Академический Документы
Профессиональный Документы
Культура Документы
Prepared by;
Names: NTAMBARA Sylvestre Owen
Telephone: +250789469955 / +250727634011
E-mails: bsowen100@gmail.com / ntambara.owen@yahoo.com
Duration: 03rd July, 2017 – 30th August, 2017 Submission date: 10th October, 2017
Industrial Attachment NTAMBARA Sylvestre Owen 215004285
DEDICATION:
DECLARATION:
I also declare that it has not been previously and concurrently submitted elsewhere for any other
academic award either at University of Rwanda or any other higher learning institutions for
publication or any other academic purpose.
ACKNOWLEDGEMENT:
First and foremost, I thank the Almighty Omnipotent, Omniscient and Omnipresent God for
giving me the strength and courage throughout the period of my internship and for his guidance
and for helping me to complete this industrial attachment.
ABSTRACT:
This industry attachment report is a 20 credits module done at the end of third year class and it is
required for partial fulfillment of the award of the bachelors in Electrical engineering organized
by Ministry of Education through the program of University of Rwanda-College of Science and
Technology.
I participated on various activities carried out during implementation of MUKINDO WATER
PROJECT including civil, mechanical and electrical work.
This report includes company training practices, the conclusion of the trainees on the work done
and the recommendations suggested for the problem of fresh water to the population in
GISAGARA District specifically in Mukindo sector that was being solved through that project
initiated by EWB-Rwanda.
Our aim was to deepen our knowledge into electrical power system used in that project to pump
the water up the hill to the community and above all in the field of solar power system since
solar system is the one which was used to provide electrical energy for powering LORENTZ
PSk2 solar submersible pump systems.
I had also a chance of getting information filters that were being fabricated by EWB-Quebec
just for filtrating the rain water and unclean water from the dams. We had an overview on how it
is fabricated, equipments and materials used while making those filters i.e. the quality and the
quantity of the materials.
This industrial attachment was conducted at Gisagara district in Mukindo sector in the different
activities of the project that was being implemented by EWB-Rwanda stated above especially
for all activities concerned with electric power from 03/07/2017 up to 30/08/2017 with the
purposes of empowering student with the practical technical skills and to train and uphold the
student with practical working conditions after 3years of lecturers.
LIST OF FIGURES:
LIST OF TABLES:
Table 1: Technical data of PSk2 controller ................................................................................................. 18
Table 2: Controller dimensions for installation .......................................................................................... 20
Table 3: Terminal explanation .................................................................................................................... 22
Table 4: Tightening torques for pump/motor connection ........................................................................... 25
Table 5: Additional weight per meter pipe length ...................................................................................... 26
TABLE OF CONTENTS:
DEDICATION: .................................................................................................................................................. i
DECLARATION: .............................................................................................................................................. ii
ACKNOWLEDGEMENT: ................................................................................................................................. iii
ABSTRACT:.................................................................................................................................................... iv
ABBREVIATIONS AND ACRONYMS: ............................................................................................................... v
LIST OF FIGURES: .......................................................................................................................................... vi
LIST OF TABLES: ............................................................................................................................................ vi
I.INTRODUCTION: .......................................................................................................................................... 1
1.1. BACKGROUND OF EWB-RWANDA: ........................................................................................... 1
1.2. MISSION: .......................................................................................................................................... 1
1.3. VISION: ............................................................................................................................................. 1
1.4. GENERAL OBJECTIVE: ................................................................................................................. 2
1.5. SPECIFIC OBJECTIVES: ................................................................................................................. 2
II. MUKINDO WATER PROJECT: ..................................................................................................................... 3
1. BACKGROUND: .......................................................................................................................................... 4
2. PRELIMINARY ACTIVITIES DONE AT THE SITE: .......................................................................................... 5
2.1. Kazabagarura water source ................................................................................................................ 5
2.2. Water departure chamber ................................................................................................................... 6
3. APPURTENANCES USED AND CIVIL WORK: ............................................................................................... 6
3.1. Pipe material ...................................................................................................................................... 6
3.2. Catchment of the source and intake ................................................................................................... 6
3.3. Location of valve on water supply system ......................................................................................... 6
3.3.1. Air release valves ........................................................................................................................ 6
3.3.2. Blow offs valve ........................................................................................................................... 7
I.INTRODUCTION:
1.1. BACKGROUND OF EWB-RWANDA:
Meeting, discussing and working with Engineers Without Borders from around the world;
having site and regional experience in needs; after analyzing the technical and managerial
capacity of the Rwandans with local potential in materials; it was required to have a Rwandan
group of Engineers to develop practical skills by giving solutions for identified problems into the
community, as per the mission, vision, and objectives here below mentioned.
Along the past years, Rwandan engineers and Experienced Advisors (namely Wellars
BAHORANYE, Dr GATABAZI Jean Damascene, Dr Leopold MBEREYAHO, SEKAMANA
Jean Damascene, Joseph NTWALI, KYAZZY Eduard, NIKUZE Joselyne , MUNYABUGINGO
Bonaventure, and MUGOROZI Theophile) sat together and analyzed the solutions as
contribution to sustainable development projects through engineering networking humanitarian
organization “Engineers Without Borders – Rwanda” in partnership with the Government,
NGOs, Institutions, Academics, Volunteers, Industries, and local communities.
1.2. MISSION:
EWB-RWANDA has been founded with a mission to partner with developing communities to
improving the quality of life through education and implementation of engineering projects.
EWB-Rwanda gives to university students and engineering professionals’ members a unique and
life changing opportunity to participate in and improve the global community.
1.3. VISION:
EWB-RWANDA has a vision in which the communities have the capacity to sustainably meet
their basic human needs, and that our members together with our partners have the global
perspectives through the innovative professional educational opportunities.
To involve the concept and implementation of engineering assistance through which most of
Rwandan citizens have the opportunity to meet their most basic needs. For that, it will partner
with EWB chapters from around the world, other organizations or institutions and local
population.
All members of the organization EWB-Rwanda will have the priority in case of recruitment of
employees; they will professionally get trained for having the capacity to do so for others; for
those members’ fresh graduates, will have the priority and facilities for keeping one’s terms
according to their major of study.
1. BACKGROUND:
Nowadays, water supply and sanitation in Rwanda is characterized by a rapid increase in access
compared to the past years in rural area. Access to potable water has been increased, starting
from 44% in 2005 to 85% by 2015(water and sanitation sector, MININFRA, April 2006).
However, in Gisagara district where Mukindo sector is located, the increase of potable water at
above level has not been accomplished. This shows that the access on safe water supply in
Gisagara district specifically in Mukindo sector is low compared to the other rural areas in
Rwanda.
Although this sector have the spring water sources that can be exploited and transformed into
water supply systems but their identification and manner of their design are not taken into
considerations. Therefore, this issue has caused the quality of such water to be unsafe due to the
aspect of human activities.
It is that reason; Mukindo Water Project was developed by EWB-Rwanda and EWB-Rwanda is
Non-Governmental Organization of Engineers without Boarders, Rwanda chapter with the main
objective of provision and implementation of any essential engineering related project to the
populations for their good healthy and development in collaboration with the Government of
Rwanda.
This project was being implemented by EWB-Rwanda in partnership with EWB-Quebec from
Canada and the government of Rwanda particularly Gisagara District. It’s target was to supply
potable water to over 10 000 people who are living in Mukindo sector through a proper
development of Kazabagarura water source located in neighbouring sector Mugombwa sector
with a designed water supply and distribution system to the householders for their health
improvement.
Therefore, it is in that way, EWB-Rwanda designed a Gravitational and Solar powered Water
Pumping system for the supply of filtered, drinkable and clean water to Mukindo sector
especially Nyabisagara and Gitega Cells which are considered as vulnerable regions in terms of
accessing potable water.
The water from Kazabagarura water source flow at a rate of 1.48liters/second to the reservoir of
25m3 due to gravitational force in fact, water source in Mugombwa sector is elevated at 5m
compared to the location of the reservoir in Mukindo sector with 1125m distance apart.
The water from the reservoir is pumped uphill to the storage tanks of 50m3by solar submersible
pump system where the tanks are elevated at 156.2m with the distance 2128m from the reservoir.
This solar water pumping system is designed to provide 50m3 per day as quantity of water for the
distribution to the people in four villages namely; Kamasiga, Mukindo, Rebero and Gatunda.
The storage tanks of 50m3 in Mukindo center are to store water during the night or periods of
cloudy weather. When tanks are fully, they can provide water to the population within 2 or 3days
without using pump and that’s why the solar system used doesn’t involve any electrical storage
(Battery) for economic aspects.
Water departure chamber is hydraulic structure built nearby the water source and it is made of
concrete or masonry for it to collect water from the source captured by one or several oil sump
filters and that constitutes the first work of regulation of the water adduction also, understand an
overflow that should be to proportion sufficiently to assure the evacuation of the maximal
discharge of source without provoking a retention to the level of the catchment.
This chamber is sized to 8m3 (2m x 2m x 2m) with an Inlet pipe from the water source, Overflow
pipe which helps the people near the water source to fetch water from the source and Outlet pipe
that carries water to the reservoir of 25m3 and this outlet pipe is a little bit lower than the inlet
pipe for the higher pressure of the water.
Water departure chamber with its overflow pipe helps to maintain the inlet of water and outlet of
the water at regulated pressure i.e. Inlet water flow rate must be equal to outlet flow rate and over
flow rate.
Appearance of the air in the chamber depresses the water level uncovering the orifice. The air
leaves out until normal water pressure in the chamber is established again. Valves used are
operated manually.
3.3.2. Blow offs valve
A blow off assembly is used to flush out accumulated sediments at low spots and dead-ends of
pipelines and for draining pipelines for repairs, maintenance, and inspection.
Blow off discharge are directed away from the pipeline into a nearby storm drain or other non-
erodible surface drainage channel.
3.3.3. Gate valve
Gate valve is the valve which is used for shut off the supplies whenever needed.
3.3.4. Non-return valves
These are valves through which flow of water can proceed in one direction only. An opposite
flow direction clauses the valves to close and remain closed until the flow is re-established in the
same direction. Hence the valves operate in on/off position, fully closed or opened by the flow
itself. The non-return valves are installed in pumping stations as a back-flow prevention
sometimes they may be found in distribution systems and as a past of service connection
3.3.5. Pressure reducing valve
Pressure reducing valves are normally used to control the pressure in isolated parts of networks if
it becomes too high. When the pressure upstream of the valve grows above the pre set value, the
valve will start closing until the downstream pressure is equal to the preset pressure. If the
upstream pressure is below the pre set value, the valve operates as fully opened.
3.3.6. Line valve
In general, line valves are installed in distribution and transmission pipelines to isolate and
depressurize pipeline segments for repairs, modifications, inspections or maintenance.
Valves are placed on all branches of crosses and tees and at each street intersection on the main
prior to the branch and on each branch of the water system.
The detail and performance of the joint between the side wall and bas slab have a significant
effect on the structural behavior of the wall.
The reservoir is elevated to provide water pressure. When a water tank is elevated, gravity forces
press water downward as it drains through a small pipe. It is the weight of the water pressing
down on itself due to gravity that creates the pressure. This allows the water to be forced through
the water system at high speeds and provides enough momentum for the water to reach homes
that are located many miles from the water tank.
3.2.1. Definition
Solar panel is a group of solar cells that work together. Solar cell is a device that can make
electricity directly from the sun light (sun shines).
Solar cell doesn’t give off any gases and it doesn’t even make noise, therefore solar cells and
solar panels have a lot of applications including; calculators, watches and flash lights.
They are also solar powered equipment like toys, radios, MP3players, cell phones and pagers.
Solar panels are sometimes used to make electricity to light up road signs and bus stops, roadside
emergency phones and ATM machines
Solar panels can also provide power for all kinds of machines, buildings including homes,
schools, hospitals and other institutions. It can also be used as backup in case of the utility power
fails to work. These solar cells that are used to convert sun light energy into usable electricity are
also known as PHOTOVOLTAIC simply Photo means Light and Voltaic refers to Electricity.
A single simple solar cell makes little electricity for this reason; cells are often linked together in
group known as solar modules. And when more power is needed, modules can be joined
together to form a large solar array.
These solar modules and arrays are sometimes called Solar panels, and whatever you call a
group of solar cells the fact remains that the more cells you link together the more electricity you
make.
4. SUN SWITCH:
Sun switch is an automatic Solar Level Switching Device.
The LORENTZ Sun Switch is designed for use with the LORENTZ pump controllers. It can also
be used for any application where you need to switch depending on solar light intensity. It is an
autonomous working unit that supplies itself with power from the solar cells on its back side.
4.1.1. Mounting
Sun switch is mounted close to the solar panel
The device must stay in the same orientation as the solar panels.
For mounting the Sun Switch light-sensor on the frame of the
solar panel you can use the provided C-bracket to clamp it to the
frame. Alternatively, you can drill two holes into the frame and
fix the Sun Switch light-sensor with machine screws.
Figure 11: Connecting SunSwitch to a PS controller with tank float switch (with low light =
OFF)
Both, the SunSwitch and the float switch can stop the PS controller. In other words, the pump
will only run if the irradiation is sufficient and the tank is not full.
5. WELL PROBE:
It is Mechanically Activated Device for Dry Run Protection in Applications with LORENTZ
Solar Pump Systems
The switch can be used to detect the water level within a well. When the
water level in the well dropped below the level of the well probe, the
LORENTZ Controller will stop the pump and indicates Source Low
LED.
5.1. Features
Reliable dry run protection
Simple to install
Trouble free operation
Corrosion-free
Splicing kit included
Splice the two probe wires using the splice kit components that are
packed with the probe. The assembly procedure is the same as the
main pump link. Wiring to the controller – The dry run protection
must be connected to the controller via plug at slot B8, Potential
problems with the low-water probe in surface water – The probe has
a moving float. It is highly resistant to deposits and debris. However,
it may stick under some extreme conditions, especially from algae or
Figure 13: Well probe fixing water creatures (snails, etc.) that may be present in surface water.
6. FLOAT SWITCH:
Float switch is a mechanically Activated Device for Water Level Detection in Applications with
LORENTZ Solar Pump Systems
The switch can be used to detect the water level within a tank. When the water
level in the tank reaches the maximum, the LORENTZ Controller will stop the
pump and indicates Tank Full LED.
6.1. Features
Reliable water level detection
Simple to install
Trouble free operation
Not sensitive to rotation
Corrosion-free
Three wires for normally open and normally closed application
7. SURGE PROTECTOR:
Device to Protect LORENTZ Pump Accessories from Voltage Spikes
7.1. Features
Reliable surge protection for all LORENTZ pump accessories
Can be installed inside the PS Controller
8. PV DISCONNECT 440-20-6:
Connection box with DC Disconnect Switch and optional lightning surge protection
8.1. Features
Designed for PS pump systems
PS150 – PS4000
For professional installation of pumping Systems
Lightning surge protection device available (optional)
8.3. Wiring
Wiring up to 6 PV-strings in parallel
DC rated disconnect switch enclosed
Enclosure class IP 54
PS9K2 7.5 380-440 9 850 500-600 18 0-60 320 450 250 290 405 220 9 17
Weight
Model Dimensions (mm) (Kg)
W1 W2 H1 H2 H3 D1 D2 D
PS9K2 320 290 500 450 425 220 250 9 17
Fit all screws; leave about 10 mm / 0.4 spaces between the screw’s head and the wall. Hang the
controller on the wall. Finally, tighten all screws.
PSk2 controllers can be mounted side by side.
The PSk2 controller converts the DC power from the solar array to digitally created AC signal to
run the motor. Motor speed (RPM) is proportional to the signal frequency. The frequency starts
low (about 20 Hz), and increases gradually to a maximum about 60 Hz.
The PSk2 C-SJ pumps are centrifugal pumps, driven by a 3-phase water cooled AC motor.
Each system consists of a pump, pump motor and a controller, this modular concept keeps all
electronics above ground, simplifying servicing and lowering cost of ownership.
10.4. Installation
To connect the pump end and the motor you must set the motor
with the clamps in the bore hole to fix it.
Lower the pump end carefully onto the motor and fix it
with the supplied screws. It is very important to avoid
heavy impact when the pump end is mounted onto the
motor.
For correct connection pay attention to the following
table with tightening torques. The screws must be
tightened diagonally.
Torque
Pump/Motor Torque (Nm) (Ibxft)
M8 18 13
M12 70 52
M16 150 110
During the process of lowering the pump into the well the motor cable
must be fixed properly to the pipe as figure 27 shows.
Where a plastic pipe is used, the longitudinal stretch of the pipe under
load must be considered by leaving a sufficient gap between the pipe
and the cable. The cable should be fixed with water-resistant tape. It is
a good installation practice to form a loop with the motor cable near the
pump and repeat it about every 40 m along the riser pipe.
Figure 27: Fixing of the motor cable at a joint (top) and a strait pipe (right)
This will keep any tensile forces away from the motor cable.
Round off the edges of a flange to prevent damage to the cable. Do not fix the cable tightly.
Leave space for the pipes to expand. The cable needs to get fixed every 3 m.
Figure 29: Bottom view of PSk2 controller: cable entries and external sockets
12. GROUNDING:
12.1. Why ground?
Before starting to work on the electrical system make sure that all components are disconnected
from the power source. Only switch on the system when you have finished all work.
Grounding is mandatory to protect the users from potentially fatal electric shocks. It also protects
against electric charging or a short circuit inside the device. This is accomplished through
clamping, bolting or other mechanical means to provide an effective grounding path to the earth
to ensure safe operation at all time.
The grounding is also important to the system for lightning protection. In general, it is meant for
indirect lightning strikes and induced electrical potentials during operation of the pump system.
Hz
1 flash >25
2 flashes >30
3 flashes >35
4 flashes >40
5 flashes >45
Source low (red) – the water source has dropped below the level of the low-water probe
or the water sensor has detected air in the suction pipe. after the water level recovers or
the suction pipe has been re-filled with water, the pump will restart after a delay of 15
minutes.
Tank full (red) – pump is turned off by action of the remote float switch (or pressure
switch or manual switch, whichever is wired to the (“remote float switch” terminals.)
Tank full (flashing red) – the pump is turned off because the solar irradiation is below the
trigger point setting. The pump will start working when the set conditions are met.
Input and output 1. input voltage 1. input voltage in the specified scope
Parameter 2. outputcurrent 2. output current under the rated value
This industrial attachment was very important to my knowledge in different ways such as:
practical knowledge, theoretical knowledge and social knowledge. In practical part, I have learnt
how to install solar panels with its accessories like controller, sun switch, float switch, PV
disconnect and well probe and other mechanical equipment such as pump, pipes, construction of
tap stand.
This knowledge, I got from this internship will help me to deal with some problems as far as
electrical engineering and other engineering field is concerned in my country and also will help
me to be competitive at work.
I learnt how to make the normal life easy based on the existing materials.
I became a professional graduate through the knowledge got from this internship
I developed my engineering career through hands on skills from the site of internship
I knew how I might Solving some problems that might arise in the society daily life
I also knew how I could cooperate with my fellow engineers in case, we are doing similar job
thus helping each other.
1. CONCLUSION:
In this internship, EWB-Rwanda in partnership with EWB-Quebec from Canada and the
government of Rwanda particularly Gisagara district tried to solve the problem of unclean water
by delivering uncontaminated water to e more than 10 000 people who are living in Mukindo
sector through that Water Project like other projects implemented by EWB-Rwanda like
Building Bridges in different part of Rwanda.
Through solar system used as a source of electricity to provide electrical energy to the pump
system used in the project to uphill the water from reservoir up to the storage tanks I got a great
experience that I mark the best starting of my carrier in electrical engineering.
I acquired practical skills that match with some of theories learnt in classroom about solar
system. And how I could make a simple costly electrical related project to help the vulnerable
community in Rwanda either provision of electrical energy or provision of safe water using the
knowledge of filters or any other field of engineering through cooperation.
Before my internship at EWB-Rwanda, things seemed to be magic and mysterious but now are
clear, evident, real and true.
Therefore, I can confidently assure you that I understand what a duty of an engineer at field is.
2. RECOMMENDATIONS:
I would like to recommend EWB-Rwanda to:
1. Make Cooperation with institutions having students studying electrical and other engineering
courses to have internships in some projects that EWB-Rwanda is under the control so that
students can be familiar with their field of study for future benefits of EWB-Rwanda, the
community, Rwanda as country and the world.
2. To make seminars to the engineering students and other engineers so as to have the required
skills for implementing the projects in different fields of engineering.
3. To have strong collaboration with other Engineers Without Boarders (EWB) from different
countries so as to share experience about different projects.
4. To have training center to its members so as to be skillfully and expertly in their respective
field of engineering.
5. To collaborate with government of Rwanda for easy implementation of those projects.
I would like to recommend UR-CST:
Our college but particularly the Electrical and Electronics Department to strength its relationship
with EWB-Rwanda , Government Institutions and Private Companies because they have a lot
that benefits the students in terms of practical work. However more, it is better the internship is
done before the final year even several times during their school life in order to help students to
find many helpful ideas from different sites during their final year projects researches.
2. Resources
www.davisandshirtliff.com
www.ewb-international.com/countries/rwanda
www.ewb-rwanda.org
www.lorentz.de
www.solar-electric.com
VII. APPENDIX:
1. Training certificate
2. Weekly log books