5 Click on the “interval avail cap” at the top left to define multiple shift sequences.
Enter information in the fields as specified in the below table:
Note: Use this to define work centers that have multiple shifts. Also use this to specify
that certain shifts have different number of capacities (used in 2nd operations). See next
page. Otherwise click on the green check, which takes you to the “Create Work
Center: Capacity Overview”.
To add an “Interval of Available Capacity”, click on the Insert Icon that appears as a page with
a yellow cross on it. The following is a view of this page.
Note: The information keyed into this screen is the dates of validity “from and to” for the
available capacity you are working on. See the table below to identify what fields need data
entered.
(Note: On above table, in column “R/O/C” ; “R” = Required, “O” = Optional, “C” =
Conditional)
Note: After completing the necessary entries, click on the green check in the lower left-hand
corner of the screen. This will send you to the “Create Work Center Capacity: Shifts
Screen”.
You are now backing at the Create Work Center Capacity: Shifts Screen. The
interval has been inserted. To see the detail of the intervals click on the Available
Capacity Profile. See the example screen below.
Note: From this screen, you have now set up all of your capacity requirements and can proceed
with creating the work center record. Click on the green back arrow. The system reverts to the
“Create Work Center: Capacity Overview” screen.
Select the Scheduling tab or choose from the menu Go to > Scheduling to continue
to the next screen.
Location group Used to assign a physical location to O Select from pull down menu. Location groups
the work center. Configuration required.
reduce the amount
of data processed
between work
centers are
determined in lead
time scheduling.
Std Queue Time an order waits at a work center O Enter time qty and UOM if desired Optional
Time before it is processed.
Min. Queue Shortest length of time an order waits O Enter time qty and UOM if desired Optional
Time for processing at the Work Center
Dimension Section Heading
and unit of
measure of
work
Work Dimension of work in Project System O Select from pull down list. Values configured in
Dimension IMG.
Work Unit Specific UOM of work in Project O Select from pull down list. Optional
System
(Note: On above table, in column “R/O/C”; “R” = Required, “O” = Optional, “C” =
Conditional)
7.. Select the Costing tab or choose from the menu Go to > Costing to continue to the
next screen.
. On screen “Create Work Center: Cost Center Assignment”, enter the information
as specified in the fields in the table below.
(Note: On above table, in column “R/O/C”; “R” = Required, “O” = Optional, “C” =
Conditional)
Select the Technical data tab or choose from the menu Go to > Technical data to
continue to the next screen.
Sort String String which you can use to sort CAPP R Select from the pull down list. Configurable.
Elements (used in calculating standard
values), or search for them.
CAPP Planner Key which identifies a person or group R Select from the pull down list. Configurable.
Group
of people responsible for maintaining
work centers.
Rnd. & add.val. Key which specifies the rounding O Select from the pull down list.
categories and the additional values to be
taken into account when standard values
are calculated for an operation.
(Note: On above table, in column “R/O/C”; “R” = Required, “O” = Optional, “C” =
Conditional)
Click on the yellow folder to save your changes. Subsequently, a message will be
displayed at the bottom of your screen: “Work Center “003” in Plant “3004” was created.”
This indicates that the work center was successfully created.
Result