Project/Run: energy model - UALISSON - Baseline Design Run Date/Time: 01/28/18 @ 14:20

Electric Demand (kW)

200

150

100

50

0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Area Lighting Exterior Usage Water Heating Refrigeration


Task Lighting Pumps & Aux. Ht Pump Supp. Heat Rejection
Misc. Equipment Ventilation Fans Space Heating Space Cooling

Electric Demand (kW)


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Space Cool 57.9 54.9 88.5 96.1 75.4 65.0 50.6 65.7 86.3 96.5 97.6 103.2 937.8
Heat Reject. - - - - - - - - - - - - -
Refrigeration - - - - - - - - - - - - -
Space Heat - - - - - - - - - - - - -
HP Supp. - - - - - - - - - - - - -
Hot Water - - - - - - - - - - - - -
Vent. Fans 8.6 8.6 8.6 8.6 8.6 8.6 8.6 8.6 8.6 8.6 8.6 8.6 102.7
Pumps & Aux. - - - - - - - - - - - - -
Ext. Usage - - - - - - - - - - - - -
Misc. Equip. 3.2 3.2 20.1 20.1 20.1 20.1 20.1 20.1 20.1 20.1 20.1 20.1 207.3
Task Lights 0.1 0.1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 5.6
Area Lights 3.8 3.8 24.4 24.4 24.4 24.4 24.4 24.4 24.4 24.4 24.4 24.4 251.5
Total 73.6 70.6 142.1 149.7 129.0 118.6 104.1 119.3 139.9 150.1 151.2 156.8 1,504.9

Gas Demand (Btu/h)


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Space Cool
Heat Reject.
Refrigeration
Space Heat
HP Supp.
Hot Water
Vent. Fans
Pumps & Aux.
Ext. Usage
Misc. Equip.
Task Lights
Area Lights
Total

eQUEST 3.64.7130 Monthly Peak Demand by Enduse Page 1