil and
structural works shall be carried out with relevant specification for the
purpose and in accordance with the approved drawings. This work as a
minimum shall include cleaning, grading, fencing, foundations etc. All
above ground structures shall be painted as per approved procedure.
Pedestals shall be cast at valve locations after embedding an insulating
hard PE Sheet of at-least 5-mm thick of equivalent as indicated in the
respective drawing. Block and SV units shall be completely assembled,
tested and made fully functional including all related instruments.
Valves with flow arrows shall be installed according to the normal flow in
the pipeline. During welding, the valves shall be in fully open position. In
addition all manufacturer instruction shall be followed. Care shall be taken
to avoid entry of sand particles etc. to valve body, seals etc. during
transportation, storage, assembly and installation.
INSULATION JOINTS
Handling and installation of the insulating joints shall be carried out with all
precautions required avoiding damage and excessive stresses and
ensuring that original pipe length is not reduced. External coating as per
relevant specifications issued for the purpose shall protect the insulating
joints and the welded joints.
Insulation joint shall be electrically tested before welding into the pipeline.
The electrical conductance test shall be carried out using a megger.
Measurement of insulation resistance across the joint shall be
approximately 1 mega ohm. The test shall be repeated after installation
and welding of the joint into the pipeline to verify that assembly is not
damaged.