Вы находитесь на странице: 1из 4

E n g in e e r in g N ew s- R ecord.

April 23, 1936

Practical Soil Mechanics at Muskingum— III


Resisting Strength o f Foundations
By Theodore T. Knappen and Robert R. Philippe
Chief. Engineering Division, and Director. Soils Meehanic» Laboratory,
U. S. Engineer Office. Zanesville. Ohio

A S W A S B R O U G H T O U T in pre- foundations, and for others it is esti­ curred the embankment will not be be­
r \ ceding articles ( E N R , March 26, mated in periods of years; in one case low the designed crown grade. It is
1936, p. 453, and April 9, p. 532), ihe estimate is 99 years. necessary to know the rate of consoli­
the foundations were of questionable It is desirable to know the total dation during construction to determine
character at the sites of several of amount of foundation consolidation that in advance what shearing strength the
the Muskingum dams. The valley fills will take place under the proposed load foundation material will have developed
on which it was proposed to locate many and the amount of this that will take at the time any particular load is ap­
of the embankments consisted of poorly place during construction, as the differ­ plied. Ordinarily we need not consider
consolidated clay and silt. Where these ence between these two figures should any granular material, such &s ¿and or
conditions existed, tests were under­ be added to the height of the embank­ gravel, as the strains o f fhese*Tnateria 1s
taken to determine definitely the be­ ment at the time of construction so that, are comparatively small, and conse­
havior to be expected under the pro­ when the eventful consolidation has oc- quently the consolidation is also small
posed loadings. The plan deserves some and takes place rapidly during the con­
emphasis. F IG . 11— C O N S O L ID A T IO N lest machine struction period. We are interested,
In the discussion of permeability and made up of purchased parts proved highly therefore, only in materials of the silt
superior in operation and has been widely
seepage in the previous article, the inti­ copied. The loading device consists of an
and clay type.
mate relation between the laboratory ordinary 1,000-lb. platform scale. The The consolidation characteristics of a
tests and the design was pointed out. consolidation device (A ) is set on the plat­ foundation may be determined by taking
form scales B. The floor of the scale is
The same objective was held to in the bored with two holes through which pass undisturbed samples of the various strata
foundation-strength design studies. Here the two arms of a yoke C, which applies of the materials occurring in the founda­
the aim has been to put the structural the load to the consolidation device. The tion and testing them. The tests are car­
load is applied to the bottom of the yoke
design of the foundations on a rational by the jack D , which is a 2V^-ton screw- ried out in consolidation machines (Fig.
basis, utilizing the excellent work of type high-grade truck jack. The jack is 11) designed and built in the laboratory;
previous research and developing a actuated by the hand wheel E. The lever these machines were assembled from
arm of the scale is counterbalanced for the
technique for applying its results to the load which is to be applied. The hand platform scales, truck jacks and dial
solution of practical problems. The wheel D is manipulated to get the balance gages, which permitted their construc­
arm of the scale in horizontal position. The
work has gone further and adopted from stop is removed from the balance arm of
tion at ^ very low cost yet gave ma­
the field of modern structural design the scale, so that as deformation of the chines that are sufficiently accurate for
the photo-elastic method of stress anal­ specimen takes place under the load the all practical purposes. The purpose of
applied load w ill not change but the dif­
ysis and applied it to foundation prob­ ference w ill be taken up in the movement
the machine is to apply uniform and un­
lems. The assumption has been of the scale platform as reflected in the varying loads to a specimen for any
throughout that there is a rational or ex­ movement of the arm. The am ount of desired length of time, often for several
consolidation of the sample is measured by
perimental method for answering every the dial gage F. days, and to be able to change the in­
foundation problem. It is realized that tensity of the load at will. The speci­
only a beginning in this work has been men is placed in a bronze ring, 1\ in.
made, and that much that is being done in depth and 4J in. in diameter; it is
will be greatly altered and improved as carved out of an undisturbed sample of
the technique is taken up and applied in the material to the exact size of the in­
general practice. There are problems side of the ring (the ring being used as
in embankment and foundation design a templet). Porous stone disks of
for which as yet there are no solutions; slightly smaller diameter than the diame­
some of these are being worked on ter of the ring provide drainage at the
here, and others are being attacked in top and bottom surfaces.
other laboratories, but to the funda­ To determine the consolidation char­
mental problems the solutions are now acteristics of the specimen in the con­
at hand. solidation service, it is necessary to
apply and maintain any desired vertical
Settlement is first problem load on the sample. The desired load
is set on the arm of the 1,000-lb. plat­
Consolidation is the process of in­ form scale used, and the load is applied
creasing the density of a soil under to the sample by a 2£-ton screw-type
applied loads. Volume tends to decrease high-grade truck jack through a yoke.
as load is applied and as water in the The stop is removed from the scale arm,
voids is squeezed out. Where materials permitting it to move as deformation
are saturated, which is the usual case in of the specimen takes place, thereby
foundations, the rapidity with which maintaining a uniform load. The scale
consolidation takes place depends on the arm is brought back to the horizontal
drainage characteristics of the material from time to time by taking up on the
and the foundation in general. Ultimate jack. The amount of consolidation of
consolidation on this project is consid­ the sample at any time is measured by
ered practically instantaneous for some the reading of the dial gage.
E ngineering N ews -Record, April 23. 1936

The general results of these tests fix


the time rate of consolidation and the
stress-strain relationship of the partic­
ular sample considered. To illustrate,
if the specimen from a stratum consoli­
dated 5 per cent under a load equal to
the proposed load over the particular
stratum which was 10 ft. thick, then the
stratum would ultimately consolidate 5
per cent of 10 ft. or 0.5 ft. due to the
embankment load. By determining the
consolidation for each stratum in this
way and adding them together, the total
ultimate consolidation of the founda­
tions under the embankment may be
determined. Further, since rate of con-||
solidation varies within limits as the(:
square of the distance between drainage J:
boundaries and assuming that the 10-ft.t
stratum is underlain by a free draining;'
material, consolidation of the stratum^

120J . I
will take j 2g»P= 9210 times as long a>
i
it did on the sample. If the consolida- r
tion of the sample took ten hours, that 8
of the stratum would take 92,100 hours, !;
or 3,840 days, or 10| years. By similar |
methods the amount of consolidation at f
any time may be determined. Thus, $
from these results the amounts of set­
tlement anticipated during construction
and after construction is completed may
be fixed with reasonable accuracy.

Stress-strength relationship

The next problem to be handled is


to determine the stress-strength rela­
tionship in the foundation of the pro­ F IG . 12— S H E A R IN G TEST M A C H IN E with enlarged view of shear box and specimen
after test; laboratory was constructed at a cost of $400. The shear box is set on
posed embankment. First, the shearing platform scales My and the vertical load is applied through yoke B motivated by jack,
strength of the foundation materials is operated by hand wheel D . A shearing load is applied to the bottom h alf o f the
determined. After that is done, the em­ shearing box E by means of yoke G , motivated by jack H . The top h alf o f the
box is connected by means o f yoke J to bellows K , which is connected in turn to
bankment must be so designed as to keep manometer L , which measures the intensity of the shearing stress in the specimen.
the stresses well below the strength of The top section F of the shearing box has a 4*in. square opening through it, and the
the foundation material. In studying bottom section E has a similar opening recessed 9/32 in. into it. In this recess at right
angles to the direction o f shearing strain is a series of parallel ribs used to grip the
foundation sections where silt or clay bottom o f the test specimen. The undisturbed test specimen is cut from the sample
type material containing a high moisture 9/16 in. thick to fit exactly the opening in the shear box. The top half o f the shear
content are found, tests should be run to box F is set down over the sample, but contact between the two halves of the box
is prevented by set screws. Through the opening in the upper h alf F a bronze piston,
determine the shearing strength of the which is corrugated on its bottom surface in the same manner as the recess in E, is
various foundation materials. For these pressed into the sample and locked in place by set screws. The clearance screws
holding the two sections of the box apart are then released, as the sample now serves
tests, as for the consolidation tests, it is that purpose. The box is now ready to insert in the machine.
necessary to have undisturbed samples
of material. Ordinarily specimens from
the same sample are used for both tests. applying and measuring the shearing zontal strains are applied by the hori­
Sand and gravel materials generally are load. For the construction of this ma­ zontal jack in increments of 15 sec. so
of no interest in this connection, as they chine, as for the consolidation machine, that a complete shear will occur in 4
consolidate as the load is applied and standard manufactured articles were min. This rapid rate of load application
develop high strength. In silt and clay utilized. The shearing box that holds tends to eliminate consolidation during
type materials it is comparatively easy the sample consists essentially of top and the time of test in so far as it is possible
to obtain undisturbed samples, as these bottom sections that are kept from con­ to do so.
materials are naturally impervious and tact with each other by the sample. The Several specimens, 4x4xtii in., carved
test pits can be put down through them box is set on a 1,000-lb. platform scale, from each undisturbed sample are tested
with very little pumping. Specimens for and the vertical load is applied as in the at different vertical loads, so that the
making the test to determine the shear­ consolidation machine. The shearing variation in shearing strength with the
ing strength of these materials may be force is applied to the bottom section of Vertical load applied can be determined,
cut from the undisturbed samples ob­ the box by a second jack set hori­ fig . 13 shows the shear curve deter­
tained from the foundation. zontally. The total shearing stress in­ mined by tests^on specimens from one
A special shearing machine (Fig. 12) duced in the specimen is transferred sample. The strength at zero vertical
was clesigned in the laboratory to make from the top half of the box through a load can be defined as the cohesion, and
these tests. Two things are desired in the yoke to a bellows. The pressure on the "the slope of the line gives the apparent
shearing machine: one is means of ap­ bellows is measured by a manometer. angle of internal friction.
plying the vertical load uniformly dur­ The desired vertical load is applied by It may be observed that during con­
ing tests, and the other is a means of setting the scale arm, and equal hori­ struction of an embankment a certain
E n g in e e r in g N e w s - R ecord, April 23, 1936

amount of consolidation does take place where c equals the maximum shearing shearing strength of the material, the
in the foundation, which in turn would stress, and p equals the intensity of factor of safety against failure under
tend to increase the shearing strength pressure at the center line. the worst combination of conditions is a
of any particular sample. However, no 2— The more usual case is where the matter of simple division.
testing method so far devised has been depth of questionable material is much
able to take this factor fully into ac­ less than the base width of the embank­ Pjioto^elasyc stress detep^nation
count, and the only approach to the ment. For the case where the depth of It must be noted that the1*formulas
problem is to test under the assumption questionable material does not exceed given above apply in limited cases only
of no consolidation during construction one-tenth of the base width of the em­ and also apply only to triangular em­
and reproduce the effect of consolida­ bankment, Jurgenson has developed the bankments. The analytical solution has
tion as effective load applied in a given following form ula: not been developed for other than tri­
time. This factor induced into the shear angular embankments or for cases be­
relationship as an increased vertical load yond those limits. For the purpose of
will give the minimum increased checking the analytical application of
strength due to consolidation and there­ pressure developed by the maximum Jurgenson’s formula and to develop
fore is a conservative analysis. Hence, height of the embankment, a is one-half methods to work out cases not covered,
with the shear relationship fixed it be­ the depth of the questionable material, a photo-elastic method of determining
comes necessary at any given time to and L is one-half the base width of the stress distribution experimentally was
estimate the vertical load effective on embankment. developed in the laboratory. Gelatin
the material under consideration. Between the limits covered by the was used as the foundation medium, and
As a preliminary explanation, it is two equations mentioned above, no sim­ the embankments were constructed of
well to point out that while at the time ple analytical solution has been de­ lead shot, as this material was found to
of instantaneous application of load the veloped for stress determinations in the be the only commercial material heavy
principal stresses are carried entirely by foundations. Recently an involved enough and suitable to give the desired
water (assuming the material to be solution has been developed by Jurgen­ results.
saturated), the resulting shear stresses son from the fundamental equation de­ The well-established principles of
must be carried by the grains them­ fined by Corruthers, but it is so un­ photo-elastic analysis were applied in
selves. As time progresses, the water wieldy that it must be eliminated from these experiments. Fig. 17 is a photo­
being under pressure is forced out at a practical use and can be best applied graph of a test showing the distribution
rate depending on the thickness and to check the experimental methods here­ of shear stress contours. W ith the ex­
permeability of the material, and as a with proposed. The Jurgenson formula periment described above, it is neces­
result the principal stresses are trans­ for the limited case does not give the sary in each case to run a calibration
ferred to the soil particles themselves. As location of the maximum stress zone in test where a known shearing load is in­
these stresses become effective the ma­ the foundation. To be safe in applying duced in a sample of the gelatin ma­
terial itself increases in shearing the formula, it must be assumed that terial cast at the same time as the model
strength. To be exact in testing, it maximum stress occurs where the ques­ material, in order to determine the con­
would be necessary first to fix the con­ tionable material is weakest. To apply tour interval of shearing stress for the
solidation and the resulting permeability this method then, it is only necessary to material at that particular age. Having
relationship in the prototype and simu­ have the embankment dimensions for determined the contour interval, the
late that condition in the testing of in­ substitution in the above formula, to get maximum stress may be determined by
dividual samples. Since this procedure the maximum stress. Knowing the counting the contours to the point of
so far has not been developed, the ac­
cepted method is a safe approximation.

D eterm ining foundation stresses

The characteristics of the foundation


material having been experimentally de­
termined, it remains to determine what
stresses will be induced in the founda­
tion under the proposed embankment F IG . 13— S H E A R TESTS were made on
design. Fig. 14 shows a triangular em­ each sample at several vertical loads.
Curve shows results of tests on one sample.
bankment load. The maximum loading
F IG . 15— T IM E - C O N S O L ID A T IO N *est
on the foundation is from the crown of curves at Clendening D am , used in deter­
the embankment marked A, and zero m ining rate of construction of embankment.
load is applied at the toes B and C. The wH
difference in load, between the load at
A and the zero load at B or C, must be
taken up as shear in the foundation.
There have been two cases for which
shearing stress in foundations have F IG . 16— D IS T R IB U T IO N O F SH EAR
been worked o u t: H G . 14— D IA G R A M O F T ERM S used in STRESSES in dam foundation (W ills
1— For an infinite depth of question­ Jurgenson form ula for stresses in founda­ Creek) established by operator’s sketch
tions under embankment load. from photo-elastic test shown by Fig. 17.
able material in the foundation: For
practical purposes, infinite depth may
be defined as depth equal to or greater
than the base width of the embankment.
For large embankments this formula
rarely has any application. Dr. Jurgen-
son, in the Journal of the Boston So­
ciety of Engineers, Vol. X X I , No. 3,
July, 1934, developed this from an ap­
plication of Corruthers formula. The
equation for maximum shearing stress is
c - 0.256 p
E n g in e e r in g N ew s- R ecord, April 23, 1936

greatest stress and multiplying the num­


ber of contours by the contour interval.
The results of the experiments are re­
corded by photographing the image of
the model produced by the polarized
light, Fig. 17. At the same time, a color
sketch is recorded by the model operator
from which the stress distribution is de­
veloped as shown by Fig. 16.
From the intensity and location of
the maximum shearing stress in the
model, the intensity and location of
maximum shear in the prototype may be
determined. To check the results of the
model experiments against the analy­
tical solution, a number of cases were
worked out for triangular embankments. F IG . 17— D IS T R IB U T IO N of shear stress contours in foundation of dam models
In about a dozen check tests the maxi­ (W ills Creek) disclosed by photographs of images produced by polarized light.
mum variation between the results ob­
tained by the two methods was 19 per
cent, and the average variation was 6 validity of such an assumption. It Final failure is characterized by a blow
per cent. As this variation is well within suffices to point out that in investigat­ of the foundation and a sudden subsi­
the limits of the factors of safety adopted ing the foundations of various condi­ dence of the load.
for use, it is believed that entirely re­ tions, each a borderline case, the results Our practice has been to design with
liable results can be obtained by the ex­ of tests indicate what was known to be a factor of safety of 1.5 against over-
perimental method where the work is an actual condition— i.e., failure or sta­ stresses and an estimated factor of
carefully done by an experienced per­ bility. The conclusion drawn from these safety against failure of 2.6. This factor
sonnel. investigations was that the error of such of safety may seem small, but since a
Gelatin was the only photo-elastic ma­ an assumption was well within the ac­ progressive increase in foundation
terial which we were able to discover curacies of such work. The analysis strength takes place after completion of
that would give the proper relations for also provides against the overstress of construction due to consolidation of the
modal study. The difficulty in using any any portion of the foundation. When foundation, the factor of safety tends to
other material develops because all other such a condition exists that at the point increase with time, and if the embank­
photo-elastic materials -which we could of maximum stress the material has just ment can be completed there is little
locate were too high in strength to de­ sufficient strength to balance this stress fear that failure will take place in the
velop sufficient stress contours within the remainder of the foundation is un­ future.
the limits of embankment loads that derstressed and capable of more load It will frequently happen that tests
could be applied readily in the labora­ than is at present exerted upon it. The will show that a foundation material
tory. As it was, it was necessary to go addition of shear stress would cause a has a very low factor of safety where
to the heaviest material obtainable in redistribution of stress to the under- the load is instantaneously applied.
commercial quantities; that is to say, stressed portions of the foundation. Only However, where the strata are com­
lead shot, for embankment construction an overload of sufficient magnitude to paratively thin or are drained by sand
in the models. produce stresses in excess of all the or gravel layers, the material will con­
It must be noted that the methods of available strength of the foundation can solidate more or less rapidly as load is
stress analysis are based upon the as­ cause a total failure. Such a failure is applied and develop increased strength
sumption of elasticity. It is not within preceded by excessive settlements and against failure in shear. The time-con-
the scope of this article to develop the characteristic mud waves at the toes. solidation curve indicated in Fig. 15
may be used to determine the amount
of consolidation and increase in strength
F IG . 18— R E L A T IO N S H IP between the computed foundation consolidation during under the proposed method of construc­
construction and the consolidation that actually took place at Clendening D am .
tion, and it may be in some cases that
t-80 1 1 by limiting the proposed rate of con­
1 struction, the desired factor of safety
1 60 Contemplated pro qrèss^
1 40
1
* — may be obtained. This is illustrated by
- j"|— ictua! progress
I 20 the Clendening Dam, where the rate of
f1 0 construction was limited to 4 ft. per
0.2
week.
A Cage No / - Sfa tion J +56 For the purpose of checking the
0.4 o " NO. Z ~ " Òtco
.'tAcfui7 / s °ftlem ent foundation consolidation during con­
0.6
. - No.Z - " 6+15
/"/ nal contemplated settlement = 2.92 struction to be sure that the factor of
0.8 safety is maintained, a system of settle­
1.0 ment gages has been installed at several
S0<1-2
Theorei ica se ?/(?/77 er t
aft oniemLilat ed orociress ' \ of the dams. Fig. 18 is a chart that
^ 1.4
\ shows the relationship between the com­
£ 1.6
!i
\ puted consolidation during construction
and the consolidation that actually took
— place for Clendening Dam. These charts
1/1 71
\ are carefully followed during the con­
sV Jheore ficcr! se ttÌemènt ¡ f struction period to see that the consoli­
24 ère apt
2.6
2.8 m IT)

f-

^
f-
r 1
Ol ^ S Ä
N
S « 2 S -
— —

= N m 2 8
dation is at least as great as the com­
puted consolidation.
In the closing article the laboratory
3.0
>%_>> _>> oi "cL "cL "ex -f- and field methods of selecting embank­
—) - 3—
3< < < C() 01 o o z z: Q Q Q
3.2
10 20 30 40 50 60 70 8» 90 100 110 120 130 140 150 160 170 180 190 200 210 220230 240 250 260 270 280
ment material and controlling its place­
Time ,Days ment are described.

Вам также может понравиться